Patrick S. Muga
            Cv Presentation




Palawan Philippines Offshore Facility Nov. 2010
Overview
Thirty three (34) years of project management
which includes :
 • Contracting and engineering design
 • Construction and installation,
 • Pre-commissioning, commissioning
 • Safety HSE management
 • I & E management
•   29 years of which were in the oil, gas and shipping industry and EPC projects that
    include the following: QHSSE management, conceptual, feasibility and risk and safety
    assessment studies, FEED and detailed safety and process control design engineering,
    procurement, planning, organizing, QA /QC, construction, offshore installation,
    modification, upgrades, pre-commissioning, start-up and commissioning, drilling
    operations coordination.
•   Experienced production operator and maintenance of international projects and gas
    plant operations for onshore & offshore oil and gas facilities. Said facilities cover FPSO,
    gas plant, terminal, oil refinery, petrochemical and oil gathering station operations, and
    offshore topsides with accommodation platforms.
Overview Continued
•   Led and organized a team of people of various nationalities, including multi-
    discipline engineers (mech., piping, elec., civil, structural, instr. and
    process), who worked on different projects in FEED, detailed design,
    contract administration, construction and commissioning activities; assured
    the flow and completion of work schedule in these projects; monitored
    expenditures, organizational targets, delivery schedules; and ensured that
    such projects were implemented with strict compliance for safety, quality
    and environment standards.

•   Lecturer/ Trainer /Resource Speaker/ facilitator for international and local
    events, conferences and workshops for oil and gas topics including EPCM
    project management, FPSO and Floating LNG risk assessment,
    HAZID/HAZOP studies, instrumentation and electrical control, I&E safety,
    project controls, safety systems, leadership and QC management training.
Position
Senior Project Engineer/ HSSE/ I&E /Commissioning
                     Engineer

Special Skills:

My personal attributes includes the following:

Excellent interpersonal skills, team-building and communication skills
coupled with pragmatism/ flexibility to build good relationship with clients and
people of different cultures and discipline; have a sense of urgency; goal and
task oriented; posses leadership, initiative and strong motivation; very
resourceful, high moral values and dedication to the work and to the project
in particular .. Proactive and common sense approach to decision making
and time management. Always organized, able to take the lead in tough
situations, sensitive to the needs of others, and doing the best quality and
safety to deliver multi-tasks on time within the budget.
Contact Information
                    Home Address:

   14 Kalantiao St., Novaliches, Caloocan City, Philippines
      Home Tel./ Fax No. +632 753 8227/+6327538227
                    CP +63 921 485 0490
             Angola HP tel no. +244 919 158 468

E mail: psmuga@yahoo.com or rdvmuga@yahoo.com, website:
   http://ph.linkedin.com/in/patrickmuga skypeID: psmuga9
Projects Successfully Completed
•   Saudi Arabia : Maintenance, construction and commissioning in Aramco and
    SCECO modification projects. Secured several contracts from Aramco.
•   Libya; Zueitina Oil Company- Zella and Fidda facilities- Natural Gas Plant Projects.
•   Malaysia; PETRONAS / Conoco-Phillips-West Natuna-Duyong gas tie-in Project,
    Exxon Mobil Nigeria - YOHO Topsides Project and EPMI Larut A Topsides
    project(800 million Dollar project), Shell SSB & SSPC Technical Integrity IR Project
    (350 Million USD project)
•   Singapore; Shell Malampaya oil and gas production topsides Project (Upstream cost
    2 billion USD)
•   Myanmar; Premier Oil ,Yetagun Topsides -Oil and Gas Production Platform Project.
•   Indonesia; Conoco- Phillips – Wellhead Platform and FPSO Belanak Project.
•   Vietnam; JVPC (Japan Vietnam Petroleum Corp.) Topsides Oil and gas platform
    Randong I Project.
•   Azerbaijan; AIOC, BP (British Petroleum), Central and West Azeri Topsides and
    drilling offshore platform Project.
•   China; Bayer Polymers Petrochemical Facilities INFRA II Project (polycarbonate &
    polyurethane production).
•   Angola: Chevron onshore Malongo terminal facilities Kerosene Tank Project, Esso
    FPSO (Kiz A and B) offshore multi-discipline brown field maintenance support
    projects, Sonangol SNLPP Block 3 offshore Fire and Gas system upgrade, and PAC
    F4 /F1 Infill project, Chevron Block 14 BBLT offshore flotation water treatment
    project, and Sonangol Refinaria De Luanda onshore Refinery Boiler Upgrades
    Project.
•   Philippines: NIDO Petroleum Oil production facility (AQ Vantage Rig Tindalo 1
Career Summary and Capabilities:
Project and Contract Management:
Fifteen (15) years managing, facilitating, coordinating and assisting project team and contract
administration for brown field and capital projects. Monitor and evaluate subcontract administrators on
the following :
 •   Prepare and review technical bid specifications and proposals, CTR’s, vendor data, resources,
     and liaise with clients, designers, PMT, vendors and subcontractors.
 •   Budget control, Close-out of Subcontractor commercial issues.
 •   Identify back charges and ensure notification to affected parties.
 •   Identification of insurance claims. Issue of Field or Site Instructions.
 •   Input to management of change, schedule change, and progress evaluations.
 •   Ensure full understanding, implementation and full compliance with prevailing company and
     country pertinent rules and regulations.
 •   Provide weekly status on contractual issues to senior management, and recommend innovation
     to improve operation and minimize cost without compromising safety, productivity and
     environmental standards.
 •   Management of Change reviewer/originator and owner for related I & E and multi-discipline
     offshore production platforms and FPSO projects.
 •   Coordinate capital shut-ins related to projects, Health, Environment and Safety, Maintain
     communication with Asset Development engineers and other FE on activities,
 •   Evaluate and Prepare for Drilling Rigs (Primary owners are the Support Engineers, and as
     assigned to Project Engineers) – support well hookup efforts, Support development and
     maintenance of project queue for annual budget planning.
 •   Manage offshore field crews and construction representatives coordination.
 •   Support Asset Development Plan updates, Evaluate opportunities for the capitalization of work
 •   Work directly with field engineers, operations personnel to fully frame opportunity and scope
     projects
Career Summary and Capabilities
                continued:
Project safety, pre-commissioning and Commissioning:

Management/Supervision of up to 300 multi-discipline / multi-cultural Engineers and
Technicians with experience on construction, pre-commissioning and commissioning of
instrumentation and control systems, including supervision of engineers; safety
management, mechanical alignments, motor and transformer tests, hydro testing, leak
testing, pigging, cleaning, flushing, blowing, flooding, re-instatement, preservation, vendor
equipment, start-up and testing, etc., QA/QC, procedure development, operations
supervision, maintenance coordination, punch listing for pipe specifications, equipment
and vessel completion, drawings, operator training.

Commissioning/HSE Management experience includes the following:

 •   Preparing monthly/weekly reports and continuous progress monitoring of projects;
 •   Interaction and coordination amongst various stakeholders, managers, clients, contractors, third
     party consultants and government agencies;
 •   Conduct frequent site visits to monitor method of execution, safety and progress of project
     works as well as decision-making and authority that includes contracting issues, safety, quality
     assurance, management of change, and schedule. Familiar with ExxonMobil, PETRONAS,
     Total, Chevron and Shell project process roadmap for value assurance and governance.
 •   Develop plans for safety talks, tool box talks and development of site HSE Procedure and
     guideline, and Communicate HSE policies, guidelines and standards to all staff through
     presentation.
 •   Prepare and supervise pre-commissioning and commissioning procedures.
Career Summary and Capabilities continued:
Instrumentation and electrical Design and HSE Engineering Mentor

•   Manage, prepare and ensure specifications and design basis for instrument
    and control systems applicable codes and standards
•   Supervise Contractors to validate integrated control and safety system
    architecture and design, ensuring that it meets legislation, codes standards
    and client requirements.
•   Ensure instrumentation and data communications system specifications and
    technical requisitions correctly define client requirements to meet project
    design objectives for control performance and reliability and that test
    inspection and other requirements are appropriately defined.
•   Complete instrument and control design work and deliverables in
    accordance with schedule and budget. - Ensure design interfaces are
    correctly managed with other disciplines in the Project Management Team
•   Supervise /coach junior engineers including development of National staff .
    Participate in safety and risk studies including HAZID, and HAZOP.
•   Provided lecture and training pertaining to safety, risk assessment,
    instrumentation, project management to local engineers and technicians for
    25 years.
Achievements:
•   Received certificate of Appreciation from Top link Event organizers(JB Malaysia) for the successful
    presentation of “Measuring, monitoring and improving project performance” as a guest speaker for the
    Successful Project Management conference held at Corus Hotel KL Malaysia, Sept.27,2010

•   Received certificate of Appreciation from Red Carpet Events Pte Ltd.(Singapore) for the successful
    presentation as a guest speaker for the World round Shape FPSO Platform for Offshore Oil and Gas
    Conference 2010 (22 April 2010). Topics presented was Risk Assessment and Hazop on an FPSO, and
    Reducing Hazards and Operability problems.

•   Received commendation from MCCI Azerbaijan Piping superintendents for delivering on time more
    than 700 hydro test packages (as Hydro test mechanical completions supervisor/coordinator)

•   Received commendation Petronas CARIGALI HUC, Operations and SARKU management for the
    successful first gas project completion held last August 8, 2002 (West Natuna- Duyong gas Tie- in
    Project) witnessed by both Indonesia and Malaysia Head of state . A fast tract project completed on
    time , with simultaneous production and construction activities.

•   Received certificate of Appreciation from Malaysian Shipyard Engineering (MSE) and Esso Production
    Malaysia Inc. (EPMI)- Larut-A CPP) Project Management, acknowledging the contribution for the
    participation, dedication and tireless efforts (as Lead commissioning engineer) in achieving high
    standards of quality and promoting the maintenance of safety throughout the project execution up to
    the successful scheduled load-out. Completed 81% onshore pre-commissioning and commissioning of
    the Topsides Platform. One of the most satisfying aspects of the Larut development is that it was the
    safest project in ExxonMobil’s history in Malaysia. Over 4.6 million work hours were completed over a
    four year period without a single employee or contractor Lost Time Injury.

•   Received commendation for preparing technical proposals which includes preparation and
    implementation of Almutawa Company Policy, maintenance standard manual, safety and Loss
    prevention Manual, QC manual, and securing several awarded contracts from Aramco and Sceco for oil
    & gas refinery maintenance; during the three years as senior E&I, safety & contracts engineer.

•   Philippine Asst. Electrical Engineering. Board exam. result released 1984 with 82.4 % board rating.
Educational Attainment:

College Degree : BS Electrical Engineering. Cebu Institute of Technology University, 1979 Graduate.
               : BS Electronics and Comm. Eng'g, Cebu Institute of Technology University, 1988
                 Graduate
               : Masters in Eng’g CIT, 1983 , (undergraduate)

Professional Licensure : Registered Electrical Engineer. Philippine
Registration No. 0025580

 •   Past Member IEEE ( Institute of Electrical and Electronic Engrs.) member no. 3963485
 •   Professional Drivers license - Philippines, Malaysia, Indonesia and Libya
 •   Holder of Petronas Malaysia Offshore safety passport
 •   Member-Consultant, Society of Industry Leaders
 •   ISNetworld ID No. 01541922
 •   Member LinkedIn: http://ph.linkedin.com/in/patrickmuga
 •   Instrumentation, Automation, and Electrical Systems Network
CABGOC Angola Training:
 •   Alarm Management and Active factory, CABGOC Malongo, 13 Aug,2012
—Subsea Module 1 to 5, 11 Aug 2012
—Contractor HES Management, 30 July 2012
—5Y Incident Investigation Course, CABGOC,16 July 2012
—OE Certification: Leadership Roles and Behavior, CABGOC Malongo 20June 2012
—MOC for Facilities and Operations Workshop (ETC) 14 June 2012
—HES Risk Management-Integrated Risk Prioritization Matrix, 9 June 2012
—FE Process Safety Training 12 June 2012
—Process Safety Management 12 June 2012
—Wellnomics Assessment Reference Point Completion 26 May 2012
—RU 214 Reliability for Leaders (ETC) 3 May 2012
—CSOC Behavioral Survey 1May 2012
—RU 222 Asset Integrity Management for operations, maintenance and Inspection, 29 Dec.2012
—SIS 101 Safety Instrumented System, 19 Dec 2011
—Managing Process safety in OE 11 Dec 2012
—Offshore Water Injection Quality and Facilities Overview, 5 Nov 2011
—Management of Change Training 10 Nov, 2012
—Abz Environmental Management Mod 1, 28 Oct 2011
—Petroleum Geology and Exploration Process, 27 Oct 2011
—Drilling and Well Completions , 26 Oct 2011
—CSOC Certification Module 0, 25 Oct. 2011
 • CPDEP Concepts; Module 1, 18 Oct 2011
Training-continued:
•     ElectricalSafe Work Practice, Chevron (SOP 43) and defensive driving, Angola, August 1- 3, 2011
•     H2S training, Business Conduct Code Ethics Code, CABGOC Cabinda Angola, 19 July 2011
•     Essentials for Enterp. Excellence, Safe Start, Weatherford Office Makati, Philippines, 27 Oct, 2010
•     BOSIET, HUET and H2S Training, CTSI Philippines, (OPITO accredited) Oct 20 to Oct.22. 2010
•     Successful Project Mang't. in Energy, Power and Utilities Industry, Malaysia, 27.Sept-30Sept 2010
•     Project Management on line Training, PRW Malaysia Jan. 2010
•     Fire and Gas systems mapping and survey SSB,Lutong Malaysia Oct, 2009
•     Contracts administration and Management, Ranhill Worley, Malaysia Sept.17, 2009.
•     Offshore Oil and Gas HSE Training, ( HSEMS OHSAS 18001) Philip. Mar 30 to April 3, 2009
•    Safety training : LNG safety, pigging , PTW, H2S, Risk assessment, Habitat & accident investigation
•    H2S Training, Boat transfer compliance, Swing rope compliance, Chevron, Angola 14 Nov.2007
•    HUET and sea survival training, Sonangol training center, Luanda Angola, Jan 2007.
•    INTOOLS Basic operations training, Bayer Integrated site, Shanghai China, Nov-27, 2005
•    Primavera P3 (Computer aided Construction Project management) Manila, 14 Feb,2005
•    Construction Project Mg't (Planning, organizing, Sched. and control) 21 Feb.,01
•    AutoCAD 14 Computer Operations, Visual basic IT Power Module
•    Programmable Logic Controllers (PLC) Allen Bradley 5/15, Zueitina Oil Co. Libya 1996
•    Electrical Energy Efficiency, U.P. ( University of the Philippines) Q.C.July, 1994
•     Maintenance Management Course, Counseling U.P. Feb. 1989,
•     Security Systems, SENELCO, Madrid Spain, April 1986

Psm Cv Presentation Aug 16, 2012

  • 1.
    Patrick S. Muga Cv Presentation Palawan Philippines Offshore Facility Nov. 2010
  • 2.
    Overview Thirty three (34)years of project management which includes : • Contracting and engineering design • Construction and installation, • Pre-commissioning, commissioning • Safety HSE management • I & E management • 29 years of which were in the oil, gas and shipping industry and EPC projects that include the following: QHSSE management, conceptual, feasibility and risk and safety assessment studies, FEED and detailed safety and process control design engineering, procurement, planning, organizing, QA /QC, construction, offshore installation, modification, upgrades, pre-commissioning, start-up and commissioning, drilling operations coordination. • Experienced production operator and maintenance of international projects and gas plant operations for onshore & offshore oil and gas facilities. Said facilities cover FPSO, gas plant, terminal, oil refinery, petrochemical and oil gathering station operations, and offshore topsides with accommodation platforms.
  • 3.
    Overview Continued • Led and organized a team of people of various nationalities, including multi- discipline engineers (mech., piping, elec., civil, structural, instr. and process), who worked on different projects in FEED, detailed design, contract administration, construction and commissioning activities; assured the flow and completion of work schedule in these projects; monitored expenditures, organizational targets, delivery schedules; and ensured that such projects were implemented with strict compliance for safety, quality and environment standards. • Lecturer/ Trainer /Resource Speaker/ facilitator for international and local events, conferences and workshops for oil and gas topics including EPCM project management, FPSO and Floating LNG risk assessment, HAZID/HAZOP studies, instrumentation and electrical control, I&E safety, project controls, safety systems, leadership and QC management training.
  • 4.
    Position Senior Project Engineer/HSSE/ I&E /Commissioning Engineer Special Skills: My personal attributes includes the following: Excellent interpersonal skills, team-building and communication skills coupled with pragmatism/ flexibility to build good relationship with clients and people of different cultures and discipline; have a sense of urgency; goal and task oriented; posses leadership, initiative and strong motivation; very resourceful, high moral values and dedication to the work and to the project in particular .. Proactive and common sense approach to decision making and time management. Always organized, able to take the lead in tough situations, sensitive to the needs of others, and doing the best quality and safety to deliver multi-tasks on time within the budget.
  • 5.
    Contact Information Home Address: 14 Kalantiao St., Novaliches, Caloocan City, Philippines Home Tel./ Fax No. +632 753 8227/+6327538227 CP +63 921 485 0490 Angola HP tel no. +244 919 158 468 E mail: psmuga@yahoo.com or rdvmuga@yahoo.com, website: http://ph.linkedin.com/in/patrickmuga skypeID: psmuga9
  • 6.
    Projects Successfully Completed • Saudi Arabia : Maintenance, construction and commissioning in Aramco and SCECO modification projects. Secured several contracts from Aramco. • Libya; Zueitina Oil Company- Zella and Fidda facilities- Natural Gas Plant Projects. • Malaysia; PETRONAS / Conoco-Phillips-West Natuna-Duyong gas tie-in Project, Exxon Mobil Nigeria - YOHO Topsides Project and EPMI Larut A Topsides project(800 million Dollar project), Shell SSB & SSPC Technical Integrity IR Project (350 Million USD project) • Singapore; Shell Malampaya oil and gas production topsides Project (Upstream cost 2 billion USD) • Myanmar; Premier Oil ,Yetagun Topsides -Oil and Gas Production Platform Project. • Indonesia; Conoco- Phillips – Wellhead Platform and FPSO Belanak Project. • Vietnam; JVPC (Japan Vietnam Petroleum Corp.) Topsides Oil and gas platform Randong I Project. • Azerbaijan; AIOC, BP (British Petroleum), Central and West Azeri Topsides and drilling offshore platform Project. • China; Bayer Polymers Petrochemical Facilities INFRA II Project (polycarbonate & polyurethane production). • Angola: Chevron onshore Malongo terminal facilities Kerosene Tank Project, Esso FPSO (Kiz A and B) offshore multi-discipline brown field maintenance support projects, Sonangol SNLPP Block 3 offshore Fire and Gas system upgrade, and PAC F4 /F1 Infill project, Chevron Block 14 BBLT offshore flotation water treatment project, and Sonangol Refinaria De Luanda onshore Refinery Boiler Upgrades Project. • Philippines: NIDO Petroleum Oil production facility (AQ Vantage Rig Tindalo 1
  • 7.
    Career Summary andCapabilities: Project and Contract Management: Fifteen (15) years managing, facilitating, coordinating and assisting project team and contract administration for brown field and capital projects. Monitor and evaluate subcontract administrators on the following : • Prepare and review technical bid specifications and proposals, CTR’s, vendor data, resources, and liaise with clients, designers, PMT, vendors and subcontractors. • Budget control, Close-out of Subcontractor commercial issues. • Identify back charges and ensure notification to affected parties. • Identification of insurance claims. Issue of Field or Site Instructions. • Input to management of change, schedule change, and progress evaluations. • Ensure full understanding, implementation and full compliance with prevailing company and country pertinent rules and regulations. • Provide weekly status on contractual issues to senior management, and recommend innovation to improve operation and minimize cost without compromising safety, productivity and environmental standards. • Management of Change reviewer/originator and owner for related I & E and multi-discipline offshore production platforms and FPSO projects. • Coordinate capital shut-ins related to projects, Health, Environment and Safety, Maintain communication with Asset Development engineers and other FE on activities, • Evaluate and Prepare for Drilling Rigs (Primary owners are the Support Engineers, and as assigned to Project Engineers) – support well hookup efforts, Support development and maintenance of project queue for annual budget planning. • Manage offshore field crews and construction representatives coordination. • Support Asset Development Plan updates, Evaluate opportunities for the capitalization of work • Work directly with field engineers, operations personnel to fully frame opportunity and scope projects
  • 8.
    Career Summary andCapabilities continued: Project safety, pre-commissioning and Commissioning: Management/Supervision of up to 300 multi-discipline / multi-cultural Engineers and Technicians with experience on construction, pre-commissioning and commissioning of instrumentation and control systems, including supervision of engineers; safety management, mechanical alignments, motor and transformer tests, hydro testing, leak testing, pigging, cleaning, flushing, blowing, flooding, re-instatement, preservation, vendor equipment, start-up and testing, etc., QA/QC, procedure development, operations supervision, maintenance coordination, punch listing for pipe specifications, equipment and vessel completion, drawings, operator training. Commissioning/HSE Management experience includes the following: • Preparing monthly/weekly reports and continuous progress monitoring of projects; • Interaction and coordination amongst various stakeholders, managers, clients, contractors, third party consultants and government agencies; • Conduct frequent site visits to monitor method of execution, safety and progress of project works as well as decision-making and authority that includes contracting issues, safety, quality assurance, management of change, and schedule. Familiar with ExxonMobil, PETRONAS, Total, Chevron and Shell project process roadmap for value assurance and governance. • Develop plans for safety talks, tool box talks and development of site HSE Procedure and guideline, and Communicate HSE policies, guidelines and standards to all staff through presentation. • Prepare and supervise pre-commissioning and commissioning procedures.
  • 9.
    Career Summary andCapabilities continued: Instrumentation and electrical Design and HSE Engineering Mentor • Manage, prepare and ensure specifications and design basis for instrument and control systems applicable codes and standards • Supervise Contractors to validate integrated control and safety system architecture and design, ensuring that it meets legislation, codes standards and client requirements. • Ensure instrumentation and data communications system specifications and technical requisitions correctly define client requirements to meet project design objectives for control performance and reliability and that test inspection and other requirements are appropriately defined. • Complete instrument and control design work and deliverables in accordance with schedule and budget. - Ensure design interfaces are correctly managed with other disciplines in the Project Management Team • Supervise /coach junior engineers including development of National staff . Participate in safety and risk studies including HAZID, and HAZOP. • Provided lecture and training pertaining to safety, risk assessment, instrumentation, project management to local engineers and technicians for 25 years.
  • 10.
    Achievements: • Received certificate of Appreciation from Top link Event organizers(JB Malaysia) for the successful presentation of “Measuring, monitoring and improving project performance” as a guest speaker for the Successful Project Management conference held at Corus Hotel KL Malaysia, Sept.27,2010 • Received certificate of Appreciation from Red Carpet Events Pte Ltd.(Singapore) for the successful presentation as a guest speaker for the World round Shape FPSO Platform for Offshore Oil and Gas Conference 2010 (22 April 2010). Topics presented was Risk Assessment and Hazop on an FPSO, and Reducing Hazards and Operability problems. • Received commendation from MCCI Azerbaijan Piping superintendents for delivering on time more than 700 hydro test packages (as Hydro test mechanical completions supervisor/coordinator) • Received commendation Petronas CARIGALI HUC, Operations and SARKU management for the successful first gas project completion held last August 8, 2002 (West Natuna- Duyong gas Tie- in Project) witnessed by both Indonesia and Malaysia Head of state . A fast tract project completed on time , with simultaneous production and construction activities. • Received certificate of Appreciation from Malaysian Shipyard Engineering (MSE) and Esso Production Malaysia Inc. (EPMI)- Larut-A CPP) Project Management, acknowledging the contribution for the participation, dedication and tireless efforts (as Lead commissioning engineer) in achieving high standards of quality and promoting the maintenance of safety throughout the project execution up to the successful scheduled load-out. Completed 81% onshore pre-commissioning and commissioning of the Topsides Platform. One of the most satisfying aspects of the Larut development is that it was the safest project in ExxonMobil’s history in Malaysia. Over 4.6 million work hours were completed over a four year period without a single employee or contractor Lost Time Injury. • Received commendation for preparing technical proposals which includes preparation and implementation of Almutawa Company Policy, maintenance standard manual, safety and Loss prevention Manual, QC manual, and securing several awarded contracts from Aramco and Sceco for oil & gas refinery maintenance; during the three years as senior E&I, safety & contracts engineer. • Philippine Asst. Electrical Engineering. Board exam. result released 1984 with 82.4 % board rating.
  • 11.
    Educational Attainment: College Degree: BS Electrical Engineering. Cebu Institute of Technology University, 1979 Graduate. : BS Electronics and Comm. Eng'g, Cebu Institute of Technology University, 1988 Graduate : Masters in Eng’g CIT, 1983 , (undergraduate) Professional Licensure : Registered Electrical Engineer. Philippine Registration No. 0025580 • Past Member IEEE ( Institute of Electrical and Electronic Engrs.) member no. 3963485 • Professional Drivers license - Philippines, Malaysia, Indonesia and Libya • Holder of Petronas Malaysia Offshore safety passport • Member-Consultant, Society of Industry Leaders • ISNetworld ID No. 01541922 • Member LinkedIn: http://ph.linkedin.com/in/patrickmuga • Instrumentation, Automation, and Electrical Systems Network
  • 12.
    CABGOC Angola Training: • Alarm Management and Active factory, CABGOC Malongo, 13 Aug,2012 —Subsea Module 1 to 5, 11 Aug 2012 —Contractor HES Management, 30 July 2012 —5Y Incident Investigation Course, CABGOC,16 July 2012 —OE Certification: Leadership Roles and Behavior, CABGOC Malongo 20June 2012 —MOC for Facilities and Operations Workshop (ETC) 14 June 2012 —HES Risk Management-Integrated Risk Prioritization Matrix, 9 June 2012 —FE Process Safety Training 12 June 2012 —Process Safety Management 12 June 2012 —Wellnomics Assessment Reference Point Completion 26 May 2012 —RU 214 Reliability for Leaders (ETC) 3 May 2012 —CSOC Behavioral Survey 1May 2012 —RU 222 Asset Integrity Management for operations, maintenance and Inspection, 29 Dec.2012 —SIS 101 Safety Instrumented System, 19 Dec 2011 —Managing Process safety in OE 11 Dec 2012 —Offshore Water Injection Quality and Facilities Overview, 5 Nov 2011 —Management of Change Training 10 Nov, 2012 —Abz Environmental Management Mod 1, 28 Oct 2011 —Petroleum Geology and Exploration Process, 27 Oct 2011 —Drilling and Well Completions , 26 Oct 2011 —CSOC Certification Module 0, 25 Oct. 2011 • CPDEP Concepts; Module 1, 18 Oct 2011
  • 13.
    Training-continued: •   ElectricalSafe Work Practice, Chevron (SOP 43) and defensive driving, Angola, August 1- 3, 2011 •   H2S training, Business Conduct Code Ethics Code, CABGOC Cabinda Angola, 19 July 2011 •   Essentials for Enterp. Excellence, Safe Start, Weatherford Office Makati, Philippines, 27 Oct, 2010 •   BOSIET, HUET and H2S Training, CTSI Philippines, (OPITO accredited) Oct 20 to Oct.22. 2010 •   Successful Project Mang't. in Energy, Power and Utilities Industry, Malaysia, 27.Sept-30Sept 2010 •   Project Management on line Training, PRW Malaysia Jan. 2010 •   Fire and Gas systems mapping and survey SSB,Lutong Malaysia Oct, 2009 •   Contracts administration and Management, Ranhill Worley, Malaysia Sept.17, 2009. •   Offshore Oil and Gas HSE Training, ( HSEMS OHSAS 18001) Philip. Mar 30 to April 3, 2009 • Safety training : LNG safety, pigging , PTW, H2S, Risk assessment, Habitat & accident investigation • H2S Training, Boat transfer compliance, Swing rope compliance, Chevron, Angola 14 Nov.2007 • HUET and sea survival training, Sonangol training center, Luanda Angola, Jan 2007. •  INTOOLS Basic operations training, Bayer Integrated site, Shanghai China, Nov-27, 2005 •  Primavera P3 (Computer aided Construction Project management) Manila, 14 Feb,2005 •  Construction Project Mg't (Planning, organizing, Sched. and control) 21 Feb.,01 •  AutoCAD 14 Computer Operations, Visual basic IT Power Module •  Programmable Logic Controllers (PLC) Allen Bradley 5/15, Zueitina Oil Co. Libya 1996 •  Electrical Energy Efficiency, U.P. ( University of the Philippines) Q.C.July, 1994 •   Maintenance Management Course, Counseling U.P. Feb. 1989, •   Security Systems, SENELCO, Madrid Spain, April 1986