SEMI-MECHANISATION BY SDLs & LHDs

          I. Satyanarayana,
                                M.Tech,MBA,MCA


    Dy. Manager, Project Planning, SCCL,


        isnindian@gmail.com,

                 visit at

    www.slideshare.net/isnindian


                       ISN
PRESENTATION
            ON


SEMI-MECHANISATION BY
      SDLs & LHDs




       I. Satyanarayana, M.Tech,MBA,MCA
        Dy. Manager
        Project Planning
             ISN
CHRONOLOGY OF INTRODUCTION OF UG
       MECHANISATION IN SCCL

1956 – Coal Cutting and Coal ploughing
1962 – Gathering arm loaders and Shuttle Cars
1976 – SDLs (GDK No. 9 Incline)
1979 – Roadheaders
1980 – LHDs (GDK No. 9 Incline)
1983 – Longwall Technology
1989 – Blasting Gallery Technology
                     ISN
INTRODUCTION
• In order to keep away with the arduous labor of
  loading coal manually, to avoid exposure of
  persons at face and improve productivity efforts
  are made to       introduction of intermediate
  technology and continuous mining systems.

• as a result, in India SDLs & LHDs have taken
  foot forward in intermediate technology.
                                         contd…

                        ISN
INTRODUCTION
• The Board and pillar method has been
  predominantly adopted in SCCL and in India for
  the extraction of coal seams due to shallow depth
  and good roof conditions.

• Although every effort is made to introduce LW
  method of mining, it is not likely to replace the
  entire board and pillar method

                                        contd…
                        ISN
STATUS OF SDLs AS ON 24.01.2011




                     ISN
STATUS OF LHDs AS ON 24.01.2011




             ISN
Cycle of Operations


•Drilling

•Blasting

•Supporting

•Coal loading (SDLs & LHDs)
                 ISN
OPERATION OF LHDs and SDLs

 Method of working

  The method of development and depillaring with LHDs/SDLs
  was similar to Conventional development of forming rectangular
  OR square pillars as per Regulation 99 of Coal Mines
  Regulations, 1957 and subsequent extraction of pillars by
  splitting and judiciously reducing it.

 Coal Preparation
  Coal preparation for LHD/SDL was done by conventional
  drilling and blasting.
Transportation
The coal carried by LHD/SDL from the face was discharged on to the
pony belt conveyor, which was maintained as near to the face as
possible, even though LHD/SDLISN cope with about 100m lead.
                               can
LOAD HAUL DUMPERS (LHDs)




            ISN
Details of LHD
• an electro-hydraulic powered underground mining equipment
• used to collect the coal, haul upto the discharge point of
hopper/chain conveyor/belt conveyor located within 100 m from
the coal face and to dump on it.
• 50 HP (811 Model) Motor and 100 HP (912E Mode) Motor
•Three forward and three reverse speeds.
• The working pressure of hydraulic system is 2200 PSI and
discharge 16 GPM.
• The hydraulic tank capacity is 210 ltrs.
• Oil is cooled by a radiator and fan run by hydraulic motor.
• The power to the machine is fed by a trailing cable 16 m2
handled by a cable reeler, which can accommodate 100 m length.
                               ISN
ISN
LHD mechanization – where the gradient is 1 in 6 & flatter




                           ISN
Load Haul Dumpers




        ISN
LHD




  ISN
LOAD HAUL DUMPER IN BLASTING
      GALLERY METHOD




             ISN
Capacity and Speed




                6.15m3




        ISN
Advantages of LHDs

(a)    Indigenous and           : To save foreign exchange and to
       availability of spares   reduce breakdown hours.
(b)    Robustness               : To withstand difficult conditions.
(c )   Compactness              : To work in restricted underground
                                space.
(d)    Reliability and          : To enable to resist difficult conditions.
       susceptibility
(e)    Adaptability             : For easy maintenance.
(f)    Portability              : Easy to move from place to place.
(g)    Safety                   : Proper guides and covers. Elect.
                                Protective devices.



                                   ISN
SAFETY FEATURES of LHDs

1. HEAD LIGHTS
2. OPERATOR’S CANOPY
3. DUMP VALVE
4. PARKING BRAKES & SERVICE BRAKES
5. GONG BELL
6. AUDIO VISUAL ALARM
7. EMERGENCY STOP BUTTON
8. DEAD MAN SWITCH
9. FLOAT (OIL LEVEL) SWITCH
10. TEMPERATURE SWITCH
11. CABLE OVERRIDING SWITCH
12. PILOT CORE PROTECTION
13. PUSH BUTTON STATION
14. BRAKE ACCUMULATORS
                 ISN
15. FIRE EXTINGUISHERS
ISN
Details of LHD                      ..Contd


•The temperature of hydraulic oil is kept well below 65o C.
Cycle Time for LHD 811 Model
1.     Available time per shift              -      390 minutes
2.     Time for trip                         -      5.7 minutes
3.     Number of trips per shift for LHD     -      65
4.     Output per shift for LHD              -      72 tonnes
5.     OMS                                   -      3.375 tonnes
6.     Output per drill                      -      60 tonnes




                               ISN
BEST PRACTICES                   ..Contd
 Keeping LHD path clean, dry and flat
Smooth and uniform discharge by LHD on the belt conveyor
Categorisation of Spares & ensuring availability of fast
moving parts in underground stores.
Providing appropriate tools for technicians
Avoiding acute angles
Preshift extention/retreating and maintenance of conveyor belts
Preshift maintenance of LHDs
Easily shiftable tail end assembly
Replacing/overhauling Transmission and axles of LHDs (biannual
Providing drill machine in each face and spare Gate End
Panels for LHDs
 Cable Vulcanising
Tyre and tube repairing and inflation
                              ISN
METHOD OF DEPILLARING




                  GOAF




          ISN
Manpower requirement for Depillaring district with 5 LHDs
   Sl.                                           SHIFT
           Designation              Gen. Shift                       Total
   No                                            I       II    III

   1.      Under Managers           1            1       1     1     4

   2.      Asst. Engineers          1            NIL     NIL   NIL   1

   3.      Overman                  1            1       1     1     4

   4.      Mining Sardars           1            1       1     1     4

   5.      Electrical Supervisors   1            Nil     NIL   NIL   1

   6.      Shotfirers               NIL          6       6     6     18

   7.      Coal cutters             NIL          24      24    24    72

   8.      Support Mazdoors         15           15      15    15    60

   9.      LHD Operators            NIL          5       5     5     15

   10.     Conveyor Operators       NIL          7       7     7     21

   11.     Fitters + Helpers        6            4       4     4     18

   12.     Electricians + Helpers   2            2       2     2     8

   13.     Conveyor shifting gang   6            NIL     NIL   NIL   6

   14.     Water Spraying           3            NIL     NIL   NIL   3

   15.     Ventilation (Mazdoors)   4            NIL     NIL   NIL   4

   16.     Tyndals                  9            NIL     NIL   NIL   9

   17.     Gen. Mazdoors            25           15      15    15    60

   18.     Cable Vulcanizer         2            NIL     NIL   NIL   2

   total                            77    ISN    81      81    81    320
SIDE DISCHARGE LOADERS
         (SDLs)




           ISN
SDL mechanization – where the gradient is 1 in 4 & flatter




                           ISN
Side Discharge Loaders




           ISN
SIDE DISCHARGE LOADER
 IN SEMI MECHANISATION




          ISN
SIDE DISCHARGE LOADER
 IN SEMI MECHANISATION




          ISN
COMPARISON BETWEEN SEMI-MECH & HANDSECTION
                           3 SDLs HS (2 Drills)
Output (LTPA)                  1.62   0.9
Men on Roll(Nos)               181    281
OMS (at dist. Level) (T)          2   1.2
Cost of Production (Rs./T)    1859   4032
Profit over HS (Rs./T)        2227     --
Initial investment on
P&M (Rs.Lakhs)                 180    57
 *Output from SDL depends on its availability & utilisation



                            ISN
ISN
ISN
SAFETY FEATURES of SDLs




           ISN
UNIVERSAL DRILL MACHINE




          ISN
ISN
ISN
ISN
CODE OF PRACTICE FOR SDL OPERATOR




                ISN
CODE OF PRACTICE FOR SDL OPERATOR




                ISN
CODE OF PRACTICE FOR SDL OPERATOR




                ISN
ISN
ISN
ISN
ISN
Code of Practice for Overman:

  He should inspect the route of LHD/SDL marching prior
to marching and take the following precautions:
  Ensure no obstruction in the way of marching. Check the
presence of W-straps, bolts, chock timber, old pipes and
other material that damage to the LHD/SDL and result to
other breakdowns.
  Take necessary precautions to prevent dislodgment of
vertical supports, if any, due to moving trailing cable.
  Ensure that the persons engaged have taken all necessary
precautions.
  Take necessary precautions while crossing track line, pipe
line etc. And also avoid rubbing of trailing cable against
hard surfaces and to pillar corners.
                           ISN
OPERATING PROBLEMS
•   Non-availability of machine

•   Poor utilization of machine

•   Lack of Coal preparation

•   Delay in supporting

•   Delay in machine tramming

•   Delay in tub supply or backup transport services
    (crusher, belts, bunkers etc.,)

•   Idle time due to shift change hours

•   Lack of spares availability
                        ISN
                                          Contd…….
OPERATING PROBLEMS
•   Lack of on-hand trained crew

•   Lack of midlife overhaul of machinery

•   Lack of maintenance of machinery

•   Poor working environment

•   Timely not positioning of supervisors

•   Poor placement of orders

•   Unsatisfactory incentive schemes

•   Untrained mechanized district crew right from
    supervisor to workmen.
                     ISN
ISN
ISN
RECOMMENDATIONS




      ISN
PERFORMANCE SUMMARY




       ISN
Approved norms of SCCL for monitoring
     UGMM equipment performance


             Bucket
                        Standard      Standard Production
Equipment   capacity
                       availability   utilization (TPA/TPD)
            in Cu m
 SDL           1.1        91%           58%      54000/180
LHD 811        1.5        91%           57%     60000/200
LHD 912        2.7        91%           57%     100000/333
BG LHD        2.7         91%           57%     100000/333



                         ISN
INPUTS FOR IMPROVING
    PRODUCTION




         ISN
1.       Improvement of availability and utilization of machinery

     –    Idle time due to shift change hours can be reduced by
          implementing overlapping 4 shifts.

     –    Proper maintenance of machinery i.e., strict scheduled
          maintenance should be followed.

     –    By making availability of coal at max. no of working faces.

     –    Reducing flitting distance of machine.

     –    Timely availability of spares by follow up with firms and
          placement of RC & departmental contracts.

     –    By introducing sufficient number of mechanized roof bolting
          machines with rated power pack/ air compressors.

     –    Deployment of trained efficient supporting crew, technicians and
          operating personnel.
                                    ISN
2. Working of full shifts.

–   Implementation of staggered shifts

–   Positioning of supervisors in time.

–   By improving good environmental conditions such are
    ventilation, supporting, drainage and house keeping.

–   Keep availability of material for supporting , ducting
    and spares.

–   Efficient back up services like pumping, work-shops,
    coal evacuation system, bunkers etc.,

–   Proper incentive schemes.
                          ISN
–   Treating people with due regard.
3. Other recommendations

–   Introduction of high capacity and cable less LHD’s

–   Good communication system at all levels.

–   Intensive monitoring at all levels.

–   Increasing length of cable by reducing diameter of cable
    or increasing drum diameter.

–   Mechanization of face drilling.

–   Introduction of multi job concept like ‘operator cum
    mechanic’, ‘coal cutter cum support men’


                          ISN                  Contd……
3. Other recommendations

–   Introduction of equipment maintenance by OEM.

–   Design of suitable training module.

–   Out sourcing of non-core activities

–   Adjusting general shift man power in production and
    retaining only in statutory requirement.

–   Explore the workings at suitable gradient.

–   Avoiding water and slurry condition by proper
    maintenance of drainage system

–   Selection of educated and young persons as operation
                        ISN
    crew.
CONCLUSION


Availability of coal faces & more yield per blast
Maintain less lead (30m)
Continuous Loading
Extensions/Retreats & Pre-shift maintenance etc
Increase machine utilization
Better working conditions
Good discipline, higher morale and well planned actions
Training
                            ISN
ISN

Semimechanization sdls&lh ds

  • 1.
    SEMI-MECHANISATION BY SDLs& LHDs I. Satyanarayana, M.Tech,MBA,MCA Dy. Manager, Project Planning, SCCL, isnindian@gmail.com, visit at www.slideshare.net/isnindian ISN
  • 2.
    PRESENTATION ON SEMI-MECHANISATION BY SDLs & LHDs I. Satyanarayana, M.Tech,MBA,MCA Dy. Manager Project Planning ISN
  • 3.
    CHRONOLOGY OF INTRODUCTIONOF UG MECHANISATION IN SCCL 1956 – Coal Cutting and Coal ploughing 1962 – Gathering arm loaders and Shuttle Cars 1976 – SDLs (GDK No. 9 Incline) 1979 – Roadheaders 1980 – LHDs (GDK No. 9 Incline) 1983 – Longwall Technology 1989 – Blasting Gallery Technology ISN
  • 4.
    INTRODUCTION • In orderto keep away with the arduous labor of loading coal manually, to avoid exposure of persons at face and improve productivity efforts are made to introduction of intermediate technology and continuous mining systems. • as a result, in India SDLs & LHDs have taken foot forward in intermediate technology. contd… ISN
  • 5.
    INTRODUCTION • The Boardand pillar method has been predominantly adopted in SCCL and in India for the extraction of coal seams due to shallow depth and good roof conditions. • Although every effort is made to introduce LW method of mining, it is not likely to replace the entire board and pillar method contd… ISN
  • 6.
    STATUS OF SDLsAS ON 24.01.2011 ISN
  • 7.
    STATUS OF LHDsAS ON 24.01.2011 ISN
  • 8.
  • 9.
    OPERATION OF LHDsand SDLs Method of working The method of development and depillaring with LHDs/SDLs was similar to Conventional development of forming rectangular OR square pillars as per Regulation 99 of Coal Mines Regulations, 1957 and subsequent extraction of pillars by splitting and judiciously reducing it. Coal Preparation Coal preparation for LHD/SDL was done by conventional drilling and blasting. Transportation The coal carried by LHD/SDL from the face was discharged on to the pony belt conveyor, which was maintained as near to the face as possible, even though LHD/SDLISN cope with about 100m lead. can
  • 10.
  • 11.
    Details of LHD •an electro-hydraulic powered underground mining equipment • used to collect the coal, haul upto the discharge point of hopper/chain conveyor/belt conveyor located within 100 m from the coal face and to dump on it. • 50 HP (811 Model) Motor and 100 HP (912E Mode) Motor •Three forward and three reverse speeds. • The working pressure of hydraulic system is 2200 PSI and discharge 16 GPM. • The hydraulic tank capacity is 210 ltrs. • Oil is cooled by a radiator and fan run by hydraulic motor. • The power to the machine is fed by a trailing cable 16 m2 handled by a cable reeler, which can accommodate 100 m length. ISN
  • 12.
  • 13.
    LHD mechanization –where the gradient is 1 in 6 & flatter ISN
  • 14.
  • 15.
  • 16.
    LOAD HAUL DUMPERIN BLASTING GALLERY METHOD ISN
  • 17.
  • 18.
    Advantages of LHDs (a) Indigenous and : To save foreign exchange and to availability of spares reduce breakdown hours. (b) Robustness : To withstand difficult conditions. (c ) Compactness : To work in restricted underground space. (d) Reliability and : To enable to resist difficult conditions. susceptibility (e) Adaptability : For easy maintenance. (f) Portability : Easy to move from place to place. (g) Safety : Proper guides and covers. Elect. Protective devices. ISN
  • 19.
    SAFETY FEATURES ofLHDs 1. HEAD LIGHTS 2. OPERATOR’S CANOPY 3. DUMP VALVE 4. PARKING BRAKES & SERVICE BRAKES 5. GONG BELL 6. AUDIO VISUAL ALARM 7. EMERGENCY STOP BUTTON 8. DEAD MAN SWITCH 9. FLOAT (OIL LEVEL) SWITCH 10. TEMPERATURE SWITCH 11. CABLE OVERRIDING SWITCH 12. PILOT CORE PROTECTION 13. PUSH BUTTON STATION 14. BRAKE ACCUMULATORS ISN 15. FIRE EXTINGUISHERS
  • 20.
  • 21.
    Details of LHD ..Contd •The temperature of hydraulic oil is kept well below 65o C. Cycle Time for LHD 811 Model 1. Available time per shift - 390 minutes 2. Time for trip - 5.7 minutes 3. Number of trips per shift for LHD - 65 4. Output per shift for LHD - 72 tonnes 5. OMS - 3.375 tonnes 6. Output per drill - 60 tonnes ISN
  • 22.
    BEST PRACTICES ..Contd Keeping LHD path clean, dry and flat Smooth and uniform discharge by LHD on the belt conveyor Categorisation of Spares & ensuring availability of fast moving parts in underground stores. Providing appropriate tools for technicians Avoiding acute angles Preshift extention/retreating and maintenance of conveyor belts Preshift maintenance of LHDs Easily shiftable tail end assembly Replacing/overhauling Transmission and axles of LHDs (biannual Providing drill machine in each face and spare Gate End Panels for LHDs Cable Vulcanising Tyre and tube repairing and inflation ISN
  • 23.
  • 24.
    Manpower requirement forDepillaring district with 5 LHDs Sl. SHIFT Designation Gen. Shift Total No I II III 1. Under Managers 1 1 1 1 4 2. Asst. Engineers 1 NIL NIL NIL 1 3. Overman 1 1 1 1 4 4. Mining Sardars 1 1 1 1 4 5. Electrical Supervisors 1 Nil NIL NIL 1 6. Shotfirers NIL 6 6 6 18 7. Coal cutters NIL 24 24 24 72 8. Support Mazdoors 15 15 15 15 60 9. LHD Operators NIL 5 5 5 15 10. Conveyor Operators NIL 7 7 7 21 11. Fitters + Helpers 6 4 4 4 18 12. Electricians + Helpers 2 2 2 2 8 13. Conveyor shifting gang 6 NIL NIL NIL 6 14. Water Spraying 3 NIL NIL NIL 3 15. Ventilation (Mazdoors) 4 NIL NIL NIL 4 16. Tyndals 9 NIL NIL NIL 9 17. Gen. Mazdoors 25 15 15 15 60 18. Cable Vulcanizer 2 NIL NIL NIL 2 total 77 ISN 81 81 81 320
  • 25.
  • 26.
    SDL mechanization –where the gradient is 1 in 4 & flatter ISN
  • 27.
  • 28.
    SIDE DISCHARGE LOADER IN SEMI MECHANISATION ISN
  • 29.
    SIDE DISCHARGE LOADER IN SEMI MECHANISATION ISN
  • 30.
    COMPARISON BETWEEN SEMI-MECH& HANDSECTION 3 SDLs HS (2 Drills) Output (LTPA) 1.62 0.9 Men on Roll(Nos) 181 281 OMS (at dist. Level) (T) 2 1.2 Cost of Production (Rs./T) 1859 4032 Profit over HS (Rs./T) 2227 -- Initial investment on P&M (Rs.Lakhs) 180 57 *Output from SDL depends on its availability & utilisation ISN
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
    CODE OF PRACTICEFOR SDL OPERATOR ISN
  • 39.
    CODE OF PRACTICEFOR SDL OPERATOR ISN
  • 40.
    CODE OF PRACTICEFOR SDL OPERATOR ISN
  • 41.
  • 42.
  • 43.
  • 44.
  • 45.
    Code of Practicefor Overman: He should inspect the route of LHD/SDL marching prior to marching and take the following precautions: Ensure no obstruction in the way of marching. Check the presence of W-straps, bolts, chock timber, old pipes and other material that damage to the LHD/SDL and result to other breakdowns. Take necessary precautions to prevent dislodgment of vertical supports, if any, due to moving trailing cable. Ensure that the persons engaged have taken all necessary precautions. Take necessary precautions while crossing track line, pipe line etc. And also avoid rubbing of trailing cable against hard surfaces and to pillar corners. ISN
  • 46.
    OPERATING PROBLEMS • Non-availability of machine • Poor utilization of machine • Lack of Coal preparation • Delay in supporting • Delay in machine tramming • Delay in tub supply or backup transport services (crusher, belts, bunkers etc.,) • Idle time due to shift change hours • Lack of spares availability ISN Contd…….
  • 47.
    OPERATING PROBLEMS • Lack of on-hand trained crew • Lack of midlife overhaul of machinery • Lack of maintenance of machinery • Poor working environment • Timely not positioning of supervisors • Poor placement of orders • Unsatisfactory incentive schemes • Untrained mechanized district crew right from supervisor to workmen. ISN
  • 48.
  • 49.
  • 50.
  • 51.
  • 52.
    Approved norms ofSCCL for monitoring UGMM equipment performance Bucket Standard Standard Production Equipment capacity availability utilization (TPA/TPD) in Cu m SDL 1.1 91% 58% 54000/180 LHD 811 1.5 91% 57% 60000/200 LHD 912 2.7 91% 57% 100000/333 BG LHD 2.7 91% 57% 100000/333 ISN
  • 53.
    INPUTS FOR IMPROVING PRODUCTION ISN
  • 54.
    1. Improvement of availability and utilization of machinery – Idle time due to shift change hours can be reduced by implementing overlapping 4 shifts. – Proper maintenance of machinery i.e., strict scheduled maintenance should be followed. – By making availability of coal at max. no of working faces. – Reducing flitting distance of machine. – Timely availability of spares by follow up with firms and placement of RC & departmental contracts. – By introducing sufficient number of mechanized roof bolting machines with rated power pack/ air compressors. – Deployment of trained efficient supporting crew, technicians and operating personnel. ISN
  • 55.
    2. Working offull shifts. – Implementation of staggered shifts – Positioning of supervisors in time. – By improving good environmental conditions such are ventilation, supporting, drainage and house keeping. – Keep availability of material for supporting , ducting and spares. – Efficient back up services like pumping, work-shops, coal evacuation system, bunkers etc., – Proper incentive schemes. ISN – Treating people with due regard.
  • 56.
    3. Other recommendations – Introduction of high capacity and cable less LHD’s – Good communication system at all levels. – Intensive monitoring at all levels. – Increasing length of cable by reducing diameter of cable or increasing drum diameter. – Mechanization of face drilling. – Introduction of multi job concept like ‘operator cum mechanic’, ‘coal cutter cum support men’ ISN Contd……
  • 57.
    3. Other recommendations – Introduction of equipment maintenance by OEM. – Design of suitable training module. – Out sourcing of non-core activities – Adjusting general shift man power in production and retaining only in statutory requirement. – Explore the workings at suitable gradient. – Avoiding water and slurry condition by proper maintenance of drainage system – Selection of educated and young persons as operation ISN crew.
  • 58.
    CONCLUSION Availability of coalfaces & more yield per blast Maintain less lead (30m) Continuous Loading Extensions/Retreats & Pre-shift maintenance etc Increase machine utilization Better working conditions Good discipline, higher morale and well planned actions Training ISN
  • 59.