The Bradley Acres Pond Retrofit project in Fairfax County, VA converted an existing dry pond into a constructed wetland pond. The project removed the existing trickle ditch, excavated three shallow marshes, constructed a step pool conveyance channel and plunge pool, and installed two stone weir structures. Native plants were seeded and trees/plugs were replanted. The project provides improved downstream water quality by removing nutrients and suspended solids from stormwater runoff.
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...Fairfax County
Chesterbrook Road Emergency Project – Summer 2019
Final Scoping Technical Memorandum – January 2020
Professional Services Contract Execution – April 2021
Community Meeting on stream restoration Pre-design/Channel alignments – April 2021
Final Preliminary Engineering Report – October 2021
Community Meeting on Sanitary Realignment Preliminary Engineering Report – October 2021
Value Engineering Study completed – November 2021
One joint study for both projects
Community Meeting with Board of Supervisor – December 2021
Community meeting – January 2022
Design Contract Development – (We are at this step)
Land Acquisition – (We are at this step)
Complete Design
Construction
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
This Fairfax County project seeks to stabilize excessive, ongoing stream erosion which threatens sanitary sewer pipes, undermines trees, impacts water quality and degrades habitat for aquatic life.
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
Restore approximately 3,500 feet of stream on Lake Werowance Inc. and privately owned properties.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream system
Improve habitat
Maintain close coordination with stakeholders
Enhance water quality and biological diversity through the enhancements of existing wetland features within the former lakebed
Little Pimmit Run at Chesterbrook Road Stream Restoration and Sanitary Reali...Fairfax County
Chesterbrook Road Emergency Project – Summer 2019
Final Scoping Technical Memorandum – January 2020
Professional Services Contract Execution – April 2021
Community Meeting on stream restoration Pre-design/Channel alignments – April 2021
Final Preliminary Engineering Report – October 2021
Community Meeting on Sanitary Realignment Preliminary Engineering Report – October 2021
Value Engineering Study completed – November 2021
One joint study for both projects
Community Meeting with Board of Supervisor – December 2021
Community meeting – January 2022
Design Contract Development – (We are at this step)
Land Acquisition – (We are at this step)
Complete Design
Construction
Cameron Run Tributary at La Vista Drive Stream Restoration June 2020Fairfax County
This Fairfax County project seeks to stabilize excessive, ongoing stream erosion which threatens sanitary sewer pipes, undermines trees, impacts water quality and degrades habitat for aquatic life.
Piney Run at Lake Werowance Stream Restoration Project Oct 2019Fairfax County
Restore approximately 3,500 feet of stream on Lake Werowance Inc. and privately owned properties.
Stabilize streambed and banks
Reduce sediment and nutrient inputs into stream system
Improve habitat
Maintain close coordination with stakeholders
Enhance water quality and biological diversity through the enhancements of existing wetland features within the former lakebed
Hunting Creek at Fairfield Stream RestorationFairfax County
The Hunting Creek at Fairchild Stream Restoration project, Substantially Completed on January 13, 2021, includes restoring, enhancing and stabilizing approximately 1,186 linear feet of stream channel in two segments and 166 linear feet of tributary through natural channel design to provide aquatic benefits, grade control, improve water quality and prevent further erosion. The work also included demolition of a condemned house and accessory structures including obtaining all associated demolition permits and restoration landscaping.
The Meadow Run (0273DP) dry pond is located within the Bull Neck Run Watershed. The project replaced a deteriorating control structure and primary spillway, increased the storage volume and incorporated water quality improvements through the use of extended detention, wetland plantings and increased travel time. The project also upgraded the maintenance access.
Bull Neck Run at Spring Hill Recreation Center Stream RestorationFairfax County
The project site is situated east of Springhill Road, north of Lewinsville Road, and south of Old Dominion Drive. This project included restoring approximately 2,000 linear feet of the Bull Neck stream channel and tributaries which drain directly to the Potomac River in Mclean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included rock sill, boulder toe protection, buried rock toe, riffle with log sill, step pools, boulder clusters, modified cross vanes with woody debris, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Backlick Run Gravity Sewer Abandonment Project June 2020Fairfax County
This is a 4,000 linear foot section of gravity sewer that was taken out of service. The pipe had deteriorated and was prone to collapse. The area was restored and site improvements were completed.
Flatlick Branch III Stream Restoration June 6, 2020Fairfax County
The Flatlick Branch Phase III Stream Stabilization Project was substantially completed on April 10, 2020. The project aims to stabilize approximately 4000 linear feet of degraded stream channel from Walney Road to the culvert at Route 28 in Fairfax County and improve the water quality of the channel and downstream receiving waters.
Merrywood Force Main Rehabilitation ProjectFairfax County
The Merrywood Force Main Rehabilitation project included rehabilitation of 1,080 linear feet of 6-inch force main, its discharge manhole, and the installation of a future bypass system in front of the pump station.
Colfax Ave Emergency Sewer Rehabilitation ProjectFairfax County
This project rehabilitated 1,200 feet of failing 10-inch cast iron sewer pipe. Work included acquisition of land access rights from citizens, installation of a bypass pumping system, extensive cleaning of the wastewater sewer pipe, rehabilitation of the wastewater sewer pipe, and site restoration.
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Fairfax County
The emergency repair of an 8-inch sanitary sewer link in Little River Turnpike and Backlick Road replaced a severely defective 8-inch concrete sewer pipe with new PVC pipe to prevent sanitary sewer overflows in the travel lanes of Little River Turnpike and Backlick Rd. in Annandale, VA.
Project Description:
The Newington Commons Pond Improvement Project has been Substantially Completed. The purpose of this project was the restoration of approximately 351 linear feet of stream and improvement of the receiving stormwater pond.
Project Overview:
Dredging of the pond to increase storage volume
Replacement of the concrete riser structure
Restoration of stream channels utilizing natural channel design
Dead Run Stream Restoration at McLean Central Park - Segments 2 and 3Fairfax County
The project restored approximately 3,000 linear feet of stream within the Dead Run Watershed which drains directly to the Potomac River in McLean, Virginia. Restoration of the stream was achieved using natural channel design principles. The project included boulder riffles, step pools, log vanes, root wad structures, buried rock sills, reinforced stream bed material, removal of invasive plants and the re-establishment of the riparian buffer with native species.
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
The Flatlick Branch Phase II Stream Restoration project included restoration of 4,600 linear feet of Flatlick Branch and its tributaries, provided a sustainable channel form, pattern and profile to meet today’s developed landscape, added in-stream habitat enhancement and flood plain restoration, rock structures to provide grade control throughout the channel and provide energy dissipation, and the planting of the stream areas with native vegetation.
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
Scotts Run @ Old Meadow Road Stream Restoration was substantially completed on March 30, 2022. The Scotts Run project consisted of restoring, enhancement, and stabilizing of approximately 2,930 linear feet of eroding stream using Natural Channel Design criteria. This project included two phases: Phase I was funded by proffers from a private development and Phase II was County funded. Also included was the removal of invasive non-native plants and the installation of new plantings to stabilize the stream and floodplain.
Similar to Bradley Acres Pond Retrofit Project (20)
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
During a routine Closed-Circuit Television (CCTV) Camera inspection by Wastewater Collection Division (WCD), it was found that 45 linear feet of 8-inch asbestos reinforced concrete pipe (RCP) between MH-292 to MH-291 was within imminent danger of failing. The bottom of the RCP was missing within the 45 linear feet of repair and the pipe was on the verge of surcharging. After an immediate pre-construction meeting with Merrifield Nursery, it was agreed to work from 6pm-10am everyday of the week to avoid disruption and potentially placing patrons at risk during the biggest time of the year for Merrifield Garden Center. The contractor mobilized to the site and began the 20-foot excavation to replace 45 linear feet of broken gravity sewer. The project started on March 14th, 2022 and was substantially complete on March 23, 2022.
The Sully Basins Stormwater Pond Retrofits project was substantially completed on April 19, 2022. The project is located within the Cub Run watershed. The project consisted of repair and enhancement of multiple stormwater basins, 0326DP, 0964DP and 1484DP. The project also included construction of new stone cascades, stone weir basin structures and the construction of wetlands with high and low marsh areas. The project will facilitate improved sediment removal and improve downstream water quality using forebays and micro pools. Aquatic and natural habitat were also added within the three basins.
Clarks Crossing Road Improvements 05-13-22Fairfax County
The Clarks Crossing Road Pedestrian Access Improvement project improved the pedestrian and bicycle access along Clarks Crossing Road and was substantially completed on March 23, 2022.
This project completed the missing link between the existing sidewalk at Brookside Lane and the previously constructed sidewalk along Clarks Crossing Road. The scope of this project included construction of asphalt sidewalk, curb ramps, curb and gutter, drainage improvements along Brookside Lane and asphalt mill/overlay on Clarks Crossing and Brookside Lane.
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
Future wastewater flows in northern Fairfax County exceed existing system capacity
Treatment capacity is available in Noman M. Cole Jr. Pollution Control Plant in Lorton, VA
New pipes and pumps are needed to move future flows to treatment plant
NEXT STEPS
Field investigations / surveys
Finalize alignments and pump station layout
Use of open cut excavation
Use of trenchless methods
Easement acquisition needed
Develop traffic control plans
Description:
The project consists of a new, 23,000 square feet, two-story, four-bay fire station facility and associated improvements to the 3.3-acre site including storm water detention, landscaping and parking. The scope also included the demolition of the existing fire station, and a temporary fire station to house the Fire and Rescue Department during construction of the new facility. The key elements of the overall project include:
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
The new 4-inch ductile iron force main will serve the surrounding community for the foreseeable future. Replacement of the force main will:
Reduce the level and frequency of maintenance required to keep the force main operating.
Prevent costly emergency repairs.
Provide residents with safe, reliable utility infrastructure.
Enhance the quality of life for residents.
Reduce risks to public health and the environment.
Burke Centre VRE Connector Phase IV project was substantially completed on March 7, 2022. This project enhanced the access to mass transit by creating a more direct connection from the VRE Station to the residential areas west of Premier Court. This project also connects the Oak Bluff community to the Virginia Rail Express (VRE) Burke Station and provides a multi-use shared pedestrian and bicycle trail for outdoor recreation.
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
Overarching Project Goals:
-Achieve Long Branch Central TMDL waste load reduction requirements.
-Provide long-term stability and have low maintenance.
-Improve water quality within the Long Branch Central Watershed.
-Improve habitat and environmental health (ecological lift).
Objectives: Share our project understanding with the council and seek input on the unique opportunities and housing goals for this site that could help guide
our master planning process.
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
4,800 linear feet of stream will be restored using Natural Channel Design methodologies
Pollutant reduction
1,439 lbs/total phosphorus
3,400 lbs/total nitrogen
462.1 tons of total suspended sediment
Protection of private property and public infrastructure
Increased ecological diversity with native vegetation
DEQ has awarded a SLAF grant to this project for these environmental benefits
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
The Lake Barton Dredging, Restoration, and Riser Modification project was substantially completed on December 29, 2021. The project is located within the Pohick Creek watershed. The project consisted of dredging and removal of approximately 19,100 cubic yards of sediment to restore the sediment trapping capacity and improve water quality. The project also included construction of new sediment forebays, in-lake haul roads, and riser modifications (new mid-level sluice gate and cold-water intake) to facilitate future maintenance, stabilize the shoreline, and improve downstream water quality. Fish habitat was also added within the lake.
Reston Arts Community Center Feasibility - Wrap UpFairfax County
This is the last of 5 engagement meetings. We are excited to report back what we heard from you – your preferences, priorities, questions, hopes, concerns. The information we received will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
Benefits of Consolidated Facility
Building and Site Efficiencies
Operational Efficiencies
Addresses Space Deficiencies
Addresses Renovations and Capital Renewal Requirements
for WCD
Provides for a Centrally Located Site that Accommodates Program
Consolidates Integrated Services on One Centrally Located Site
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
This is the 4th of 5 engagement meetings. We are excited to hear from you – your preferences, priorities, questions, hopes, concerns. The information we receive today will be used to inform the space allocations and cost estimating for discussion of the proffer by Fairfax County.
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
Neighborhood was built in the 1980s, and the sewer infrastructure has been in operation since.
Aged pump station equipment – pumps, valves, fans, concrete, etc.
This aging equipment has the potential of causing:
Sanitary Sewer Overflows (SSO)
Sewer back-ups into homes
Environmental damages
Maintenance problems
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
Identify and evaluate house flooding and public safety concerns
Improve drainage conditions to convey 100-year storm if feasible
Reduce and treat stormwater runoff at the source
Improve water quality and stream protection
Use resilient & functional designs
Make improvements compatible with characteristics of neighborhood
Partner with community to develop sound, cost effective solutions that can be collaboratively implemented and maintained
Build on lessons learned to help improve site development process for infill development
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Fairfax County
These community outreach meetings are being conducted to understand community needs for a proposed arts venue in the Reston Town Center.
The proposed arts center would be a result of a proffer from Boston Properties in the next phase of Reston Town Center development (Block J).
The proffer would provide for an approximately 60,000 gross square foot facility to house a stage suitable for large-scale music and dance performances, as well as other arts-related amenities.
01062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
03062024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
‘वोटर्स विल मस्ट प्रीवेल’ (मतदाताओं को जीतना होगा) अभियान द्वारा जारी हेल्पलाइन नंबर, 4 जून को सुबह 7 बजे से दोपहर 12 बजे तक मतगणना प्रक्रिया में कहीं भी किसी भी तरह के उल्लंघन की रिपोर्ट करने के लिए खुला रहेगा।
In a May 9, 2024 paper, Juri Opitz from the University of Zurich, along with Shira Wein and Nathan Schneider form Georgetown University, discussed the importance of linguistic expertise in natural language processing (NLP) in an era dominated by large language models (LLMs).
The authors explained that while machine translation (MT) previously relied heavily on linguists, the landscape has shifted. “Linguistics is no longer front and center in the way we build NLP systems,” they said. With the emergence of LLMs, which can generate fluent text without the need for specialized modules to handle grammar or semantic coherence, the need for linguistic expertise in NLP is being questioned.
role of women and girls in various terror groupssadiakorobi2
Women have three distinct types of involvement: direct involvement in terrorist acts; enabling of others to commit such acts; and facilitating the disengagement of others from violent or extremist groups.
हम आग्रह करते हैं कि जो भी सत्ता में आए, वह संविधान का पालन करे, उसकी रक्षा करे और उसे बनाए रखे।" प्रस्ताव में कुल तीन प्रमुख हस्तक्षेप और उनके तंत्र भी प्रस्तुत किए गए। पहला हस्तक्षेप स्वतंत्र मीडिया को प्रोत्साहित करके, वास्तविकता पर आधारित काउंटर नैरेटिव का निर्माण करके और सत्तारूढ़ सरकार द्वारा नियोजित मनोवैज्ञानिक हेरफेर की रणनीति का मुकाबला करके लोगों द्वारा निर्धारित कथा को बनाए रखना और उस पर कार्यकरना था।
31052024_First India Newspaper Jaipur.pdfFIRST INDIA
Find Latest India News and Breaking News these days from India on Politics, Business, Entertainment, Technology, Sports, Lifestyle and Coronavirus News in India and the world over that you can't miss. For real time update Visit our social media handle. Read First India NewsPaper in your morning replace. Visit First India.
CLICK:- https://firstindia.co.in/
#First_India_NewsPaper
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
Bradley Acres Pond Retrofit Project
Contract No. CN14125118
Project No. SD-000031-106
Task Order No. 16
Hunter Mill District
May 18, 2015
2. Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Bradley Acres Pond Retrofit
Post Construction
3. Project Details
Bradley Acres Pond Retrofit
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
Description:
The Bradley Acres Pond Retrofit project was substantially completed on March 16, 2015. The project is located in the
Horespen Creek Watershed and is bounded by residential units from the northwest, southeast, an open space from the
northeast and bounded by West Ox Road from the south. The project converted an existing extended detention dry
pond to a constructed stormwater wetland pond. The project provides improved down stream water quality benefits
and detention improvement. The water quality benefits realized by this project will be the removal of 21.19 lbs./year of
total phosphorus, 97.77 lbs./year of total nitrogen and 3,751.99 lbs./year of total suspended solids.
Project Overview:
• Removed the existing trickle ditch
• Excavated and constructed three shallow marshes
• Constructed step pool conveyance channel and plunge pool below the existing 42”X27” culvert
• Constructed two imbricated stone weir structures
• Constructed an access maintenance road with 2- 24” RCP culvert structure
• Re-graded the pond as per the approved plan
• Seeded all the disturbed areas with selective Native Grass, Upland and High Marsh Seed mix
• Replanted the site with a mix of trees and plugs
Project Team:
• Stormwater and Planning Division–Martin Chang
• Utilities Design and Construction Division- Yousef Rayyan
• Utilities Design and Construction Division- Keith Ferrell
• Land Acquisition Division- Clinton Preston
• Surveyor- Gregory Harper
4. Bradley Acres Pond Retrofit
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
Hunter Mill District, VA, Tax Map #25-3
Project Site
5. Bradley Acres Pond Retrofit
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Pre-Existing Conditions
6. Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
Bradley Acres Pond Retrofit
Post Construction
New Access Road
Shallow Marsh #3
Stone Weir #2
Shallow Marsh #2
Stone Weir #1
New Step Pool Conveyance Channel
Shallow Marsh #1
An Existing RC Outlet Pipe 42”x27”
7. Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Bra
Bradley Acres Pond Retrofit
Pre-Existing Conditions
The Inflow RC Outlet 42”x27” Pipe Conditions
8. Bradley Acres Pond Retrofit
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch
Post-Construction
9. Bradley Acres Pond Retrofit
Capital Facilities/Utilities Design and Construction Division/Transportation and Stormwater Construction Branch
Pre-Existing Conditions
10. Bradley Acres Pond Retrofit
Post Construction
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Bra
West Ox Rd
Access Road Gate
2- 24” RCP Culvert Structure
11. Additional Information
For additional Information, please call
www.fairfaxcounty.gov/dpwes
Ben Boxer, Public Information Officer
703-324-5880, TTY 711
Ben. Ben Boxer, Public Information Officer
703-324-5880, TTY 711
Ben. Ben Boxer, Public Information Officer
703-324-5880, TTY 711
Ben.Boxer@fairfaxcounty.gov
Irene Haske, Public Information Officer
703-324-5500, TTY 711
Irene.Haske@fairfaxcounty.gov
Capital Facilities/Utilities Design and Construction Division/Transportation Stormwater Construction Branch