CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
Department of Public Works and Environmental Services 
A Fairfax County, VA, publication 
Working for You! 
Contract Number CN13316004 
Project Number SD-000017-002 
Task Order No. 22 
Springfield District 
June 5, 2014
CROSSPOINTE SEC. 15 PD 15A (#0775DP) 
PROJECT 
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
Project Details 
Description: 
The Crosspointe Sec. 15 PD (#0775DP) project was substantially completed on August 23, 2014. This 
is an existing SWM facility and it is located adjacent to the intersection of Cross Chase Court and Cross 
Chase Circle in Fairfax Station. The project pond was retrofitted to provide improved water quality 
benefits and additional storage. The proposed water quality benefits realized by this project will be 
the removal of 10.99 lbs./year of total phosphorus, 2.41 lbs./year of total nitrogen and 472.58 
lbs./year of total suspended solids. 
Project Overview: 
• Re-graded the facility to lengthen the flow path and maximize the pond volume. 
• Excavated and constructed three micro-pools at a maximum depth of 18” below the pond bottom. 
• Extended class I riprap of the existing two inflow structures to the bottom of the micro pools. 
• Installed a rock weir structure in addition to minor grading to the stream channel that outfalls into 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch 
the existing pond. 
• Replaced the existing gravel trail and extended it to the location shown on the plan. 
• Restored the site with seed mix, trees will be planted at the end of Sept. 2014. 
Project Team: 
• Stormwater and Planning Division – Charles Smith 
• Utilities Design and Construction Division - Yousef Rayyan 
• Utilities Design and Construction Division – Joseph Adzovie 
• Surveyor - Gregory Harper
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
Fairfax Station, VA, Tax Map #106-2 
Project Site 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
PRE-EXISTING CONDITIONS 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch 
AN EXISTING RISER
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
POST CONSTRUCTION 
MICRO-POOL NO.2 
MICRO-POOL NO.1 
MICRO-POOL NO.3 
EXTENDING THE RIP-RAP 
TO THE BOTTOM 
OF THE MICR-POOL 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
PRE-EXISTING CONDITIONS 
15” RCP INFLOWS FROM THE 
NORTH END OF THE POND 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
POST CONSTRUCTION 
THE ACCESS ROAD 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch 
15” RCP INFLOWS FROM THE 
NORTH END OF THE POND 
MICRO-POOL NO.3
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
PRE-EXISTING CONDITIONS OF THE TRAIL 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
THE NEW TRAIL AFTER REPLACEMENT 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
ROCK WEIR STRUCTURE AND THE IMPROVEMNET OF THE EXISTING CHANNEL 
A ROCK WEIR STRUCTURE AND MINOR GRADING 
WERE PROPOSED TO IMPROVE THE STREAM 
CHANNEL THAT OUTFALLS FROM THE WEST END 
INTO THE POND
CROSSPOINTE SEC. 15 PD 15A (#0775DP) PROJECT 
Before After 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
Additional Information 
For additional Information, please call 
Irene Ben Haske, Boxer, Public Public Information Information Officer 
Officer 
703-324-5880, TTY 711 
703-Ben. 324-Ben Boxer, 5500, Public Information TTY 711 
Officer 
703-324-5880, TTY 711 
Irene.Ben. Haske@Ben Boxer, Public fairfaxcounty.Information Officer 
gov 
703-324-5880, TTY 711 
Ben.Boxer@fairfaxcounty.gov 
www.fairfaxcounty.gov/dpwes 
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch

Crosspointe Pond Retrofit 2014

  • 1.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT Department of Public Works and Environmental Services A Fairfax County, VA, publication Working for You! Contract Number CN13316004 Project Number SD-000017-002 Task Order No. 22 Springfield District June 5, 2014
  • 2.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
  • 3.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT Project Details Description: The Crosspointe Sec. 15 PD (#0775DP) project was substantially completed on August 23, 2014. This is an existing SWM facility and it is located adjacent to the intersection of Cross Chase Court and Cross Chase Circle in Fairfax Station. The project pond was retrofitted to provide improved water quality benefits and additional storage. The proposed water quality benefits realized by this project will be the removal of 10.99 lbs./year of total phosphorus, 2.41 lbs./year of total nitrogen and 472.58 lbs./year of total suspended solids. Project Overview: • Re-graded the facility to lengthen the flow path and maximize the pond volume. • Excavated and constructed three micro-pools at a maximum depth of 18” below the pond bottom. • Extended class I riprap of the existing two inflow structures to the bottom of the micro pools. • Installed a rock weir structure in addition to minor grading to the stream channel that outfalls into Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch the existing pond. • Replaced the existing gravel trail and extended it to the location shown on the plan. • Restored the site with seed mix, trees will be planted at the end of Sept. 2014. Project Team: • Stormwater and Planning Division – Charles Smith • Utilities Design and Construction Division - Yousef Rayyan • Utilities Design and Construction Division – Joseph Adzovie • Surveyor - Gregory Harper
  • 4.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT Fairfax Station, VA, Tax Map #106-2 Project Site Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
  • 5.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT PRE-EXISTING CONDITIONS Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch AN EXISTING RISER
  • 6.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT POST CONSTRUCTION MICRO-POOL NO.2 MICRO-POOL NO.1 MICRO-POOL NO.3 EXTENDING THE RIP-RAP TO THE BOTTOM OF THE MICR-POOL Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
  • 7.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT PRE-EXISTING CONDITIONS 15” RCP INFLOWS FROM THE NORTH END OF THE POND Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
  • 8.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT POST CONSTRUCTION THE ACCESS ROAD Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch 15” RCP INFLOWS FROM THE NORTH END OF THE POND MICRO-POOL NO.3
  • 9.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT PRE-EXISTING CONDITIONS OF THE TRAIL Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
  • 10.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT THE NEW TRAIL AFTER REPLACEMENT Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
  • 11.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT ROCK WEIR STRUCTURE AND THE IMPROVEMNET OF THE EXISTING CHANNEL A ROCK WEIR STRUCTURE AND MINOR GRADING WERE PROPOSED TO IMPROVE THE STREAM CHANNEL THAT OUTFALLS FROM THE WEST END INTO THE POND
  • 12.
    CROSSPOINTE SEC. 15PD 15A (#0775DP) PROJECT Before After Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
  • 13.
    Additional Information Foradditional Information, please call Irene Ben Haske, Boxer, Public Public Information Information Officer Officer 703-324-5880, TTY 711 703-Ben. 324-Ben Boxer, 5500, Public Information TTY 711 Officer 703-324-5880, TTY 711 Irene.Ben. Haske@Ben Boxer, Public fairfaxcounty.Information Officer gov 703-324-5880, TTY 711 Ben.Boxer@fairfaxcounty.gov www.fairfaxcounty.gov/dpwes Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch