SlideShare a Scribd company logo
Department of Electrical Engineering
TRAFFIC INFORMATION SYSTEM TO DELIVER
IN-VEHICLE MESSAGES ON PRE-DEFINED
ROUTES USING DSRC BASED V2V
COMMUNICATION
Attiq Uz Zaman
M.I. Hayee
University of Minnesota Duluth
Navin Katta
Sean Mooney
Savari Inc.
Department of Electrical Engineering
Motivation
• 579 deaths due to work zones in
2013
• Work zones constituted to $700
million in fuel loss
• 12% of all delay on freeways Is
caused due to work zones.
Department of Electrical Engineering
Outline
• Introduction
• Hopping algorithm
• Simulation and results
• Preliminary field tests and future work
• Summary
Department of Electrical Engineering
Introduction
Work zones lane closure can cause congestion
to build up.
Intelligent Traffic Information Systems can help.
Main objectives of a traffic information system
 Gather dynamic traffic parameters e.g.,
travel time, back of the queue etc.
 Disseminate these parameters to the
vehicles approaching the congestion.
 DSRC a preferred choice due to its low latency
and highly secure protocol
Department of Electrical Engineering
Overall System and Challenges
RSU’s broadcast range is not enough to directly reach far off vehicles
Desired Region
RSU
Start of Work
Zone
End of work
zone
Hopping distance should be maximized without causing broadcast storm
Strict hopping route should be followed
OBUs don’t need to modify original message
Varying Starting
Location of Congestion
Range of RSU
Department of Electrical Engineering
RSU M = 1
End of work
zone
Smaller rectangles for
curved paths
Longer Rectangles for
straight paths
Pre-Defined Route
Start of Work
Zone
Desired Region
OBUs outside the rectangular
regions recognize msg not intended
for them
Department of Electrical Engineering
• Each Rectangle is virtually sub-divided into multiple sub-rectangles
• Each sub-rectangle is less than or equal to 250 m in length.
Hopping Windows
RSU M = 1
M = 4
N = 1 N = 2 N = 3 N = 4
- - - - - - - - - - - - - - - - - - - - - - - -
N = NM
L1-4 ≈ 250 m
L1
Length of Rectangles more than range of DSRC
Department of Electrical Engineering
Hop Timing control
N = 1 N = 2 N = 3 N = 7N = 4 N = 5 N = 6
Hopping time windows
(msec.)
RSU M = 1
M = 4
L1
‘b’ will hop before ‘a’ ‘d’ didn’t receive
100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800
200 msec
0 m
100 msec Distance from beginning of
main-rectangle
HoppingTimes
300 msec
400 msec
250 m 500 m 750 m
Department of Electrical Engineering
Hop Timing control
g ih jfd eca b
Hopping time windows
(msec.)
RSU M = 1
M = 4
L1
‘b’ will hop before ‘a’
100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800
RSU
Department of Electrical Engineering
Hop Timing control
g ih jfd eca b
Hopping time windows
(msec.)
RSU M = 1
M = 4
L1
‘a’ stops hopping process after receiving message from ‘b’
100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800
RSU
Department of Electrical Engineering
Hop Timing control
g ih jfd eca b
Hopping time windows
(msec.)
RSU M = 1
M = 4
L1
‘b’ will hop before ‘a’ ‘d’ didn’t receive
100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800
RSU
Department of Electrical Engineering
Hop Timing control
g ih jfd eca b
Hopping time windows
(msec.)
RSU M = 1
M = 4
L1
‘d’ will not hop message since it received this msg inside its hopping window
100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800
RSU
Department of Electrical Engineering
DSRC Specific Timing Control Issue
• 100 msec divided into control and service windows of 50 msec. each
• TIM is received/sent only in service window
0 10 20 30 40 50 60 70 80 90 100
IEEE 1609.4 standard
Control channel interval Service channel interval
0 10 20 30 40 50 60 70 80 90 100
Non IEEE 1609.4 standard
Full window available
Department of Electrical Engineering
a b
250 m
200 ms
Full window
available
b hops
100 ms
A does not
hop
DSRC Specific Hop Timing Control Solution
cRSU
200 ms
Service window
available
Control window100 ms Service window150 ms 250 ms
250 ms150 ms
100 msec
200 msec
0 m 250 m
Distance
HoppingTime
150 msec
Department of Electrical Engineering
Sub-rectangle And Hopping Time
Calculations
))(1.0())1.0)(((__
1
1
NiN=LimitTimeLower
M
i M 


)1.0(
250
250)1((
1.0 


ND
LTL=HWT M






250
M
M
L
ceil=N (1)
M
M
SRM
N
L
=L (2)






SRM
M
L
D
ceil=N (3)
05.))(1.0())1.0)(((__
1
1



NiN=LimitTimeLower
M
i M
)05.0(
250
250)1((
1.0 


ND
LTL=HWT M
DSRC specific hopping time calculation
Hopping time calculationSub-rectangle calculation
Department of Electrical Engineering
Simulation Setup
OBU 6
OBU 7
OBU 8
N = 1 N = 2 N = 3 N = 3 N = 4 N = 5N = 4 N = 1 N = 2 N = 6
OBU 1 OBU 2 OBU 3 OBU 4 OBU 5 OBU 9 OBU 10 OBU 12OBU 11
https://maps.google.com/
M = 2M = 1
Roadside unit
 We chose the West Arrowhead Road in Duluth, MN for simulation and preliminary field tests
 Total length of road segment is about 2.5 Km
 Twelve distinct points (latitude, longitude pair) were selected as potential OBU positions
 Two rectangles of length 1.5 and 1 Km each were used to cover the road segment.
Department of Electrical Engineering
OBU
No.
Distance from
roadside unit
(m)
LTL-UTL
(msec)
TIME at which TIM
is received
(msec)
TIME at which TIM
is supposed to
hop
(msec)
TIM hopped?
(Yes/No)
1 240 150-199 0.0 152 Yes
2 490 250-299 152 251 Yes
3 725 350-399 251 353 Yes
4 990 450-499 353 451 Yes
5 1200 550-599 451 558 Yes
6 1425 650-699 558 664 No (TIM hopped by OBU
#7 at 650 msec)
7 1495 650-699 558 650 Yes
8 Not Applicable NA 650 Not Applicable No (OBU is not on the
predefined route)
9 1740 750-799 650 751 Yes
OBU 6
OBU 7
OBU 8
N = 1 N = 2 N = 3 N = 3 N = 4 N = 5N = 4 N = 1 N = 2 N = 6
OBU 1 OBU 2 OBU 3 OBU 4 OBU 5 OBU 9 OBU 10 OBU 12OBU 11
Simulation Results
Department of Electrical Engineering
OBU 3OBU 2OBU 1RSU
PCMS
1.2 Km
Preliminary Road Tests
• 1 RSU and 3 OBUs placed on west arrowhead road Duluth
• Hopped TIM to 1.2 Km distance
Department of Electrical Engineering
Summary
 A traffic information system is designed which
 Disseminate messages on a desired route(s) using V2V communication
 Avoids broadcast storm
 Working on acquiring dynamic traffic parameters from the incoming vehicles
and on a GUI for dashboard display panel
Department of Electrical Engineering
Thank You
Attiq Uz Zaman
zaman013@d.umn.edu
Department of Electrical Engineering
University of Minnesota Duluth

More Related Content

What's hot

MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...
MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...
MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...
csandit
 
Iai rcl sm6_l_specsheet
Iai rcl sm6_l_specsheetIai rcl sm6_l_specsheet
Iai rcl sm6_l_specsheet
Electromate
 
Akribis acm brochure
Akribis acm brochureAkribis acm brochure
Akribis acm brochure
Electromate
 
Observer-based controller design and simulation for an active suspension system
Observer-based controller design and simulation for an active suspension systemObserver-based controller design and simulation for an active suspension system
Observer-based controller design and simulation for an active suspension systemTom Hemans
 
Iai rcl sa6_l_specsheet
Iai rcl sa6_l_specsheetIai rcl sa6_l_specsheet
Iai rcl sa6_l_specsheet
Electromate
 
Iai rcs3 ct8_c_ctz5c_specsheet
Iai rcs3 ct8_c_ctz5c_specsheetIai rcs3 ct8_c_ctz5c_specsheet
Iai rcs3 ct8_c_ctz5c_specsheet
Electromate
 
Iai rcl sa3_l_specsheet
Iai rcl sa3_l_specsheetIai rcl sa3_l_specsheet
Iai rcl sa3_l_specsheet
Electromate
 
Ais 040(rev.1)
Ais 040(rev.1)Ais 040(rev.1)
Ais 040(rev.1)
Dhruv Upadhaya
 
Ais 039(rev.1)
Ais 039(rev.1)Ais 039(rev.1)
Ais 039(rev.1)
Dhruv Upadhaya
 
Ais 041(rev.1)
Ais 041(rev.1)Ais 041(rev.1)
Ais 041(rev.1)
Dhruv Upadhaya
 
"Nothing on the road axle detection system using direct strain measurements –...
"Nothing on the road axle detection system using direct strain measurements –..."Nothing on the road axle detection system using direct strain measurements –...
"Nothing on the road axle detection system using direct strain measurements –...
TRUSS ITN
 
[8] implementation of pmsm servo drive using digital signal processing
[8] implementation of pmsm servo drive using digital signal processing[8] implementation of pmsm servo drive using digital signal processing
[8] implementation of pmsm servo drive using digital signal processing
Ngoc Dinh
 
Dyadics _scn4_ Spec Sheet
Dyadics _scn4_ Spec SheetDyadics _scn4_ Spec Sheet
Dyadics _scn4_ Spec Sheet
Electromate
 
Iai rcp2 sa5_r_specsheet
Iai rcp2 sa5_r_specsheetIai rcp2 sa5_r_specsheet
Iai rcp2 sa5_r_specsheet
Electromate
 
Npm scr stage_specsheet
Npm scr stage_specsheetNpm scr stage_specsheet
Npm scr stage_specsheet
Electromate
 
Iai rca a6_r_specsheet
Iai rca a6_r_specsheetIai rca a6_r_specsheet
Iai rca a6_r_specsheet
Electromate
 

What's hot (17)

MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...
MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...
MODELING AND DESIGN OF CRUISE CONTROL SYSTEM WITH FEEDFORWARD FOR ALL TERRIAN...
 
Iai rcl sm6_l_specsheet
Iai rcl sm6_l_specsheetIai rcl sm6_l_specsheet
Iai rcl sm6_l_specsheet
 
Akribis acm brochure
Akribis acm brochureAkribis acm brochure
Akribis acm brochure
 
Observer-based controller design and simulation for an active suspension system
Observer-based controller design and simulation for an active suspension systemObserver-based controller design and simulation for an active suspension system
Observer-based controller design and simulation for an active suspension system
 
Iai rcl sa6_l_specsheet
Iai rcl sa6_l_specsheetIai rcl sa6_l_specsheet
Iai rcl sa6_l_specsheet
 
Iai rcs3 ct8_c_ctz5c_specsheet
Iai rcs3 ct8_c_ctz5c_specsheetIai rcs3 ct8_c_ctz5c_specsheet
Iai rcs3 ct8_c_ctz5c_specsheet
 
Iai rcl sa3_l_specsheet
Iai rcl sa3_l_specsheetIai rcl sa3_l_specsheet
Iai rcl sa3_l_specsheet
 
Ais 040(rev.1)
Ais 040(rev.1)Ais 040(rev.1)
Ais 040(rev.1)
 
Ais 039(rev.1)
Ais 039(rev.1)Ais 039(rev.1)
Ais 039(rev.1)
 
Ais 041(rev.1)
Ais 041(rev.1)Ais 041(rev.1)
Ais 041(rev.1)
 
"Nothing on the road axle detection system using direct strain measurements –...
"Nothing on the road axle detection system using direct strain measurements –..."Nothing on the road axle detection system using direct strain measurements –...
"Nothing on the road axle detection system using direct strain measurements –...
 
[8] implementation of pmsm servo drive using digital signal processing
[8] implementation of pmsm servo drive using digital signal processing[8] implementation of pmsm servo drive using digital signal processing
[8] implementation of pmsm servo drive using digital signal processing
 
Dyadics _scn4_ Spec Sheet
Dyadics _scn4_ Spec SheetDyadics _scn4_ Spec Sheet
Dyadics _scn4_ Spec Sheet
 
Iai rcp2 sa5_r_specsheet
Iai rcp2 sa5_r_specsheetIai rcp2 sa5_r_specsheet
Iai rcp2 sa5_r_specsheet
 
Npm scr stage_specsheet
Npm scr stage_specsheetNpm scr stage_specsheet
Npm scr stage_specsheet
 
Iai rca a6_r_specsheet
Iai rca a6_r_specsheetIai rca a6_r_specsheet
Iai rca a6_r_specsheet
 
Cruise control
Cruise controlCruise control
Cruise control
 

Viewers also liked

Enhancing Traffic Intersection Control with Intelligent Objects
Enhancing Traffic Intersection Control with Intelligent ObjectsEnhancing Traffic Intersection Control with Intelligent Objects
Enhancing Traffic Intersection Control with Intelligent Objects
Rudi Ball
 
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
Naoki Shibata
 
Traffic simulation
Traffic simulationTraffic simulation
Traffic simulation
Praful -
 
Major ppt
Major pptMajor ppt
Major ppt
Amit Baghel
 
Simulation of traffic at T-Junction
Simulation of traffic at T-JunctionSimulation of traffic at T-Junction
Simulation of traffic at T-JunctionAbhishek Upperwal
 
Advait Project Report
Advait Project ReportAdvait Project Report
Advait Project ReportAdvait Patel
 

Viewers also liked (6)

Enhancing Traffic Intersection Control with Intelligent Objects
Enhancing Traffic Intersection Control with Intelligent ObjectsEnhancing Traffic Intersection Control with Intelligent Objects
Enhancing Traffic Intersection Control with Intelligent Objects
 
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
(Slides) A Technique for Information Sharing using Inter-Vehicle Communicatio...
 
Traffic simulation
Traffic simulationTraffic simulation
Traffic simulation
 
Major ppt
Major pptMajor ppt
Major ppt
 
Simulation of traffic at T-Junction
Simulation of traffic at T-JunctionSimulation of traffic at T-Junction
Simulation of traffic at T-Junction
 
Advait Project Report
Advait Project ReportAdvait Project Report
Advait Project Report
 

Similar to TRAFFIC INFORMATION SYSTEM TO DELIVER IN-VEHICLE MESSAGES ON PRE-DEFINED ROUTES USING DSRC BASED V2V COMMUNICATION

DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computationDSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
Deltares
 
Ejemplo_AG2
Ejemplo_AG2Ejemplo_AG2
Ejemplo_AG2
UbaldoJGarca
 
Traffic state estimation with multi-sensor data for large networks with macro...
Traffic state estimation with multi-sensor data for large networks with macro...Traffic state estimation with multi-sensor data for large networks with macro...
Traffic state estimation with multi-sensor data for large networks with macro...
YazanSafadi
 
Three phase BLDC motor
Three phase BLDC motorThree phase BLDC motor
Three phase BLDC motor
Anoop S
 
Caged Quadrotor Drone for Inspection of HVAC Ducts
Caged Quadrotor Drone for Inspection of HVAC DuctsCaged Quadrotor Drone for Inspection of HVAC Ducts
Caged Quadrotor Drone for Inspection of HVAC Ducts
Arwa Abougharib
 
PSC Presentation Slides (2).pptx
PSC Presentation Slides (2).pptxPSC Presentation Slides (2).pptx
PSC Presentation Slides (2).pptx
LAYTH3
 
Simulation of a Telephone system & Reliability Problem
Simulation of a Telephone system & Reliability ProblemSimulation of a Telephone system & Reliability Problem
Simulation of a Telephone system & Reliability Problem
Altafur Rahman
 
Lect2 up250 (100328)
Lect2 up250 (100328)Lect2 up250 (100328)
Lect2 up250 (100328)aicdesign
 
新加坡国立大学 硅共振加速度计
新加坡国立大学 硅共振加速度计新加坡国立大学 硅共振加速度计
新加坡国立大学 硅共振加速度计
文峰 贾
 
rcwire.ppt
rcwire.pptrcwire.ppt
rcwire.ppt
SomnathPal64
 
Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...
Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...
Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...
IJPEDS-IAES
 
BMRCL.ppt
 BMRCL.ppt BMRCL.ppt
BMRCL.ppt
sridharGowda20
 
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
IRJET Journal
 
Presentation CIE619
Presentation CIE619 Presentation CIE619
Presentation CIE619
Sharath Chandra
 
JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel
Electromate
 
General condition-relating-to-electricity new
General condition-relating-to-electricity newGeneral condition-relating-to-electricity new
General condition-relating-to-electricity newDineshsenthil
 
Btl control system-lab-manual-10 eel68
Btl control system-lab-manual-10 eel68Btl control system-lab-manual-10 eel68
Btl control system-lab-manual-10 eel68Gopinath.B.L Naidu
 
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
Dr. Babasaheb Ambedkar Technological University
 

Similar to TRAFFIC INFORMATION SYSTEM TO DELIVER IN-VEHICLE MESSAGES ON PRE-DEFINED ROUTES USING DSRC BASED V2V COMMUNICATION (20)

DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computationDSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
DSD-INT - SWAN Advanced Course - 02 - Setting up a SWAN computation
 
Simulation-Iss4
Simulation-Iss4Simulation-Iss4
Simulation-Iss4
 
Ejemplo_AG2
Ejemplo_AG2Ejemplo_AG2
Ejemplo_AG2
 
Traffic state estimation with multi-sensor data for large networks with macro...
Traffic state estimation with multi-sensor data for large networks with macro...Traffic state estimation with multi-sensor data for large networks with macro...
Traffic state estimation with multi-sensor data for large networks with macro...
 
Three phase BLDC motor
Three phase BLDC motorThree phase BLDC motor
Three phase BLDC motor
 
Caged Quadrotor Drone for Inspection of HVAC Ducts
Caged Quadrotor Drone for Inspection of HVAC DuctsCaged Quadrotor Drone for Inspection of HVAC Ducts
Caged Quadrotor Drone for Inspection of HVAC Ducts
 
PSC Presentation Slides (2).pptx
PSC Presentation Slides (2).pptxPSC Presentation Slides (2).pptx
PSC Presentation Slides (2).pptx
 
Simulation of a Telephone system & Reliability Problem
Simulation of a Telephone system & Reliability ProblemSimulation of a Telephone system & Reliability Problem
Simulation of a Telephone system & Reliability Problem
 
Lect2 up250 (100328)
Lect2 up250 (100328)Lect2 up250 (100328)
Lect2 up250 (100328)
 
新加坡国立大学 硅共振加速度计
新加坡国立大学 硅共振加速度计新加坡国立大学 硅共振加速度计
新加坡国立大学 硅共振加速度计
 
rcwire.ppt
rcwire.pptrcwire.ppt
rcwire.ppt
 
Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...
Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...
Performance Analysis of a DTC and SVM Based Field- Orientation Control Induct...
 
BMRCL.ppt
 BMRCL.ppt BMRCL.ppt
BMRCL.ppt
 
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
 
loai_Resume
loai_Resumeloai_Resume
loai_Resume
 
Presentation CIE619
Presentation CIE619 Presentation CIE619
Presentation CIE619
 
JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel JVL Intergrated Servo Motor in Stainless Steel
JVL Intergrated Servo Motor in Stainless Steel
 
General condition-relating-to-electricity new
General condition-relating-to-electricity newGeneral condition-relating-to-electricity new
General condition-relating-to-electricity new
 
Btl control system-lab-manual-10 eel68
Btl control system-lab-manual-10 eel68Btl control system-lab-manual-10 eel68
Btl control system-lab-manual-10 eel68
 
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
“HOT LINE CLEANING ROBOT USED IN TRANSMISSION LINE AND SUBSTATION”
 

Recently uploaded

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
BrazilAccount1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 

Recently uploaded (20)

Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
English lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdfEnglish lab ppt no titlespecENG PPTt.pdf
English lab ppt no titlespecENG PPTt.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 

TRAFFIC INFORMATION SYSTEM TO DELIVER IN-VEHICLE MESSAGES ON PRE-DEFINED ROUTES USING DSRC BASED V2V COMMUNICATION

  • 1. Department of Electrical Engineering TRAFFIC INFORMATION SYSTEM TO DELIVER IN-VEHICLE MESSAGES ON PRE-DEFINED ROUTES USING DSRC BASED V2V COMMUNICATION Attiq Uz Zaman M.I. Hayee University of Minnesota Duluth Navin Katta Sean Mooney Savari Inc.
  • 2. Department of Electrical Engineering Motivation • 579 deaths due to work zones in 2013 • Work zones constituted to $700 million in fuel loss • 12% of all delay on freeways Is caused due to work zones.
  • 3. Department of Electrical Engineering Outline • Introduction • Hopping algorithm • Simulation and results • Preliminary field tests and future work • Summary
  • 4. Department of Electrical Engineering Introduction Work zones lane closure can cause congestion to build up. Intelligent Traffic Information Systems can help. Main objectives of a traffic information system  Gather dynamic traffic parameters e.g., travel time, back of the queue etc.  Disseminate these parameters to the vehicles approaching the congestion.  DSRC a preferred choice due to its low latency and highly secure protocol
  • 5. Department of Electrical Engineering Overall System and Challenges RSU’s broadcast range is not enough to directly reach far off vehicles Desired Region RSU Start of Work Zone End of work zone Hopping distance should be maximized without causing broadcast storm Strict hopping route should be followed OBUs don’t need to modify original message Varying Starting Location of Congestion Range of RSU
  • 6. Department of Electrical Engineering RSU M = 1 End of work zone Smaller rectangles for curved paths Longer Rectangles for straight paths Pre-Defined Route Start of Work Zone Desired Region OBUs outside the rectangular regions recognize msg not intended for them
  • 7. Department of Electrical Engineering • Each Rectangle is virtually sub-divided into multiple sub-rectangles • Each sub-rectangle is less than or equal to 250 m in length. Hopping Windows RSU M = 1 M = 4 N = 1 N = 2 N = 3 N = 4 - - - - - - - - - - - - - - - - - - - - - - - - N = NM L1-4 ≈ 250 m L1 Length of Rectangles more than range of DSRC
  • 8. Department of Electrical Engineering Hop Timing control N = 1 N = 2 N = 3 N = 7N = 4 N = 5 N = 6 Hopping time windows (msec.) RSU M = 1 M = 4 L1 ‘b’ will hop before ‘a’ ‘d’ didn’t receive 100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800 200 msec 0 m 100 msec Distance from beginning of main-rectangle HoppingTimes 300 msec 400 msec 250 m 500 m 750 m
  • 9. Department of Electrical Engineering Hop Timing control g ih jfd eca b Hopping time windows (msec.) RSU M = 1 M = 4 L1 ‘b’ will hop before ‘a’ 100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800 RSU
  • 10. Department of Electrical Engineering Hop Timing control g ih jfd eca b Hopping time windows (msec.) RSU M = 1 M = 4 L1 ‘a’ stops hopping process after receiving message from ‘b’ 100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800 RSU
  • 11. Department of Electrical Engineering Hop Timing control g ih jfd eca b Hopping time windows (msec.) RSU M = 1 M = 4 L1 ‘b’ will hop before ‘a’ ‘d’ didn’t receive 100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800 RSU
  • 12. Department of Electrical Engineering Hop Timing control g ih jfd eca b Hopping time windows (msec.) RSU M = 1 M = 4 L1 ‘d’ will not hop message since it received this msg inside its hopping window 100 – 200 200 – 300 300 – 400 400 - 500 500 – 600 600 – 700 700 – 800 RSU
  • 13. Department of Electrical Engineering DSRC Specific Timing Control Issue • 100 msec divided into control and service windows of 50 msec. each • TIM is received/sent only in service window 0 10 20 30 40 50 60 70 80 90 100 IEEE 1609.4 standard Control channel interval Service channel interval 0 10 20 30 40 50 60 70 80 90 100 Non IEEE 1609.4 standard Full window available
  • 14. Department of Electrical Engineering a b 250 m 200 ms Full window available b hops 100 ms A does not hop DSRC Specific Hop Timing Control Solution cRSU 200 ms Service window available Control window100 ms Service window150 ms 250 ms 250 ms150 ms 100 msec 200 msec 0 m 250 m Distance HoppingTime 150 msec
  • 15. Department of Electrical Engineering Sub-rectangle And Hopping Time Calculations ))(1.0())1.0)(((__ 1 1 NiN=LimitTimeLower M i M    )1.0( 250 250)1(( 1.0    ND LTL=HWT M       250 M M L ceil=N (1) M M SRM N L =L (2)       SRM M L D ceil=N (3) 05.))(1.0())1.0)(((__ 1 1    NiN=LimitTimeLower M i M )05.0( 250 250)1(( 1.0    ND LTL=HWT M DSRC specific hopping time calculation Hopping time calculationSub-rectangle calculation
  • 16. Department of Electrical Engineering Simulation Setup OBU 6 OBU 7 OBU 8 N = 1 N = 2 N = 3 N = 3 N = 4 N = 5N = 4 N = 1 N = 2 N = 6 OBU 1 OBU 2 OBU 3 OBU 4 OBU 5 OBU 9 OBU 10 OBU 12OBU 11 https://maps.google.com/ M = 2M = 1 Roadside unit  We chose the West Arrowhead Road in Duluth, MN for simulation and preliminary field tests  Total length of road segment is about 2.5 Km  Twelve distinct points (latitude, longitude pair) were selected as potential OBU positions  Two rectangles of length 1.5 and 1 Km each were used to cover the road segment.
  • 17. Department of Electrical Engineering OBU No. Distance from roadside unit (m) LTL-UTL (msec) TIME at which TIM is received (msec) TIME at which TIM is supposed to hop (msec) TIM hopped? (Yes/No) 1 240 150-199 0.0 152 Yes 2 490 250-299 152 251 Yes 3 725 350-399 251 353 Yes 4 990 450-499 353 451 Yes 5 1200 550-599 451 558 Yes 6 1425 650-699 558 664 No (TIM hopped by OBU #7 at 650 msec) 7 1495 650-699 558 650 Yes 8 Not Applicable NA 650 Not Applicable No (OBU is not on the predefined route) 9 1740 750-799 650 751 Yes OBU 6 OBU 7 OBU 8 N = 1 N = 2 N = 3 N = 3 N = 4 N = 5N = 4 N = 1 N = 2 N = 6 OBU 1 OBU 2 OBU 3 OBU 4 OBU 5 OBU 9 OBU 10 OBU 12OBU 11 Simulation Results
  • 18. Department of Electrical Engineering OBU 3OBU 2OBU 1RSU PCMS 1.2 Km Preliminary Road Tests • 1 RSU and 3 OBUs placed on west arrowhead road Duluth • Hopped TIM to 1.2 Km distance
  • 19. Department of Electrical Engineering Summary  A traffic information system is designed which  Disseminate messages on a desired route(s) using V2V communication  Avoids broadcast storm  Working on acquiring dynamic traffic parameters from the incoming vehicles and on a GUI for dashboard display panel
  • 20. Department of Electrical Engineering Thank You Attiq Uz Zaman zaman013@d.umn.edu Department of Electrical Engineering University of Minnesota Duluth

Editor's Notes

  1. most of the work zone crashes involve rear-ending collision, usually at the end of the traffic queue (4) which necessitates the need of an intelligent traffic information system for work zones which can dynamically acquire and provide drivers safety critical information in a timely manner (5,6).