4. Electric FansNew Process Design
A. Make-to- Stock Fans
B. Custom- Made Fans
1. Polymer parts are created
2. Assembly of all parts
3. Assembled fans are packaged
1. Custom Design Fans are Developed
2. Manufacture Only a Few
3. Manufacture Small Amount
4. Test Fans and Sell to Customer
2a. Assess production cost
3a. Assess design deviation
(University of Phoenix, 2013)
5. Bottlenecks in New Process
Unexpected variations in the assemble and packaging phase
Understanding the process, continuous monitoring, and managerial support
Failure to meet goals and deadlines
Single most event that creates bottlenecks
Parts shortage
Importance of missing deadlines
6. Bottlenecks in New Process
Poor estimates on process design and production cost
Poor planning and execution leads to bottlenecks
Incorrect production cost estimates cause process design failure
Bottlenecks delay processes and disrupts supply chain
7. TQM tools towards Process Improvement
1Focus Groups
2Flow Charts
3Tree Diagram
8. Why TQM Tools Help
1Focus Groups: Customer insight prior to implementation
2Flow Charts: Identify bottlenecks and other issues
3Tree Diagrams: Organizational structure and each responsibility
9. Project Plan: Make to Stock Fans
Made to stock fans
Duration
Item
Role
Deliverable(s)
M1
Day 1
Polymer parts creation
Manufacturing
Parts created to spec from engineering team with less than 2% error/resubmit rate.
A1
Day 1 -2
Assembly team -retool & refit
Assembly team
Attend retool & refit class on new assembly techniques.
A2
Day 2 -4
Assembly team -new teams
Assembly team
Reorg teams into layered assembly teams to fall inline with item A1
A3
Day 4+
Assembly team -Start new assembly process
Assembly team
Execute item A1's new process with A2 teams
P1
Day 1 -2
Packaging team -new packing process
Packaging team
Attend new packaging class for parts from M1 and A1
P2
Day 2+
Packaging team -execution of process
Packaging team
Start packaging M1 and A1 deliverables for shipping.
11. Project Plan: Custom Made Fans
Custom made fans
Duration
Item
Role
Deliverable(s)
SA1
Day 1
Custom fan design development
Special Acct team
Specs received by Special Accounts team on new fan design.
E1
Day 1 -2
CAD custom design for 3D printer team
Engineering team
SA1 specs are printed and milled to less than 2% error rate.
E1
Day 2
Deliver printed parts to assembly teams
Assembly team
Printed parts are delivered to assembly teams A1 in custom batch lots
PC1
Day 1 -2
Production cost assessment
Production Cost team
Assess production costs, report to management
T1
Day 1 -2
Testing team process start
Test team
Test new design, report findings to E1 and management
E1
Day 2+
Engineering team -defect report
Engineering team
Report defects from T1 submission. If below 4% send to warehouse and email sales team
S1
Day 2+
Sales team -sell produced inventory
Sales team
If E1 report is ready for sale take inventory report and start customer contact for sales process
13. Conclusion
Time is Money!!!
Identified Antiquated Process as Inefficient
Process Improvements were Implemented
New Process Shortens Manufacture Time
Constant Evaluation and Improvement
14. Reference Page
University of Phoenix. (2013). Riordan Manufacturing Operations: Supply Chain –
Hangzou, China. Retrieved from
https://ecampus.phoenix.edu/secure/aapd/CIST/VOP/Business/Riordan/
Ops/SupplyChain.asp?hangzhou