SlideShare a Scribd company logo
HANGING – OFF AN ANCHOR
PURPOSE OF OPERATION:
To remove the anchor out of the hawse pipe and enable the vessel to be moored to a buoy or towed using the
anchor chain through the hawse pipe.
MATERIALS REQUIRED FOR A 10 TONNE ANCHOR:
1. 3 Nos of 30 mm wire (SWL 6.0 tonnes) – For 1st
Easing wire
2nd
Easing wire
Preventer wire
2. shackles with SWL of 6 tonnes
3. Other tools required to carry out the operation as per normal seamanship practices.
SEQUENCE OF OPERATION:
1. Walk back the anchor clear of the hawse pipe.
2. Secure one end of the 1st
easing wire on the mooring bit.
3. Pass the other end through the panama lead, through the anchor crown D shackle (as a bight) and back
through the Panama lead on to the warping drum of the windlass.
4. Rig a preventer wire (as a bight) through the anchor crown D shackle, pass it through the fairlead well
forward and secure it on the mooring bits.
5. Ensure there is sufficient slack on the preventer wire.
6. Slack on the anchor chain until the preventer becomes taut and the 1st
easing wire is up and down and the
anchor is under the shoulder.
7. Continue to walk back the chain until the next joining shackle is on the deck.
8. Heave on the 1st
easing wire and secure the anchor in the up and down position.
9. Rig up the 2nd
easing wire forward of the joining shackle (on a bight) and take up the weight of the chain.
10. Break the joining shackle.
11. Walk back the 2nd
easing wire to bring the end of the cable clear of the hawse pipe.
12. Recover this end of the cable using rope hawsers through the Panama lead.
13. Now walk back the anchor chain through the hawse pipe and the cable is now ready for towing or mooring
operation.
MEDITERRANEAN MOOR
PURPOSE:
When the quay space is restricted and it is required to berth several vessels or when a stern discharge/loading is
required, the Mediterranean moor is used.
ADVANTAGES:
1. A number of vessels can be moored to a single berth.
2. Stern discharge/loading can be achieved.
DISADVANTAGES:
1. Dry cargo vessels can discharge only into barges.
2. In bad weather chances of fowling cables, especially with many vessels moored close-by.
SEQUENCE OF OPERATION:
1. Vessel to approach middle of berth to its Port side.
2. Engine speed DS Ahead.
3. Vessel should be as parallel as possible to the berth.
4. Let go the offshore anchor and continue steaming round the anchor with the engine H ahead and helm
hard over to Stbd.
5. Continue paying out the cable as the vessel moves ahead.
6. Let go inshore anchor and engines on H Astern, paying out on the 2nd
anchor and picking up slack on the
offshore anchor.
7. The transverse thrust due to stern propulsion will swing the vessel’s bow to Stbd.
8. Stop the engines and check the stern way of the vessel by braking on the cable.
9. Manoeuvre the vessel within to heaving line distance to the quay by use of engines and cables.
10. Pass the stern moorings to the quay.
11. Once moorings are on the quay, heave on the cables and vessel is in position.
CLEARING A FOUL HAWSE
PURPOSE:
Clearing a foul anchor.
VARIOUS METHODS AVAILABLE:
1. If the foul is only one turn this can be cleared by using the engines and steaming in the opposite direction
during the change of the tide.
2. Using a tug from the stern of the vessel, steam around till the turns are removed.
3. Hire a motorised barge, break the sleeping cable, lower into the barge and use the barge to clear the foul.
4. Use the manpower and expertise available as follows:
MATERIALS REQUIRED:
1. Natural fibre rope for lashing.
2. Preventer wire
3. Wire rope messenger
4. Temporary easing wire
5. Other equipment as required in good seamanship for carrying out this operation safely.
SEQUENCE OF OPERATION:
1. The time available for this operation is approx. 6 hours from the end of last tide to the beginning of the
next tide.
2. All preparations should be done well in advance and the clearing of the foul hawse should start
immediately at the end of the last tide.
3. Pick up the riding cable so as to have the foul clear of the water.
4. Lash the natural fibre rope above the foul (if the lashing is made after the turns and the tide changes before
completion of the operation, the full weight of the vessel at anchor would come on the lashing which is a
highly undesirable condition).
5. Rig a wire preventer from the Stbd side lead through the sleeping cable after the lashing.
6. Heave up the preventer wire and have it lashed on the mooring bitt. This will prevent the cable being lost.
7. The preventer wire should be rigged in such a manner so that it may be slipped from the deck upon
clearing the foul.
8. Walk back the sleeping cable till the next joining shackle is on deck.
9. Rig up a easing wire on the shackle forward of the joining shackle and on to the warping drum and take
the weight on the easing wire.
10. Break open the kenter shackle and the weight of the sleeping cable is now on the easing wire.
11. Rig a wire rope messenger from the Port side windlass warping drum.
12. Take a half turn on the riding cable with the wire messenger in a direction opposite to the foul direction
and pass the end of the wire messenger up through the hawse pipe of the sleeping cable and secure it to the
end of the sleeping cable.
13. Heave away on the wire messenger and at the same time ease out on the easing wire, thus removing half a
turn from the fouled cable.
14. Repeat this procedure removing half a turn at a time until the foul is cleared.
15. Heave up on the easing wire and at the same time slack on the messenger wire until the end of the sleeping
cable can be re-joined.
16. Once the cable is re-joined, temporary easing wire and the wire rope messenger can be removed, the
preventer wire can be slipped and cleared.
17. The lashing can be cut using a sharp knife with a man helper. Alternatively, the lashings could be soaked
in inflammable liquid and set on fire and heaving on the cables to help them part.
18. Heave away on both the cables.
19. Pick any slack.
RUNNING MOOR
1. The Running moor is an anchoring operation carried out in areas of restricted manoeuvrability where the wind
and tide are strong and from different directions.
2. Stem the tide. In this case tide is 090˚ and wind is 000˚.
3. Let go the weather anchor with engines going ahead (at about 4-5 knots).
4. Stop the engines, maintain headway, Continue to pay anchor cable to 8 shackles (double the required
shackles).
5. The vessel will stop due to the braking action of the anchor and will start falling astern. Let go the lee anchor
and pay out the cable, meanwhile picking up slack on the weather anchor and manoeuvring vessel away from
the lee anchor towards the weather anchor.
6. The vessel may need astern propulsion to begin astern movement.
7. Once the vessel has reached the position (half way between i.e. 4 shackles on each cable).
8. The lee anchor will be the riding cable.
STANDING MOOR
1. Stem the tide.
2. Vessel should be stopped over the ground.
3. Obtain stern way either by the effect of the tidal stream or by operating stern propulsion.
4. Let go the lee anchor (riding cable).
5. Allow the vessel to drop astern.
6. Pay out the cable up to 8 shackles (double the required length).
7. Take the stern way off the vessel by use of engines ahead and by checking out the cables.
8. Order maximum helm away from the released anchor.
9. Let go the weather anchor now (sleeping anchor)
10. Continue to heave on the riding cable and pay out on the sleeping cable until the vessel is brought up.
11. Continue to use engines ahead or astern as necessary to ease the weight on the cables.
BALTIC MOOR
PURPOSE:
A Baltic moor is used in ports where there is a strong onshore wind to prevent damages to the jetty or the vessel.
The vessel’s anchor and stern mooring wire are used to make a controlled approach to the berth.
PREPARATIONS:
The stern mooring wire is passed in bights and connected to the Ganger length of the anchor which is to be used.
Light sail twine secure the mooring wire in bights.
The shackles used for the operation shall be capable of passing through the hawse pipe for easy and safe
operation.
SEQUENCE OF OPERATION:
1. An approach is made with the vessel parallel to the berth with the wind on the beam OR slightly abaft of
the beam.
2. The offshore anchor is let go when the vessel 3 shackles off the berth. The distance off the berth depends
upon the wind and weather conditions.
3. As the anchor cable is paid out the seizings part and the stern mooring wire is also paid out.
4. The vessel will be pushed by the wind and approaches the berth slowly.
5. The cable and the wire are evenly paid out.
6. Ship’s fenders are to be used to prevent any damage.
7. Pass head and stern line as soon as possible.
8. Take the weight on the moorings before taking weight on the anchor and the mooring wire.
9. The moorings fore and aft prevent the vessel from ranging the berth.
10. This tends to harden up the inshore moorings.
11. During unberthing the achor and the stern mooring wire can be used to bodily draw the vessel off the
quay.
12. Once clear of the quay engines and the helm can be used to clear the berth safely and get underway.
OPEN MOOR
PURPOSE:
Te Open moor is used extensively when additional holding power is required in very strong tide or wind
conditions.
SEQUENCE OF OPERATION:
1. Stem the current and/or headwind.
2. Walk back both the anchors just above water level.
3. Steam to a position where the vessel intends to let go the windward anchor.
4. Let go the port anchor and continue to steam with a minimum headway to the required number of
shackles, paying out on the port anchor cable.
5. Once the second anchor position is reached, let go the stbd anchor and with minimum sternway, hold on to
the port anchor and pay out on the stbd anchor until both the anchors have even scope.
6. Once both the anchors have even scope additional shackles can be paid out as required, till the vessel is at
the required position.
7. Once the vessel is in the final mooring position, it is necessary to check on both the cables and ensure both
the anchors are embedded and holding.
STERNBORE INTO WIND
PURPOSE:
There are three tendencies of a vessel in a wind:
1. To lie across it when stopped
2. To run across it when under headway
3. To sternbore into it under sternway
SEQUENCE OF OPERATION:
1. Initially the vessel is shown running with the wind on the port quarter.
2. As she loses headway, she runs across the wind.
3. Now her engines rea reversed and she gathers sternway.
4. Her bow develops a reverse swing to stbd and she bores her stern into the wind.
5. She does not reach her original position due to leeway.

More Related Content

What's hot

Liferafts versus lifeboats
Liferafts versus lifeboatsLiferafts versus lifeboats
Liferafts versus lifeboatsPat Cabangis
 
Ship Construction (Structure Part)
Ship Construction (Structure Part)Ship Construction (Structure Part)
Ship Construction (Structure Part)
Marine Study
 
COLREG 1972, A Presentation
COLREG 1972, A PresentationCOLREG 1972, A Presentation
COLREG 1972, A Presentation
Amarinder Singh Brar
 
IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004
Abdulla Wanis
 
Nautical Rules of the Road
Nautical Rules of the RoadNautical Rules of the Road
Nautical Rules of the RoadLynn Seckinger
 
Personal safety on deck
Personal safety on deckPersonal safety on deck
Personal safety on deck
Universidad Maritima del Caribe
 
Basic stability 1
Basic stability 1Basic stability 1
Basic stability 1Acex Aribal
 
ORALS
ORALSORALS
LIFE SAVING APPLIANCES by Capt Aung Myin Moe
LIFE SAVING APPLIANCES by Capt Aung Myin MoeLIFE SAVING APPLIANCES by Capt Aung Myin Moe
LIFE SAVING APPLIANCES by Capt Aung Myin Moe
CaptAMM
 
Ship Construction- Ship Dimensions
Ship Construction- Ship DimensionsShip Construction- Ship Dimensions
Ship Construction- Ship Dimensions
Mohammud Hanif Dewan M.Phil.
 
Passage planning
Passage planningPassage planning
Passage planning
Capt Ashok Menon
 
Taking over a navigational watch lrg
Taking over a  navigational watch lrg Taking over a  navigational watch lrg
Taking over a navigational watch lrg Lance Grindley
 
Loadlines & draft marks
Loadlines & draft marks   Loadlines & draft marks
Loadlines & draft marks
Moises Tenyosa
 
Responsibilities of the oow lrg
Responsibilities of the oow  lrgResponsibilities of the oow  lrg
Responsibilities of the oow lrgLance Grindley
 
MANEUVERING & COLLISION AVOIDANCE
MANEUVERING & COLLISION AVOIDANCEMANEUVERING & COLLISION AVOIDANCE
MANEUVERING & COLLISION AVOIDANCE
Learnmarine
 
Oil tankers
Oil tankersOil tankers

What's hot (20)

Liferafts versus lifeboats
Liferafts versus lifeboatsLiferafts versus lifeboats
Liferafts versus lifeboats
 
Ship Construction (Structure Part)
Ship Construction (Structure Part)Ship Construction (Structure Part)
Ship Construction (Structure Part)
 
COLREG 1972, A Presentation
COLREG 1972, A PresentationCOLREG 1972, A Presentation
COLREG 1972, A Presentation
 
Anchoring lrg
Anchoring lrgAnchoring lrg
Anchoring lrg
 
IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004IMO's Ballast Water Management Convention 2004
IMO's Ballast Water Management Convention 2004
 
Nautical Rules of the Road
Nautical Rules of the RoadNautical Rules of the Road
Nautical Rules of the Road
 
Personal safety on deck
Personal safety on deckPersonal safety on deck
Personal safety on deck
 
Basic stability 1
Basic stability 1Basic stability 1
Basic stability 1
 
ORALS
ORALSORALS
ORALS
 
LIFE SAVING APPLIANCES by Capt Aung Myin Moe
LIFE SAVING APPLIANCES by Capt Aung Myin MoeLIFE SAVING APPLIANCES by Capt Aung Myin Moe
LIFE SAVING APPLIANCES by Capt Aung Myin Moe
 
Ship Construction- Ship Dimensions
Ship Construction- Ship DimensionsShip Construction- Ship Dimensions
Ship Construction- Ship Dimensions
 
Passage planning
Passage planningPassage planning
Passage planning
 
ROR review
ROR reviewROR review
ROR review
 
Taking over a navigational watch lrg
Taking over a  navigational watch lrg Taking over a  navigational watch lrg
Taking over a navigational watch lrg
 
Loadlines & draft marks
Loadlines & draft marks   Loadlines & draft marks
Loadlines & draft marks
 
Ship handling
Ship handlingShip handling
Ship handling
 
Navigation Rules1-5
Navigation Rules1-5Navigation Rules1-5
Navigation Rules1-5
 
Responsibilities of the oow lrg
Responsibilities of the oow  lrgResponsibilities of the oow  lrg
Responsibilities of the oow lrg
 
MANEUVERING & COLLISION AVOIDANCE
MANEUVERING & COLLISION AVOIDANCEMANEUVERING & COLLISION AVOIDANCE
MANEUVERING & COLLISION AVOIDANCE
 
Oil tankers
Oil tankersOil tankers
Oil tankers
 

Similar to Ship handling

STANDARD ANCHORING AND ANCHORING PROCEDURES
STANDARD ANCHORING AND ANCHORING PROCEDURESSTANDARD ANCHORING AND ANCHORING PROCEDURES
STANDARD ANCHORING AND ANCHORING PROCEDURES
ssuser81322e
 
ground tackle (anchoring and mooring)
ground tackle (anchoring and mooring)ground tackle (anchoring and mooring)
ground tackle (anchoring and mooring)
Marvin Furton
 
CHAPTER 8.pptx
CHAPTER 8.pptxCHAPTER 8.pptx
CHAPTER 8.pptx
devmarineacademy
 
Rigging and derigging a keel boat instruaction assingment
Rigging and derigging a keel boat instruaction assingmentRigging and derigging a keel boat instruaction assingment
Rigging and derigging a keel boat instruaction assingmentWilliam Brown
 
Cable landing station
Cable landing stationCable landing station
Cable landing station
choudhurygargi
 
Auxiliary marine machinery systems
Auxiliary marine machinery systemsAuxiliary marine machinery systems
Auxiliary marine machinery systems
WBUAFS
 
Lifeboatppt
LifeboatpptLifeboatppt
Lifeboatppt
Palani Rajeshwar
 
deck machinery.pptx
deck machinery.pptxdeck machinery.pptx
deck machinery.pptx
devmarineacademy
 
Sailing Study Guide
Sailing Study GuideSailing Study Guide
Sailing Study Guidevasiliswp84
 
Epic V7 Manual
Epic V7 ManualEpic V7 Manual
Epic V7 Manual
Jefferson Sestaro
 
Ship Anchor and it's application
Ship Anchor and it's applicationShip Anchor and it's application
Ship Anchor and it's application
AnujSharma815
 
1_Accommodation Ladder On Ships.docx
1_Accommodation Ladder On Ships.docx1_Accommodation Ladder On Ships.docx
1_Accommodation Ladder On Ships.docx
KateRamirez18
 
English 7 section A
English  7 section AEnglish  7 section A
English 7 section A
cristhian robles laya
 
Global arc
Global arcGlobal arc
Global arc
Valentin Bañaco
 
CGL402N, 2024 YEAR.pptx for helping youjhsihuuih
CGL402N, 2024 YEAR.pptx for helping youjhsihuuihCGL402N, 2024 YEAR.pptx for helping youjhsihuuih
CGL402N, 2024 YEAR.pptx for helping youjhsihuuih
shuklamittt0077
 
How clamshell bucket works
How clamshell bucket worksHow clamshell bucket works
How clamshell bucket works
Apr Bright Industries
 

Similar to Ship handling (20)

STANDARD ANCHORING AND ANCHORING PROCEDURES
STANDARD ANCHORING AND ANCHORING PROCEDURESSTANDARD ANCHORING AND ANCHORING PROCEDURES
STANDARD ANCHORING AND ANCHORING PROCEDURES
 
ground tackle (anchoring and mooring)
ground tackle (anchoring and mooring)ground tackle (anchoring and mooring)
ground tackle (anchoring and mooring)
 
CHAPTER 8.pptx
CHAPTER 8.pptxCHAPTER 8.pptx
CHAPTER 8.pptx
 
Rigging and derigging a keel boat instruaction assingment
Rigging and derigging a keel boat instruaction assingmentRigging and derigging a keel boat instruaction assingment
Rigging and derigging a keel boat instruaction assingment
 
Cable landing station
Cable landing stationCable landing station
Cable landing station
 
Aus lcu 2000-tarwater
Aus lcu 2000-tarwaterAus lcu 2000-tarwater
Aus lcu 2000-tarwater
 
Auxiliary marine machinery systems
Auxiliary marine machinery systemsAuxiliary marine machinery systems
Auxiliary marine machinery systems
 
Lifeboatppt
LifeboatpptLifeboatppt
Lifeboatppt
 
deck machinery.pptx
deck machinery.pptxdeck machinery.pptx
deck machinery.pptx
 
Sailing Study Guide
Sailing Study GuideSailing Study Guide
Sailing Study Guide
 
Epic V7 Manual
Epic V7 ManualEpic V7 Manual
Epic V7 Manual
 
78998058 chk-lists
78998058 chk-lists78998058 chk-lists
78998058 chk-lists
 
Ship Anchor and it's application
Ship Anchor and it's applicationShip Anchor and it's application
Ship Anchor and it's application
 
Drills
DrillsDrills
Drills
 
1_Accommodation Ladder On Ships.docx
1_Accommodation Ladder On Ships.docx1_Accommodation Ladder On Ships.docx
1_Accommodation Ladder On Ships.docx
 
Nuclear submarine tecnology
Nuclear submarine tecnologyNuclear submarine tecnology
Nuclear submarine tecnology
 
English 7 section A
English  7 section AEnglish  7 section A
English 7 section A
 
Global arc
Global arcGlobal arc
Global arc
 
CGL402N, 2024 YEAR.pptx for helping youjhsihuuih
CGL402N, 2024 YEAR.pptx for helping youjhsihuuihCGL402N, 2024 YEAR.pptx for helping youjhsihuuih
CGL402N, 2024 YEAR.pptx for helping youjhsihuuih
 
How clamshell bucket works
How clamshell bucket worksHow clamshell bucket works
How clamshell bucket works
 

More from jabbar2002pk200 (20)

Ig system & equipment oil tankers
Ig system &  equipment oil tankersIg system &  equipment oil tankers
Ig system & equipment oil tankers
 
Marine coating assigment
Marine coating  assigmentMarine coating  assigment
Marine coating assigment
 
Garbage
GarbageGarbage
Garbage
 
Rule 2004
Rule 2004Rule 2004
Rule 2004
 
M.v i kom k case study assigment
M.v  i kom k  case study assigmentM.v  i kom k  case study assigment
M.v i kom k case study assigment
 
Meteorology presentation.pptx lates
Meteorology presentation.pptx latesMeteorology presentation.pptx lates
Meteorology presentation.pptx lates
 
Meteorology presentation
Meteorology presentationMeteorology presentation
Meteorology presentation
 
Dg impor
Dg imporDg impor
Dg impor
 
Solas assigment
Solas  assigmentSolas  assigment
Solas assigment
 
Psc
PscPsc
Psc
 
Marpol annex v
Marpol annex vMarpol annex v
Marpol annex v
 
Classification societes. presentation
Classification societes. presentationClassification societes. presentation
Classification societes. presentation
 
Garbage
GarbageGarbage
Garbage
 
Sewage treatement plant
Sewage treatement plantSewage treatement plant
Sewage treatement plant
 
Loadline
LoadlineLoadline
Loadline
 
welding
weldingwelding
welding
 
International convention on load lines 1968 group 2
International convention on load lines 1968 group 2International convention on load lines 1968 group 2
International convention on load lines 1968 group 2
 
ship case study
ship case studyship case study
ship case study
 
Hatch ways
Hatch waysHatch ways
Hatch ways
 
Marpol annex 3& 6
Marpol annex 3& 6Marpol annex 3& 6
Marpol annex 3& 6
 

Recently uploaded

一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
smpc3nvg
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
cy0krjxt
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
7sd8fier
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
smpc3nvg
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
7sd8fier
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
Mansi Shah
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
9a93xvy
 
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
asuzyq
 
Can AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI preludeCan AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI prelude
Alan Dix
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
boryssutkowski
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
n0tivyq
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
madhavlakhanpal29
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
M. A. Architect
 
7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint
Alvis Oh
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
taqyed
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
cy0krjxt
 
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
708pb191
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
9a93xvy
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
Confidence Ago
 

Recently uploaded (20)

一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
一比一原版(Bristol毕业证书)布里斯托大学毕业证成绩单如何办理
 
RTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,DRTUYUIJKLDSADAGHBDJNKSMAL,D
RTUYUIJKLDSADAGHBDJNKSMAL,D
 
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
一比一原版(MMU毕业证书)曼彻斯特城市大学毕业证成绩单如何办理
 
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
一比一原版(Brunel毕业证书)布鲁内尔大学毕业证成绩单如何办理
 
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
一比一原版(UNUK毕业证书)诺丁汉大学毕业证如何办理
 
White wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva TschoppWhite wonder, Work developed by Eva Tschopp
White wonder, Work developed by Eva Tschopp
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
一比一原版(RHUL毕业证书)伦敦大学皇家霍洛威学院毕业证如何办理
 
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
一比一原版(Columbia毕业证)哥伦比亚大学毕业证如何办理
 
Can AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI preludeCan AI do good? at 'offtheCanvas' India HCI prelude
Can AI do good? at 'offtheCanvas' India HCI prelude
 
Borys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior designBorys Sutkowski portfolio interior design
Borys Sutkowski portfolio interior design
 
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
一比一原版(Glasgow毕业证书)格拉斯哥大学毕业证成绩单如何办理
 
Common Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid themCommon Designing Mistakes and How to avoid them
Common Designing Mistakes and How to avoid them
 
Mohannad Abdullah portfolio _ V2 _22-24
Mohannad Abdullah  portfolio _ V2 _22-24Mohannad Abdullah  portfolio _ V2 _22-24
Mohannad Abdullah portfolio _ V2 _22-24
 
7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint7 Alternatives to Bullet Points in PowerPoint
7 Alternatives to Bullet Points in PowerPoint
 
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理一比一原版(毕业证)长崎大学毕业证成绩单如何办理
一比一原版(毕业证)长崎大学毕业证成绩单如何办理
 
Design Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinkingDesign Thinking Design thinking Design thinking
Design Thinking Design thinking Design thinking
 
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
一比一原版(UAL毕业证书)伦敦艺术大学毕业证成绩单如何办理
 
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
一比一原版(CITY毕业证书)谢菲尔德哈勒姆大学毕业证如何办理
 
Book Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for DesignersBook Formatting: Quality Control Checks for Designers
Book Formatting: Quality Control Checks for Designers
 

Ship handling

  • 1. HANGING – OFF AN ANCHOR PURPOSE OF OPERATION: To remove the anchor out of the hawse pipe and enable the vessel to be moored to a buoy or towed using the anchor chain through the hawse pipe. MATERIALS REQUIRED FOR A 10 TONNE ANCHOR: 1. 3 Nos of 30 mm wire (SWL 6.0 tonnes) – For 1st Easing wire 2nd Easing wire Preventer wire 2. shackles with SWL of 6 tonnes 3. Other tools required to carry out the operation as per normal seamanship practices. SEQUENCE OF OPERATION: 1. Walk back the anchor clear of the hawse pipe. 2. Secure one end of the 1st easing wire on the mooring bit. 3. Pass the other end through the panama lead, through the anchor crown D shackle (as a bight) and back through the Panama lead on to the warping drum of the windlass. 4. Rig a preventer wire (as a bight) through the anchor crown D shackle, pass it through the fairlead well forward and secure it on the mooring bits. 5. Ensure there is sufficient slack on the preventer wire. 6. Slack on the anchor chain until the preventer becomes taut and the 1st easing wire is up and down and the anchor is under the shoulder. 7. Continue to walk back the chain until the next joining shackle is on the deck. 8. Heave on the 1st easing wire and secure the anchor in the up and down position. 9. Rig up the 2nd easing wire forward of the joining shackle (on a bight) and take up the weight of the chain. 10. Break the joining shackle. 11. Walk back the 2nd easing wire to bring the end of the cable clear of the hawse pipe. 12. Recover this end of the cable using rope hawsers through the Panama lead. 13. Now walk back the anchor chain through the hawse pipe and the cable is now ready for towing or mooring operation.
  • 2. MEDITERRANEAN MOOR PURPOSE: When the quay space is restricted and it is required to berth several vessels or when a stern discharge/loading is required, the Mediterranean moor is used. ADVANTAGES: 1. A number of vessels can be moored to a single berth. 2. Stern discharge/loading can be achieved. DISADVANTAGES: 1. Dry cargo vessels can discharge only into barges. 2. In bad weather chances of fowling cables, especially with many vessels moored close-by. SEQUENCE OF OPERATION: 1. Vessel to approach middle of berth to its Port side. 2. Engine speed DS Ahead. 3. Vessel should be as parallel as possible to the berth. 4. Let go the offshore anchor and continue steaming round the anchor with the engine H ahead and helm hard over to Stbd. 5. Continue paying out the cable as the vessel moves ahead. 6. Let go inshore anchor and engines on H Astern, paying out on the 2nd anchor and picking up slack on the offshore anchor. 7. The transverse thrust due to stern propulsion will swing the vessel’s bow to Stbd. 8. Stop the engines and check the stern way of the vessel by braking on the cable. 9. Manoeuvre the vessel within to heaving line distance to the quay by use of engines and cables. 10. Pass the stern moorings to the quay. 11. Once moorings are on the quay, heave on the cables and vessel is in position.
  • 3. CLEARING A FOUL HAWSE PURPOSE: Clearing a foul anchor. VARIOUS METHODS AVAILABLE: 1. If the foul is only one turn this can be cleared by using the engines and steaming in the opposite direction during the change of the tide. 2. Using a tug from the stern of the vessel, steam around till the turns are removed. 3. Hire a motorised barge, break the sleeping cable, lower into the barge and use the barge to clear the foul. 4. Use the manpower and expertise available as follows: MATERIALS REQUIRED: 1. Natural fibre rope for lashing. 2. Preventer wire 3. Wire rope messenger 4. Temporary easing wire 5. Other equipment as required in good seamanship for carrying out this operation safely. SEQUENCE OF OPERATION: 1. The time available for this operation is approx. 6 hours from the end of last tide to the beginning of the next tide. 2. All preparations should be done well in advance and the clearing of the foul hawse should start immediately at the end of the last tide. 3. Pick up the riding cable so as to have the foul clear of the water. 4. Lash the natural fibre rope above the foul (if the lashing is made after the turns and the tide changes before completion of the operation, the full weight of the vessel at anchor would come on the lashing which is a highly undesirable condition). 5. Rig a wire preventer from the Stbd side lead through the sleeping cable after the lashing. 6. Heave up the preventer wire and have it lashed on the mooring bitt. This will prevent the cable being lost. 7. The preventer wire should be rigged in such a manner so that it may be slipped from the deck upon clearing the foul. 8. Walk back the sleeping cable till the next joining shackle is on deck. 9. Rig up a easing wire on the shackle forward of the joining shackle and on to the warping drum and take the weight on the easing wire. 10. Break open the kenter shackle and the weight of the sleeping cable is now on the easing wire. 11. Rig a wire rope messenger from the Port side windlass warping drum. 12. Take a half turn on the riding cable with the wire messenger in a direction opposite to the foul direction and pass the end of the wire messenger up through the hawse pipe of the sleeping cable and secure it to the end of the sleeping cable. 13. Heave away on the wire messenger and at the same time ease out on the easing wire, thus removing half a turn from the fouled cable. 14. Repeat this procedure removing half a turn at a time until the foul is cleared. 15. Heave up on the easing wire and at the same time slack on the messenger wire until the end of the sleeping cable can be re-joined. 16. Once the cable is re-joined, temporary easing wire and the wire rope messenger can be removed, the preventer wire can be slipped and cleared. 17. The lashing can be cut using a sharp knife with a man helper. Alternatively, the lashings could be soaked in inflammable liquid and set on fire and heaving on the cables to help them part. 18. Heave away on both the cables. 19. Pick any slack.
  • 4. RUNNING MOOR 1. The Running moor is an anchoring operation carried out in areas of restricted manoeuvrability where the wind and tide are strong and from different directions. 2. Stem the tide. In this case tide is 090˚ and wind is 000˚. 3. Let go the weather anchor with engines going ahead (at about 4-5 knots). 4. Stop the engines, maintain headway, Continue to pay anchor cable to 8 shackles (double the required shackles). 5. The vessel will stop due to the braking action of the anchor and will start falling astern. Let go the lee anchor and pay out the cable, meanwhile picking up slack on the weather anchor and manoeuvring vessel away from the lee anchor towards the weather anchor. 6. The vessel may need astern propulsion to begin astern movement. 7. Once the vessel has reached the position (half way between i.e. 4 shackles on each cable). 8. The lee anchor will be the riding cable.
  • 5. STANDING MOOR 1. Stem the tide. 2. Vessel should be stopped over the ground. 3. Obtain stern way either by the effect of the tidal stream or by operating stern propulsion. 4. Let go the lee anchor (riding cable). 5. Allow the vessel to drop astern. 6. Pay out the cable up to 8 shackles (double the required length). 7. Take the stern way off the vessel by use of engines ahead and by checking out the cables. 8. Order maximum helm away from the released anchor. 9. Let go the weather anchor now (sleeping anchor) 10. Continue to heave on the riding cable and pay out on the sleeping cable until the vessel is brought up. 11. Continue to use engines ahead or astern as necessary to ease the weight on the cables.
  • 6. BALTIC MOOR PURPOSE: A Baltic moor is used in ports where there is a strong onshore wind to prevent damages to the jetty or the vessel. The vessel’s anchor and stern mooring wire are used to make a controlled approach to the berth. PREPARATIONS: The stern mooring wire is passed in bights and connected to the Ganger length of the anchor which is to be used. Light sail twine secure the mooring wire in bights. The shackles used for the operation shall be capable of passing through the hawse pipe for easy and safe operation. SEQUENCE OF OPERATION: 1. An approach is made with the vessel parallel to the berth with the wind on the beam OR slightly abaft of the beam. 2. The offshore anchor is let go when the vessel 3 shackles off the berth. The distance off the berth depends upon the wind and weather conditions. 3. As the anchor cable is paid out the seizings part and the stern mooring wire is also paid out. 4. The vessel will be pushed by the wind and approaches the berth slowly. 5. The cable and the wire are evenly paid out. 6. Ship’s fenders are to be used to prevent any damage. 7. Pass head and stern line as soon as possible. 8. Take the weight on the moorings before taking weight on the anchor and the mooring wire. 9. The moorings fore and aft prevent the vessel from ranging the berth. 10. This tends to harden up the inshore moorings. 11. During unberthing the achor and the stern mooring wire can be used to bodily draw the vessel off the quay. 12. Once clear of the quay engines and the helm can be used to clear the berth safely and get underway.
  • 7. OPEN MOOR PURPOSE: Te Open moor is used extensively when additional holding power is required in very strong tide or wind conditions. SEQUENCE OF OPERATION: 1. Stem the current and/or headwind. 2. Walk back both the anchors just above water level. 3. Steam to a position where the vessel intends to let go the windward anchor. 4. Let go the port anchor and continue to steam with a minimum headway to the required number of shackles, paying out on the port anchor cable. 5. Once the second anchor position is reached, let go the stbd anchor and with minimum sternway, hold on to the port anchor and pay out on the stbd anchor until both the anchors have even scope. 6. Once both the anchors have even scope additional shackles can be paid out as required, till the vessel is at the required position. 7. Once the vessel is in the final mooring position, it is necessary to check on both the cables and ensure both the anchors are embedded and holding.
  • 8. STERNBORE INTO WIND PURPOSE: There are three tendencies of a vessel in a wind: 1. To lie across it when stopped 2. To run across it when under headway 3. To sternbore into it under sternway SEQUENCE OF OPERATION: 1. Initially the vessel is shown running with the wind on the port quarter. 2. As she loses headway, she runs across the wind. 3. Now her engines rea reversed and she gathers sternway. 4. Her bow develops a reverse swing to stbd and she bores her stern into the wind. 5. She does not reach her original position due to leeway.