Senior Facilities / Project Engineering Manager
October 2013 – present. Oryx Petroleum, Geneva.
 Demir Dhag DD (Hawler Block, Kurdistan) Greenfield development: GOSP
Production facility with H2S stripping, Export Pipeline and Tanker Loading Station
(TLS) facilities. In -field infrastructure: pipelines/communications and well flowlines.
 Achieved First Oil from DD block via EPF Facilities and First Export to road tankers.
In parallel with the design and installation of 30kbpd sweet and 10kbpd sour service
production trains, with export pumping and fiscal metering to KEP (Kurdistan Export
Pipeline) and TLS for local market sales. In-field infrastructure: 10km of buried 12”
pipeline to TLS, 1km 16” export spur to KEP and 20km of 6” flowlines from wells.
Senior FPSO Project Manager
September 2005 – September 2013 Addax Petroleum, Geneva.
 OML126 (Offshore) Okwori : Management of external design contractors and in-
house teams in the preparation, revision and implementation of Field Development
Plan. Scope covered development of production and control systems for an
additional sixteen subsea wells. Project developed three six-slot subsea manifolded
areas producing to an existing FPSO. As an on-going development project,
significant subsea re-architecture was required.
 Management of design teams in the preparation of documents for FEED initiation
and conception. Option selection and evaluation leading to concept approval
through gated project management processes.
 Okwori Phase III Development: Expansion of FPSO process facilities to accept
seven new producers and one gas injection well. Expansion of FPSO balcony with
six additional manifold slots and a subsea well control system, with electro-hydraulic
capability. Tie back of new subsea wellheads to FPSO. Development of improved
well response measures. Award and completion of design, procurement and
manufacturing contracts to x-works of all project equipment within budget and
schedule. Design and manufacture value circa $140M.
 Management of manufacturing process achieving manufacturing targets for 26km of
subsea EH multi-core umbilicals, high pressure flexible flowlines and eight dynamic
risers. Management of installation processes topside and subsea spread
contractors. Installation and commissioning of subsea production and control
systems.
 Okwori Pase II and Adanga North Field Development: Expansion of FPSO
facilities to accommodate eight new manifold slots and installation of a multiplexed
electro-hydraulic subsea control pod. Development and tie back of six subsea
wellheads risers, flowlines and control umbilicals to existing FPSO. Offshore
installation and tie-in of new manifold slots. Installation of flowlines, gas lift and
control umbilicals, with both direct hydraulic and multiplexed communications-on-
power control schemes. Development of the Adanga North Field proposed as an
18 well development with two platforms tied back to Adanga central production
facilities. Construction and installation of single extended well test platform for field
appraisal leading to financial investment decision for entire Adanga North Field
Development. Installation of extended welltest platform production and gaslift
subsea pipelines to host facilities.
Scott Smith
10 Rosewell Terrace
Aberdeen, AB15 6HP
+41 79 172 4640
Scottsr12000@yahoo.com
Resident Project Engineer
January 2003- August 2005 Shell Gabon, Gamba, Rabi and Toucan Oilfields
 Rabi Phase III Field Expansion Project : An Interface Management role between
Company and EPCM contractor. Project objectives were to increase gas injection
capacity, improving reservoir management and achieve “flares-out” targets. A new
booster compression plant was installed and existing lift compressors re-wheeled.
Balance of plant serving lift compression stages required overhaul to meet
increased duty. Control systems were upgraded from pneumatics to electronics to
respond to faster system dynamics. Gas collection and distribution pipeline
networks were also expanded.
 Project doubled Rabi gas compression capacity to 120mmscfd for gas injection and
gas lift and systems, and achieved “flares out” before 2007 deadline. Project budget
$148 M.
 Toucan Greenfield Development Project: Construction of greenfield GOSP
production facility for 20kbpd, three phase processing of heavy, 18API crude, and
export to Rabi Central host facilities. Process employed two phase separation,
followed by heating and dehydration. Installation of facilities for crude export, gas
lift, water injection and utilities. Development was powered through extension of
Rabi 22KV system. Installation of EPF capable of 8 kbbl/d initial production.
 Completion of basic and detailed design, long lead procurement and expediting to
site. Completion of all civils and preparation for construction contract issue. Project
budgeted at $105 million.
Project Engineer
January 2001- January 2003 Shell Gabon, Gamba, Gamba and Rabi Oilfields.
 Rabi Gas lift/ Gas Injection capacity upgrade: Implement capacity up-grades of
the field gas lift and gas injection systems.
 Installation and commissioning of lift gas collection and distribution pipeline systems
in Rabi field. Sponsor for the project including: HAZOP and HAZID risk assessment
studies. Managed all phases from concept to commissioning and handover.
 Gamba Terminal produced water treatment capacity upgrade: Doubled terminal
produced water systems processing capacity via installation of gas floatation units.
 Completed upgrade, reducing oil in water content discharged to sea to below
company target of 4 ppm. Completed project from concept to commissioning and
handover.
Senior Mechanical Engineer
March 2000- January 2001 Gasco, Abu Dhabi, BuHasa NGL Plant.
 BuHasa NGL Plant Capacity Expansion: Front end engineering design (FEED)
review, estimation and planning, for NGL Plant capacity expansion.
 P&ID preparation & review, with tie-in planning for molecular sieve, cryogenic HEX,
turbo expander / compressor and plant residue gas compressor.
Scott Smith
10 Rosewell Terrace
Aberdeen, AB15 6HP
+41 79 172 4640
Scottsr12000@yahoo.com
Project Engineer
May 1995- August 1999 Shell Gabon, Gamba, Lucina (offshore) and Rabi Oilfields.
 Co-ordination and planning of multiple projects for brown field system upgrades
within Rabi and satellite fields. Ownership of the Facility Improvement/Change (FIC)
Process, management of design, procurement and construction activities,
Integration with operations, maintenance and shutdown planning, project
estimation, budget and cost control.
 Lift gas system de-bottlenecking upgrade, involving nine hot taps into 80 barg
operating gas lines. Gathering station de-bottle necking: installation of Coriolis
meters, allowing conversion of test train facilities to production service. Ninth water
injection pump: additional capacity in accordance with projected water balance.
Mechanical/ Process Engineer
January 1993 - May 1995 Shell Gabon, Gamba, Lucina (offshore) and Rabi Oilfields.
 Field Upgrades - Mechanical / Process design, procurement and construction
activities for multiple projects on Shell Gabon operated concessions. Production of:
conceptual studies and key documents leading to detail design and construction.
Preparation of equipment specifications, requisitions and completion of bid analysis
and system handover to operations.
 Completed and handed over approximately 150 plant change/modifications,
covering process systems and utilities: wellheads, manifolds, vessels, pumps,
compressors, and control elements within these systems.
Mechanical/ Process Engineer
September 1989- January 1993 PLT Engineering, London.
 Process modeling/simulation for oil, gas and multi-product, single and networked
pipeline systems. Basic and detailed engineering including preparation of Design
Basis Manuals, PFD's, P&ID's, and study reports. Preparation of specification and
requisition documents and follow up bid analysis.
 Dorsch Consult - Stegal/Midal Pipeline System Development.
 Kinetica Ltd. - Theddlethorpe to London Gas Pipeline.
 Esso Petroleum Co. - Brecon Pump Station.
 Philippines Shell Petroleum Corp. - (PSPC), Tabanga Terminal Extension.
 ADCO - Jebel Dhana Piping Replacement.

Scott Smith-complete-employment-history

  • 1.
    Scott Smith 10 RosewellTerrace Aberdeen, AB15 6HP +41 79 172 4640 Scottsr12000@yahoo.com Employment History Senior Facilities / Project Engineering Manager October 2013 – present. Oryx Petroleum, Geneva.  Demir Dhag DD (Hawler Block, Kurdistan) Greenfield development: GOSP Production facility with H2S stripping, Export Pipeline and Tanker Loading Station (TLS) facilities. In -field infrastructure: pipelines/communications and well flowlines.  Achieved First Oil from DD block via EPF Facilities and First Export to road tankers. In parallel with the design and installation of 30kbpd sweet and 10kbpd sour service production trains, with export pumping and fiscal metering to KEP (Kurdistan Export Pipeline) and TLS for local market sales. In-field infrastructure: 10km of buried 12” pipeline to TLS, 1km 16” export spur to KEP and 20km of 6” flowlines from wells. Senior FPSO Project Manager September 2005 – September 2013 Addax Petroleum, Geneva.  OML126 (Offshore) Okwori : Management of external design contractors and in- house teams in the preparation, revision and implementation of Field Development Plan. Scope covered development of production and control systems for an additional sixteen subsea wells. Project developed three six-slot subsea manifolded areas producing to an existing FPSO. As an on-going development project, significant subsea re-architecture was required.  Management of design teams in the preparation of documents for FEED initiation and conception. Option selection and evaluation leading to concept approval through gated project management processes.  Okwori Phase III Development: Expansion of FPSO process facilities to accept seven new producers and one gas injection well. Expansion of FPSO balcony with six additional manifold slots and a subsea well control system, with electro-hydraulic capability. Tie back of new subsea wellheads to FPSO. Development of improved well response measures. Award and completion of design, procurement and manufacturing contracts to x-works of all project equipment within budget and schedule. Design and manufacture value circa $140M.  Management of manufacturing process achieving manufacturing targets for 26km of subsea EH multi-core umbilicals, high pressure flexible flowlines and eight dynamic risers. Management of installation processes topside and subsea spread contractors. Installation and commissioning of subsea production and control systems.  Okwori Pase II and Adanga North Field Development: Expansion of FPSO facilities to accommodate eight new manifold slots and installation of a multiplexed electro-hydraulic subsea control pod. Development and tie back of six subsea wellheads risers, flowlines and control umbilicals to existing FPSO. Offshore installation and tie-in of new manifold slots. Installation of flowlines, gas lift and control umbilicals, with both direct hydraulic and multiplexed communications-on- power control schemes. Development of the Adanga North Field proposed as an 18 well development with two platforms tied back to Adanga central production facilities. Construction and installation of single extended well test platform for field appraisal leading to financial investment decision for entire Adanga North Field Development. Installation of extended welltest platform production and gaslift subsea pipelines to host facilities.
  • 2.
    Scott Smith 10 RosewellTerrace Aberdeen, AB15 6HP +41 79 172 4640 Scottsr12000@yahoo.com Resident Project Engineer January 2003- August 2005 Shell Gabon, Gamba, Rabi and Toucan Oilfields  Rabi Phase III Field Expansion Project : An Interface Management role between Company and EPCM contractor. Project objectives were to increase gas injection capacity, improving reservoir management and achieve “flares-out” targets. A new booster compression plant was installed and existing lift compressors re-wheeled. Balance of plant serving lift compression stages required overhaul to meet increased duty. Control systems were upgraded from pneumatics to electronics to respond to faster system dynamics. Gas collection and distribution pipeline networks were also expanded.  Project doubled Rabi gas compression capacity to 120mmscfd for gas injection and gas lift and systems, and achieved “flares out” before 2007 deadline. Project budget $148 M.  Toucan Greenfield Development Project: Construction of greenfield GOSP production facility for 20kbpd, three phase processing of heavy, 18API crude, and export to Rabi Central host facilities. Process employed two phase separation, followed by heating and dehydration. Installation of facilities for crude export, gas lift, water injection and utilities. Development was powered through extension of Rabi 22KV system. Installation of EPF capable of 8 kbbl/d initial production.  Completion of basic and detailed design, long lead procurement and expediting to site. Completion of all civils and preparation for construction contract issue. Project budgeted at $105 million. Project Engineer January 2001- January 2003 Shell Gabon, Gamba, Gamba and Rabi Oilfields.  Rabi Gas lift/ Gas Injection capacity upgrade: Implement capacity up-grades of the field gas lift and gas injection systems.  Installation and commissioning of lift gas collection and distribution pipeline systems in Rabi field. Sponsor for the project including: HAZOP and HAZID risk assessment studies. Managed all phases from concept to commissioning and handover.  Gamba Terminal produced water treatment capacity upgrade: Doubled terminal produced water systems processing capacity via installation of gas floatation units.  Completed upgrade, reducing oil in water content discharged to sea to below company target of 4 ppm. Completed project from concept to commissioning and handover. Senior Mechanical Engineer March 2000- January 2001 Gasco, Abu Dhabi, BuHasa NGL Plant.  BuHasa NGL Plant Capacity Expansion: Front end engineering design (FEED) review, estimation and planning, for NGL Plant capacity expansion.  P&ID preparation & review, with tie-in planning for molecular sieve, cryogenic HEX, turbo expander / compressor and plant residue gas compressor.
  • 3.
    Scott Smith 10 RosewellTerrace Aberdeen, AB15 6HP +41 79 172 4640 Scottsr12000@yahoo.com Project Engineer May 1995- August 1999 Shell Gabon, Gamba, Lucina (offshore) and Rabi Oilfields.  Co-ordination and planning of multiple projects for brown field system upgrades within Rabi and satellite fields. Ownership of the Facility Improvement/Change (FIC) Process, management of design, procurement and construction activities, Integration with operations, maintenance and shutdown planning, project estimation, budget and cost control.  Lift gas system de-bottlenecking upgrade, involving nine hot taps into 80 barg operating gas lines. Gathering station de-bottle necking: installation of Coriolis meters, allowing conversion of test train facilities to production service. Ninth water injection pump: additional capacity in accordance with projected water balance. Mechanical/ Process Engineer January 1993 - May 1995 Shell Gabon, Gamba, Lucina (offshore) and Rabi Oilfields.  Field Upgrades - Mechanical / Process design, procurement and construction activities for multiple projects on Shell Gabon operated concessions. Production of: conceptual studies and key documents leading to detail design and construction. Preparation of equipment specifications, requisitions and completion of bid analysis and system handover to operations.  Completed and handed over approximately 150 plant change/modifications, covering process systems and utilities: wellheads, manifolds, vessels, pumps, compressors, and control elements within these systems. Mechanical/ Process Engineer September 1989- January 1993 PLT Engineering, London.  Process modeling/simulation for oil, gas and multi-product, single and networked pipeline systems. Basic and detailed engineering including preparation of Design Basis Manuals, PFD's, P&ID's, and study reports. Preparation of specification and requisition documents and follow up bid analysis.  Dorsch Consult - Stegal/Midal Pipeline System Development.  Kinetica Ltd. - Theddlethorpe to London Gas Pipeline.  Esso Petroleum Co. - Brecon Pump Station.  Philippines Shell Petroleum Corp. - (PSPC), Tabanga Terminal Extension.  ADCO - Jebel Dhana Piping Replacement.