SlideShare a Scribd company logo
Group #9
Bay
Bridge
Eric Chan
Jolene Kuo
Huiting Tang
Lele Zheng
Contents
Introduction
Modeling, Data gathering and Analysis
Conclusions and Recommendations4
Executive Summary1
2
3
Executive Summary
In the following paper
we focus on two of
the challenges that
arose at different
times in the project’s
life cycle. Our focus:
1
2
3
4
The importance and
the uniqueness of
these two problems
The conflicts that
were caused by the
limited resources
Their scopes and
interdependence
The project management
processes that were
used to manage them
What comes to mind?
The “Other” Bridge
The “Other” Bridge
What’s the difference?
The “Other” Bridge
Loma Prieta Earthquake of 1989
Loma Prieta Earthquake of 1989
Problems
Initial Problem Further problems
Overrun Costs
• Address the
significant overrun
costs that occurred,
causing a complete
halt to the
construction.
 Retrofitting the existing
east span to be more
seismically safe
 Construct a new
seismically safe
structure all together
Problem 1
Seismic Issue
Seismic Issue
• Portion of Bay Bridge collapsed in 1989 due to earthquake
• Bay Bridge lies within 10 miles of 2 earthquake fault lines
• Caltrans investigated and suggested either retrofit or rebuild of
the bridge
• Rebuilding the bridge would last up to 100 years rather than 30
• Started building in 2002. Built to withstand 8.5 magnitude
earthquake and set to SEE (This is defined as an earthquake
that generates the largest motions expected to occur at the
bridge site once every 1,500 years )
• As of now, major components in place. Should open by
September 2013
Timeline- Main Points
• 1989 Loma Prieta earthquake
• Dec. 1996 Caltrans recommends rebuilding
• 1997 budget estimated at $1.5 billion
• 2001 Caltrans releases new budget of $2.1 billion
• 2002 construction begins
• 2003 Caltrans revises cost at $2.95 billion
• 2004 Caltrans reveals cost of $5.1 billion
• 2008 foundation laid, however labor disputes arise and costs rise to
$5.7 billion
• 2013 bridge expected to be completed
East Span construction
The NEW East Span
Problem 2
Cost Issue
Overrun Costs
California ran
out of money
Raw Material
Cost Increase
9/ 11 increased
the cost of
bonds for
construction
Overrun
costs =
???
Top down budgeting was not working
Resource usage changed
Contingency fund was not enough
Budgeting Management
Involved engineers and outside
resources
Governor Office had the right to
audit Bridge finances
Bottom up
Fiscal
Responsibility
Change
Resources
Lower raw materials cost
Solutions
Budgeting Management
Involved engineers and outside
resourcesBottom up
Divide the project into 13 smaller
projects to obtain competitive bids
“Buy America” Clause
Budgeting Management
Governor Office had the right to
audit Bridge finances
Fiscal
Responsibility
California Legislation eased bond requirements so
Caltrans could obtain bonds for the overrun cost.
California would cover 43% of the overrun
cost.
Caltrans traded federal funding with state
funding
Budgeting Management
Change
Resources
Lower raw materials cost
“Buy America” Clause
Caltrans traded federal funding with state
funding
Able to use foreign steels and other raw materials
Outsource the building to China, Japan, Korea, and
England
Conclusion
Conclusions & Recommendations
Recommendations
Recourse Leveling
Planning-monitoring-
controlling
process
May help avoid lagging the
project and finish it before
the deadline of 2q013.
May help foresee any
causes that could either
delay the project or produce
extra overrun costs
Conclusions
 The first issue
 Reflects the application of risk
planning and budgeting in
project management.
 However, the construction is
still underway.
 The second issue
 Relates to cost estimating in
project management.
 The cost estimating process
may be the main factor of the
overrun costs.
The Bay Lights

More Related Content

What's hot

Post lintel
Post lintelPost lintel
Post lintel
Golam Mostofa
 
Isolated footing Site report
Isolated footing Site reportIsolated footing Site report
Isolated footing Site report
skmunazzar
 
Architecture Culture & History 2 Project 2 Report
Architecture Culture & History 2 Project 2 ReportArchitecture Culture & History 2 Project 2 Report
Architecture Culture & History 2 Project 2 Report
douglasloon
 
Building Technology 1 "Construction Solutions"
Building Technology 1 "Construction Solutions"Building Technology 1 "Construction Solutions"
Building Technology 1 "Construction Solutions"
Digital Space Consultancy Ltd
 
Stucture large span area
Stucture large span areaStucture large span area
Stucture large span area
Abhishek Mewada
 
Organisation IN CPM
Organisation IN CPMOrganisation IN CPM
Organisation IN CPM
Er Ajay Makwana
 
Visual Building Inspection Report - House Check NSW
Visual Building Inspection Report - House Check NSWVisual Building Inspection Report - House Check NSW
Visual Building Inspection Report - House Check NSW
House Check NSW
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
Yap Xin
 
BURJ AL ARAB
BURJ AL ARABBURJ AL ARAB
BURJ AL ARAB
Sushil Kumar Gupta.
 
Ct3 steel space frame roof
Ct3 steel space frame roofCt3 steel space frame roof
Ct3 steel space frame roof
MELVIN tan
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group report
XingYue0907
 
Ce 451 design of commercial building in jubail industrial city
Ce 451 design of commercial building in jubail industrial cityCe 451 design of commercial building in jubail industrial city
Ce 451 design of commercial building in jubail industrial city
Ali Asaad Al-Jaziri
 
Trusses
TrussesTrusses
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
Amritpal Singh
 
Project management
Project managementProject management
Project management
Benjamin Tan
 
City planing of medieval europe
City planing of medieval europeCity planing of medieval europe
City planing of medieval europe
UzairIqbal27
 
basic structural system in architecture
basic structural system in architecturebasic structural system in architecture
basic structural system in architecture
shahul130103
 
Real estate market analysis overview
Real estate market analysis overviewReal estate market analysis overview
Real estate market analysis overview
Michael S Robinson Utah
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
jupallipavan2911
 
Grand 99 Hotel Floor Plans
Grand 99 Hotel Floor PlansGrand 99 Hotel Floor Plans
Grand 99 Hotel Floor Plans
Alicia Koo
 

What's hot (20)

Post lintel
Post lintelPost lintel
Post lintel
 
Isolated footing Site report
Isolated footing Site reportIsolated footing Site report
Isolated footing Site report
 
Architecture Culture & History 2 Project 2 Report
Architecture Culture & History 2 Project 2 ReportArchitecture Culture & History 2 Project 2 Report
Architecture Culture & History 2 Project 2 Report
 
Building Technology 1 "Construction Solutions"
Building Technology 1 "Construction Solutions"Building Technology 1 "Construction Solutions"
Building Technology 1 "Construction Solutions"
 
Stucture large span area
Stucture large span areaStucture large span area
Stucture large span area
 
Organisation IN CPM
Organisation IN CPMOrganisation IN CPM
Organisation IN CPM
 
Visual Building Inspection Report - House Check NSW
Visual Building Inspection Report - House Check NSWVisual Building Inspection Report - House Check NSW
Visual Building Inspection Report - House Check NSW
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
BURJ AL ARAB
BURJ AL ARABBURJ AL ARAB
BURJ AL ARAB
 
Ct3 steel space frame roof
Ct3 steel space frame roofCt3 steel space frame roof
Ct3 steel space frame roof
 
Building construction 1 group report
Building construction 1 group reportBuilding construction 1 group report
Building construction 1 group report
 
Ce 451 design of commercial building in jubail industrial city
Ce 451 design of commercial building in jubail industrial cityCe 451 design of commercial building in jubail industrial city
Ce 451 design of commercial building in jubail industrial city
 
Trusses
TrussesTrusses
Trusses
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
Project management
Project managementProject management
Project management
 
City planing of medieval europe
City planing of medieval europeCity planing of medieval europe
City planing of medieval europe
 
basic structural system in architecture
basic structural system in architecturebasic structural system in architecture
basic structural system in architecture
 
Real estate market analysis overview
Real estate market analysis overviewReal estate market analysis overview
Real estate market analysis overview
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
Grand 99 Hotel Floor Plans
Grand 99 Hotel Floor PlansGrand 99 Hotel Floor Plans
Grand 99 Hotel Floor Plans
 

Viewers also liked

Quake-proof Power Point
Quake-proof Power PointQuake-proof Power Point
Quake-proof Power Point
DeEtta Andersen
 
Echm ppt
Echm pptEchm ppt
Echm ppt
Dina shah
 
Tunned mass damper
Tunned mass damperTunned mass damper
Tunned mass damper
Eknath Talele
 
Twin Tower Attack
Twin Tower AttackTwin Tower Attack
Twin Tower Attack
Carmentorrance
 
CT Presentation (KLCC)
CT Presentation (KLCC)CT Presentation (KLCC)
CT Presentation (KLCC)
Yap Xin
 
Tuned Mass Damper
Tuned Mass DamperTuned Mass Damper
Tuned Mass Damper
Rafi Perdana Setyo
 
Mass damper - vibration absorber
Mass damper - vibration absorberMass damper - vibration absorber
Mass damper - vibration absorber
Eidos Engineering
 
Earthquake resistance structures
Earthquake resistance structuresEarthquake resistance structures
Earthquake resistance structures
Uday kumar Devalla
 
Skyscrapers- Petronas Towers
Skyscrapers- Petronas TowersSkyscrapers- Petronas Towers
Skyscrapers- Petronas Towers
Ranju Ravindran
 
Petronas towers
Petronas towersPetronas towers
Petronas towers
Flobz Caloy
 
Petronas twin towers malaysia
Petronas twin towers malaysiaPetronas twin towers malaysia
Petronas twin towers malaysia
humayoun shah
 
Earthquake and earthquake resistant design
Earthquake   and earthquake resistant designEarthquake   and earthquake resistant design
Earthquake and earthquake resistant design
PARVEEN JANGRA
 
presentation on petronas twin tower
 presentation on petronas twin tower presentation on petronas twin tower
presentation on petronas twin tower
Kaish Pasha
 
Design Steps for Earthquake Resistant Structures
Design Steps for Earthquake Resistant StructuresDesign Steps for Earthquake Resistant Structures
Design Steps for Earthquake Resistant Structures
Ishan Garg
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin tower
Somya Gupta
 
Petronas Towers
Petronas TowersPetronas Towers
Petronas Towers
Ranju Ravindran
 
Earthquake resistant construction
Earthquake resistant constructionEarthquake resistant construction
Earthquake resistant construction
Harsh Jain
 
Earthquake resistant buildings in india
Earthquake resistant buildings in indiaEarthquake resistant buildings in india
Earthquake resistant buildings in india
Viva Bella Interiors
 
Welcome To Geography!
Welcome To Geography!Welcome To Geography!
Welcome To Geography!
Simon Jones
 
Tallest building in india
Tallest building in indiaTallest building in india
Tallest building in india
Boman-Rustom-Irani
 

Viewers also liked (20)

Quake-proof Power Point
Quake-proof Power PointQuake-proof Power Point
Quake-proof Power Point
 
Echm ppt
Echm pptEchm ppt
Echm ppt
 
Tunned mass damper
Tunned mass damperTunned mass damper
Tunned mass damper
 
Twin Tower Attack
Twin Tower AttackTwin Tower Attack
Twin Tower Attack
 
CT Presentation (KLCC)
CT Presentation (KLCC)CT Presentation (KLCC)
CT Presentation (KLCC)
 
Tuned Mass Damper
Tuned Mass DamperTuned Mass Damper
Tuned Mass Damper
 
Mass damper - vibration absorber
Mass damper - vibration absorberMass damper - vibration absorber
Mass damper - vibration absorber
 
Earthquake resistance structures
Earthquake resistance structuresEarthquake resistance structures
Earthquake resistance structures
 
Skyscrapers- Petronas Towers
Skyscrapers- Petronas TowersSkyscrapers- Petronas Towers
Skyscrapers- Petronas Towers
 
Petronas towers
Petronas towersPetronas towers
Petronas towers
 
Petronas twin towers malaysia
Petronas twin towers malaysiaPetronas twin towers malaysia
Petronas twin towers malaysia
 
Earthquake and earthquake resistant design
Earthquake   and earthquake resistant designEarthquake   and earthquake resistant design
Earthquake and earthquake resistant design
 
presentation on petronas twin tower
 presentation on petronas twin tower presentation on petronas twin tower
presentation on petronas twin tower
 
Design Steps for Earthquake Resistant Structures
Design Steps for Earthquake Resistant StructuresDesign Steps for Earthquake Resistant Structures
Design Steps for Earthquake Resistant Structures
 
Petronas twin tower
Petronas twin towerPetronas twin tower
Petronas twin tower
 
Petronas Towers
Petronas TowersPetronas Towers
Petronas Towers
 
Earthquake resistant construction
Earthquake resistant constructionEarthquake resistant construction
Earthquake resistant construction
 
Earthquake resistant buildings in india
Earthquake resistant buildings in indiaEarthquake resistant buildings in india
Earthquake resistant buildings in india
 
Welcome To Geography!
Welcome To Geography!Welcome To Geography!
Welcome To Geography!
 
Tallest building in india
Tallest building in indiaTallest building in india
Tallest building in india
 

Similar to San Francisco Bay Bridge - Project Management Issues

What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover dam
Jasmine Tung
 
Blog posts, 2011
Blog posts, 2011Blog posts, 2011
Blog posts, 2011
Lisa Meiman
 
Priority List Infrastructure Projects
Priority List Infrastructure ProjectsPriority List Infrastructure Projects
Priority List Infrastructure Projects
Marco Terruzzin
 
Priority List Infrastructure Projects
Priority List Infrastructure ProjectsPriority List Infrastructure Projects
Priority List Infrastructure Projects
Marco Terruzzin
 
State senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperState senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaper
peggydrouet
 
Bridge
BridgeBridge
Bridge
Bobby Hanes
 
Improved Jacketing Repair System For Steel H Beams
Improved Jacketing Repair System For Steel H Beams Improved Jacketing Repair System For Steel H Beams
Improved Jacketing Repair System For Steel H Beams
kphodel
 
2.6 Harbour bridge intro
2.6 Harbour bridge intro2.6 Harbour bridge intro
2.6 Harbour bridge intro
Taka Geo
 
Project Complexity (Case study)
Project Complexity (Case study)Project Complexity (Case study)
Project Complexity (Case study)
Sunny Mahajan
 
Financing nuclear projects — A. Abdel Aziz
Financing nuclear projects — A. Abdel AzizFinancing nuclear projects — A. Abdel Aziz
Financing nuclear projects — A. Abdel Aziz
This account is closed
 
01Caroline-Leon-Gary
01Caroline-Leon-Gary01Caroline-Leon-Gary
01Caroline-Leon-Gary
Leon Botham
 
Policy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at ScalePolicy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at Scale
cassiebent
 
Policy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at ScalePolicy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at Scale
Mintz Levin
 
LTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
LTC_Lovell_SAME_E&S_Webinar_FEB_16_FinalLTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
LTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
Kevin Lovell, PMP
 
Nuclear Expansion
Nuclear ExpansionNuclear Expansion
Nuclear Expansion
jdoolitt
 
Nuclear Expansion
Nuclear ExpansionNuclear Expansion
Nuclear Expansion
jdoolitt
 
Nuclear Expansion
Nuclear ExpansionNuclear Expansion
Nuclear Expansion
jdoolitt
 
Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort
Priyank Jain
 
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
Deltares
 
Delay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionDelay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant Construction
Charles Fournier
 

Similar to San Francisco Bay Bridge - Project Management Issues (20)

What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover dam
 
Blog posts, 2011
Blog posts, 2011Blog posts, 2011
Blog posts, 2011
 
Priority List Infrastructure Projects
Priority List Infrastructure ProjectsPriority List Infrastructure Projects
Priority List Infrastructure Projects
 
Priority List Infrastructure Projects
Priority List Infrastructure ProjectsPriority List Infrastructure Projects
Priority List Infrastructure Projects
 
State senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaperState senate transpo hearings 11 13-13 backgroundpaper
State senate transpo hearings 11 13-13 backgroundpaper
 
Bridge
BridgeBridge
Bridge
 
Improved Jacketing Repair System For Steel H Beams
Improved Jacketing Repair System For Steel H Beams Improved Jacketing Repair System For Steel H Beams
Improved Jacketing Repair System For Steel H Beams
 
2.6 Harbour bridge intro
2.6 Harbour bridge intro2.6 Harbour bridge intro
2.6 Harbour bridge intro
 
Project Complexity (Case study)
Project Complexity (Case study)Project Complexity (Case study)
Project Complexity (Case study)
 
Financing nuclear projects — A. Abdel Aziz
Financing nuclear projects — A. Abdel AzizFinancing nuclear projects — A. Abdel Aziz
Financing nuclear projects — A. Abdel Aziz
 
01Caroline-Leon-Gary
01Caroline-Leon-Gary01Caroline-Leon-Gary
01Caroline-Leon-Gary
 
Policy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at ScalePolicy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at Scale
 
Policy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at ScalePolicy & Legal Implications of Implementing Renewable Energy at Scale
Policy & Legal Implications of Implementing Renewable Energy at Scale
 
LTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
LTC_Lovell_SAME_E&S_Webinar_FEB_16_FinalLTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
LTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
 
Nuclear Expansion
Nuclear ExpansionNuclear Expansion
Nuclear Expansion
 
Nuclear Expansion
Nuclear ExpansionNuclear Expansion
Nuclear Expansion
 
Nuclear Expansion
Nuclear ExpansionNuclear Expansion
Nuclear Expansion
 
Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort
 
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
 
Delay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant ConstructionDelay Claims Mitigation for US Nuclear Power Plant Construction
Delay Claims Mitigation for US Nuclear Power Plant Construction
 

Recently uploaded

Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
obriengroupinc04
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
valvereliz227
 
The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...
The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...
The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...
YourLegal Accounting
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
Freelance
 
Enhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: IntroductionEnhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: Introduction
Cor Verdouw
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
dpbossdpboss69
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
advik4387
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
my Pandit
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
Ksquare Energy Pvt. Ltd.
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
HajeJanKamps
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
CIOWomenMagazine
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
dazzjoker
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
ZevinAttisha
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 

Recently uploaded (20)

Discover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling ServiceDiscover the Beauty and Functionality of The Expert Remodeling Service
Discover the Beauty and Functionality of The Expert Remodeling Service
 
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
Dpboss Matka Guessing Satta Matta Matka Kalyan panel Chart Indian Matka Dpbos...
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
 
The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...
The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...
The Role of White Label Bookkeeping Services in Supporting the Growth and Sca...
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
Prescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPTPrescriptive analytics BA4206 Anna University PPT
Prescriptive analytics BA4206 Anna University PPT
 
Enhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: IntroductionEnhancing Adoption of AI in Agri-food: Introduction
Enhancing Adoption of AI in Agri-food: Introduction
 
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
Call 8867766396 Dpboss Matka Guessing Satta Matta Matka Kalyan Chart Indian M...
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15High-Quality IPTV Monthly Subscription for $15
High-Quality IPTV Monthly Subscription for $15
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
The Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac SignThe Steadfast and Reliable Bull: Taurus Zodiac Sign
The Steadfast and Reliable Bull: Taurus Zodiac Sign
 
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
PM Surya Ghar Muft Bijli Yojana: Online Application, Eligibility, Subsidies &...
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
 
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdfRegistered-Establishment-List-in-Uttarakhand-pdf.pdf
Registered-Establishment-List-in-Uttarakhand-pdf.pdf
 
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
CULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for dukeCULR Spring 2024 Journal.pdf testing for duke
CULR Spring 2024 Journal.pdf testing for duke
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 

San Francisco Bay Bridge - Project Management Issues

  • 1. Group #9 Bay Bridge Eric Chan Jolene Kuo Huiting Tang Lele Zheng
  • 2. Contents Introduction Modeling, Data gathering and Analysis Conclusions and Recommendations4 Executive Summary1 2 3
  • 3. Executive Summary In the following paper we focus on two of the challenges that arose at different times in the project’s life cycle. Our focus: 1 2 3 4 The importance and the uniqueness of these two problems The conflicts that were caused by the limited resources Their scopes and interdependence The project management processes that were used to manage them
  • 11. Problems Initial Problem Further problems Overrun Costs • Address the significant overrun costs that occurred, causing a complete halt to the construction.  Retrofitting the existing east span to be more seismically safe  Construct a new seismically safe structure all together
  • 13. Seismic Issue • Portion of Bay Bridge collapsed in 1989 due to earthquake • Bay Bridge lies within 10 miles of 2 earthquake fault lines • Caltrans investigated and suggested either retrofit or rebuild of the bridge • Rebuilding the bridge would last up to 100 years rather than 30 • Started building in 2002. Built to withstand 8.5 magnitude earthquake and set to SEE (This is defined as an earthquake that generates the largest motions expected to occur at the bridge site once every 1,500 years ) • As of now, major components in place. Should open by September 2013
  • 14. Timeline- Main Points • 1989 Loma Prieta earthquake • Dec. 1996 Caltrans recommends rebuilding • 1997 budget estimated at $1.5 billion • 2001 Caltrans releases new budget of $2.1 billion • 2002 construction begins • 2003 Caltrans revises cost at $2.95 billion • 2004 Caltrans reveals cost of $5.1 billion • 2008 foundation laid, however labor disputes arise and costs rise to $5.7 billion • 2013 bridge expected to be completed
  • 16. The NEW East Span
  • 17.
  • 19. Overrun Costs California ran out of money Raw Material Cost Increase 9/ 11 increased the cost of bonds for construction Overrun costs = ??? Top down budgeting was not working Resource usage changed Contingency fund was not enough
  • 20. Budgeting Management Involved engineers and outside resources Governor Office had the right to audit Bridge finances Bottom up Fiscal Responsibility Change Resources Lower raw materials cost Solutions
  • 21. Budgeting Management Involved engineers and outside resourcesBottom up Divide the project into 13 smaller projects to obtain competitive bids “Buy America” Clause
  • 22. Budgeting Management Governor Office had the right to audit Bridge finances Fiscal Responsibility California Legislation eased bond requirements so Caltrans could obtain bonds for the overrun cost. California would cover 43% of the overrun cost. Caltrans traded federal funding with state funding
  • 23. Budgeting Management Change Resources Lower raw materials cost “Buy America” Clause Caltrans traded federal funding with state funding Able to use foreign steels and other raw materials Outsource the building to China, Japan, Korea, and England
  • 25. Conclusions & Recommendations Recommendations Recourse Leveling Planning-monitoring- controlling process May help avoid lagging the project and finish it before the deadline of 2q013. May help foresee any causes that could either delay the project or produce extra overrun costs Conclusions  The first issue  Reflects the application of risk planning and budgeting in project management.  However, the construction is still underway.  The second issue  Relates to cost estimating in project management.  The cost estimating process may be the main factor of the overrun costs.