SlideShare a Scribd company logo
L290-AQ-PLN-10850
Status
LCPL QA (Sub Contractor) Leightons - LCPL (Sub Contractor) JKC (Contractor)
Name: Name: Name:
Date: Date: Date:
Signature: Signature: Signature:
IVB
1.0
1.1 Issued for Construction - IFC Drawings (IFI drawing for temporary works) PE Each activity
L290-AB-PRC-0004_0 Instruction for Vendor
Documentation-Section 6.4
Stamped / Approved Drawings
Stamped Code: A=Approved without Comment B=Approved with minor
Comment N=Not Approved F= Not subject to review
N/A Stamped IFC drawing
1.2 Calibration of Equipment PE
As per equipment calibration
register
L290-AQ-SPC-0009: Quality Control
Requirements for subcontractor
Clause 4.6.3 of L290-AQ-SPC-0009 Documentation sighted, for inclusion into MDR, Approved ITP N/A calibration certificates
1.3 Relevant codes & Specifications sighted / Correct revision PE Each activity
Section H Contract. Contract Exhibit E Drawings
& Specifications
Section H Contract. Contract Exhibit E Drawings &
Specifications
Documents sighted / Approved ITP / Check Sheet SSF01 N/A Approved ITP
1.4 Development and approval of ITP prior to construction activities PE Each activity
L290-AQ-SPC-0009: Quality Control
requirements for Subcontractors
Clause 4.5 of L290-AQ-SPC-0009 Documentation sighted on approved ITP N/A Approved ITP
1.5
Pre-Inspection Meeting Minutes of Meeting (PIM MOM) if required as per the
criticality matrix
QM Each activity as required
L290-AQ-SPC-0009: Quality Control
requirements for Subcontractors, L290- AB-PRC-
0004:INSTRUCTION FOR VENDOR
DOCUMENTATION
Clause 4.4.3 of L290-AQ-SPC-0009, Clause 5.1 of L290-AB-
PRC-0004
MOM Documentation sighted N/A PIM- MOM
1.6 QC Inspector Qualification - Electrical QM Once per person L290-AQ-SPC-0009
L290-AQ-SPC-0009 Section 4.14.1.3: working knowledge os
AS 2381: “Electrical Equipment for Hazardous Areas”,
AS/NZS 60079.17: “Explosive atmospheres –Electrical...,
and AS/NZS 60079.18: “Explosive atmospheres – ...
Sighted approval of Inspector document N/A Approval document
1.7 Verify SHEWMS available and approved PE Each activity Relevant Specification As Per Schedule Approved SHEWMS N/A Approved SWEHMS
2.0
2.1 Material Certificates received for all components SUP Each Delivery Contract Exhibit H and L290-AQ-SPC-0010
Section 4.11 of Exhibit H and clause 2.2 for L290-AQ-SPC-
0010
Material Register & Material Certificates sighted, for inclusion into MDR N/A material certificates
2.2 Inspection of received goods SUP Each Delivery
L290-AQ-PRC-0008: QUALITY CONTROL
COORDINATION PROCEDURE FOR
SUBCONTRACTOR
Clause 4.5.2 of L290-AQ-PRC-0008 Material Register & Material Certificates sighted, for inclusion into MDR N/A Material inspection report
3.0
3.1 Installations as per gneral arrangement and layouts SUP/ENG Each Lot
IFC drawing, AS 3000, L290-AQ-TAC-0005
(Inspection and Test Plan for Electrical Works)
Clause 5.5.5 of AS 3000: 2007 Inspection Test Record EP08, EP01, EP30 (L290-AR-FRM-10002) N/A ITR EP08, EP01, EP30
3.2 Equipment is tagged correctly against drawings and project specification PE Each Lot
IFC drawing, AS 3000, L290-AQ-TAC-0005
(Inspection and Test Plan for Electrical Works)
IFC Drawings/ Clause 5.5.1.3 of AS 3000:2007 Inspection Test Record EP08, EP01, EP30 (L290-AR-FRM-10002) N/A ITR EP08, EP01, EP30
3.3
Verify Earthing straps and Conductors cross section as per drawings and
specification
SUP/ENG Each Lot
IFC drawing, AS 3000, L290-AQ-TAC-0005
(Inspection and Test Plan for Electrical Works)
Clause 5.3.3 of AS 3000: 2007 Inspection Test Record EP08, EP01,(L290-AR-FRM-10002) N/A ITR EP08, EP01
3.5 Main earthing cable and earthing boss checked SUP/ENG Each Lot
IFC drawing, AS 3000, L290-AQ-TAC-0005
(Inspection and Test Plan for Electrical Works)
Clause 5.3.3.4 of AS 3000: 2007 Inspection Test Record EP01 (L290-AR-FRM-10002) N/A ITR EP01
3.6 Main earthing bar checked SUP/ENG Each Lot
IFC drawing, AS 3000, L290-AQ-TAC-0005
(Inspection and Test Plan for Electrical Works)
Clause 5.3.2.1 of AS 3000:2007 Inspection Test Record EP29 (L290-AR-FRM-10002) N/A ITR EP29
3.7 Main earthing rod checked SUP/ENG Each Lot
IFC drawing, AS 3000, L290-AQ-TAC-0005
(Inspection and Test Plan for Electrical Works)
Clause 5.3.6 of AS 3000:2007 Inspection Test Record EP30 (L290-AR-FRM-10002) N/A ITR EP30
4.0
4.1 Check type of cable tray, conduits, ladders, junction boxes & fittings. SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 IFC Drawings/ AS /NZS 3000:2007 Clause 3.8
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
4.2 Check conduit and cable tray size, routing for no obstructions and elevation. SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3, Section 7 IFC Drawings/ AS /NZS 3000:2007 Clause 3.9, 7.4
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
4.3
Check coupler plates, elbows, dropout tees, conduit fittings and accessories are
properly installed.
SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 IFC Drawings/ AS /NZS 3000:2007 Clause 3.9
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
4.4
Check tray and conduit supports are correct and tightened using the appropriate
tool ensuring no deflection.
SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 .9 IFC Drawings/ AS /NZS 3000:2007 Clause 3.9.6
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
4.5 Check tray covers and protection is provided. SUP/ENG Each Lot IFC Drawings/ AS 3000 Clause 3.2 to 3.4 IFC Drawings/ AS /NZS 3000:2007 Clause 3.3.2.6 Inspection Test Record EP10 (290-AR-FRM-10002) N/A ITR - EP10
4.6 Check pulling guide rope in concealed conduit is installed. SUP/ENG Each Lot AS 3000 Section 3 AS /NZS 3000:2007 Clause 3.9 Field Inspection Check Sheet ELC19 (L290-AR-FRM-10002) N/A FIC- ELC19
4.7 Check all wall penetrations are completely sealed and fire rated. SUP/ENG Each Lot AS 3000 Clause 3.9.9 AS /NZS 3000:2007 Clause 3.9.9.3 Inspection Test Record EP10 (290-AR-FRM-10002) N/A ITR - EP10
4.8 Check tray and conduit sharp edges have been removed. SUP/ENG Each Lot AS 3000 Clause 3.10.1 to 3.10.4 AS /NZS 3000:2007 Clause 3.10.3.5
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
4.9 Check cable tray, conduits are properly cleaned prior to cable pulling. SUP/ENG Each Lot AS 3000 Clause 3.10 to 3.11 AS /NZS 3000:2007 Clause 3.10.3.5, 3.6
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
4.10 Verify complete cable tray installation against drawings and specifications SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 IFC Drawings/ AS 3000 Section 3
Field Inspection Check Sheet ELC19 and Inspection Test Record
EP10 (L290-AR-FRM-10002)
N/A FIC- ELC19, ITR - EP10
5.0
5.1 Visual inspection of cable type, size & tag no. SUP/ENG Each Lot AS 3000 Clause 8.2 AS /NZS 3000:2007 Clause 8.2.1, 8.2.2(d)
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
Date:
Signature:
H W
Name:
H H S S
BUILDING EARTHING
Date:
Signature:
Record Remarks
Subcontractor
H
W
W
H H R S
W
H
CABLEWAYS & CONDUITS
W S S S
Acceptance Criteria/Specification Verifying Documents
Package Name: EPC BUILDING WORKS (P-31D-BLD-1), Subcontractor's Document Number: Q1447-CS-PCP-6025
ITP Title: INSPECTION AND TEST PLAN - ELECTRICAL - POWER DISTRIBUTION SYSTEMS - EPC BUILDING WORKS
ITP Number: L290-AQ-PLN-10850 Contractor's Number: V-31D1-BLD-1-Z40124
H
H H W S
Lower Tier Sub Contractor (LTSC)
Name:ITP Accepted:
No.
W S
Independent Verification Body (IVB)
W S S
W S S
SR S
H
W S S S
W S
H
H H
W
SSW
SW
W S S
Quality Verification Activity/Stage Reference Procedure
H
Contractor Company
APPROVALS AND OTHER PRELIMINARY REQUIREMENTS
LTSC
Required Inspection
S S
H W S S
H W S S
H
ABOVE GROUND CABLING
SS
9
H H W R
SH
H
W
W
S
S
S
S
W S S
W
S
S S
MATERIAL RECEIVING/DOCUMENT INSPECTION
H W S
H W
H H
H W W S
Responsibility Frequency
H
H
H
H
H
Q1447-CS-PCP-6025-08 (1).xlsx:Page 1/2
L290-AQ-PLN-10850
Status
LCPL QA (Sub Contractor) Leightons - LCPL (Sub Contractor) JKC (Contractor)
Name: Name: Name:
Date: Date: Date:
Signature: Signature: Signature:
IVB
Date:
Signature:
Name:
Date:
Signature:
Record Remarks
Subcontractor
Acceptance Criteria/Specification Verifying Documents
Package Name: EPC BUILDING WORKS (P-31D-BLD-1), Subcontractor's Document Number: Q1447-CS-PCP-6025
ITP Title: INSPECTION AND TEST PLAN - ELECTRICAL - POWER DISTRIBUTION SYSTEMS - EPC BUILDING WORKS
ITP Number: L290-AQ-PLN-10850 Contractor's Number: V-31D1-BLD-1-Z40124
Lower Tier Sub Contractor (LTSC)
Name:ITP Accepted:
No.
Independent Verification Body (IVB)
Quality Verification Activity/Stage Reference Procedure
Contractor CompanyLTSC
Required Inspection
9
Responsibility Frequency
5.2 Visually inspect the cable is not damaged or snagged during cable pulling. SUP/ENG Each Lot AS 3000 Section 3 AS /NZS 3000:2007 Clause 3.3.2.7, 3.3.2.8
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.3 Check cable-bending radius according to specifications. SUP/ENG Each Lot AS 3000 Clause 3.9 AS /NZS 3000:2007 Clause 3.9.6
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.4 Check cable segregation as per drawings SUP/ENG Each Lot IFC drawing /AS 3000 Section 3.9 AS /NZS 3000:2007 Clause 3.9.8.3, IFC drawings
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.5 Check cable fixing on tray properly installed. SUP/ENG Each Lot AS 3000 Clause 3.3 AS /NZS 3000:2007 Clause 3.3.2.6
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.6 Check wiring above ceiling is properly installed. SUP/ENG Each Lot AS 3000 Section 3.9 AS /NZS 3000:2007 Clause 3.9.3.2
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.7 Check cable ID tag no. Is properly installed. SUP/ENG Each Lot AS 3000 section 3 AS /NZS 3000:2007 Clause 3.9
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.8 Check cable continuity and megger test after pulling. SUP/ENG Each Lot AS 3000 Clause 3.10 AS /NZS 3000:2007 Clause 3.10.3.3
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
5.9 Check protection of cable ends after megger test. SUP/ENG Each Lot AS 3000 Clause 3.10 AS /NZS 3000:2007 Clause 3.10.3.5
Inspection Test Record EP40 and EP01 for single cables only if
relevant (L290-AR-FRM-10002)
N/A ITR - EP40, EP01
6.0
6.1 Check general arrangement of installation meets drawings and specifications. SUP/ENG Each Lot IFC Drawing/ AS 3000 Clause 4.3 IFC Drawing/ AS/NZS 3000: 2007 Clause 4.3.3
Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM-
10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42
6.2
Check Socket Outlet/ Junction Boxes/ Isolators are correct alligned, leveled,
ridget and secured with correct fixings.
SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 4.4.2
Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM-
10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42
6.3 Check earthing and bonding of sockets outlets against drawings. SUP/ENG Each Lot IFC Drawing/ AS 3000 Clause 4.4 IFC Drawing/ AS/NZS 3000: 2007 Clause 4.4.3
Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM-
10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42
6.4
Check Socket Outlet/ Junction Boxes/ Isolators is clean and free from
dust/debris, internal internals.
SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 4.4.2.2(a)
Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM-
10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42
6.5
Check all terminals and connections are tight, correctly made and identified as
per drawings.
SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 4.4.2.2©
Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM-
10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42
6.6 Perform insulation resistance test. Each phase to earth. SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 8.3.6
Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM-
10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42
6.7 Conduct Earth loop impedance test. SUP/ENG Each Lot AS 3000 Clause 8.3 AS/NZS 3000: 2007 Clause 8.3.9
Inspection Test Record EP05, EP07, EP14 EP37, EP42, EP44 (290-
AR-FRM-10002)
N/A
ITR - EP05,EP07, EP14,
EP37,EP42, EP44
7.0
7.1 Verify sign-off of all Inspection and Test documentation ENG Each Lot ITP/ FICs Signed off ITP/ FICs Completed ITP checklist N/A ITP, FICs
7.2 Verify all drawings 'As built' status PE/QM Each drawing
IFC Drawing/ As Built drawing, Contract exhibit
H
IFC Drawing/ As Built drawing Completed As-built drawings N/A respective drawing
7.3 Completion and handover/delivery of relevant QA documentation to MDR
PE/QM
Each lot/Activity
Collate records as perL290-AQ-SPC-0001, L290-
AQ-SPC-0010, Exhbit H applicable sections, As
3000 and IFC drawings and FICS, test reports,
material certificates and all other relevant
records
Collate records as perL290-AQ-SPC-0001, L290-AQ-SPC-
0010, Exhbit H applicable sections, As 3000 and IFC
drawings and FIC's/ ITR's, test reports, material certificates
and all other relevant records
IFC drawings, signed off FIC's/ ITR's, test reports, material
certificates, inspection reports, survey reports and all other relevant
records of ITP
N/A Partial MDR
H - Hold Point SUP Supervisor LTSC PIM
W - Witness Point ENG LCPL Engineer LCPL MOM
IW - Initial Witness PE LCPL Project Engineer JKC QA
S - Surveillance JKC JKC Representative INPEX FICS
R - Record Review SHEWMS
Safety,Health and Environmental
Work Method Statement N/A MDR
OR - Official Record IVB IFC
IR - Internal Record Document Number: L290-AQ-PLN-10850 IFI
Subcontractor
Contractor
W R S
W S
COMPLETION AND HANDOVER / DELIVERY
Company
Not Applicable
H
H H W S
W S
S
W
SOCKET OUTLET/ JUNCTION BOX/ ISOLATOR
S
Independent Verification Body
Low Tier Subcontractor
H
H H
S S
H
S
W
W
S
W
R
W
S
S
W
S
Issued for construction
S
S
S
S
W
H
H
W
H
H
S
R
W
S
S
S
S
S
S
Issued for information
Minutes of Meeting
Quality Assuarance
Field Inspection Check Sheet
Manufacturers' Data record
Pre Inspection Meeting
S
S
H
W
W
W
S
S
H/R RH H
H
H
H
W
W
S
S
S
S
Q1447-CS-PCP-6025-08 (1).xlsx:Page 2/2

More Related Content

What's hot

Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
Sergio Augusto Esteves
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
Sharad Naik
 
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & GasResume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
jaison varkey
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
OGDoilandgasdocs
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
Dwarika Bhushan Sharma
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
Shaik Mohsin
 
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Bimal Chandra Das
 
Basic Flagman Training
Basic Flagman TrainingBasic Flagman Training
Basic Flagman Training
Natasha Azura
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.maqsood1459
 
Pr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedurePr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedure
Ragul Selvam
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
moumo1
 
Saudi Aramco Typical Inspection Plan (SATIP)
Saudi Aramco Typical Inspection Plan (SATIP)Saudi Aramco Typical Inspection Plan (SATIP)
Saudi Aramco Typical Inspection Plan (SATIP)ROBERTO BATAHOY GAMALE JR
 
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docxELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
Dwarika Bhushan Sharma
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
Dwarika Bhushan Sharma
 
QA-QC WELDING & NDT Inspector for poland updated
QA-QC WELDING &  NDT Inspector for poland updatedQA-QC WELDING &  NDT Inspector for poland updated
QA-QC WELDING & NDT Inspector for poland updatedSantosh Gurajada
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
Dwarika Bhushan Sharma
 
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
Dwarika Bhushan Sharma
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 

What's hot (20)

Lifting plan template
Lifting plan templateLifting plan template
Lifting plan template
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & GasResume of jaison varkey, QA/QC  inspector welding,coating offshore Oil & Gas
Resume of jaison varkey, QA/QC inspector welding,coating offshore Oil & Gas
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
Saudi Aramco Inspection Procedure (SAIP)
Saudi Aramco Inspection Procedure (SAIP)Saudi Aramco Inspection Procedure (SAIP)
Saudi Aramco Inspection Procedure (SAIP)
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
 
Basic Flagman Training
Basic Flagman TrainingBasic Flagman Training
Basic Flagman Training
 
Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.Ms 12.doc 7.6.13.
Ms 12.doc 7.6.13.
 
Pr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedurePr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedure
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
 
Saudi Aramco Typical Inspection Plan (SATIP)
Saudi Aramco Typical Inspection Plan (SATIP)Saudi Aramco Typical Inspection Plan (SATIP)
Saudi Aramco Typical Inspection Plan (SATIP)
 
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docxELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
ELECTRICAL INSTALLATIONS INSPECTION CHECKLIST Form # HSEQ - EIIC Rev 7.docx
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
QA-QC WELDING & NDT Inspector for poland updated
QA-QC WELDING &  NDT Inspector for poland updatedQA-QC WELDING &  NDT Inspector for poland updated
QA-QC WELDING & NDT Inspector for poland updated
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docxAIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
AIR COMPRESSOR CHECKLIST Form # HSEQ - ACL Rev 2.docx
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 

Similar to Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-6025-08

Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...Gary Hayes
 
Bid document bhel
Bid document bhelBid document bhel
Bid document bhel
ravi chandar
 
testing formats
testing formatstesting formats
testing formats
Abhishek Shukla
 
14 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-014 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-0
Fidel Condori Choque
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
michaeljmack
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS
Mary Calkins
 
Booster fan cr1 fn02 platform & duct support calculation note
Booster fan cr1 fn02 platform & duct support calculation noteBooster fan cr1 fn02 platform & duct support calculation note
Booster fan cr1 fn02 platform & duct support calculation note
Ali Elkashef
 
Aproved QCP.pdf
Aproved QCP.pdfAproved QCP.pdf
Aproved QCP.pdf
hyperm2m
 
2017 JAN - Aviation - Mark Koppa Personal Resume
2017 JAN - Aviation - Mark Koppa Personal Resume2017 JAN - Aviation - Mark Koppa Personal Resume
2017 JAN - Aviation - Mark Koppa Personal ResumeMark Koppa
 
Motorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works SpecificationMotorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works Specification
Thorne & Derrick International
 
List of EN1317 Compliant RRS January 2015
List of EN1317 Compliant RRS January 2015 List of EN1317 Compliant RRS January 2015
List of EN1317 Compliant RRS January 2015
Thorne & Derrick International
 
Cube test report..xlsx
Cube test report..xlsxCube test report..xlsx
Cube test report..xlsxjimit langalia
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
Tonni Bruce
 
550 ICA AS-550-900 Rev A
550 ICA AS-550-900 Rev A550 ICA AS-550-900 Rev A
550 ICA AS-550-900 Rev AStephen Stuart
 
Technical instructions to work
Technical instructions to workTechnical instructions to work
Technical instructions to work
Amit Kumar
 
C.q.e catalogo ipc
C.q.e   catalogo ipcC.q.e   catalogo ipc
C.q.e catalogo ipc
Gonçalves Vandy
 
PSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdfPSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdf
romuloac
 
BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15
BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15
BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15Maher (Mack) Eltarhoni
 

Similar to Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-6025-08 (20)

Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
 
18rf 31170-ts-002 (flange)
18rf 31170-ts-002 (flange)18rf 31170-ts-002 (flange)
18rf 31170-ts-002 (flange)
 
Bid document bhel
Bid document bhelBid document bhel
Bid document bhel
 
testing formats
testing formatstesting formats
testing formats
 
14 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-014 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-0
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS
 
Booster fan cr1 fn02 platform & duct support calculation note
Booster fan cr1 fn02 platform & duct support calculation noteBooster fan cr1 fn02 platform & duct support calculation note
Booster fan cr1 fn02 platform & duct support calculation note
 
Aproved QCP.pdf
Aproved QCP.pdfAproved QCP.pdf
Aproved QCP.pdf
 
Svr part 4_e
Svr part 4_eSvr part 4_e
Svr part 4_e
 
2017 JAN - Aviation - Mark Koppa Personal Resume
2017 JAN - Aviation - Mark Koppa Personal Resume2017 JAN - Aviation - Mark Koppa Personal Resume
2017 JAN - Aviation - Mark Koppa Personal Resume
 
Motorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works SpecificationMotorway Communications - Series 1500 - Highway Works Specification
Motorway Communications - Series 1500 - Highway Works Specification
 
List of EN1317 Compliant RRS January 2015
List of EN1317 Compliant RRS January 2015 List of EN1317 Compliant RRS January 2015
List of EN1317 Compliant RRS January 2015
 
Cube test report..xlsx
Cube test report..xlsxCube test report..xlsx
Cube test report..xlsx
 
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
( Itp ag pipe) rapid p006 a scs qac itp 3200 0007
 
550 ICA AS-550-900 Rev A
550 ICA AS-550-900 Rev A550 ICA AS-550-900 Rev A
550 ICA AS-550-900 Rev A
 
Technical instructions to work
Technical instructions to workTechnical instructions to work
Technical instructions to work
 
C.q.e catalogo ipc
C.q.e   catalogo ipcC.q.e   catalogo ipc
C.q.e catalogo ipc
 
PSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdfPSI-130-30-0002-RC-R1_Agitators.pdf
PSI-130-30-0002-RC-R1_Agitators.pdf
 
BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15
BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15
BU813618 Two Notch- Amin091-006_Verizon Wireless 91580_SA85770_004_01_11.11.15
 

More from Gary Hayes

Small Projects - PAWA
Small Projects - PAWASmall Projects - PAWA
Small Projects - PAWAGary Hayes
 
Small Projects - Kestral Coal Mine
Small Projects - Kestral Coal MineSmall Projects - Kestral Coal Mine
Small Projects - Kestral Coal MineGary Hayes
 
275kV Feeder - Ross Substation Automation Project - Powerlink-2
275kV Feeder - Ross Substation Automation Project - Powerlink-2275kV Feeder - Ross Substation Automation Project - Powerlink-2
275kV Feeder - Ross Substation Automation Project - Powerlink-2Gary Hayes
 
275kV Feeder - Ross Substation Automation Project - Powerlink-1
275kV Feeder - Ross Substation Automation Project - Powerlink-1275kV Feeder - Ross Substation Automation Project - Powerlink-1
275kV Feeder - Ross Substation Automation Project - Powerlink-1Gary Hayes
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3e
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3eCSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3e
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3eGary Hayes
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3c
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3cCSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3c
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3cGary Hayes
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3a
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3aCSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3a
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3aGary Hayes
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1Gary Hayes
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2Gary Hayes
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1Gary Hayes
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2Gary Hayes
 
132-110kV Cabolture Substation - Primary Plant 2- Energex
132-110kV Cabolture Substation - Primary Plant 2- Energex132-110kV Cabolture Substation - Primary Plant 2- Energex
132-110kV Cabolture Substation - Primary Plant 2- EnergexGary Hayes
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6Gary Hayes
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5Gary Hayes
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4Gary Hayes
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3Gary Hayes
 
1332-110kV Cabolture Substation - Primary Plant - Energex
1332-110kV Cabolture Substation - Primary Plant - Energex1332-110kV Cabolture Substation - Primary Plant - Energex
1332-110kV Cabolture Substation - Primary Plant - EnergexGary Hayes
 
Redbank Plaza Upgrade - Street Lighting
Redbank Plaza Upgrade - Street LightingRedbank Plaza Upgrade - Street Lighting
Redbank Plaza Upgrade - Street LightingGary Hayes
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...Gary Hayes
 
Gallipoli Barracks Enhanced Land Force Stage 2B - HV Distribution
Gallipoli Barracks Enhanced Land Force Stage 2B - HV DistributionGallipoli Barracks Enhanced Land Force Stage 2B - HV Distribution
Gallipoli Barracks Enhanced Land Force Stage 2B - HV DistributionGary Hayes
 

More from Gary Hayes (20)

Small Projects - PAWA
Small Projects - PAWASmall Projects - PAWA
Small Projects - PAWA
 
Small Projects - Kestral Coal Mine
Small Projects - Kestral Coal MineSmall Projects - Kestral Coal Mine
Small Projects - Kestral Coal Mine
 
275kV Feeder - Ross Substation Automation Project - Powerlink-2
275kV Feeder - Ross Substation Automation Project - Powerlink-2275kV Feeder - Ross Substation Automation Project - Powerlink-2
275kV Feeder - Ross Substation Automation Project - Powerlink-2
 
275kV Feeder - Ross Substation Automation Project - Powerlink-1
275kV Feeder - Ross Substation Automation Project - Powerlink-1275kV Feeder - Ross Substation Automation Project - Powerlink-1
275kV Feeder - Ross Substation Automation Project - Powerlink-1
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3e
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3eCSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3e
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3e
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3c
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3cCSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3c
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3c
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3a
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3aCSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3a
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 3a
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 1
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 2
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design 1
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 2
 
132-110kV Cabolture Substation - Primary Plant 2- Energex
132-110kV Cabolture Substation - Primary Plant 2- Energex132-110kV Cabolture Substation - Primary Plant 2- Energex
132-110kV Cabolture Substation - Primary Plant 2- Energex
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 6
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 5
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 4
 
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3
Ipswich Motorway Upgrade-Intelligent Transport Systems (ITS) Layouts 3
 
1332-110kV Cabolture Substation - Primary Plant - Energex
1332-110kV Cabolture Substation - Primary Plant - Energex1332-110kV Cabolture Substation - Primary Plant - Energex
1332-110kV Cabolture Substation - Primary Plant - Energex
 
Redbank Plaza Upgrade - Street Lighting
Redbank Plaza Upgrade - Street LightingRedbank Plaza Upgrade - Street Lighting
Redbank Plaza Upgrade - Street Lighting
 
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...
CSR Sugar Mill Upgrade -Ayer QLD - Instrumentation & PLC Design - Cable Block...
 
Gallipoli Barracks Enhanced Land Force Stage 2B - HV Distribution
Gallipoli Barracks Enhanced Land Force Stage 2B - HV DistributionGallipoli Barracks Enhanced Land Force Stage 2B - HV Distribution
Gallipoli Barracks Enhanced Land Force Stage 2B - HV Distribution
 

Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-6025-08

  • 1. L290-AQ-PLN-10850 Status LCPL QA (Sub Contractor) Leightons - LCPL (Sub Contractor) JKC (Contractor) Name: Name: Name: Date: Date: Date: Signature: Signature: Signature: IVB 1.0 1.1 Issued for Construction - IFC Drawings (IFI drawing for temporary works) PE Each activity L290-AB-PRC-0004_0 Instruction for Vendor Documentation-Section 6.4 Stamped / Approved Drawings Stamped Code: A=Approved without Comment B=Approved with minor Comment N=Not Approved F= Not subject to review N/A Stamped IFC drawing 1.2 Calibration of Equipment PE As per equipment calibration register L290-AQ-SPC-0009: Quality Control Requirements for subcontractor Clause 4.6.3 of L290-AQ-SPC-0009 Documentation sighted, for inclusion into MDR, Approved ITP N/A calibration certificates 1.3 Relevant codes & Specifications sighted / Correct revision PE Each activity Section H Contract. Contract Exhibit E Drawings & Specifications Section H Contract. Contract Exhibit E Drawings & Specifications Documents sighted / Approved ITP / Check Sheet SSF01 N/A Approved ITP 1.4 Development and approval of ITP prior to construction activities PE Each activity L290-AQ-SPC-0009: Quality Control requirements for Subcontractors Clause 4.5 of L290-AQ-SPC-0009 Documentation sighted on approved ITP N/A Approved ITP 1.5 Pre-Inspection Meeting Minutes of Meeting (PIM MOM) if required as per the criticality matrix QM Each activity as required L290-AQ-SPC-0009: Quality Control requirements for Subcontractors, L290- AB-PRC- 0004:INSTRUCTION FOR VENDOR DOCUMENTATION Clause 4.4.3 of L290-AQ-SPC-0009, Clause 5.1 of L290-AB- PRC-0004 MOM Documentation sighted N/A PIM- MOM 1.6 QC Inspector Qualification - Electrical QM Once per person L290-AQ-SPC-0009 L290-AQ-SPC-0009 Section 4.14.1.3: working knowledge os AS 2381: “Electrical Equipment for Hazardous Areas”, AS/NZS 60079.17: “Explosive atmospheres –Electrical..., and AS/NZS 60079.18: “Explosive atmospheres – ... Sighted approval of Inspector document N/A Approval document 1.7 Verify SHEWMS available and approved PE Each activity Relevant Specification As Per Schedule Approved SHEWMS N/A Approved SWEHMS 2.0 2.1 Material Certificates received for all components SUP Each Delivery Contract Exhibit H and L290-AQ-SPC-0010 Section 4.11 of Exhibit H and clause 2.2 for L290-AQ-SPC- 0010 Material Register & Material Certificates sighted, for inclusion into MDR N/A material certificates 2.2 Inspection of received goods SUP Each Delivery L290-AQ-PRC-0008: QUALITY CONTROL COORDINATION PROCEDURE FOR SUBCONTRACTOR Clause 4.5.2 of L290-AQ-PRC-0008 Material Register & Material Certificates sighted, for inclusion into MDR N/A Material inspection report 3.0 3.1 Installations as per gneral arrangement and layouts SUP/ENG Each Lot IFC drawing, AS 3000, L290-AQ-TAC-0005 (Inspection and Test Plan for Electrical Works) Clause 5.5.5 of AS 3000: 2007 Inspection Test Record EP08, EP01, EP30 (L290-AR-FRM-10002) N/A ITR EP08, EP01, EP30 3.2 Equipment is tagged correctly against drawings and project specification PE Each Lot IFC drawing, AS 3000, L290-AQ-TAC-0005 (Inspection and Test Plan for Electrical Works) IFC Drawings/ Clause 5.5.1.3 of AS 3000:2007 Inspection Test Record EP08, EP01, EP30 (L290-AR-FRM-10002) N/A ITR EP08, EP01, EP30 3.3 Verify Earthing straps and Conductors cross section as per drawings and specification SUP/ENG Each Lot IFC drawing, AS 3000, L290-AQ-TAC-0005 (Inspection and Test Plan for Electrical Works) Clause 5.3.3 of AS 3000: 2007 Inspection Test Record EP08, EP01,(L290-AR-FRM-10002) N/A ITR EP08, EP01 3.5 Main earthing cable and earthing boss checked SUP/ENG Each Lot IFC drawing, AS 3000, L290-AQ-TAC-0005 (Inspection and Test Plan for Electrical Works) Clause 5.3.3.4 of AS 3000: 2007 Inspection Test Record EP01 (L290-AR-FRM-10002) N/A ITR EP01 3.6 Main earthing bar checked SUP/ENG Each Lot IFC drawing, AS 3000, L290-AQ-TAC-0005 (Inspection and Test Plan for Electrical Works) Clause 5.3.2.1 of AS 3000:2007 Inspection Test Record EP29 (L290-AR-FRM-10002) N/A ITR EP29 3.7 Main earthing rod checked SUP/ENG Each Lot IFC drawing, AS 3000, L290-AQ-TAC-0005 (Inspection and Test Plan for Electrical Works) Clause 5.3.6 of AS 3000:2007 Inspection Test Record EP30 (L290-AR-FRM-10002) N/A ITR EP30 4.0 4.1 Check type of cable tray, conduits, ladders, junction boxes & fittings. SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 IFC Drawings/ AS /NZS 3000:2007 Clause 3.8 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 4.2 Check conduit and cable tray size, routing for no obstructions and elevation. SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3, Section 7 IFC Drawings/ AS /NZS 3000:2007 Clause 3.9, 7.4 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 4.3 Check coupler plates, elbows, dropout tees, conduit fittings and accessories are properly installed. SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 IFC Drawings/ AS /NZS 3000:2007 Clause 3.9 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 4.4 Check tray and conduit supports are correct and tightened using the appropriate tool ensuring no deflection. SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 .9 IFC Drawings/ AS /NZS 3000:2007 Clause 3.9.6 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 4.5 Check tray covers and protection is provided. SUP/ENG Each Lot IFC Drawings/ AS 3000 Clause 3.2 to 3.4 IFC Drawings/ AS /NZS 3000:2007 Clause 3.3.2.6 Inspection Test Record EP10 (290-AR-FRM-10002) N/A ITR - EP10 4.6 Check pulling guide rope in concealed conduit is installed. SUP/ENG Each Lot AS 3000 Section 3 AS /NZS 3000:2007 Clause 3.9 Field Inspection Check Sheet ELC19 (L290-AR-FRM-10002) N/A FIC- ELC19 4.7 Check all wall penetrations are completely sealed and fire rated. SUP/ENG Each Lot AS 3000 Clause 3.9.9 AS /NZS 3000:2007 Clause 3.9.9.3 Inspection Test Record EP10 (290-AR-FRM-10002) N/A ITR - EP10 4.8 Check tray and conduit sharp edges have been removed. SUP/ENG Each Lot AS 3000 Clause 3.10.1 to 3.10.4 AS /NZS 3000:2007 Clause 3.10.3.5 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 4.9 Check cable tray, conduits are properly cleaned prior to cable pulling. SUP/ENG Each Lot AS 3000 Clause 3.10 to 3.11 AS /NZS 3000:2007 Clause 3.10.3.5, 3.6 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 4.10 Verify complete cable tray installation against drawings and specifications SUP/ENG Each Lot IFC Drawings/ AS 3000 Section 3 IFC Drawings/ AS 3000 Section 3 Field Inspection Check Sheet ELC19 and Inspection Test Record EP10 (L290-AR-FRM-10002) N/A FIC- ELC19, ITR - EP10 5.0 5.1 Visual inspection of cable type, size & tag no. SUP/ENG Each Lot AS 3000 Clause 8.2 AS /NZS 3000:2007 Clause 8.2.1, 8.2.2(d) Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 Date: Signature: H W Name: H H S S BUILDING EARTHING Date: Signature: Record Remarks Subcontractor H W W H H R S W H CABLEWAYS & CONDUITS W S S S Acceptance Criteria/Specification Verifying Documents Package Name: EPC BUILDING WORKS (P-31D-BLD-1), Subcontractor's Document Number: Q1447-CS-PCP-6025 ITP Title: INSPECTION AND TEST PLAN - ELECTRICAL - POWER DISTRIBUTION SYSTEMS - EPC BUILDING WORKS ITP Number: L290-AQ-PLN-10850 Contractor's Number: V-31D1-BLD-1-Z40124 H H H W S Lower Tier Sub Contractor (LTSC) Name:ITP Accepted: No. W S Independent Verification Body (IVB) W S S W S S SR S H W S S S W S H H H W SSW SW W S S Quality Verification Activity/Stage Reference Procedure H Contractor Company APPROVALS AND OTHER PRELIMINARY REQUIREMENTS LTSC Required Inspection S S H W S S H W S S H ABOVE GROUND CABLING SS 9 H H W R SH H W W S S S S W S S W S S S MATERIAL RECEIVING/DOCUMENT INSPECTION H W S H W H H H W W S Responsibility Frequency H H H H H Q1447-CS-PCP-6025-08 (1).xlsx:Page 1/2
  • 2. L290-AQ-PLN-10850 Status LCPL QA (Sub Contractor) Leightons - LCPL (Sub Contractor) JKC (Contractor) Name: Name: Name: Date: Date: Date: Signature: Signature: Signature: IVB Date: Signature: Name: Date: Signature: Record Remarks Subcontractor Acceptance Criteria/Specification Verifying Documents Package Name: EPC BUILDING WORKS (P-31D-BLD-1), Subcontractor's Document Number: Q1447-CS-PCP-6025 ITP Title: INSPECTION AND TEST PLAN - ELECTRICAL - POWER DISTRIBUTION SYSTEMS - EPC BUILDING WORKS ITP Number: L290-AQ-PLN-10850 Contractor's Number: V-31D1-BLD-1-Z40124 Lower Tier Sub Contractor (LTSC) Name:ITP Accepted: No. Independent Verification Body (IVB) Quality Verification Activity/Stage Reference Procedure Contractor CompanyLTSC Required Inspection 9 Responsibility Frequency 5.2 Visually inspect the cable is not damaged or snagged during cable pulling. SUP/ENG Each Lot AS 3000 Section 3 AS /NZS 3000:2007 Clause 3.3.2.7, 3.3.2.8 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.3 Check cable-bending radius according to specifications. SUP/ENG Each Lot AS 3000 Clause 3.9 AS /NZS 3000:2007 Clause 3.9.6 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.4 Check cable segregation as per drawings SUP/ENG Each Lot IFC drawing /AS 3000 Section 3.9 AS /NZS 3000:2007 Clause 3.9.8.3, IFC drawings Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.5 Check cable fixing on tray properly installed. SUP/ENG Each Lot AS 3000 Clause 3.3 AS /NZS 3000:2007 Clause 3.3.2.6 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.6 Check wiring above ceiling is properly installed. SUP/ENG Each Lot AS 3000 Section 3.9 AS /NZS 3000:2007 Clause 3.9.3.2 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.7 Check cable ID tag no. Is properly installed. SUP/ENG Each Lot AS 3000 section 3 AS /NZS 3000:2007 Clause 3.9 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.8 Check cable continuity and megger test after pulling. SUP/ENG Each Lot AS 3000 Clause 3.10 AS /NZS 3000:2007 Clause 3.10.3.3 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 5.9 Check protection of cable ends after megger test. SUP/ENG Each Lot AS 3000 Clause 3.10 AS /NZS 3000:2007 Clause 3.10.3.5 Inspection Test Record EP40 and EP01 for single cables only if relevant (L290-AR-FRM-10002) N/A ITR - EP40, EP01 6.0 6.1 Check general arrangement of installation meets drawings and specifications. SUP/ENG Each Lot IFC Drawing/ AS 3000 Clause 4.3 IFC Drawing/ AS/NZS 3000: 2007 Clause 4.3.3 Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM- 10002) N/A ITR - EP05,EP07, EP14, EP37,EP42 6.2 Check Socket Outlet/ Junction Boxes/ Isolators are correct alligned, leveled, ridget and secured with correct fixings. SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 4.4.2 Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM- 10002) N/A ITR - EP05,EP07, EP14, EP37,EP42 6.3 Check earthing and bonding of sockets outlets against drawings. SUP/ENG Each Lot IFC Drawing/ AS 3000 Clause 4.4 IFC Drawing/ AS/NZS 3000: 2007 Clause 4.4.3 Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM- 10002) N/A ITR - EP05,EP07, EP14, EP37,EP42 6.4 Check Socket Outlet/ Junction Boxes/ Isolators is clean and free from dust/debris, internal internals. SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 4.4.2.2(a) Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM- 10002) N/A ITR - EP05,EP07, EP14, EP37,EP42 6.5 Check all terminals and connections are tight, correctly made and identified as per drawings. SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 4.4.2.2© Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM- 10002) N/A ITR - EP05,EP07, EP14, EP37,EP42 6.6 Perform insulation resistance test. Each phase to earth. SUP/ENG Each Lot AS 3000 Clause 4.4 AS/NZS 3000 : 2007 Clause 8.3.6 Inspection Test Record EP05, EP07, EP14 EP37, EP42 (290-AR-FRM- 10002) N/A ITR - EP05,EP07, EP14, EP37,EP42 6.7 Conduct Earth loop impedance test. SUP/ENG Each Lot AS 3000 Clause 8.3 AS/NZS 3000: 2007 Clause 8.3.9 Inspection Test Record EP05, EP07, EP14 EP37, EP42, EP44 (290- AR-FRM-10002) N/A ITR - EP05,EP07, EP14, EP37,EP42, EP44 7.0 7.1 Verify sign-off of all Inspection and Test documentation ENG Each Lot ITP/ FICs Signed off ITP/ FICs Completed ITP checklist N/A ITP, FICs 7.2 Verify all drawings 'As built' status PE/QM Each drawing IFC Drawing/ As Built drawing, Contract exhibit H IFC Drawing/ As Built drawing Completed As-built drawings N/A respective drawing 7.3 Completion and handover/delivery of relevant QA documentation to MDR PE/QM Each lot/Activity Collate records as perL290-AQ-SPC-0001, L290- AQ-SPC-0010, Exhbit H applicable sections, As 3000 and IFC drawings and FICS, test reports, material certificates and all other relevant records Collate records as perL290-AQ-SPC-0001, L290-AQ-SPC- 0010, Exhbit H applicable sections, As 3000 and IFC drawings and FIC's/ ITR's, test reports, material certificates and all other relevant records IFC drawings, signed off FIC's/ ITR's, test reports, material certificates, inspection reports, survey reports and all other relevant records of ITP N/A Partial MDR H - Hold Point SUP Supervisor LTSC PIM W - Witness Point ENG LCPL Engineer LCPL MOM IW - Initial Witness PE LCPL Project Engineer JKC QA S - Surveillance JKC JKC Representative INPEX FICS R - Record Review SHEWMS Safety,Health and Environmental Work Method Statement N/A MDR OR - Official Record IVB IFC IR - Internal Record Document Number: L290-AQ-PLN-10850 IFI Subcontractor Contractor W R S W S COMPLETION AND HANDOVER / DELIVERY Company Not Applicable H H H W S W S S W SOCKET OUTLET/ JUNCTION BOX/ ISOLATOR S Independent Verification Body Low Tier Subcontractor H H H S S H S W W S W R W S S W S Issued for construction S S S S W H H W H H S R W S S S S S S Issued for information Minutes of Meeting Quality Assuarance Field Inspection Check Sheet Manufacturers' Data record Pre Inspection Meeting S S H W W W S S H/R RH H H H H W W S S S S Q1447-CS-PCP-6025-08 (1).xlsx:Page 2/2