SlideShare a Scribd company logo
1 of 6
Continental Migration Review
1
I
Legg Company Migration after action Report
Project Name: Migration Report
Prepared by: William Baldwin
Date (MM/DD/YYYY): 03/20/2014
Version History (insertrows as needed):
Version Date
(MM/DD/YYYY)
Comments
1.0 03/20/2014 Initial creation
Contents
1. Executive Summary........................................................................................................... 2
2. Project Objectives .............................................................................................................. 2
3. Project Description............................................................................................................. 2
For each area below, provide sufficient detail to define this project adequately: ................. 2
3.1 Project Scope.................................................................................................................... 2
4. Project Milestones.............................................................................................................. 5
5. Authorizations (Modify lists as needed) ........................................................................... 6
Continental Migration Review
2
1. Executive Summary
Provide below a briefoverview of this project(e.g., projectpurpose and justification):
Provide an understanding of the elements necessary for the migration of the Legg Company Technology
Infrastructure to the Continental technology standards. This report is for potential assistance for other
sites for historical reference and understandings of possible items necessary for new implementation and
resolutions utilized by this site for its project completion.
2. Project Objectives
2.1 Project Description (Solution):
Implementation of Technology Infrastructure of Legg Company Inc
2.2 Business Objectives:
The overall objectives of the Migration was to modify the current technological infrastructure to a
solution acceptable to Continental standards in its day to day information technology standards:
 Implementation of new HP Desktops  Laptops devices with standardized software loads and services
 Modification of current networking mapping from servers,switches, and proxy solution.
 Modification of imaging services (printers) and solutions.
 Provide customer understanding of changes of technology business processes for new environment.
 Identify legacy non-standard software requirements and problem resolution of migration effort.
 Implementation of new communicationemail software solution and retirement of existing email
environment.
3. Project Description
For each area below,provide sufficient detail to define this project adequately:
3.1 Project Scope
The current Legg Company network and computing devices are identified for replacement to the new
Continental structure. Work will include, but not be limited to:
Continental Migration Review
3
3. Project Description
A. Computing:
1. Identification of non-standard software on computing devices and configurations
2. Identification of computing requirements vs business requirements for employee work
requirements (hardware performancesoftware specifications)
3. Hardware replacement of computing devices, printers, as necessary.
a. Reimage of legacy hardware for resale or donation
b. Software inventory for reuse, resale,or donation
c. Ordering and placement of new devices.
d. HPAM (training)  adding new devices to HPAM
e. HPSM (training)
f. Active Directory Training.
g. QIP (Training)
B. Networking:
1. User Security and account creation.
a. User accounts
b. Group accounts (Tandem with File server process)
c. Service Accounts
2. Implementation/Addition of Proxy Server (K82C201A)
a. Configuration with Contitech Admin personnel
3. Implementation/Addition of File Server (K8FS001)
a. Old server migration plan
b. Identification of files for transfer
c. File security process
d. New identified File structure
e. Cutover plan (Network Trust? / added 2nd
network card)
4. Implementation/Addition of Print Server (K8PS001)
a. Creation of print queues for network printers (print drivers)
b. Identification of direct attached devices and retirement plan (application association with
direct attached printers, legacy programs, UPS device)
5. Implementation /Addition of Domino/Lotus Notes Server (K8LC001/K8LC002)
a. Configuration with Domino team
b. Identification of storage space for new mail server
c. iNotes setup
d. Afaria (phone) ACL access with new server
e. Cutover plan (transition of mail, vendorcustomer notification, user notification, user
training, migration plan, achieving of existing mail)
f. Mail accounts requests (Individual, Group, Distribution lists)
6. Company Website
a. Contitech control of hosting and web services. Registration.
3.2 Project Completion Criteria:
Continental Migration Review
4
3. Project Description
Document, Design, Implementation, and Maintenance:
Document (Phase 1):
 Current Network architecture Infrastructure
 Hardware devices (Computers, Printers, Faxes, Switches, Servers, Wireless Access Points),
accessibility, and requirement
 Users accounts, access rights, roles, responsibilities
 Building layouts, device locations, power locations, network locations
Design (Phase 2)
 Modification of existing network architecture. (New cabling, channeling, plug-ins.
 Identify necessary replacement solutions for:
Computing
Printing
MFP (Multi-Function Printing)
Switches
Servers
Server room re-modification or replacement
Wireless Access Points
Network cabling
 Define new Workgroups model for data access rights and roles
 Define new File Server architecture, project groups, mailbox groups,
 Validate Network layouts, device migration plan, phase model, communication plan, mail
changeover plan
 Phone server plans, Notes mail accounts, ACL (Access Control List request prep for Notes)
Implementation (Phase 3)
 Training for personnel (Office, Administration, Production)
 Ongoing maintenance process
- Scheduling server updates
- PC updates
- Phase out of legacy technology equipment
 Communication processes (Continental – standards?)
- Intercompany communication
- Mail address change notification to vendors, distributors, retiring old mail server
- Use r ticketing or technology request process
 Physical change out of hardware (PCs, printing, switches, WAP, technology devices)
 New networking drops for potential network restructure
 Establishment of Technology responsibility list (Service groups mail, phone, contact support,
SLA)
 Establishment of T-Systems setup for network VPN connectivity to Continental and fail over.
3.3 External Dependencies:
Continental Migration Review
5
3. Project Description
Customer requirements and approval
External Support
- Lotus Notes Administration
- Proxy Server Administration
- T-Systems Administration
3.4 Assumptions:
3.5 Constraints:
4. Project Milestones
Estimated Schedules – List key projectmilestones relative to project start. (Insert rowsas needed)
Project Milestone Target Date
(MM/DD/YYYY)
Project Start (LTFP Phase) 08/01/2014
PC Change out 02/21/2014
Lotus Email System setup (accounts,groups established) 03/01/2012
MS Exchange Sever (Legacy) mail forwarded to new accounts 03/01/2014
Training Users on Lotus Notes Mail, Training videos, etc..
MS Exchange Server (Legacy) ports disabled (Sunsetlegacymail server) 08/29/2014
Legacy PCs wiped,sold,destroyed 06/01/2014
T-Systems Implementation
ImplementHPSMTicketing System
5. Project Issues
Identification Conflicts – List projectissues relative to projecttimeline.(Insertrows as needed)
Project Issues Target Date
(MM/DD/YYYY)
Project Start (LTFP Phase) 08/01/2014
Network lines notworking after new VPN network established 02/21/2014
File Server Security violations – Delay in permissions picked up allowing users to
access files notauthorized to them. Accounting information.
02/21/2014
File mapping ofcommon work processes were broken and new links had to be
established.
02/21/2014
Lotus Notes Server administration failed to complete prior to migration ofnetwork. 02/23/2014
Continental Migration Review
6
5. Project Issues
Setup redundantserver in Hungry to maintain email operations.Created overburden
Server in Hungry due to added latency.
Communication notpassed to all employees bymanagementofactivities even though
placards were posted ofevent.
02/21/2014
Legacy File Server structure in poor organization.Forced implementation ofnew
structure withoutopportunity to discuss with all state holders
02/21/2014
T-Systems Implementation was notthoroughlycommunicated to local IT and would
often have stage implementation happening with no advanced notice
02/30 – 06/30
Users adaptation to new mail system created unwanted challenges 02/21/2014
Server Trustunable to be approved requiring multiple facets ofmaintaining existing
legacy network servers and operations and processes
02/21/2014
Employees attempting to access old network file systems rather than using new
network file server creating data file integrity issues
02/30/2014
Exchange mail system was notassumed byContinental to create a proper file
forwarding process.Work around to file forwarding had to be implemented
02/21/2014
Local IT inexperienced (still learning work processes) with Continental operations and
provided insufficientresponsibilitycontactlist for conflictresolution.
02/30/2014
6. Authorizations (Modify lists as needed)
Project performance baseline changes will be approved by the:
 William Baldwin
 Jan Faerber
Project deliverableswill be approved/accepted by the:
 William Baldwin

More Related Content

What's hot

Robert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 LnkedinRobert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 LnkedinBob Hensel
 
Db2 analytics accelerator technical update
Db2 analytics accelerator  technical updateDb2 analytics accelerator  technical update
Db2 analytics accelerator technical updateCuneyt Goksu
 
Lotus Admin Training Part II
Lotus Admin Training Part IILotus Admin Training Part II
Lotus Admin Training Part IISanjaya K Saxena
 
Topic 4 database recovery
Topic 4 database recoveryTopic 4 database recovery
Topic 4 database recoveryacap paei
 
Eliminate the Risk from Your IMS to Db2 Plans
Eliminate the Risk from Your IMS to Db2 PlansEliminate the Risk from Your IMS to Db2 Plans
Eliminate the Risk from Your IMS to Db2 PlansPrecisely
 
DB2 pureScale Overview Sept 2010
DB2 pureScale Overview Sept 2010DB2 pureScale Overview Sept 2010
DB2 pureScale Overview Sept 2010Laura Hood
 
A Three Step Approach to Low-Risk IMS Modernization
A Three Step Approach to Low-Risk IMS ModernizationA Three Step Approach to Low-Risk IMS Modernization
A Three Step Approach to Low-Risk IMS ModernizationPrecisely
 
The unified data center for cloud david yen
The unified data center for cloud david yenThe unified data center for cloud david yen
The unified data center for cloud david yendeepersnet
 

What's hot (11)

Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Robert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 LnkedinRobert Hensel resume v111416 Lnkedin
Robert Hensel resume v111416 Lnkedin
 
Db2 analytics accelerator technical update
Db2 analytics accelerator  technical updateDb2 analytics accelerator  technical update
Db2 analytics accelerator technical update
 
Lotus Admin Training Part II
Lotus Admin Training Part IILotus Admin Training Part II
Lotus Admin Training Part II
 
Topic 4 database recovery
Topic 4 database recoveryTopic 4 database recovery
Topic 4 database recovery
 
Eliminate the Risk from Your IMS to Db2 Plans
Eliminate the Risk from Your IMS to Db2 PlansEliminate the Risk from Your IMS to Db2 Plans
Eliminate the Risk from Your IMS to Db2 Plans
 
Osac2012
Osac2012Osac2012
Osac2012
 
DB2 pureScale Overview Sept 2010
DB2 pureScale Overview Sept 2010DB2 pureScale Overview Sept 2010
DB2 pureScale Overview Sept 2010
 
A Three Step Approach to Low-Risk IMS Modernization
A Three Step Approach to Low-Risk IMS ModernizationA Three Step Approach to Low-Risk IMS Modernization
A Three Step Approach to Low-Risk IMS Modernization
 
The unified data center for cloud david yen
The unified data center for cloud david yenThe unified data center for cloud david yen
The unified data center for cloud david yen
 
IMSDB - DBRC
IMSDB - DBRCIMSDB - DBRC
IMSDB - DBRC
 

Viewers also liked

50 States Survey Complete with Notes 7-061
50 States Survey Complete with Notes 7-06150 States Survey Complete with Notes 7-061
50 States Survey Complete with Notes 7-061Abby Ruskey
 
comprehensive_ee_article_final_2.24_sm.2
comprehensive_ee_article_final_2.24_sm.2comprehensive_ee_article_final_2.24_sm.2
comprehensive_ee_article_final_2.24_sm.2Abby Ruskey
 
Earth Day 1990 grades 7-12 curriculum
Earth Day 1990 grades 7-12 curriculumEarth Day 1990 grades 7-12 curriculum
Earth Day 1990 grades 7-12 curriculumAbby Ruskey
 
WA ESLP Final July 29.2011
WA ESLP Final July 29.2011WA ESLP Final July 29.2011
WA ESLP Final July 29.2011Abby Ruskey
 
LC_Article_7-18-06.1.1
LC_Article_7-18-06.1.1LC_Article_7-18-06.1.1
LC_Article_7-18-06.1.1Abby Ruskey
 
Vestige cnt presentation in Hindi (Latest)
Vestige cnt presentation in Hindi (Latest)Vestige cnt presentation in Hindi (Latest)
Vestige cnt presentation in Hindi (Latest)Keshav Kumar Singh
 
Earth Day 1990 K-6 Curriculum
Earth Day 1990 K-6 CurriculumEarth Day 1990 K-6 Curriculum
Earth Day 1990 K-6 CurriculumAbby Ruskey
 
Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)
Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)
Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)Keshav Kumar Singh
 
Vestige Updated CNT Presentation by Glorious Team
Vestige Updated CNT Presentation by Glorious TeamVestige Updated CNT Presentation by Glorious Team
Vestige Updated CNT Presentation by Glorious TeamKeshav Kumar Singh
 
Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043
Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043
Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043Keshav Kumar Singh
 
Vestige CNT By Keshav Kumar Singh (Glorious Team) In Hindi
Vestige CNT By Keshav Kumar Singh (Glorious Team) In HindiVestige CNT By Keshav Kumar Singh (Glorious Team) In Hindi
Vestige CNT By Keshav Kumar Singh (Glorious Team) In HindiKeshav Kumar Singh
 

Viewers also liked (14)

Espinoza
EspinozaEspinoza
Espinoza
 
50 States Survey Complete with Notes 7-061
50 States Survey Complete with Notes 7-06150 States Survey Complete with Notes 7-061
50 States Survey Complete with Notes 7-061
 
comprehensive_ee_article_final_2.24_sm.2
comprehensive_ee_article_final_2.24_sm.2comprehensive_ee_article_final_2.24_sm.2
comprehensive_ee_article_final_2.24_sm.2
 
Earth Day 1990 grades 7-12 curriculum
Earth Day 1990 grades 7-12 curriculumEarth Day 1990 grades 7-12 curriculum
Earth Day 1990 grades 7-12 curriculum
 
WA ESLP Final July 29.2011
WA ESLP Final July 29.2011WA ESLP Final July 29.2011
WA ESLP Final July 29.2011
 
HSVGrant
HSVGrantHSVGrant
HSVGrant
 
LC_Article_7-18-06.1.1
LC_Article_7-18-06.1.1LC_Article_7-18-06.1.1
LC_Article_7-18-06.1.1
 
Vestige cnt presentation in Hindi (Latest)
Vestige cnt presentation in Hindi (Latest)Vestige cnt presentation in Hindi (Latest)
Vestige cnt presentation in Hindi (Latest)
 
Earth Day 1990 K-6 Curriculum
Earth Day 1990 K-6 CurriculumEarth Day 1990 K-6 Curriculum
Earth Day 1990 K-6 Curriculum
 
Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)
Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)
Vestige CNT in Hindi By Keshav Kumar Singh (Glorious Team)
 
Vestige Updated CNT Presentation by Glorious Team
Vestige Updated CNT Presentation by Glorious TeamVestige Updated CNT Presentation by Glorious Team
Vestige Updated CNT Presentation by Glorious Team
 
Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043
Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043
Vestige CNT latest presentation by Glorious Team (Delhi) 09990567043
 
Vestige CNT By Keshav Kumar Singh (Glorious Team) In Hindi
Vestige CNT By Keshav Kumar Singh (Glorious Team) In HindiVestige CNT By Keshav Kumar Singh (Glorious Team) In Hindi
Vestige CNT By Keshav Kumar Singh (Glorious Team) In Hindi
 
Dubraska_Nunez
Dubraska_NunezDubraska_Nunez
Dubraska_Nunez
 

Similar to Legg Company Migration Report Summary

2232016 Sample Implementation Plan1.htmlfileCUsers.docx
2232016 Sample Implementation Plan1.htmlfileCUsers.docx2232016 Sample Implementation Plan1.htmlfileCUsers.docx
2232016 Sample Implementation Plan1.htmlfileCUsers.docxeugeniadean34240
 
Initiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case StudiesInitiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case Studieschanderdw
 
Merger and Acquisition and Office 365
Merger and Acquisition and Office 365Merger and Acquisition and Office 365
Merger and Acquisition and Office 365Thomas Stensitzki
 
ops300 Project(3)
ops300 Project(3)ops300 Project(3)
ops300 Project(3)trayyoo
 
ops300 Project(4)
ops300 Project(4)ops300 Project(4)
ops300 Project(4)trayyoo
 
Fidel Ramirez Resume
Fidel Ramirez ResumeFidel Ramirez Resume
Fidel Ramirez ResumeFidel Ramirez
 
Fidel Ramirez Resume
Fidel Ramirez ResumeFidel Ramirez Resume
Fidel Ramirez ResumeFidel Ramirez
 
Windows Server Virtualization
Windows Server VirtualizationWindows Server Virtualization
Windows Server Virtualizationwebhostingguy
 
Windows Server Virtualization
Windows Server VirtualizationWindows Server Virtualization
Windows Server Virtualizationwebhostingguy
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt projectSamehTeleb
 
Evolution of Big Data Messaging
Evolution of Big Data Messaging Evolution of Big Data Messaging
Evolution of Big Data Messaging Kartik Paramasivam
 
SUBRAT KUMAR THATOI -
SUBRAT KUMAR THATOI -SUBRAT KUMAR THATOI -
SUBRAT KUMAR THATOI -Subrat Thatoi
 
IT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docxIT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docxpriestmanmable
 
PowerPoint PresentationThis section will include an online pre.docx
PowerPoint PresentationThis section will include an online pre.docxPowerPoint PresentationThis section will include an online pre.docx
PowerPoint PresentationThis section will include an online pre.docxChantellPantoja184
 
Project DescriptionThe new computer-controlled conveyor belt is .docx
Project DescriptionThe new computer-controlled conveyor belt is .docxProject DescriptionThe new computer-controlled conveyor belt is .docx
Project DescriptionThe new computer-controlled conveyor belt is .docxbriancrawford30935
 
Client server technology main
Client server technology mainClient server technology main
Client server technology mainAnwar Kamal
 

Similar to Legg Company Migration Report Summary (20)

2232016 Sample Implementation Plan1.htmlfileCUsers.docx
2232016 Sample Implementation Plan1.htmlfileCUsers.docx2232016 Sample Implementation Plan1.htmlfileCUsers.docx
2232016 Sample Implementation Plan1.htmlfileCUsers.docx
 
Initiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case StudiesInitiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case Studies
 
Merger and Acquisition and Office 365
Merger and Acquisition and Office 365Merger and Acquisition and Office 365
Merger and Acquisition and Office 365
 
ops300 Project(3)
ops300 Project(3)ops300 Project(3)
ops300 Project(3)
 
ops300 Project(4)
ops300 Project(4)ops300 Project(4)
ops300 Project(4)
 
DocNmbr_0030 AIG
DocNmbr_0030 AIGDocNmbr_0030 AIG
DocNmbr_0030 AIG
 
Fidel Ramirez Resume
Fidel Ramirez ResumeFidel Ramirez Resume
Fidel Ramirez Resume
 
Fidel Ramirez Resume
Fidel Ramirez ResumeFidel Ramirez Resume
Fidel Ramirez Resume
 
Windows Server Virtualization
Windows Server VirtualizationWindows Server Virtualization
Windows Server Virtualization
 
Windows Server Virtualization
Windows Server VirtualizationWindows Server Virtualization
Windows Server Virtualization
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
Neeraj_PM
Neeraj_PMNeeraj_PM
Neeraj_PM
 
Evolution of Big Data Messaging
Evolution of Big Data Messaging Evolution of Big Data Messaging
Evolution of Big Data Messaging
 
SUBRAT KUMAR THATOI -
SUBRAT KUMAR THATOI -SUBRAT KUMAR THATOI -
SUBRAT KUMAR THATOI -
 
Resume_Tarun
Resume_TarunResume_Tarun
Resume_Tarun
 
IT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docxIT327-1404A-01 Implementing, Managing and Mainta.docx
IT327-1404A-01 Implementing, Managing and Mainta.docx
 
PowerPoint PresentationThis section will include an online pre.docx
PowerPoint PresentationThis section will include an online pre.docxPowerPoint PresentationThis section will include an online pre.docx
PowerPoint PresentationThis section will include an online pre.docx
 
Project DescriptionThe new computer-controlled conveyor belt is .docx
Project DescriptionThe new computer-controlled conveyor belt is .docxProject DescriptionThe new computer-controlled conveyor belt is .docx
Project DescriptionThe new computer-controlled conveyor belt is .docx
 
Client server technology main
Client server technology mainClient server technology main
Client server technology main
 
Module 1
Module 1Module 1
Module 1
 

Legg Company Migration Report Summary

  • 1. Continental Migration Review 1 I Legg Company Migration after action Report Project Name: Migration Report Prepared by: William Baldwin Date (MM/DD/YYYY): 03/20/2014 Version History (insertrows as needed): Version Date (MM/DD/YYYY) Comments 1.0 03/20/2014 Initial creation Contents 1. Executive Summary........................................................................................................... 2 2. Project Objectives .............................................................................................................. 2 3. Project Description............................................................................................................. 2 For each area below, provide sufficient detail to define this project adequately: ................. 2 3.1 Project Scope.................................................................................................................... 2 4. Project Milestones.............................................................................................................. 5 5. Authorizations (Modify lists as needed) ........................................................................... 6
  • 2. Continental Migration Review 2 1. Executive Summary Provide below a briefoverview of this project(e.g., projectpurpose and justification): Provide an understanding of the elements necessary for the migration of the Legg Company Technology Infrastructure to the Continental technology standards. This report is for potential assistance for other sites for historical reference and understandings of possible items necessary for new implementation and resolutions utilized by this site for its project completion. 2. Project Objectives 2.1 Project Description (Solution): Implementation of Technology Infrastructure of Legg Company Inc 2.2 Business Objectives: The overall objectives of the Migration was to modify the current technological infrastructure to a solution acceptable to Continental standards in its day to day information technology standards:  Implementation of new HP Desktops Laptops devices with standardized software loads and services  Modification of current networking mapping from servers,switches, and proxy solution.  Modification of imaging services (printers) and solutions.  Provide customer understanding of changes of technology business processes for new environment.  Identify legacy non-standard software requirements and problem resolution of migration effort.  Implementation of new communicationemail software solution and retirement of existing email environment. 3. Project Description For each area below,provide sufficient detail to define this project adequately: 3.1 Project Scope The current Legg Company network and computing devices are identified for replacement to the new Continental structure. Work will include, but not be limited to:
  • 3. Continental Migration Review 3 3. Project Description A. Computing: 1. Identification of non-standard software on computing devices and configurations 2. Identification of computing requirements vs business requirements for employee work requirements (hardware performancesoftware specifications) 3. Hardware replacement of computing devices, printers, as necessary. a. Reimage of legacy hardware for resale or donation b. Software inventory for reuse, resale,or donation c. Ordering and placement of new devices. d. HPAM (training) adding new devices to HPAM e. HPSM (training) f. Active Directory Training. g. QIP (Training) B. Networking: 1. User Security and account creation. a. User accounts b. Group accounts (Tandem with File server process) c. Service Accounts 2. Implementation/Addition of Proxy Server (K82C201A) a. Configuration with Contitech Admin personnel 3. Implementation/Addition of File Server (K8FS001) a. Old server migration plan b. Identification of files for transfer c. File security process d. New identified File structure e. Cutover plan (Network Trust? / added 2nd network card) 4. Implementation/Addition of Print Server (K8PS001) a. Creation of print queues for network printers (print drivers) b. Identification of direct attached devices and retirement plan (application association with direct attached printers, legacy programs, UPS device) 5. Implementation /Addition of Domino/Lotus Notes Server (K8LC001/K8LC002) a. Configuration with Domino team b. Identification of storage space for new mail server c. iNotes setup d. Afaria (phone) ACL access with new server e. Cutover plan (transition of mail, vendorcustomer notification, user notification, user training, migration plan, achieving of existing mail) f. Mail accounts requests (Individual, Group, Distribution lists) 6. Company Website a. Contitech control of hosting and web services. Registration. 3.2 Project Completion Criteria:
  • 4. Continental Migration Review 4 3. Project Description Document, Design, Implementation, and Maintenance: Document (Phase 1):  Current Network architecture Infrastructure  Hardware devices (Computers, Printers, Faxes, Switches, Servers, Wireless Access Points), accessibility, and requirement  Users accounts, access rights, roles, responsibilities  Building layouts, device locations, power locations, network locations Design (Phase 2)  Modification of existing network architecture. (New cabling, channeling, plug-ins.  Identify necessary replacement solutions for: Computing Printing MFP (Multi-Function Printing) Switches Servers Server room re-modification or replacement Wireless Access Points Network cabling  Define new Workgroups model for data access rights and roles  Define new File Server architecture, project groups, mailbox groups,  Validate Network layouts, device migration plan, phase model, communication plan, mail changeover plan  Phone server plans, Notes mail accounts, ACL (Access Control List request prep for Notes) Implementation (Phase 3)  Training for personnel (Office, Administration, Production)  Ongoing maintenance process - Scheduling server updates - PC updates - Phase out of legacy technology equipment  Communication processes (Continental – standards?) - Intercompany communication - Mail address change notification to vendors, distributors, retiring old mail server - Use r ticketing or technology request process  Physical change out of hardware (PCs, printing, switches, WAP, technology devices)  New networking drops for potential network restructure  Establishment of Technology responsibility list (Service groups mail, phone, contact support, SLA)  Establishment of T-Systems setup for network VPN connectivity to Continental and fail over. 3.3 External Dependencies:
  • 5. Continental Migration Review 5 3. Project Description Customer requirements and approval External Support - Lotus Notes Administration - Proxy Server Administration - T-Systems Administration 3.4 Assumptions: 3.5 Constraints: 4. Project Milestones Estimated Schedules – List key projectmilestones relative to project start. (Insert rowsas needed) Project Milestone Target Date (MM/DD/YYYY) Project Start (LTFP Phase) 08/01/2014 PC Change out 02/21/2014 Lotus Email System setup (accounts,groups established) 03/01/2012 MS Exchange Sever (Legacy) mail forwarded to new accounts 03/01/2014 Training Users on Lotus Notes Mail, Training videos, etc.. MS Exchange Server (Legacy) ports disabled (Sunsetlegacymail server) 08/29/2014 Legacy PCs wiped,sold,destroyed 06/01/2014 T-Systems Implementation ImplementHPSMTicketing System 5. Project Issues Identification Conflicts – List projectissues relative to projecttimeline.(Insertrows as needed) Project Issues Target Date (MM/DD/YYYY) Project Start (LTFP Phase) 08/01/2014 Network lines notworking after new VPN network established 02/21/2014 File Server Security violations – Delay in permissions picked up allowing users to access files notauthorized to them. Accounting information. 02/21/2014 File mapping ofcommon work processes were broken and new links had to be established. 02/21/2014 Lotus Notes Server administration failed to complete prior to migration ofnetwork. 02/23/2014
  • 6. Continental Migration Review 6 5. Project Issues Setup redundantserver in Hungry to maintain email operations.Created overburden Server in Hungry due to added latency. Communication notpassed to all employees bymanagementofactivities even though placards were posted ofevent. 02/21/2014 Legacy File Server structure in poor organization.Forced implementation ofnew structure withoutopportunity to discuss with all state holders 02/21/2014 T-Systems Implementation was notthoroughlycommunicated to local IT and would often have stage implementation happening with no advanced notice 02/30 – 06/30 Users adaptation to new mail system created unwanted challenges 02/21/2014 Server Trustunable to be approved requiring multiple facets ofmaintaining existing legacy network servers and operations and processes 02/21/2014 Employees attempting to access old network file systems rather than using new network file server creating data file integrity issues 02/30/2014 Exchange mail system was notassumed byContinental to create a proper file forwarding process.Work around to file forwarding had to be implemented 02/21/2014 Local IT inexperienced (still learning work processes) with Continental operations and provided insufficientresponsibilitycontactlist for conflictresolution. 02/30/2014 6. Authorizations (Modify lists as needed) Project performance baseline changes will be approved by the:  William Baldwin  Jan Faerber Project deliverableswill be approved/accepted by the:  William Baldwin