The document provides an update on the planned preventative maintenance for the data center network on June 4, 2016. The original plan to temporarily reroute network traffic and migrate applications to alternate storage has been altered. The new approach will permanently implement a direct network connection between virtual machines and storage, avoiding any potential outages. Next steps include finalizing the list of impacted applications and communication efforts to inform stakeholders of the changes and potential impacts. A detailed timeline is provided outlining the sequence of activities planned for the maintenance window.