SlideShare a Scribd company logo
Data Center Network Preventative
Maintenance
(a.k.a DC Outage)
June 4, 2016
Project Update
April 14, 2016 Thursday 12:00 PM Lamont Library
• Meeting Purpose and Intended Outcomes
• Network Bypass Plan…
• Netapp Solution Identified…
• New Risk Identified…
• Altered Approach…
• Project Update
• Next steps
• Communication
• Draft June 4 Plan
2
Agenda
Purpose
To provide an update on the current state of the project preparation activities
and review of the communication plan for the scheduled data center network
preventative maintenance (data center outage) on the weekend of June 4.
Intended Outcomes
• Provide an overview on the changes to the plan
• Provide an update on the action items from the last Service Delivery
Subgroup
• Share next steps and actions
• Provide an update on the communication approach
• Share Draft “Day-of” Timeline
Meeting Purpose and Intended Outcomes
3
The goal is to maintain current service levels for data center networking
and to avoid unplanned application outages. The plan was to
accomplish this by temporarily changing network routing and migrating
critical applications to non-impacted storage.
Network Bypass Plan…
4
Current plan is to temporarily initiate a network bypass. This is key to
avoiding application outages during the cross site switching system
upgrade. This diagram represents at a high level view of HUIT DC Networks
and the bypass router.
Router
The concept of migrating critical applications to non-impacted storage
was abandoned as the amount of storage needed to implement the
solution is significantly greater than the available Tier 1 storage.
An alternative option to connect the VM environment directly to the
NetApp, eliminating intermediate routing was identified, designed and
tested.
● Eliminates the risk of VMs disconnecting from standard storage
● Eliminates the need to promote applications to Tier 1 storage for the
maintenance
● Eliminates the need to take down the 60 Oxford Street VM Systems
● Is a permanent solution
NetApp Solution identified…
5
The team identified an additional risk to applications that use Oracle
Real Application Cluster (RAC).
● Oracle RAC cannot tolerate more than 30sec network outage or it will
reboot and may cause some of the applications to need to be restarted
● We have identified 2 production application servers at 60 Oxford that
support several College and Athletics applications. These could
potentially be impacted.
● We are working with the DBA, SOC and Application teams to identify
appropriate preparation activities
A New Risk Was Identified…
6
The goal is to maintain current service levels for data center networking
and to avoid unplanned application outages by temporarily changing by
passing network routing and permanently implementing a network
modification
Altered Approach...
7
Router
removed
permanently
Temporary
Since the last Service Delivery Subgroup on April 7, the following
progress has been made against requested action items:
Project Update
8
Action Description Status Update/Next Steps
1. Investigate rearchitecting
standard storage to server
connectivity alternatives
Investigate feasibility of creating a new
network and moving impacted storage
connected to the VM environment.
Complete The routed network connected
between the DC primary switch
and the Netapp is being replace
with a direct connection.
2. Contact vendors for on-site
support
Contact and schedule key vendors from
EMC, NetApp, Cisco, and VMWare
In
progress
EMC: Complete
NetApp: In Progress
Cisco: In Progress
VMWare:In Progress
3. Schedule Vendor Pre-event
Preparation meeting
Bring all vendors on site to review our
plans and activities for the event
May Planning Underway
4. Contact ATS release
management for impacted
Enterprise Apps
Work with Miroslav for ATS to
coordinate release management for
any impacted enterprise applications
In
progress
Met with ATS team on March
14th. Next step is to share New
Oracle RAC server impact list with
College and Athletics
Since the last Service Delivery Subgroup on March 24th, the following
progress has been made against requested action items:
Project Update
9
Action Description Status Update/Next Steps
5. Decommission FAS UNIX
WebMail
Decommission on premise
environment of WebMail to prevent
outage impact and retire legacy
hardware (UC run project)
In progress Underway
6. Identify mitigation for the
ORACLE RAC impact
Impact identified is to a few servers
that support College and Athletics
April Contact Diane Stronach to
confirm previous ok to take down
associated servers/applications.
7. Contact SEAS to determine
action (SEAS manages
servers)
Discuss impact to Fileshares (p.
parker and spidey) due to bypass
network blip; potential for applications
to freeze and need to be restarted
April Contact SEAS Team to discuss
8. Determine communication
path for ICEMAIL impacted
users
OPEN ITEM: At March 24 SD
meeting the question of local
departments communicating Jun 4
impact was raised
Open Determine
The following activities are the next steps in preparing for June 4
maintenance
Next Steps
10
Action Description Status/Mitigation
1. Finalize scope of application
shutdown
(as required)
1. Create list of impacted, applications on the DC Oracle
RACs and Virtual Guests at Summer St that are at risk
during the by-pass connection and disconnection. Impact
would cause a manually remount effort with is significant.
2. Identify application owners and determine strategy for
Jun 4. (Likely: SEAS, Icemail, College & Athletics, others
TBD)
In progress
(Target: April 22)
2. Review impact to Campus
Services
Understand impact and propose implementation support
needs for building controls (if needed)
In progress
(Target: April)
3. Implement network solution
that avoids 60 OX VM outage
RISK
Implement the connectivity between the Virtual Hosts
(VMs) and the NetApp Storage - eliminating the risk of
dropping VMs during the maintenance
90% Complete
(End of April)
4. Finalize “day of” events
action plan
Create implementation sequence and complete full review
of “day of” events.
April 2016
Communication Plan
11
Date Goal Audience Description of Communication
March 7-11
HUIT Leadership
Comm.
SLT
● HUIT communication of new June date (HUIT Senior Leadership
validates June date and provides feedback)
April 5th
Comm with Leaders
inside and outside
of HUIT to validate
date of maintenance
Leadership Across
University
● Communication with Key Leaders who depend on HUIT services.
Announce change and share communication powerpoint.
● List includes: School CIOs, HUIT Senior Leadership, Practice Managers,
FAS/CA Major Stakeholders, Critical 1 & 2 application technical and
functional owners.
April 18th
First Targeted
Comm.
Owners of: Servers
Databases
Applications
● Initial communication of targeted June date highlighting impact and
details of maintenance
● Reference brown bag communication sessions
April 12 - April 21
Stakeholder Brown
Bag Sessions
System owners / IT
staff
● Brown Bag sessions for stakeholders
● Communicate with NetApp and fileshare technical contacts to determine
availability impact and requirements
April 19 “Day Of” Events
System owners / IT
staff
● Continue to receive feedback from stakeholders and business owners to
fine-tune the “Day Of” events
● Share the “day of” plan
April 28 Go-live Readiness SLT
● SLT final review and readiness validation for update
May 3 - June 3 Weekly Reminders All populations
● Reminders sent to all populations
June 4 All Clear Message
Leadership/ System
owners
● All clear message sent after maintenance is declared finished to business
stakeholders and leadership vetting list. No all clear to full account holder
populations unless clarification needed.
March-April
Engage Support
Services
HUIT Support
Services
● Conduct working session with Support Services to outline coverage and
needs during implementation
This table represents the proposed communication plan to the community to inform
them of the network change and potential impacts to applications and services
Jun 4 Activity Sequencing - Network ByPass & VSS Upgrade
12
When (Estimated) What Who Description
1 Jun 3, 8:00 PM - 11:00 AM Prep Activities
SOC & Self
Service IT
Partners
1. Shut down any Dev/Test/Other Services as Determined by
Infrastructure Investigation and/or IT Client Request.
2. Self Managed IT Partners are welcome to shut down services
in preparation for Network activity
3. Reschedule any impacted system back up
2 May 23 - Jun 3 Prep Activities Network
1. Prepare hardware, cable connections
2. Verify By-Pass Router Readiness
3. Hand Off to System’s Teams
3 Jun 3, 11:00 - 11:59PM
Take Down:
1. C & A Apps on
Oracle RAC
2. IceMAIL
3.SEAS Apps
1.DBAs, SOC
2. SOC -
Windows
3. SEAS IT
1. College and Athletics have several servers on the Oracle
RAC that could be affected by the network connection to the
BY PASS ROUTER. It has been agreed to that these servers
will be down for the duration of the network activity
2. IceMAIL services high profile users. It will be brought down
prior to the bypass and back up once the network is on bypass
3. SEAS IT will make the call and initiate action for their services
on File Shares: Spidy / Pparker
4. Hand Off to Network Team
4 Jun 4, 00:00 - 01:00AM
Enable Network
By Pass
Network
1. Enables network traffic to circumvent the cross data center
switching mechanism
2. Network Team connects the bypass and disconnects the VSS.
3. Network verifies traffic is transiting the bypass
4. Notify Server Teams when complete
5 Jun 4, 01:05 -03:00AM
1.Upgrade VSS
2. Bring up
services from #3
1.Network
2.SOC
1. Install and configure the VSS
2. Bring up services taken down prior to bypass implementation.
a. ICEmail
b. &TBD with services owners.
6 Jun 4, 03:10 - 4:10A Repeat #3 Same as #3 ● Same as #3
7 Jun 4, 4:15A - 4:45A
Reverse Network
ByPass
Network
Jun 4 Activity Sequencing -
60 Oxford DC Primary Switch Patch
13
When (Estimated) What Who Description
A Jun 4, 06:10 - 08:00 AM
Implement
Security
Software
Upgrade
Network
1. Maintain network connectivity
2. Upgrade back up devices, test, switch traffic
3. Upgrade primary device, test, switch traffic
4. Notify SOC
B Jun 4, 06:10 -08:00 AM
Test Apps that
were down
DBA, Self
Served
Customers
● Confirm applications are functioning normally
C Jun 4, 07:00 - 09:00 AM
Verify
Applications
DBAs,
Application
Teams
● Confirm applications are functioning normally
D Jun 4, 09:00 - 10:00 AM
Stabilization
Period
Network
● Communicate Activity Status
● Staff on site for one hour after last applicaition verification
● Continue to monitor maintenance channels
E Jun 4, 10:00 AM
Maintenance
Window Closes
Team
● Communicate “All Clear”
● Announce Window Closed
● Release Infrastructure & Network Staff
Communication Manager: Noah Selsby
Project Manager: Vicki Hall
Thank you!
Appendix
Since the last Service Delivery Subgroup on March 10th, the following
progress has been made against requested action items:
Project Update
16
Action Description Status Update/Next Steps
1. Schedule Weekly Executive
Check-ins
Schedule a weekly project check in with
the CTO and key project team members
Complete Scheduled weekly at 10:30AM
on Wednesdays
2. Produce and share list of
impacted Executive
leadership and Technical
leadership
Document the contact list for key
stakeholders and share with the Service
Delivery Subgroup
Complete Included as a hand-out
Distribution List built
3. Provide communication
mechanism for “day of”
transition mgmt
Identify and communicate formal
channels for reporting against the plan
during the maintenance window
Complete Plan to open bridges (partner
and technical) and send
emails throughout the
maintenance that align to
updates on the wiki
4. Meet with Support Services
to discuss outage planning
Initial meeting with Support Services to
review application impact and support
needs
Complete Confirm additional HelpDesk
resource needs based on
known application impact

More Related Content

What's hot

Powering Virtualization, Applications, and Data Center Transformation with Co...
Powering Virtualization, Applications, and Data Center Transformation with Co...Powering Virtualization, Applications, and Data Center Transformation with Co...
Powering Virtualization, Applications, and Data Center Transformation with Co...
Dell World
 
Recommended Design Considerations for Enterprise Monitoring
Recommended Design Considerations for Enterprise Monitoring Recommended Design Considerations for Enterprise Monitoring
Recommended Design Considerations for Enterprise Monitoring
Prolifics
 
Velostrata cloud migration --Whitepaper
Velostrata cloud migration --WhitepaperVelostrata cloud migration --Whitepaper
Velostrata cloud migration --Whitepaper
Abhishek Sood
 
Oracle: Building Cloud Native Applications
Oracle: Building Cloud Native ApplicationsOracle: Building Cloud Native Applications
Oracle: Building Cloud Native Applications
Kelly Goetsch
 
Cloud migration
Cloud migrationCloud migration
Cloud migration
ChahalDhilraj
 
Arcadia overview nr2
Arcadia overview nr2Arcadia overview nr2
Arcadia overview nr2
EU ARCADIA PROJECT
 
How ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDC
How ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDCHow ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDC
How ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDC
Veeva Systems
 
Suffering from “Franken” Monitoring?
Suffering from “Franken” Monitoring?Suffering from “Franken” Monitoring?
Suffering from “Franken” Monitoring?
Riverbed Technology
 
Using Vault eTMF Milestones and EDLs to Support Inspection Readiness
Using Vault eTMF Milestones and EDLs to Support Inspection ReadinessUsing Vault eTMF Milestones and EDLs to Support Inspection Readiness
Using Vault eTMF Milestones and EDLs to Support Inspection Readiness
Veeva Systems
 
Baby-Stepping Into the Cloud with Hybrid Workloads
Baby-Stepping Into the Cloud with Hybrid WorkloadsBaby-Stepping Into the Cloud with Hybrid Workloads
Baby-Stepping Into the Cloud with Hybrid Workloads
Christian Buckley
 
Agile DevOps Transformation Strategy
Agile DevOps Transformation StrategyAgile DevOps Transformation Strategy
Agile DevOps Transformation Strategy
Satish Nath
 
Arjun_Prathap_CV
Arjun_Prathap_CVArjun_Prathap_CV
Arjun_Prathap_CV
Arjun Prathap
 
DevOps in the Hybrid Cloud
DevOps in the Hybrid CloudDevOps in the Hybrid Cloud
DevOps in the Hybrid Cloud
Richard Irving
 
HPE ALM Octane | DevOps | Agile
HPE ALM Octane | DevOps | AgileHPE ALM Octane | DevOps | Agile
HPE ALM Octane | DevOps | Agile
Jeffrey Nunn
 
How NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOpsHow NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOps
Sanjeev Sharma
 
Datasheet.net pluginforrd
Datasheet.net pluginforrdDatasheet.net pluginforrd
Datasheet.net pluginforrd
MidVision
 
Immunomedics: Transforming TMF Operations
Immunomedics: Transforming TMF OperationsImmunomedics: Transforming TMF Operations
Immunomedics: Transforming TMF Operations
Veeva Systems
 
Deployment Strategy PowerPoint Presentation Slides
Deployment Strategy PowerPoint Presentation SlidesDeployment Strategy PowerPoint Presentation Slides
Deployment Strategy PowerPoint Presentation Slides
SlideTeam
 
Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...
Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...
Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...
Prolifics
 
A Disruptive Approach: Managing Dynamic Supply Chains
A Disruptive Approach: Managing Dynamic Supply Chains A Disruptive Approach: Managing Dynamic Supply Chains
A Disruptive Approach: Managing Dynamic Supply Chains
Pneuron
 

What's hot (20)

Powering Virtualization, Applications, and Data Center Transformation with Co...
Powering Virtualization, Applications, and Data Center Transformation with Co...Powering Virtualization, Applications, and Data Center Transformation with Co...
Powering Virtualization, Applications, and Data Center Transformation with Co...
 
Recommended Design Considerations for Enterprise Monitoring
Recommended Design Considerations for Enterprise Monitoring Recommended Design Considerations for Enterprise Monitoring
Recommended Design Considerations for Enterprise Monitoring
 
Velostrata cloud migration --Whitepaper
Velostrata cloud migration --WhitepaperVelostrata cloud migration --Whitepaper
Velostrata cloud migration --Whitepaper
 
Oracle: Building Cloud Native Applications
Oracle: Building Cloud Native ApplicationsOracle: Building Cloud Native Applications
Oracle: Building Cloud Native Applications
 
Cloud migration
Cloud migrationCloud migration
Cloud migration
 
Arcadia overview nr2
Arcadia overview nr2Arcadia overview nr2
Arcadia overview nr2
 
How ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDC
How ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDCHow ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDC
How ICON, Lotus, and Bioforum are Improving Study Efficiency with a Modern EDC
 
Suffering from “Franken” Monitoring?
Suffering from “Franken” Monitoring?Suffering from “Franken” Monitoring?
Suffering from “Franken” Monitoring?
 
Using Vault eTMF Milestones and EDLs to Support Inspection Readiness
Using Vault eTMF Milestones and EDLs to Support Inspection ReadinessUsing Vault eTMF Milestones and EDLs to Support Inspection Readiness
Using Vault eTMF Milestones and EDLs to Support Inspection Readiness
 
Baby-Stepping Into the Cloud with Hybrid Workloads
Baby-Stepping Into the Cloud with Hybrid WorkloadsBaby-Stepping Into the Cloud with Hybrid Workloads
Baby-Stepping Into the Cloud with Hybrid Workloads
 
Agile DevOps Transformation Strategy
Agile DevOps Transformation StrategyAgile DevOps Transformation Strategy
Agile DevOps Transformation Strategy
 
Arjun_Prathap_CV
Arjun_Prathap_CVArjun_Prathap_CV
Arjun_Prathap_CV
 
DevOps in the Hybrid Cloud
DevOps in the Hybrid CloudDevOps in the Hybrid Cloud
DevOps in the Hybrid Cloud
 
HPE ALM Octane | DevOps | Agile
HPE ALM Octane | DevOps | AgileHPE ALM Octane | DevOps | Agile
HPE ALM Octane | DevOps | Agile
 
How NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOpsHow NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOps
 
Datasheet.net pluginforrd
Datasheet.net pluginforrdDatasheet.net pluginforrd
Datasheet.net pluginforrd
 
Immunomedics: Transforming TMF Operations
Immunomedics: Transforming TMF OperationsImmunomedics: Transforming TMF Operations
Immunomedics: Transforming TMF Operations
 
Deployment Strategy PowerPoint Presentation Slides
Deployment Strategy PowerPoint Presentation SlidesDeployment Strategy PowerPoint Presentation Slides
Deployment Strategy PowerPoint Presentation Slides
 
Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...
Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...
Architecting and Tuning IIB/eXtreme Scale for Maximum Performance and Reliabi...
 
A Disruptive Approach: Managing Dynamic Supply Chains
A Disruptive Approach: Managing Dynamic Supply Chains A Disruptive Approach: Managing Dynamic Supply Chains
A Disruptive Approach: Managing Dynamic Supply Chains
 

Viewers also liked

Navigating saa s agreements
Navigating saa s agreementsNavigating saa s agreements
Navigating saa s agreements
kevin_donovan
 
Information security
Information securityInformation security
Information security
kevin_donovan
 
Standard i sites migration
Standard i sites migrationStandard i sites migration
Standard i sites migration
kevin_donovan
 
It summit 2014_migrating_applications_to_the_cloud-5
It summit 2014_migrating_applications_to_the_cloud-5It summit 2014_migrating_applications_to_the_cloud-5
It summit 2014_migrating_applications_to_the_cloud-5
margaret_ronald
 
Noc and soc deck
Noc and soc deckNoc and soc deck
Noc and soc deck
kevin_donovan
 
14.05.08 bcdr working_group_update
14.05.08 bcdr working_group_update14.05.08 bcdr working_group_update
14.05.08 bcdr working_group_update
kevin_donovan
 
Portal apps (slt)
Portal apps (slt)Portal apps (slt)
Portal apps (slt)
kevin_donovan
 
ESP POC Findings
ESP POC FindingsESP POC Findings
ESP POC Findings
kevin_donovan
 
14.05.08 network working_group_update
14.05.08 network working_group_update14.05.08 network working_group_update
14.05.08 network working_group_update
kevin_donovan
 
It summit facilitate-researchcomputing-mercecrosas
It summit facilitate-researchcomputing-mercecrosasIt summit facilitate-researchcomputing-mercecrosas
It summit facilitate-researchcomputing-mercecrosas
kevin_donovan
 
It academy
It academyIt academy
It academy
kevin_donovan
 
14.05.08 cloud dev_ops_working_group_update
14.05.08 cloud dev_ops_working_group_update14.05.08 cloud dev_ops_working_group_update
14.05.08 cloud dev_ops_working_group_update
kevin_donovan
 
Fas technology renewal
Fas technology renewalFas technology renewal
Fas technology renewal
kevin_donovan
 
Making the Case for UX
Making the Case for UXMaking the Case for UX
Making the Case for UX
HUXgroup
 
Harvard phone it summit demo 06.02.16
Harvard phone it summit demo 06.02.16Harvard phone it summit demo 06.02.16
Harvard phone it summit demo 06.02.16
kevin_donovan
 
Itsummit2015 blizzard
Itsummit2015 blizzardItsummit2015 blizzard
Itsummit2015 blizzard
kevin_donovan
 

Viewers also liked (16)

Navigating saa s agreements
Navigating saa s agreementsNavigating saa s agreements
Navigating saa s agreements
 
Information security
Information securityInformation security
Information security
 
Standard i sites migration
Standard i sites migrationStandard i sites migration
Standard i sites migration
 
It summit 2014_migrating_applications_to_the_cloud-5
It summit 2014_migrating_applications_to_the_cloud-5It summit 2014_migrating_applications_to_the_cloud-5
It summit 2014_migrating_applications_to_the_cloud-5
 
Noc and soc deck
Noc and soc deckNoc and soc deck
Noc and soc deck
 
14.05.08 bcdr working_group_update
14.05.08 bcdr working_group_update14.05.08 bcdr working_group_update
14.05.08 bcdr working_group_update
 
Portal apps (slt)
Portal apps (slt)Portal apps (slt)
Portal apps (slt)
 
ESP POC Findings
ESP POC FindingsESP POC Findings
ESP POC Findings
 
14.05.08 network working_group_update
14.05.08 network working_group_update14.05.08 network working_group_update
14.05.08 network working_group_update
 
It summit facilitate-researchcomputing-mercecrosas
It summit facilitate-researchcomputing-mercecrosasIt summit facilitate-researchcomputing-mercecrosas
It summit facilitate-researchcomputing-mercecrosas
 
It academy
It academyIt academy
It academy
 
14.05.08 cloud dev_ops_working_group_update
14.05.08 cloud dev_ops_working_group_update14.05.08 cloud dev_ops_working_group_update
14.05.08 cloud dev_ops_working_group_update
 
Fas technology renewal
Fas technology renewalFas technology renewal
Fas technology renewal
 
Making the Case for UX
Making the Case for UXMaking the Case for UX
Making the Case for UX
 
Harvard phone it summit demo 06.02.16
Harvard phone it summit demo 06.02.16Harvard phone it summit demo 06.02.16
Harvard phone it summit demo 06.02.16
 
Itsummit2015 blizzard
Itsummit2015 blizzardItsummit2015 blizzard
Itsummit2015 blizzard
 

Similar to Stakeholder update 4 14 data center outage

Data center outage project update
Data center outage project updateData center outage project update
Data center outage project update
kevin_donovan
 
IT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docxIT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docx
priestmanmable
 
Slide management project
Slide management projectSlide management project
Slide management project
theogrouptech
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
Captainsamcox
 
NSA Capstone Project III final pp
NSA Capstone Project III final ppNSA Capstone Project III final pp
NSA Capstone Project III final pp
Alfonso Zamorano
 
Management project
Management projectManagement project
Management project
gusfaleo firnando
 
Solution scope
Solution scopeSolution scope
Solution scope
Limen Spot
 
SMEUG 2006 - Project IBIS: ERP at UAE University
SMEUG 2006 - Project IBIS: ERP at UAE UniversitySMEUG 2006 - Project IBIS: ERP at UAE University
SMEUG 2006 - Project IBIS: ERP at UAE University
Michael Dobe, Ph.D.
 
Doc web milestone 1 report
Doc web milestone 1 report Doc web milestone 1 report
Doc web milestone 1 report
Stephen Cain Jr.
 
Project scheduler doc
Project scheduler docProject scheduler doc
Project scheduler doc
NAGENDRA KUAMR
 
News UK - Our Journey to Cloud
News UK - Our Journey to CloudNews UK - Our Journey to Cloud
News UK - Our Journey to Cloud
Amazon Web Services
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
seminiMaya
 
Introducing Events and Stream Processing into Nationwide Building Society
Introducing Events and Stream Processing into Nationwide Building SocietyIntroducing Events and Stream Processing into Nationwide Building Society
Introducing Events and Stream Processing into Nationwide Building Society
confluent
 
THEORY
THEORYTHEORY
THEORY
Ethan Cloete
 
Migration Report
Migration ReportMigration Report
Migration Report
William Baldwin
 
EPC Group's - Microsoft SharePoint Health Check Methodology
EPC Group's - Microsoft SharePoint Health Check MethodologyEPC Group's - Microsoft SharePoint Health Check Methodology
EPC Group's - Microsoft SharePoint Health Check Methodology
EPC Group
 
Advantage Energy Technology Data Center Migration—Part A.docx
Advantage Energy Technology Data Center Migration—Part A.docxAdvantage Energy Technology Data Center Migration—Part A.docx
Advantage Energy Technology Data Center Migration—Part A.docx
AMMY30
 
Application Migration from Pivotal Application Service to Anthos GKE on Prem
Application Migration from Pivotal Application Service to Anthos GKE on PremApplication Migration from Pivotal Application Service to Anthos GKE on Prem
Application Migration from Pivotal Application Service to Anthos GKE on Prem
DevOps Indonesia
 
43194352-Feasibility-study.ppt
43194352-Feasibility-study.ppt43194352-Feasibility-study.ppt
43194352-Feasibility-study.ppt
IsmathIqbal2
 
Ram kumar ok
Ram kumar okRam kumar ok
Ram kumar ok
kalpanadevarajan1
 

Similar to Stakeholder update 4 14 data center outage (20)

Data center outage project update
Data center outage project updateData center outage project update
Data center outage project update
 
IT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docxIT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docx
 
Slide management project
Slide management projectSlide management project
Slide management project
 
R squared weekly-status_03012010[1]
R squared  weekly-status_03012010[1]R squared  weekly-status_03012010[1]
R squared weekly-status_03012010[1]
 
NSA Capstone Project III final pp
NSA Capstone Project III final ppNSA Capstone Project III final pp
NSA Capstone Project III final pp
 
Management project
Management projectManagement project
Management project
 
Solution scope
Solution scopeSolution scope
Solution scope
 
SMEUG 2006 - Project IBIS: ERP at UAE University
SMEUG 2006 - Project IBIS: ERP at UAE UniversitySMEUG 2006 - Project IBIS: ERP at UAE University
SMEUG 2006 - Project IBIS: ERP at UAE University
 
Doc web milestone 1 report
Doc web milestone 1 report Doc web milestone 1 report
Doc web milestone 1 report
 
Project scheduler doc
Project scheduler docProject scheduler doc
Project scheduler doc
 
News UK - Our Journey to Cloud
News UK - Our Journey to CloudNews UK - Our Journey to Cloud
News UK - Our Journey to Cloud
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Introducing Events and Stream Processing into Nationwide Building Society
Introducing Events and Stream Processing into Nationwide Building SocietyIntroducing Events and Stream Processing into Nationwide Building Society
Introducing Events and Stream Processing into Nationwide Building Society
 
THEORY
THEORYTHEORY
THEORY
 
Migration Report
Migration ReportMigration Report
Migration Report
 
EPC Group's - Microsoft SharePoint Health Check Methodology
EPC Group's - Microsoft SharePoint Health Check MethodologyEPC Group's - Microsoft SharePoint Health Check Methodology
EPC Group's - Microsoft SharePoint Health Check Methodology
 
Advantage Energy Technology Data Center Migration—Part A.docx
Advantage Energy Technology Data Center Migration—Part A.docxAdvantage Energy Technology Data Center Migration—Part A.docx
Advantage Energy Technology Data Center Migration—Part A.docx
 
Application Migration from Pivotal Application Service to Anthos GKE on Prem
Application Migration from Pivotal Application Service to Anthos GKE on PremApplication Migration from Pivotal Application Service to Anthos GKE on Prem
Application Migration from Pivotal Application Service to Anthos GKE on Prem
 
43194352-Feasibility-study.ppt
43194352-Feasibility-study.ppt43194352-Feasibility-study.ppt
43194352-Feasibility-study.ppt
 
Ram kumar ok
Ram kumar okRam kumar ok
Ram kumar ok
 

More from kevin_donovan

It summit data mgmt-2016.06.02-final
It summit data mgmt-2016.06.02-finalIt summit data mgmt-2016.06.02-final
It summit data mgmt-2016.06.02-final
kevin_donovan
 
2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard
kevin_donovan
 
Fphs informatics for 2016 it summit 160531
Fphs informatics for 2016 it summit   160531Fphs informatics for 2016 it summit   160531
Fphs informatics for 2016 it summit 160531
kevin_donovan
 
It summit 2016_combined
It summit 2016_combinedIt summit 2016_combined
It summit 2016_combined
kevin_donovan
 
It summit dataverse-bigdata-mercecrosas
It summit dataverse-bigdata-mercecrosasIt summit dataverse-bigdata-mercecrosas
It summit dataverse-bigdata-mercecrosas
kevin_donovan
 
Hms crash planitsummit2016
Hms crash planitsummit2016Hms crash planitsummit2016
Hms crash planitsummit2016
kevin_donovan
 
Lightbox ham it_summit_final
Lightbox ham it_summit_finalLightbox ham it_summit_final
Lightbox ham it_summit_final
kevin_donovan
 
It summit salesforce
It summit salesforceIt summit salesforce
It summit salesforce
kevin_donovan
 
Harvard it summit 2016 - opencast in the cloud at harvard dce- live and on-d...
Harvard it summit 2016  - opencast in the cloud at harvard dce- live and on-d...Harvard it summit 2016  - opencast in the cloud at harvard dce- live and on-d...
Harvard it summit 2016 - opencast in the cloud at harvard dce- live and on-d...
kevin_donovan
 
Fa qs 2016-04-21
Fa qs 2016-04-21Fa qs 2016-04-21
Fa qs 2016-04-21
kevin_donovan
 
Tlt and friends it summit 2016
Tlt and friends it summit 2016Tlt and friends it summit 2016
Tlt and friends it summit 2016
kevin_donovan
 
2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard
kevin_donovan
 
Phish, flop, or fine
Phish, flop, or fine Phish, flop, or fine
Phish, flop, or fine
kevin_donovan
 
Waldo Summit 2016
Waldo Summit 2016Waldo Summit 2016
Waldo Summit 2016
kevin_donovan
 
IT Academy at IT Summti
IT Academy at IT SummtiIT Academy at IT Summti
IT Academy at IT Summti
kevin_donovan
 
Mobile firstpresentation huit
Mobile firstpresentation huitMobile firstpresentation huit
Mobile firstpresentation huit
kevin_donovan
 
Saving our social_media
Saving our social_mediaSaving our social_media
Saving our social_media
kevin_donovan
 
Urc it summit-2
Urc it summit-2Urc it summit-2
Urc it summit-2
kevin_donovan
 
Tlt success
Tlt successTlt success
Tlt success
kevin_donovan
 
Open housepix
Open housepixOpen housepix
Open housepix
kevin_donovan
 

More from kevin_donovan (20)

It summit data mgmt-2016.06.02-final
It summit data mgmt-2016.06.02-finalIt summit data mgmt-2016.06.02-final
It summit data mgmt-2016.06.02-final
 
2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard
 
Fphs informatics for 2016 it summit 160531
Fphs informatics for 2016 it summit   160531Fphs informatics for 2016 it summit   160531
Fphs informatics for 2016 it summit 160531
 
It summit 2016_combined
It summit 2016_combinedIt summit 2016_combined
It summit 2016_combined
 
It summit dataverse-bigdata-mercecrosas
It summit dataverse-bigdata-mercecrosasIt summit dataverse-bigdata-mercecrosas
It summit dataverse-bigdata-mercecrosas
 
Hms crash planitsummit2016
Hms crash planitsummit2016Hms crash planitsummit2016
Hms crash planitsummit2016
 
Lightbox ham it_summit_final
Lightbox ham it_summit_finalLightbox ham it_summit_final
Lightbox ham it_summit_final
 
It summit salesforce
It summit salesforceIt summit salesforce
It summit salesforce
 
Harvard it summit 2016 - opencast in the cloud at harvard dce- live and on-d...
Harvard it summit 2016  - opencast in the cloud at harvard dce- live and on-d...Harvard it summit 2016  - opencast in the cloud at harvard dce- live and on-d...
Harvard it summit 2016 - opencast in the cloud at harvard dce- live and on-d...
 
Fa qs 2016-04-21
Fa qs 2016-04-21Fa qs 2016-04-21
Fa qs 2016-04-21
 
Tlt and friends it summit 2016
Tlt and friends it summit 2016Tlt and friends it summit 2016
Tlt and friends it summit 2016
 
2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard2016 it summit_accessibility_2016-05-24_standard
2016 it summit_accessibility_2016-05-24_standard
 
Phish, flop, or fine
Phish, flop, or fine Phish, flop, or fine
Phish, flop, or fine
 
Waldo Summit 2016
Waldo Summit 2016Waldo Summit 2016
Waldo Summit 2016
 
IT Academy at IT Summti
IT Academy at IT SummtiIT Academy at IT Summti
IT Academy at IT Summti
 
Mobile firstpresentation huit
Mobile firstpresentation huitMobile firstpresentation huit
Mobile firstpresentation huit
 
Saving our social_media
Saving our social_mediaSaving our social_media
Saving our social_media
 
Urc it summit-2
Urc it summit-2Urc it summit-2
Urc it summit-2
 
Tlt success
Tlt successTlt success
Tlt success
 
Open housepix
Open housepixOpen housepix
Open housepix
 

Recently uploaded

writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
Nguyen Thanh Tu Collection
 
How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience
Wahiba Chair Training & Consulting
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
TechSoup
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
Priyankaranawat4
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
TechSoup
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
Israel Genealogy Research Association
 
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Diana Rendina
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
Nguyen Thanh Tu Collection
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
Celine George
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
Priyankaranawat4
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
imrankhan141184
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
Nguyen Thanh Tu Collection
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 

Recently uploaded (20)

writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
 
How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience How to Create a More Engaging and Human Online Learning Experience
How to Create a More Engaging and Human Online Learning Experience
 
Walmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdfWalmart Business+ and Spark Good for Nonprofits.pdf
Walmart Business+ and Spark Good for Nonprofits.pdf
 
clinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdfclinical examination of hip joint (1).pdf
clinical examination of hip joint (1).pdf
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Leveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit InnovationLeveraging Generative AI to Drive Nonprofit Innovation
Leveraging Generative AI to Drive Nonprofit Innovation
 
The Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collectionThe Diamonds of 2023-2024 in the IGRA collection
The Diamonds of 2023-2024 in the IGRA collection
 
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
Reimagining Your Library Space: How to Increase the Vibes in Your Library No ...
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
How to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 InventoryHow to Setup Warehouse & Location in Odoo 17 Inventory
How to Setup Warehouse & Location in Odoo 17 Inventory
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdfANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
ANATOMY AND BIOMECHANICS OF HIP JOINT.pdf
 
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
Traditional Musical Instruments of Arunachal Pradesh and Uttar Pradesh - RAYH...
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2023-2024 (CÓ FI...
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 

Stakeholder update 4 14 data center outage

  • 1. Data Center Network Preventative Maintenance (a.k.a DC Outage) June 4, 2016 Project Update April 14, 2016 Thursday 12:00 PM Lamont Library
  • 2. • Meeting Purpose and Intended Outcomes • Network Bypass Plan… • Netapp Solution Identified… • New Risk Identified… • Altered Approach… • Project Update • Next steps • Communication • Draft June 4 Plan 2 Agenda
  • 3. Purpose To provide an update on the current state of the project preparation activities and review of the communication plan for the scheduled data center network preventative maintenance (data center outage) on the weekend of June 4. Intended Outcomes • Provide an overview on the changes to the plan • Provide an update on the action items from the last Service Delivery Subgroup • Share next steps and actions • Provide an update on the communication approach • Share Draft “Day-of” Timeline Meeting Purpose and Intended Outcomes 3
  • 4. The goal is to maintain current service levels for data center networking and to avoid unplanned application outages. The plan was to accomplish this by temporarily changing network routing and migrating critical applications to non-impacted storage. Network Bypass Plan… 4 Current plan is to temporarily initiate a network bypass. This is key to avoiding application outages during the cross site switching system upgrade. This diagram represents at a high level view of HUIT DC Networks and the bypass router. Router
  • 5. The concept of migrating critical applications to non-impacted storage was abandoned as the amount of storage needed to implement the solution is significantly greater than the available Tier 1 storage. An alternative option to connect the VM environment directly to the NetApp, eliminating intermediate routing was identified, designed and tested. ● Eliminates the risk of VMs disconnecting from standard storage ● Eliminates the need to promote applications to Tier 1 storage for the maintenance ● Eliminates the need to take down the 60 Oxford Street VM Systems ● Is a permanent solution NetApp Solution identified… 5
  • 6. The team identified an additional risk to applications that use Oracle Real Application Cluster (RAC). ● Oracle RAC cannot tolerate more than 30sec network outage or it will reboot and may cause some of the applications to need to be restarted ● We have identified 2 production application servers at 60 Oxford that support several College and Athletics applications. These could potentially be impacted. ● We are working with the DBA, SOC and Application teams to identify appropriate preparation activities A New Risk Was Identified… 6
  • 7. The goal is to maintain current service levels for data center networking and to avoid unplanned application outages by temporarily changing by passing network routing and permanently implementing a network modification Altered Approach... 7 Router removed permanently Temporary
  • 8. Since the last Service Delivery Subgroup on April 7, the following progress has been made against requested action items: Project Update 8 Action Description Status Update/Next Steps 1. Investigate rearchitecting standard storage to server connectivity alternatives Investigate feasibility of creating a new network and moving impacted storage connected to the VM environment. Complete The routed network connected between the DC primary switch and the Netapp is being replace with a direct connection. 2. Contact vendors for on-site support Contact and schedule key vendors from EMC, NetApp, Cisco, and VMWare In progress EMC: Complete NetApp: In Progress Cisco: In Progress VMWare:In Progress 3. Schedule Vendor Pre-event Preparation meeting Bring all vendors on site to review our plans and activities for the event May Planning Underway 4. Contact ATS release management for impacted Enterprise Apps Work with Miroslav for ATS to coordinate release management for any impacted enterprise applications In progress Met with ATS team on March 14th. Next step is to share New Oracle RAC server impact list with College and Athletics
  • 9. Since the last Service Delivery Subgroup on March 24th, the following progress has been made against requested action items: Project Update 9 Action Description Status Update/Next Steps 5. Decommission FAS UNIX WebMail Decommission on premise environment of WebMail to prevent outage impact and retire legacy hardware (UC run project) In progress Underway 6. Identify mitigation for the ORACLE RAC impact Impact identified is to a few servers that support College and Athletics April Contact Diane Stronach to confirm previous ok to take down associated servers/applications. 7. Contact SEAS to determine action (SEAS manages servers) Discuss impact to Fileshares (p. parker and spidey) due to bypass network blip; potential for applications to freeze and need to be restarted April Contact SEAS Team to discuss 8. Determine communication path for ICEMAIL impacted users OPEN ITEM: At March 24 SD meeting the question of local departments communicating Jun 4 impact was raised Open Determine
  • 10. The following activities are the next steps in preparing for June 4 maintenance Next Steps 10 Action Description Status/Mitigation 1. Finalize scope of application shutdown (as required) 1. Create list of impacted, applications on the DC Oracle RACs and Virtual Guests at Summer St that are at risk during the by-pass connection and disconnection. Impact would cause a manually remount effort with is significant. 2. Identify application owners and determine strategy for Jun 4. (Likely: SEAS, Icemail, College & Athletics, others TBD) In progress (Target: April 22) 2. Review impact to Campus Services Understand impact and propose implementation support needs for building controls (if needed) In progress (Target: April) 3. Implement network solution that avoids 60 OX VM outage RISK Implement the connectivity between the Virtual Hosts (VMs) and the NetApp Storage - eliminating the risk of dropping VMs during the maintenance 90% Complete (End of April) 4. Finalize “day of” events action plan Create implementation sequence and complete full review of “day of” events. April 2016
  • 11. Communication Plan 11 Date Goal Audience Description of Communication March 7-11 HUIT Leadership Comm. SLT ● HUIT communication of new June date (HUIT Senior Leadership validates June date and provides feedback) April 5th Comm with Leaders inside and outside of HUIT to validate date of maintenance Leadership Across University ● Communication with Key Leaders who depend on HUIT services. Announce change and share communication powerpoint. ● List includes: School CIOs, HUIT Senior Leadership, Practice Managers, FAS/CA Major Stakeholders, Critical 1 & 2 application technical and functional owners. April 18th First Targeted Comm. Owners of: Servers Databases Applications ● Initial communication of targeted June date highlighting impact and details of maintenance ● Reference brown bag communication sessions April 12 - April 21 Stakeholder Brown Bag Sessions System owners / IT staff ● Brown Bag sessions for stakeholders ● Communicate with NetApp and fileshare technical contacts to determine availability impact and requirements April 19 “Day Of” Events System owners / IT staff ● Continue to receive feedback from stakeholders and business owners to fine-tune the “Day Of” events ● Share the “day of” plan April 28 Go-live Readiness SLT ● SLT final review and readiness validation for update May 3 - June 3 Weekly Reminders All populations ● Reminders sent to all populations June 4 All Clear Message Leadership/ System owners ● All clear message sent after maintenance is declared finished to business stakeholders and leadership vetting list. No all clear to full account holder populations unless clarification needed. March-April Engage Support Services HUIT Support Services ● Conduct working session with Support Services to outline coverage and needs during implementation This table represents the proposed communication plan to the community to inform them of the network change and potential impacts to applications and services
  • 12. Jun 4 Activity Sequencing - Network ByPass & VSS Upgrade 12 When (Estimated) What Who Description 1 Jun 3, 8:00 PM - 11:00 AM Prep Activities SOC & Self Service IT Partners 1. Shut down any Dev/Test/Other Services as Determined by Infrastructure Investigation and/or IT Client Request. 2. Self Managed IT Partners are welcome to shut down services in preparation for Network activity 3. Reschedule any impacted system back up 2 May 23 - Jun 3 Prep Activities Network 1. Prepare hardware, cable connections 2. Verify By-Pass Router Readiness 3. Hand Off to System’s Teams 3 Jun 3, 11:00 - 11:59PM Take Down: 1. C & A Apps on Oracle RAC 2. IceMAIL 3.SEAS Apps 1.DBAs, SOC 2. SOC - Windows 3. SEAS IT 1. College and Athletics have several servers on the Oracle RAC that could be affected by the network connection to the BY PASS ROUTER. It has been agreed to that these servers will be down for the duration of the network activity 2. IceMAIL services high profile users. It will be brought down prior to the bypass and back up once the network is on bypass 3. SEAS IT will make the call and initiate action for their services on File Shares: Spidy / Pparker 4. Hand Off to Network Team 4 Jun 4, 00:00 - 01:00AM Enable Network By Pass Network 1. Enables network traffic to circumvent the cross data center switching mechanism 2. Network Team connects the bypass and disconnects the VSS. 3. Network verifies traffic is transiting the bypass 4. Notify Server Teams when complete 5 Jun 4, 01:05 -03:00AM 1.Upgrade VSS 2. Bring up services from #3 1.Network 2.SOC 1. Install and configure the VSS 2. Bring up services taken down prior to bypass implementation. a. ICEmail b. &TBD with services owners. 6 Jun 4, 03:10 - 4:10A Repeat #3 Same as #3 ● Same as #3 7 Jun 4, 4:15A - 4:45A Reverse Network ByPass Network
  • 13. Jun 4 Activity Sequencing - 60 Oxford DC Primary Switch Patch 13 When (Estimated) What Who Description A Jun 4, 06:10 - 08:00 AM Implement Security Software Upgrade Network 1. Maintain network connectivity 2. Upgrade back up devices, test, switch traffic 3. Upgrade primary device, test, switch traffic 4. Notify SOC B Jun 4, 06:10 -08:00 AM Test Apps that were down DBA, Self Served Customers ● Confirm applications are functioning normally C Jun 4, 07:00 - 09:00 AM Verify Applications DBAs, Application Teams ● Confirm applications are functioning normally D Jun 4, 09:00 - 10:00 AM Stabilization Period Network ● Communicate Activity Status ● Staff on site for one hour after last applicaition verification ● Continue to monitor maintenance channels E Jun 4, 10:00 AM Maintenance Window Closes Team ● Communicate “All Clear” ● Announce Window Closed ● Release Infrastructure & Network Staff Communication Manager: Noah Selsby Project Manager: Vicki Hall
  • 16. Since the last Service Delivery Subgroup on March 10th, the following progress has been made against requested action items: Project Update 16 Action Description Status Update/Next Steps 1. Schedule Weekly Executive Check-ins Schedule a weekly project check in with the CTO and key project team members Complete Scheduled weekly at 10:30AM on Wednesdays 2. Produce and share list of impacted Executive leadership and Technical leadership Document the contact list for key stakeholders and share with the Service Delivery Subgroup Complete Included as a hand-out Distribution List built 3. Provide communication mechanism for “day of” transition mgmt Identify and communicate formal channels for reporting against the plan during the maintenance window Complete Plan to open bridges (partner and technical) and send emails throughout the maintenance that align to updates on the wiki 4. Meet with Support Services to discuss outage planning Initial meeting with Support Services to review application impact and support needs Complete Confirm additional HelpDesk resource needs based on known application impact