SlideShare a Scribd company logo
RV THUWAL REFIT
PROJECT OVERVIEW
27/09/2017 – 02/02/2018
15 February 2018
RV Thuwal – Condition Summary
RV Thuwal operates in the Red Sea in harsh conditions. The vessel’s condition was a
reflection of heavy use, harsh conditions and extended dry-docking and maintenance
periods.
VESSEL HISTORY
PROJECT OVERVIEW
Vessel Refit Requirements and Yard Selection
A Scientific, Electrical and HVAC upgrade provided a trigger for a vessel refit.
After a broad search and using a rating system, six yards were considered based on
quality, price and location; it was decided that the Lusben Shipyard in Viareggio, Italy
was the preferred option.
Project deadlines
The vessel arrived at Lusben Shipyard, Viareggio on 27/09/2017 with a projected
departure date of 27/12/2017.
The three month refit project work list doubled quickly and many of the tasks that were
added were complex and required more time.
Project Manager Isabelle Bazile did not miss a day during this period and ensured the RV
Thuwal was a high priority vessel for the Shipyard and contractors.
PROJECT OVERVIEW
PROJECT MANAGEMENT
Maritime Survey Australia appointed as project managers
Maritime Survey Australia managed the project using a cloud drive system enabling all
parties to monitor the project in real time.
The project time line was updated daily and images were uploading with specific dates
and locations.
Furthermore, a weekly report was sent to management and as the project headed
towards completion a daily report was also sent.
Maritime Survey Australia is happy to report that the project was a success.
WORKS COMPLETED
 Bilge pump system service
 Main engine throttle repair
 Fire system service
 Sea water valve service.
 Scientific equipment package
 Dimensional control survey
 Propeller shaft replacement
 Galley upgrade
 Refrigeration upgrade
 Mechanical seal replacement
 Fire Pump installation
 Electronic work package
 Navigation System
 HVAC work package
 Hauling and Standing
 Rudder shaft removal and service
 Water tank cleaning
 Anti-fouling paint application
 Diesel tank cleaning
 Seawater valves
 Hamilton jet routine service
 Propeller shaft removal and service
 Sewage treatment cleaning
CHALLENGES
Major tasks not included in the original work list.
• Hull plate replacement
• Galley upgrade
• Anchor winch overhaul
• Bow Thruster overhauled
• Hamilton jets
• Fresh Water system
• Bilge system and valve upgrade
• Main Engine Shaft driveline
Condition Assessment
Various holes were identified in the hull.
HULL
Actions
 Washing of the under waterline with
high pressure water machine.
 Hull blasting using Garnet 20/40
sand.
 Application of HEMPEL cycle epoxy
primer & antifouling.
 Cutting of the affected plates (six
areas).
 Welding of new hull plates (ALU
5083).
 Completed paint application on new
plates.
 Fabrication of new plates for existing
central keel blister & fitting of the
new deep sounder transducer.
 Supply of new zinc anodes.
HULL
Details of previous installation
• 3 Direct expansion units
(approx 60,000 BTU)
• Domestic Fancoil units
• No longer in legal production
R22 Refrigerant
• No condensate drainage
• No Fresh air make up ventilation
system
• Reduction in suction pressure
when multiple units in use.
HVAC UPGRADE
New installation
 360,000 BTU system sufficient
for Saudi Arabia
 25 Fancoil units were installed
 New piping system throughout
 Redundancy in system pumps
 Soft starting compressor which
reduce generator loads
HVAC UPGRADE
 Issuing of new
drawings.
 Blister fabrication and
welded on to the hull.
 Blister cycle paint.
 Transducers installation
(EM710; ADCP).
 Transceiver installation.
 Motion sensor
installation.
 Sound velocity sensor
installation.
 Cabling between all
units.
BLISTER &
SCIENTIFIC EQUIPMENT
BLISTER & SCIENTIFIC EQUIPMENT
Details of previous conditions:
• The existing shaft has been found out of round.
• The stern tube has been found badly corroded.
• Cutless bearing ceased on to the the surface.
MAIN ENGINE
PROPELLER SHAFT
Actions:
 Removal of the old shaft (4 days).
 Laser verification of the alignment from the engine to the propeller.
 Boring of the stern tube (outside and inside) to remove corrosion (4 mm)
 Fabrication of custom made cutless bearings.
 Installation of a new shaft in V174 steel.
 Installation of a mechanical seal (MICROTEM mod. MTM903 1150 S1NGDJ1J1)
MAIN ENGINE PROPELLER SHAFT
Details of previous conditions:
The vessel was not fitted with a dedicated fire pump prior to the refit.
Actions:
 New Bilge, Fire Pump and General Service Pump installed.
 Dedicated Fire pump in both main engine room and aft engine room.
Before After
BILGE FIRE SYSTEM
The company, Olectric was chosen after receiving three quotes. They were chosen
based on price, quality and availability.
The following projects were completed:
1. 425/220 upgrade (circuit breakers, governors, software, synchronizing units etc.)
2. Survey room upgrade (switchboards, cabling, switches, circuit boards etc.)
3. Navigation and communication upgrade (DC switchboard, Emergency switchboard,
Battery isolator, Navigation systems etc.)
ELECTRICAL UPGRADE
Pictured below is the condition of the wiring in the wheelhouse
ELECTRICAL UPGRADE
Before After
Survey room
Before After
ELECTRICAL UPGRADE
ELECTRICAL UPGRADE
Major Achievements:
 Safer vessel – Electrical stray currents and hazards identified and removed, Fire
system now compliant.
 Holes in the Hull have been repaired.
 Fuel Savings
 Energy Savings
 Scientific equipment upgrade
 Completed works including extra items in 4 months
 Crew comfort – HVAC upgrade, LED lighting, Galley condition
 Navigation Equipment upgrade
 Communication Equipment upgrade
 Anchor winch now safer and compliant
 Bow Thruster now operational
 Throttle control now provides Master with better stabilization for scientists.
For any further information for any future project email
mail@maritimesurveyaustralia.com.au

More Related Content

What's hot

Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
Vedam design & Techincal Consultancy Pvt Ltd.
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
DOE Office of River Protection
 
Russell bruce cv 2016.
Russell bruce cv 2016.Russell bruce cv 2016.
Russell bruce cv 2016.
Russell Bruce
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONElliott Molnar
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011abughaws
 
14OTC 25107-Active Heating for Life of Field Flow Assurance
14OTC 25107-Active Heating for Life of Field Flow Assurance14OTC 25107-Active Heating for Life of Field Flow Assurance
14OTC 25107-Active Heating for Life of Field Flow AssurancePaul McDermott
 
Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith
 
Kealii Ribao - Lam Research MECOP Project List
Kealii Ribao - Lam Research MECOP Project ListKealii Ribao - Lam Research MECOP Project List
Kealii Ribao - Lam Research MECOP Project ListKealii Ribao
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
Islam Nassef
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
DeanGarratt
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017Czero
 
Stewart Kane CV 2015
Stewart Kane CV 2015Stewart Kane CV 2015
Stewart Kane CV 2015Stewart Kane
 
Hydroworks innovation
Hydroworks innovationHydroworks innovation
Hydroworks innovation
Ian McInnes
 

What's hot (20)

Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
 
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
Office of River Protection Manager Scott Samuelson’s tank waste cleanup updat...
 
Russell bruce cv 2016.
Russell bruce cv 2016.Russell bruce cv 2016.
Russell bruce cv 2016.
 
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATIONNRG INTERN POWER DOWN END OF SUMMER PRESENTATION
NRG INTERN POWER DOWN END OF SUMMER PRESENTATION
 
ERICK RENALDI REZAL CV
ERICK RENALDI REZAL CVERICK RENALDI REZAL CV
ERICK RENALDI REZAL CV
 
EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011EPC-4 Package Status Update September 16-09-2011
EPC-4 Package Status Update September 16-09-2011
 
14OTC 25107-Active Heating for Life of Field Flow Assurance
14OTC 25107-Active Heating for Life of Field Flow Assurance14OTC 25107-Active Heating for Life of Field Flow Assurance
14OTC 25107-Active Heating for Life of Field Flow Assurance
 
Satham Mohamed.A-CV..
Satham Mohamed.A-CV..Satham Mohamed.A-CV..
Satham Mohamed.A-CV..
 
Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-history
 
3 - 01 - 2015
3 - 01 - 20153 - 01 - 2015
3 - 01 - 2015
 
Kealii Ribao - Lam Research MECOP Project List
Kealii Ribao - Lam Research MECOP Project ListKealii Ribao - Lam Research MECOP Project List
Kealii Ribao - Lam Research MECOP Project List
 
Richard Martinez #1 PDF
Richard Martinez #1 PDFRichard Martinez #1 PDF
Richard Martinez #1 PDF
 
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKSDAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
DAMMAM SECOND INDUSTRIAL CITY - IPS REHABILITATION WORKS
 
Harshad Patel Resume- hkp-G15
Harshad Patel Resume- hkp-G15Harshad Patel Resume- hkp-G15
Harshad Patel Resume- hkp-G15
 
OKEREKE CHISOM CV
OKEREKE CHISOM CVOKEREKE CHISOM CV
OKEREKE CHISOM CV
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
 
Stewart Kane CV 2015
Stewart Kane CV 2015Stewart Kane CV 2015
Stewart Kane CV 2015
 
Hydroworks innovation
Hydroworks innovationHydroworks innovation
Hydroworks innovation
 

Similar to RV Thuwal - Refit project overview by Maritime Survey Australia

Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Neil Woodward
 
Oil and Gas Applications & Innovations
Oil and Gas Applications & InnovationsOil and Gas Applications & Innovations
Oil and Gas Applications & Innovations
Altra Industrial Motion
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
Mujahid Ali Akhtar
 
C&K Overview Presentation - 6
C&K Overview Presentation - 6C&K Overview Presentation - 6
C&K Overview Presentation - 6Tad Jenkins
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
Amer Abdul Aziz
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
DeanDallwitz
 
Piotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut
 
Lining Track Records & Case Histories
Lining Track Records & Case HistoriesLining Track Records & Case Histories
Lining Track Records & Case Histories
International Paint
 
Presentation on cooling tower
Presentation on cooling towerPresentation on cooling tower
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
Comit Projects Ltd
 
Hvac chiller Engineer Tech
Hvac chiller Engineer Tech Hvac chiller Engineer Tech
Hvac chiller Engineer Tech
Kamran Saeed
 
Marine Market Applications & Innovations
Marine Market Applications & InnovationsMarine Market Applications & Innovations
Marine Market Applications & Innovations
Altra Industrial Motion
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTAled Long
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
UK Carbon Capture and Storage Research Centre
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
Shaun West
 
Technical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._FreebornTechnical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._FreebornBob Freeborn
 

Similar to RV Thuwal - Refit project overview by Maritime Survey Australia (20)

Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...Subsea pipelines the remotely welded retrofit tee for hot tap applications   ...
Subsea pipelines the remotely welded retrofit tee for hot tap applications ...
 
COMPL OF WORKS1
COMPL OF WORKS1COMPL OF WORKS1
COMPL OF WORKS1
 
Oil and Gas Applications & Innovations
Oil and Gas Applications & InnovationsOil and Gas Applications & Innovations
Oil and Gas Applications & Innovations
 
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
CASE STUDY: JABEL ALI REFINERY SHUTDOWN-2016
 
C&K Overview Presentation - 6
C&K Overview Presentation - 6C&K Overview Presentation - 6
C&K Overview Presentation - 6
 
Stress Analysis in District Cooling Projects
Stress Analysis in District Cooling ProjectsStress Analysis in District Cooling Projects
Stress Analysis in District Cooling Projects
 
Appsolu
AppsoluAppsolu
Appsolu
 
Barangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
 
11-IAGT-202_paper
11-IAGT-202_paper11-IAGT-202_paper
11-IAGT-202_paper
 
Piotr Blaut Student Placement
Piotr Blaut Student PlacementPiotr Blaut Student Placement
Piotr Blaut Student Placement
 
Project review
Project reviewProject review
Project review
 
Lining Track Records & Case Histories
Lining Track Records & Case HistoriesLining Track Records & Case Histories
Lining Track Records & Case Histories
 
Presentation on cooling tower
Presentation on cooling towerPresentation on cooling tower
Presentation on cooling tower
 
CD 2016 March - Advisian Showcase
CD 2016 March - Advisian ShowcaseCD 2016 March - Advisian Showcase
CD 2016 March - Advisian Showcase
 
Hvac chiller Engineer Tech
Hvac chiller Engineer Tech Hvac chiller Engineer Tech
Hvac chiller Engineer Tech
 
Marine Market Applications & Innovations
Marine Market Applications & InnovationsMarine Market Applications & Innovations
Marine Market Applications & Innovations
 
KEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXTKEY ATTRIBUTES FULL TEXT
KEY ATTRIBUTES FULL TEXT
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
 
Technical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._FreebornTechnical_Career_Accomplishments-R._Freeborn
Technical_Career_Accomplishments-R._Freeborn
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 

RV Thuwal - Refit project overview by Maritime Survey Australia

  • 1. RV THUWAL REFIT PROJECT OVERVIEW 27/09/2017 – 02/02/2018 15 February 2018
  • 2. RV Thuwal – Condition Summary RV Thuwal operates in the Red Sea in harsh conditions. The vessel’s condition was a reflection of heavy use, harsh conditions and extended dry-docking and maintenance periods. VESSEL HISTORY
  • 3. PROJECT OVERVIEW Vessel Refit Requirements and Yard Selection A Scientific, Electrical and HVAC upgrade provided a trigger for a vessel refit. After a broad search and using a rating system, six yards were considered based on quality, price and location; it was decided that the Lusben Shipyard in Viareggio, Italy was the preferred option.
  • 4. Project deadlines The vessel arrived at Lusben Shipyard, Viareggio on 27/09/2017 with a projected departure date of 27/12/2017. The three month refit project work list doubled quickly and many of the tasks that were added were complex and required more time. Project Manager Isabelle Bazile did not miss a day during this period and ensured the RV Thuwal was a high priority vessel for the Shipyard and contractors. PROJECT OVERVIEW
  • 5. PROJECT MANAGEMENT Maritime Survey Australia appointed as project managers Maritime Survey Australia managed the project using a cloud drive system enabling all parties to monitor the project in real time. The project time line was updated daily and images were uploading with specific dates and locations. Furthermore, a weekly report was sent to management and as the project headed towards completion a daily report was also sent. Maritime Survey Australia is happy to report that the project was a success.
  • 6. WORKS COMPLETED  Bilge pump system service  Main engine throttle repair  Fire system service  Sea water valve service.  Scientific equipment package  Dimensional control survey  Propeller shaft replacement  Galley upgrade  Refrigeration upgrade  Mechanical seal replacement  Fire Pump installation  Electronic work package  Navigation System  HVAC work package  Hauling and Standing  Rudder shaft removal and service  Water tank cleaning  Anti-fouling paint application  Diesel tank cleaning  Seawater valves  Hamilton jet routine service  Propeller shaft removal and service  Sewage treatment cleaning
  • 7. CHALLENGES Major tasks not included in the original work list. • Hull plate replacement • Galley upgrade • Anchor winch overhaul • Bow Thruster overhauled • Hamilton jets • Fresh Water system • Bilge system and valve upgrade • Main Engine Shaft driveline
  • 8. Condition Assessment Various holes were identified in the hull. HULL
  • 9. Actions  Washing of the under waterline with high pressure water machine.  Hull blasting using Garnet 20/40 sand.  Application of HEMPEL cycle epoxy primer & antifouling.  Cutting of the affected plates (six areas).  Welding of new hull plates (ALU 5083).  Completed paint application on new plates.  Fabrication of new plates for existing central keel blister & fitting of the new deep sounder transducer.  Supply of new zinc anodes. HULL
  • 10. Details of previous installation • 3 Direct expansion units (approx 60,000 BTU) • Domestic Fancoil units • No longer in legal production R22 Refrigerant • No condensate drainage • No Fresh air make up ventilation system • Reduction in suction pressure when multiple units in use. HVAC UPGRADE
  • 11. New installation  360,000 BTU system sufficient for Saudi Arabia  25 Fancoil units were installed  New piping system throughout  Redundancy in system pumps  Soft starting compressor which reduce generator loads HVAC UPGRADE
  • 12.  Issuing of new drawings.  Blister fabrication and welded on to the hull.  Blister cycle paint.  Transducers installation (EM710; ADCP).  Transceiver installation.  Motion sensor installation.  Sound velocity sensor installation.  Cabling between all units. BLISTER & SCIENTIFIC EQUIPMENT
  • 13. BLISTER & SCIENTIFIC EQUIPMENT
  • 14. Details of previous conditions: • The existing shaft has been found out of round. • The stern tube has been found badly corroded. • Cutless bearing ceased on to the the surface. MAIN ENGINE PROPELLER SHAFT
  • 15. Actions:  Removal of the old shaft (4 days).  Laser verification of the alignment from the engine to the propeller.  Boring of the stern tube (outside and inside) to remove corrosion (4 mm)  Fabrication of custom made cutless bearings.  Installation of a new shaft in V174 steel.  Installation of a mechanical seal (MICROTEM mod. MTM903 1150 S1NGDJ1J1) MAIN ENGINE PROPELLER SHAFT
  • 16. Details of previous conditions: The vessel was not fitted with a dedicated fire pump prior to the refit. Actions:  New Bilge, Fire Pump and General Service Pump installed.  Dedicated Fire pump in both main engine room and aft engine room. Before After BILGE FIRE SYSTEM
  • 17. The company, Olectric was chosen after receiving three quotes. They were chosen based on price, quality and availability. The following projects were completed: 1. 425/220 upgrade (circuit breakers, governors, software, synchronizing units etc.) 2. Survey room upgrade (switchboards, cabling, switches, circuit boards etc.) 3. Navigation and communication upgrade (DC switchboard, Emergency switchboard, Battery isolator, Navigation systems etc.) ELECTRICAL UPGRADE
  • 18. Pictured below is the condition of the wiring in the wheelhouse ELECTRICAL UPGRADE Before After
  • 21. Major Achievements:  Safer vessel – Electrical stray currents and hazards identified and removed, Fire system now compliant.  Holes in the Hull have been repaired.  Fuel Savings  Energy Savings  Scientific equipment upgrade  Completed works including extra items in 4 months  Crew comfort – HVAC upgrade, LED lighting, Galley condition  Navigation Equipment upgrade  Communication Equipment upgrade  Anchor winch now safer and compliant  Bow Thruster now operational  Throttle control now provides Master with better stabilization for scientists. For any further information for any future project email mail@maritimesurveyaustralia.com.au