The Rio Vista Drive channel stabilization project in Fairfax County, VA involved stabilizing an existing drainage channel along Rio Vista Drive east of Haislip Lane. The project included excavating and grading the channel, installing a grass-lined V-ditch and rip-rap lined trapezoidal ditch, and adding endwalls and rip-rap to reduce flow velocity and erosion. Jute mesh was used to stabilize the banks and establish vegetation in the V-ditch. The project was substantially completed in May 2015 and improved drainage and water quality to the Occoquan Bay watershed.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
South Lakes Drive Walkway was substantially completed on September 17, 2021. The project included construction of 3,370 linear feet of sidewalk, pedestrian ramps, pedestrian signals, handrail, bus shelter and loading pads, curbs and gutters, asphalt milling and paving, pavement markings and signage, fire hydrant relocation, and drainage adjustment.
The Quander Road Walkway project was substantially completed on June 15, 2021. The project included construction of approximately 1,800 linear feet of five-foot wide concrete sidewalk along the west side of Quander Road with curb and gutter, refuge island with ramps, curb-cut ramps, driveway aprons, vast storm drainage improvements, utility relocations, asphalt pavement, pavement markings, and roadway widening to provide minimum lane widths of 11 feet between Emmett Drive and Stokes Lane.
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
The Telegraph Walkway Project was substantially completed on time and under budget on September 13, 2021. This project consisted of construction of 5’ concrete sidewalk, curb ramp, curb & gutter, drilled shaft for slope stability, RW-3, handrail, pavement mill and overlay, pavement marking, water line relocation and some other related items.
South Lakes Drive Walkway was substantially completed on September 17, 2021. The project included construction of 3,370 linear feet of sidewalk, pedestrian ramps, pedestrian signals, handrail, bus shelter and loading pads, curbs and gutters, asphalt milling and paving, pavement markings and signage, fire hydrant relocation, and drainage adjustment.
The Quander Road Walkway project was substantially completed on June 15, 2021. The project included construction of approximately 1,800 linear feet of five-foot wide concrete sidewalk along the west side of Quander Road with curb and gutter, refuge island with ramps, curb-cut ramps, driveway aprons, vast storm drainage improvements, utility relocations, asphalt pavement, pavement markings, and roadway widening to provide minimum lane widths of 11 feet between Emmett Drive and Stokes Lane.
The North Shore Drive Sidewalk Improvements project has been Substantially Completed. The overall project scope was to increase pedestrian safety along North Shore Drive . The new pedestrian walkway consists of 2,315 lineal feet of 5-foot wide concrete sidewalk and 224 lineal feet of 6-foot wide asphalt walking path. The project started approximately 500 feet West of Sycamore Valley drive and extended to approximately 400 feet East of Links Drive. Also, along with the improved pedestrian access, upgrades were made to the storm drain system, a new concrete pad was placed for the existing bus shelter and the Eastbound lane of North Shore Drive was milled and new asphalt and striping was installed.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
Reston Parkway at Dulles Toll Road EB and WB provides pedestrian access improvement at the intersection of Reston Parkway at Dulles Toll Road and to the intersection of Fairfax County Parkway and Sunset Hills Road.
Reston Parkway at Dulles Toll Road EB off-ramp and Reston Parkway at Dulles Toll Road WB on-ramp was substantially completed on October 6, 2021. Due to COVID-19 Pandemic, some of pedestrian signal electrical hardware and software supply delayed and created huge gap from the substantial completion date to the full activation of the project. The scope of this project was construction of concrete median islands, curb ramps, curb and gutter, and full replacement of asphalt trail, asphalt mill/overlay, signs and new pedestrian signals installation.
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
North Beauregard Street at North Chambliss Street Spot Improvement project was substantially completed on October 10, 2021. The scope of this project was the construction of pedestrian access spot improvement at the intersection of North Beauregard Street and North Chambliss Street. The improvement consists of modifying the existing island at North Beauregard Street to reduce the pedestrian crossing distance and install pedestrian flashing beacon. The project also includes the Landmark’s shopping Plaza access improvements.
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
The scope of this project was construction of concrete sidewalk, curb and gutter, curb-cut ramps, retaining wall, pavement mill and overlay, pavement markings and signings, closed drainage system improvements and watermain relocation.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleFairfax County
The Sunrise Valley Dr. Sidewalk Improvements – River Birch Road to Legacy Circle project included construction of approximately 387 linear feet of concrete sidewalk along Sunrise Valley Drive connecting River Birch Road to Legacy Circle, a new concrete bus pad and 5 pedestrian accessible ramps.
Backlick Run Gravity Sewer Abandonment Project June 2020Fairfax County
This is a 4,000 linear foot section of gravity sewer that was taken out of service. The pipe had deteriorated and was prone to collapse. The area was restored and site improvements were completed.
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
In this slideshow, Micheal ONeill, Senior Advisor to the Director, VA Innovation Initiative (VAi2), US Department of Veterans Affairs, outlines the need for a new approach to electronic health record systems and the benefits of establishing a new, open source community worldwide, in order to drive innovation.
Michael ONeill presented at the Nuffield Trust seminar: Sharing international experience: Is implementing the VA's electronic health record system an option for the NHS? in July 2012.
Geraint Lewis: The VA’s Open-Source Electronic Medical Record System: An oppo...Nuffield Trust
In this slideshow, Geraint Lewis, Senior Fellow at the Nuffield Trust, outlines why VistA, an open source electronic medical record system, would be a viable option for the NHS.
Geraint Lewis presented at the Nuffield Trust seminar: Sharing international experience: Is implementing the VA's electronic health record system an option for the NHS? in July 2012.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
Reston Parkway at Dulles Toll Road EB and WB provides pedestrian access improvement at the intersection of Reston Parkway at Dulles Toll Road and to the intersection of Fairfax County Parkway and Sunset Hills Road.
Reston Parkway at Dulles Toll Road EB off-ramp and Reston Parkway at Dulles Toll Road WB on-ramp was substantially completed on October 6, 2021. Due to COVID-19 Pandemic, some of pedestrian signal electrical hardware and software supply delayed and created huge gap from the substantial completion date to the full activation of the project. The scope of this project was construction of concrete median islands, curb ramps, curb and gutter, and full replacement of asphalt trail, asphalt mill/overlay, signs and new pedestrian signals installation.
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
North Beauregard Street at North Chambliss Street Spot Improvement project was substantially completed on October 10, 2021. The scope of this project was the construction of pedestrian access spot improvement at the intersection of North Beauregard Street and North Chambliss Street. The improvement consists of modifying the existing island at North Beauregard Street to reduce the pedestrian crossing distance and install pedestrian flashing beacon. The project also includes the Landmark’s shopping Plaza access improvements.
Fairfax County Fleet Drive Walkway Improvements Sept 2020Fairfax County
The scope of this project was construction of concrete sidewalk, curb and gutter, curb-cut ramps, retaining wall, pavement mill and overlay, pavement markings and signings, closed drainage system improvements and watermain relocation.
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
Leigh Meadow & Towlston Basin project was substantially completed on October 29, 2021. This project consists of 1,660 feet of stream restoration, a 22,300 cubic foot Regenerative Stormwater Conveyance (RSC) facility and a 28,500 cubic foot sand filter. The scope of work also included grading, excavation, pollution and sediment removal, and restoration planting.
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
Accotink Creek at Wakefield Park Stream Restoration project was substantially completed on November 23, 2021. This project consists of restoring, enhancing, and stabilizing of approximately 4,900 linear feet of stream channel through the installation of four Newbury Riffles within the main channel of Accotink Creek and one Newbury Riffle within a side channel to provide aquatic benefits, grade control, improve water quality and prevent further erosion.
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleFairfax County
The Sunrise Valley Dr. Sidewalk Improvements – River Birch Road to Legacy Circle project included construction of approximately 387 linear feet of concrete sidewalk along Sunrise Valley Drive connecting River Birch Road to Legacy Circle, a new concrete bus pad and 5 pedestrian accessible ramps.
Backlick Run Gravity Sewer Abandonment Project June 2020Fairfax County
This is a 4,000 linear foot section of gravity sewer that was taken out of service. The pipe had deteriorated and was prone to collapse. The area was restored and site improvements were completed.
Gallows Road and Prosperity Avenue ImprovementsFairfax County
The Gallows Road and Prosperity Avenue improvements Project extended a four-foot concrete median along Gallows Road near the intersection of Prosperity Avenue to prevent illegal left turns. The Improvements include extending the existing median, resetting existing sign, eradicating existing pavement markings and placing new pavement marking around the new median.
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
2019 study evaluated several alternatives for replacement
Selected alternative would:
Eliminate the exposed sewer/stream crossing
Maintain level of sewer services to the community
Provide future access ease to Fairfax County’s wastewater operator
Improve system’s reliability in the area
Reduce future risk of sanitary sewer overflows
Reduce risk to public health and the environment
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
In this slideshow, Micheal ONeill, Senior Advisor to the Director, VA Innovation Initiative (VAi2), US Department of Veterans Affairs, outlines the need for a new approach to electronic health record systems and the benefits of establishing a new, open source community worldwide, in order to drive innovation.
Michael ONeill presented at the Nuffield Trust seminar: Sharing international experience: Is implementing the VA's electronic health record system an option for the NHS? in July 2012.
Geraint Lewis: The VA’s Open-Source Electronic Medical Record System: An oppo...Nuffield Trust
In this slideshow, Geraint Lewis, Senior Fellow at the Nuffield Trust, outlines why VistA, an open source electronic medical record system, would be a viable option for the NHS.
Geraint Lewis presented at the Nuffield Trust seminar: Sharing international experience: Is implementing the VA's electronic health record system an option for the NHS? in July 2012.
Guinea Road and Lakepointe Drive Sidewalk and Intersection ImprovementsFairfax County
This project consisted of construction of approximately 800 feet of 5-foot wide concrete sidewalk, curb and gutter, curb ramps, concrete bus pads, and an upgrade of the existing storm water conveyance system along with storm water control features. This project will enhance the safety of pedestrian traffic through the intersection of Guinea Road and Lakepointe Drive.
Difficult Run Tributary at Brittenford Drive Stream RestorationFairfax County
Difficult Run Tributary at Brittenford Drive Stream Restoration Project has been substantially completed. The purpose of this project was to rehabilitate approximately 5,400 linear feet of the Difficult Run stream and tributaries in Vienna, VA through the use of natural channel design (NCD) techniques to restore “natural” stream flow.
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Fairfax County
The emergency repair of an 8-inch sanitary sewer link in Little River Turnpike and Backlick Road replaced a severely defective 8-inch concrete sewer pipe with new PVC pipe to prevent sanitary sewer overflows in the travel lanes of Little River Turnpike and Backlick Rd. in Annandale, VA.
Fairfax County Little River Turnpike Walkway August 2020Fairfax County
The Little River Turnpike walkway pedestrian improvement project was completed on June 29, 2020. The project increases pedestrian safety from Columbia Rd. to Mayhunt Ct. with 2580 linear feet of 5-foot wide concrete sidewalk.
Hunter Mill Road and Sunrise Valley Drive Pedestrian ImprovementsFairfax County
The project provides pedestrian improvements at the intersection of Hunter Mill Road (Route 674) and Sunrise Valley Drive (Route 6320). Improvements include installing 1,037 linear feet of concrete sidewalk, curb and gutter, concrete sidewalks, curb ramps, refuge island, realigning the southbound right turn lane, and milling and asphalt paving near the intersection. Drainage improvements include installing 1,069 linear feet of storm drain pipes, curb drop inlets, and a Filterra unit.
Hayfield Road Pipe Conveyance System January 2021Fairfax County
The purpose of this project was to alleviate an ongoing stormwater surcharge issue in the Hayfield Road community by providing additional capacity to the stormwater sewer system through the installation of a new stormwater sewer line and outlet into the woods.
Similar to Rio Vista Drive Channel Stabilization (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
31052024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
In a May 9, 2024 paper, Juri Opitz from the University of Zurich, along with Shira Wein and Nathan Schneider form Georgetown University, discussed the importance of linguistic expertise in natural language processing (NLP) in an era dominated by large language models (LLMs).
The authors explained that while machine translation (MT) previously relied heavily on linguists, the landscape has shifted. “Linguistics is no longer front and center in the way we build NLP systems,” they said. With the emergence of LLMs, which can generate fluent text without the need for specialized modules to handle grammar or semantic coherence, the need for linguistic expertise in NLP is being questioned.
01062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
role of women and girls in various terror groupssadiakorobi2
Women have three distinct types of involvement: direct involvement in terrorist acts; enabling of others to commit such acts; and facilitating the disengagement of others from violent or extremist groups.
03062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
हम आग्रह करते हैं कि जो भी सत्ता में आए, वह संविधान का पालन करे, उसकी रक्षा करे और उसे बनाए रखे।" प्रस्ताव में कुल तीन प्रमुख हस्तक्षेप और उनके तंत्र भी प्रस्तुत किए गए। पहला हस्तक्षेप स्वतंत्र मीडिया को प्रोत्साहित करके, वास्तविकता पर आधारित काउंटर नैरेटिव का निर्माण करके और सत्तारूढ़ सरकार द्वारा नियोजित मनोवैज्ञानिक हेरफेर की रणनीति का मुकाबला करके लोगों द्वारा निर्धारित कथा को बनाए रखना और उस पर कार्यकरना था।
‘वोटर्स विल मस्ट प्रीवेल’ (मतदाताओं को जीतना होगा) अभियान द्वारा जारी हेल्पलाइन नंबर, 4 जून को सुबह 7 बजे से दोपहर 12 बजे तक मतगणना प्रक्रिया में कहीं भी किसी भी तरह के उल्लंघन की रिपोर्ट करने के लिए खुला रहेगा।
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Rio Vista Drive Channel Stabilization
Contract No. CN3125900
Project No. SD-000031-043A
Task Order No. 22
Mount Vernon District
August 12, 2015
2. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization
Post Construction
Jute Mesh used to stabilized the banks
3. Rio Vista Drive Channel Stabilization
Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Mount Vernon District, Tax Map #118-1
Project Site
4. Project Details
Rio Vista Drive Channel Stabilization
Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Description:
The Rio Vista Drive channel stabilization project was substantially completed on May 18, 2015. The existing
roadside channel is located along the Northern side of Rio Vista Drive, east of Haislip Lane, and within the
Kane Creek Watershed. The project provides improvements to the existing drainage channel by stabilizing
the roadside ditch with a grass lined V-ditch and rip-rap trapezoidal ditch. The improvements will reduce the
flow velocity, provide stability, and enhance water quality along the steep slopes leading to the Occoquan
Bay.
Project Overview:
• Removing concrete rubble along the existing channel
• Excavating and grading the existing roadside channel
• Installing a V-ditch and rip-rap lined trapezoidal ditch
• Installing a soil retention mat to stabilize and establish the vegetated V-ditch
• Lining the trapezoidal ditch with rip-rap
• Installing an endwall at each of the existing and new concrete pipes
• Stabilizing the storm pipe outfall area with geotextile fabric and rip-rap
• Restoring the existing road to its original surface
Project Team:
• Maintenance and Stormwater Management Division – Jeff Vish
• Utilities Design and Construction Division - Yousef Rayyan
• Utilities Design and Construction Division - Howard Champ
• Land Survey Branch - Gregory Harper
5. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization
Pre-Construction
6. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization
Post Construction
7. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization
Pre-Construction
8. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization
Post Construction
9. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Pre-Construction
Rio Vista Drive Channel Stabilization
10. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization
Post Construction
11. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Pre-construction
Rio Vista Drive Channel Stabilization
12. Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Post Construction
Rio Vista Drive Channel Stabilization
14. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
Ben Boxer, Public Information Officer
703-324-5880, TTY 711
Ben. Ben Boxer, Public Information Officer
703-324-5880, TTY 711
Ben. Ben Boxer, Public Information Officer
703-324-5880, TTY 711
Ben.Boxer@fairfaxcounty.gov
Irene Haske, Public Information Officer
703-324-5500, TTY 711
Irene.Haske@fairfaxcounty.gov
Capital Facilities/Utilities Design and Construction Division/Transportation & Stormwater Construction Branch
Rio Vista Drive Channel Stabilization