RESUME 
DINESH KUMAR SARDA 
Permanent Address: Email ID: dsarda.rec@gmail.com 
C/O Mr.Kishore Bajaj, Contact No: 7566983348 
H NO:26,New Panchsheel Nagar,Civil lines, 
Raipur –492001,Chhattisgarh. 
Career Objective: 
To work as an electrical engineer in project management and electrical designing utilising technical 
engineering background and manufacturing experience contributing to company’s growth and in turn 
ensuring personal growth within the organization. 
Work Experience: Three years, 4 months and continuing. 
Designation: Assistant Manager. 
Employer: JAYASWAL NECO INDUSTRIES LIMITED(Raipur, Chhattisgarh) 
One year of extensive training in captive power plant- net capacity of 69 MW (including both AFBC and 
WHRB type boiler {utilizing waste heat of Direct Reduced Iron and Blast Furnace }) 
Part of Power Management System (PMS) project {PLC :PAC RX3i by General Electricals Intelligent 
platform based on GE Proficy Machine Edition 2007 logic developer & Cimplicity (SCADA)} and currently 
looking after the maintenance of Main Receiving Sub Station (220 kV and 132 kV). 
Job Responsibilities: 
 Reading Electrical Drawings, Planning of Projects, Erection & Maintenance. 
 Short circuit calculation. 
 Earth bus calculations and sizing 
 Hazardous area classification. 
 Sizing of Cables, Generator, Motor, Transformer, LT & HT Breaker. 
 Preparation of Single Line Diagram. 
 Preparation of cable route drawings. 
 Preparation of technical specifications for Transformer, HT Breaker, LT panel. 
 Preparation of cost estimate & bill of Material for electrical work. 
 Technical Bid analysis for material & service contracts. 
 Installation, testing & commissioning of LT & HT equipments like Transformer, HT Breaker,Motor, 
Generator. 
 Co ordination with electrical contractors during execution of electrical work. 
 Relay co-ordination. 
 Inspection of material at vendor’s / Manufacturer’s site.
 Responsible for all the switching operations and maintenance of LT and HT motors(up to 375KW), 
ACB(L&T 415V),VCB(SIEMENS 6.6KV&11KV,AREVA 6.6 KV& 33KV,GEC ALSTHOM 6.6KV) and SF6 
breakers(CROMPTON GREAVES 132KV, KIRLOSKAR 33KV& SIEMENS 220KV&132KV) CT&PT( both 
outdoor and indoor type), UPS, Battery Bank, Isolators, Power & Distribution transformers(up to 120 
MVA),Generator LAPT and NGR and AVR panel, distribution board lighting systems, cabling and control 
wiring. 
 Planning and conducting effective shut down and preventive maintenance, overhauling, repair schedule, 
of various machineries and instrument to increase system up time and long term system reliability,as per 
ISO 9001-2008 norms. 
 Handling Management Information System (MIS) reports as well as maintaining spares. 
 Ferruling,luging,tagging,wiring of control cables in the PLC, CONTROL DESK and H.T FEEDERS (220 Kv,132 
kv,33Kv, 11Kv and 6.6Kv).Tray work, cable laying, dressing, gland termination as per the prescribed 
schedule. 
 Testing and installation of Analog (disk and induction type), Overload electronic relays as well as 
microprocessor based relays (MICOM series- 120,122,&341,632 SIEMENS 7UT61, 
7SJ61,7SJ62,7SJ8031&7SJ8011); used in generator,motor,feeder and transformer protection. 
 Ensuring 100% plant load factor and housekeeping using 5S. 
 Operation and maintenance of starters (DOL, R-DOL and STAR-DELTA) and its feeder wiring including 
energy meters and trivector meters. 
 To conduct Synchronization of generator & feeder breakers when needed. 
 Calculating overall plant generation, maintaining export and import data ,energy balance report and 
CAR(corrective action report). 
 To conduct Fault Level Calculation for different bus bars to know the fault level current and decide the 
suitable breaker ratings, as well as relay coordination.
CAT 2013 score: 80.28 percentile 
Examination 
Passed 
Year of 
passing 
Name of Board/University 
School/College 
Studied 
B.Tech(E.E.E) 2010 
Biju Pattnaik University Of 
Technology(B.P.U.T) 
Raajdhani Engineering 
College(Bhubaneswar) 
Class XII(H.S.C) 2005 I.S.C ST.Joseph’s Convent 
High School(Sambalpur) 61.20% 
Class X(S.S.C) 2003 I.C.S.E ST.Joseph’s Convent 
High School(Sambalpur) 64.80% 
Projects done: 
 Errection, Commissioning & testing of “SYNCHRONISING PANEL” for 6.6KV breaker. 
Percentage Scored 
7.25 CGPA 
 Errection, Commissioning & testing of “33 KV BREAKER CONTROL AND RELAY PANEL CUM TAP 
CHANGER” for 16 MVA TRANSFORMER. 
Software Skills: 
 Operating Systems : Windows 2007/XP 
 Package : MS Office 2007 
Strengths: 
Self-confident, Optimistic with good communication skills, Determined, Patient, believe in Hard Work. I have 
a quest and zeal to learn new technologies. 
Hobbies: 
Like to play Chess, Swimming, Cooking, listening to music, watching movies, visiting new places and 
interacting with new people.

RESUME_Dinesh Sarda 2

  • 1.
    RESUME DINESH KUMARSARDA Permanent Address: Email ID: dsarda.rec@gmail.com C/O Mr.Kishore Bajaj, Contact No: 7566983348 H NO:26,New Panchsheel Nagar,Civil lines, Raipur –492001,Chhattisgarh. Career Objective: To work as an electrical engineer in project management and electrical designing utilising technical engineering background and manufacturing experience contributing to company’s growth and in turn ensuring personal growth within the organization. Work Experience: Three years, 4 months and continuing. Designation: Assistant Manager. Employer: JAYASWAL NECO INDUSTRIES LIMITED(Raipur, Chhattisgarh) One year of extensive training in captive power plant- net capacity of 69 MW (including both AFBC and WHRB type boiler {utilizing waste heat of Direct Reduced Iron and Blast Furnace }) Part of Power Management System (PMS) project {PLC :PAC RX3i by General Electricals Intelligent platform based on GE Proficy Machine Edition 2007 logic developer & Cimplicity (SCADA)} and currently looking after the maintenance of Main Receiving Sub Station (220 kV and 132 kV). Job Responsibilities:  Reading Electrical Drawings, Planning of Projects, Erection & Maintenance.  Short circuit calculation.  Earth bus calculations and sizing  Hazardous area classification.  Sizing of Cables, Generator, Motor, Transformer, LT & HT Breaker.  Preparation of Single Line Diagram.  Preparation of cable route drawings.  Preparation of technical specifications for Transformer, HT Breaker, LT panel.  Preparation of cost estimate & bill of Material for electrical work.  Technical Bid analysis for material & service contracts.  Installation, testing & commissioning of LT & HT equipments like Transformer, HT Breaker,Motor, Generator.  Co ordination with electrical contractors during execution of electrical work.  Relay co-ordination.  Inspection of material at vendor’s / Manufacturer’s site.
  • 2.
     Responsible forall the switching operations and maintenance of LT and HT motors(up to 375KW), ACB(L&T 415V),VCB(SIEMENS 6.6KV&11KV,AREVA 6.6 KV& 33KV,GEC ALSTHOM 6.6KV) and SF6 breakers(CROMPTON GREAVES 132KV, KIRLOSKAR 33KV& SIEMENS 220KV&132KV) CT&PT( both outdoor and indoor type), UPS, Battery Bank, Isolators, Power & Distribution transformers(up to 120 MVA),Generator LAPT and NGR and AVR panel, distribution board lighting systems, cabling and control wiring.  Planning and conducting effective shut down and preventive maintenance, overhauling, repair schedule, of various machineries and instrument to increase system up time and long term system reliability,as per ISO 9001-2008 norms.  Handling Management Information System (MIS) reports as well as maintaining spares.  Ferruling,luging,tagging,wiring of control cables in the PLC, CONTROL DESK and H.T FEEDERS (220 Kv,132 kv,33Kv, 11Kv and 6.6Kv).Tray work, cable laying, dressing, gland termination as per the prescribed schedule.  Testing and installation of Analog (disk and induction type), Overload electronic relays as well as microprocessor based relays (MICOM series- 120,122,&341,632 SIEMENS 7UT61, 7SJ61,7SJ62,7SJ8031&7SJ8011); used in generator,motor,feeder and transformer protection.  Ensuring 100% plant load factor and housekeeping using 5S.  Operation and maintenance of starters (DOL, R-DOL and STAR-DELTA) and its feeder wiring including energy meters and trivector meters.  To conduct Synchronization of generator & feeder breakers when needed.  Calculating overall plant generation, maintaining export and import data ,energy balance report and CAR(corrective action report).  To conduct Fault Level Calculation for different bus bars to know the fault level current and decide the suitable breaker ratings, as well as relay coordination.
  • 3.
    CAT 2013 score:80.28 percentile Examination Passed Year of passing Name of Board/University School/College Studied B.Tech(E.E.E) 2010 Biju Pattnaik University Of Technology(B.P.U.T) Raajdhani Engineering College(Bhubaneswar) Class XII(H.S.C) 2005 I.S.C ST.Joseph’s Convent High School(Sambalpur) 61.20% Class X(S.S.C) 2003 I.C.S.E ST.Joseph’s Convent High School(Sambalpur) 64.80% Projects done:  Errection, Commissioning & testing of “SYNCHRONISING PANEL” for 6.6KV breaker. Percentage Scored 7.25 CGPA  Errection, Commissioning & testing of “33 KV BREAKER CONTROL AND RELAY PANEL CUM TAP CHANGER” for 16 MVA TRANSFORMER. Software Skills:  Operating Systems : Windows 2007/XP  Package : MS Office 2007 Strengths: Self-confident, Optimistic with good communication skills, Determined, Patient, believe in Hard Work. I have a quest and zeal to learn new technologies. Hobbies: Like to play Chess, Swimming, Cooking, listening to music, watching movies, visiting new places and interacting with new people.