SlideShare a Scribd company logo
REINFORCED
CONCRETE FRAME
STRUCTURE
Tantish Kamaruddin,PhD
UTM Skudai, Malaysia
MEASUREMENT OF RC
FRAMED STRUCTURE
Framed concrete structure in building consists of the
following components:
1. Columns/Stiffeners
2. Floor/Roof beams
3. Floor/Roof Slab
2
COLUMNS
■ Items to be measured:
a. Concrete to column (VRC Grade 20 –30,
etc)
b. Formwork to sides of columns
c. Reinforcement
i) Main bar
ii) Links
3
COLUMNS
■ Measurement of the items above are similar to
the principles of measurements of column
stumps.
■ For the purpose of measurement, the height of
column is taken from the upper surface of
ground beam (upper surface of column stump)
to the upper surface of the floor/roof beams
above.
4
■ Starter bar must be added at (41d) from the
column height (if the measurement was not appeared in
drawings, however, this is not common with CAD drawings
provided nowadays).
■ Link bend formula (6d) for each bend x 4
(with bend cannot less than 900 angle), 4x6d
■ Note: Stirrups will end only at beam length.
Not in intersection area which only links will
be available in that area.
5
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete
Grade 25 as described:
Columns m3
0.80
0.80
3.15
6
TK
Clause F3.1 &
F3.15
2.02
2
L
W
D TK
ALWAYS ADHERE TO
THIS PRINCIPLES OF
MEASUREMENT RULE
b. Formwork
■ Formwork is measured to sides of columns.
■ Formwork to column is measured in SQUARE
METRE (F.15.1 and F.15.4 and F.10.3).
7
8
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sawn formwork Grade C timber as described
to:
Sides of columns
0.80
3.15
4
TK
m2
Clause (F.15.1 and F.15.4 and F.10.3)
TK
10.08
10
c. Reinforcement
■ Reinforcement to columns shall be measures in m which
later be converted to kg.
■ Consisting of two(2) types:
i) Main bars ( High tensile). (F8.4)-according to elements
ii) Links (Mild steel). (F8.3)
9
10
Study
reinforceme
nt layouts
according to
your building
technology
textbooks!
11
https://www.pinterest.com/pin/372250725434898988/
12
Link/stirrup
s
Main bars (check
diameter)
Measurement of links-
do this calculation on your side
cast.
■ Length of ONE link:
4/300
less 4/25 100 (cover)
1,100
add 4/6d (24d) 144 (say 6mm)
1,244
(4/6d also acceptable in links/stirrups bends which is equivalent to
24d)
(Ahmad Abdullah;2012)
13
Number of links in columns:
■ Assuming the height of column= 3.00 m
Centre to centre of links = 150 mm c/c
No. of link = 3,000 + 1
150
= 21 nos
14
Measurement of main bar
■ The length of main bar are measured based on the height
of column together with all laps and bends.
■ Normally, there are four(4) main bars in a columns and
high tensile steel are used.
15
16
17
18
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
20mm Diameter high tensile
reinforcement as described to:
Columns
3.60
5
TK
m
C5 (at 5
location),
marks
according
to grid in
drawings
TK
3.60
Convert to kg
after finish
measuring all
20mm dia for
columns
19
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
6mm Diameter mild steel reinforcement
as described to:
Links to columns
0.80
21
TK
m
Assuming the height of column= 3.00
m
Centre to centre of links = 150 mm c/c
No. of link = 3000 + 1
150
= 21 nos
5
84.00
Convert to kg
after finish
measuring all
6mm dia for
columns
FLOOR BEAM/ROOF BEAM
Items to be measured:
a. Concrete to floor/roof beams
■ Uses Vibrated Reinforced Concrete Grade 20 etc.
■ Measurement of concrete in beams is in CUBIC METRE
(volume) in accordance to F.3.1 and F.3.14.
■ Length is measured between the columns.
20
How to measure beam
length?
21
Column
Beam
Length of beam is taken between
columns
22
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete Grade 25
as described:
Upper floor/roof beams
5.00
0.45
0.45
TK
m3
Clause F3.2, F3.14
L
W
D
Take note on the
arrangement of
dimension
placement,
arrangement
differs from
columns to beams
b. Formwork
■ Formwork are required at both sides and soffit of the
beam since it is suspended.
■ F.14.1 Formwork to sides and soffit of beam is measured
in SQUARE METRE according to the following
classification:
a. Horizontal
b. Sloping not exc. 150 from horizontal
c. Sloping over 150 from horizontal
23
b. Formwork
■ F.14.3 Formwork to secondary beam shall be measured up
to the sides of main beams but NO DEDUCTION shall be
made from the formwork of the main beam where the
secondary beam intersects it.
■ F.14.4 Formwork to beam which intersect with column
shall be measured up to them on all sides. (stop at end of
columns)
24
25
https://gharpedia.com/things-check-before-
concreting-beam-slab/
26
https://www.sgmedhat.com/en/product-list/modular-
formwork-system/beam-and-slam-formwork
27
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sawn formwork Grade C timber as described:
To sides and soffit of floor/roof
beam
5.00
0.45
TK
m2
Clause F14.1
c. Reinforcement
i) Main bar – high tensile steel
■ Top main bar
■ Bottom main bar
ii) Stirrups – mild steel
■ Measurement of main bar and stirrups in floor/roof beams
are similar to the principles of measurement of
reinforcement in ground beams.
28
MEASUREMENT OF CONCRETE
SUSPENDED SLAB
Items to be measured:
a. Concrete to suspended floor slab.
b. Formwork
i) To soffit of slab
ii) To edge of slab ( not associated to beams)
iii) To top of slab ( exc. 150 from horizontal)
c. Reinforcement
d. Expansion joint (if any)
29
Concrete to floor slab
■ Uses vibrated reinforced concrete Grade 20 etc.
■ Measured in CUBIC METRE which shall include thickening
but excludes upstands stating the thickness according to
F.2.1. (F.3.1 and F.3.9 ).
30
Concrete to upper floor
slab
■ If the slab is laid sloping, this shall be stated in the
description according to:
i) Sloping not exceeding 150 from horizontal
ii) Sloping over 150 from horizontal ( Refer F.1.7 )
■ Usually the measurement to find the area of slab is taken
ACROSS THE BEAM.
31
32
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete Grade 25 as
described to:
Suspended floor slab exceeding 100
mm not exceeding 150 mm thick
25.00
10.00
0.15
TK
m3
Clause F.3.1 &
F.3.9
L
W
D
33
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Vibrated reinforced concrete Grade 25 as
described to:
Suspended floor slab exceeding 100
mm not exceeding 150 mm thick laid
sloping not exc. 150
25.00
10.00
0.15
TK
m3
Clause F.3.1 & F.3.14
Concrete to floor slab
Formwork
■ Formwork to soffit of slab is measured in SQUARE METRE and
classified as follows (F.12.1 ):
a. Horizontal
b. Sloping not exceeding 150 from horizontal
c. Sloping over 150 from horizontal.
34
Concrete to floor slab
■ Formwork to soffit of solid slab exceeding 200 mm thick
shall be measured separately in SQUARE METRE and the
thickness in stages of 100 mm ( F.12.2 ).
■ Formwork to upper sloping surfaces of slabs where more
than 150 from horizontal shall be measured in SQUARE
METRES (F.12.3 ).
35
Concrete to floor slab
Formwork to edges of slabs (not associated with
downstand beams or projecting eaves), shall be measured
in LINEAR METRE according the following categories
(F.12.5) :
■ Not exceeding 250 mm deep
■ 250 – 500 mm deep
Where exceeding 500 mm deep, the depth shall be
stated.
36
Concrete to floor slab
Formwork to ends and perimeter of openings exceeding
1.00m girth shall be measured in LINEAR METRE
according the following categories ( F.12.6):
– Not exceeding 250 mm wide
– 250 – 500 mm wide
Where exceeding 500 mm wide, the width shall be
stated.
37
Concrete to floor slab
Note:
■ F.10.9 Formwork to soffits or soffits of beams over 3.50 m
high shall be so described stating the height in further
stages of 1.50m.
■ If the soffit of floor slab exceeds 3.50m high then it is
subjected to this clause.
38
39
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sawn formwork Grade C timber as
described to:
Soffit of suspended floor slab
exceeding 200 mm thick; exc. 3.50m
but not exc. 5.00m high
25.00
10.00
TK
m2
(Clause F.3.1, F10.9 &
F12.2)
Concrete to floor slab
Reinforcement
■ The type of reinforcement used in suspended slab are normally
high tensile bar reinforcement even though fabric
reinforcement can also be used.
■ F.8.4 Classification of bar reinforcement shall be as follows:
a. In foundation which shall include column bases (pad
foundation), ground beams, pile caps and the like.
b. In ground slab which shall include beds, roads, footpaths and
paving.
c. In suspended slab which shall include attached beams,
upstand, kerbs and lintels.
d. In walls which shall include columns.
40
Concrete to floor slab
■ Therefore based on F.8.4(c) , principally the
measurement of reinforcements in suspended slab should
be done together with the reinforcements for suspended
floor/roof beams.
■ Typical layout of reinforcement in suspended slab is as
shown in the following transparencies.
■ The most important thing to do before starting the
process of taking off is to understand the layout of the
reinforcements and if possible sketches of the layout be
made to avoid confusion due to the several layers of the
reinforcements.
41
Concrete to floor slab
■ Measurements if bar reinforcement follows the same
principles of other bar reinforcement according to:
i) Type of steel used
ii) Diameter of steel bar
42
Expansion joints
■ Expansion joint is sometimes incorporated
in the design of suspended slab for the
purpose for providing a mechanism to cater
for the expansion and compression of the
slab due to heat.
■ F.4.2 Designed joints including those
required to be a special profile or which
incorporate water stops, EXPANSION OR
COMPRESSION jointing materials which are
required in the formation of bays shall be
measured in LINEAR METRE.
43
44
Project Element/Trade Slip No
Heading
Description: Unit
Quantity
Taker Off
Squaring
Chk. Squaring
Rate
Sundries:
Expansion joint, 25mm wide in 100mm thick slab filled
with and approved non-shrinking grout and pointed on
both sides with aluminium strip 20mm x 4mm thick
including all necessary formwork and any necessary
treatment to the reinforcement
21.00
TK
m
Clause F4.3
Length
8,000
add 7,000
add 6,000
21,000
Side Cast
Concrete to floor slab
■ Particulars of the following shall be stated in the
description:
i. Any necessary formwork.
ii. Treatment of reinforcement crossing the joint.
iii. Water stop, expansion or compression jointing and
pointing materials.
45
46

More Related Content

What's hot

Loads acting on buildings
Loads  acting on buildingsLoads  acting on buildings
Loads acting on buildings
Nilraj Vasandia
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
purvi golecha
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
hlksd
 
Wind loading
Wind loadingWind loading
Wind loading
Deepak Kumar
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
BBS Preparation
BBS PreparationBBS Preparation
BBS Preparation
Abhay Gharpure
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
Hossam Shafiq II
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
Dayat Mohamad
 
Reinforced concrete column
Reinforced concrete columnReinforced concrete column
Reinforced concrete column
civilengineeringfreedownload
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Table formwork
Table formwork Table formwork
Table formwork
Davis Ciprikis
 
Concrete works
Concrete worksConcrete works
Concrete works
Rajiva Gupta
 
Structural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project ReportStructural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project Reportherry924
 
Truss & its analysis
Truss & its analysisTruss & its analysis
Truss & its analysis
Sunil Kumar
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT
jolynnTJL
 
Concrete Honeycombs
Concrete Honeycombs Concrete Honeycombs
Concrete Honeycombs
Dimuthuchat
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
maylene san luis
 

What's hot (20)

Loads acting on buildings
Loads  acting on buildingsLoads  acting on buildings
Loads acting on buildings
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Wind loading
Wind loadingWind loading
Wind loading
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
BBS Preparation
BBS PreparationBBS Preparation
BBS Preparation
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
Reinforced concrete column
Reinforced concrete columnReinforced concrete column
Reinforced concrete column
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Table formwork
Table formwork Table formwork
Table formwork
 
Concrete works
Concrete worksConcrete works
Concrete works
 
Structural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project ReportStructural Steel and Timber Design EV306 Project Report
Structural Steel and Timber Design EV306 Project Report
 
Truss & its analysis
Truss & its analysisTruss & its analysis
Truss & its analysis
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Stairs
StairsStairs
Stairs
 
BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT BUILDING STRUCTURE FINAL REPORT
BUILDING STRUCTURE FINAL REPORT
 
Concrete Honeycombs
Concrete Honeycombs Concrete Honeycombs
Concrete Honeycombs
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 

Similar to Reinforced Concrete Frame Structure

Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiUrsachi Răzvan
 
Stepped footing
Stepped footingStepped footing
Stepped footing
Pritesh Parmar
 
Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)Yeasir Gerrard
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimateimaduddin91
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project report
Praba Haran
 
Rectangular tank
Rectangular tankRectangular tank
Rectangular tank
JayswalShashank1
 
Memo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternMemo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-pattern
S.s. Lee
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
AmokBajracharya2
 
Geotechnical Pad Foundation (11-1-2021).pptx
Geotechnical Pad Foundation (11-1-2021).pptxGeotechnical Pad Foundation (11-1-2021).pptx
Geotechnical Pad Foundation (11-1-2021).pptx
muyideenabdulkareem
 
flat Slab
flat Slabflat Slab
flat Slab
Vikas Mehta
 
ppt.pptx
ppt.pptxppt.pptx
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete Design
Roshni Ramakrishnan
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
Tanvir Khan
 
Design-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfDesign-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdf
AsifHameed33
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0CSAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0CSunit Dhingra
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
ADITYAPILLAI29
 
Design of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfDesign of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdf
mohamed abdo
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
sharda university
 
Design Of Flat Slab
Design Of Flat Slab Design Of Flat Slab
Design Of Flat Slab
Abdul Sahid
 

Similar to Reinforced Concrete Frame Structure (20)

Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering IaşiLecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
Lecture 5 s.s.iii Design of Steel Structures - Faculty of Civil Engineering Iaşi
 
Stepped footing
Stepped footingStepped footing
Stepped footing
 
Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)Flat plate slab design (10.01.03.052)
Flat plate slab design (10.01.03.052)
 
12724469 wtp-cost-estimate
12724469 wtp-cost-estimate12724469 wtp-cost-estimate
12724469 wtp-cost-estimate
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project report
 
Rectangular tank
Rectangular tankRectangular tank
Rectangular tank
 
Memo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-patternMemo 55c-tss-41-rekommended-reinforcement-pattern
Memo 55c-tss-41-rekommended-reinforcement-pattern
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
Geotechnical Pad Foundation (11-1-2021).pptx
Geotechnical Pad Foundation (11-1-2021).pptxGeotechnical Pad Foundation (11-1-2021).pptx
Geotechnical Pad Foundation (11-1-2021).pptx
 
flat Slab
flat Slabflat Slab
flat Slab
 
ppt.pptx
ppt.pptxppt.pptx
ppt.pptx
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete Design
 
Heals - structural presentation
Heals -  structural presentationHeals -  structural presentation
Heals - structural presentation
 
Design-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfDesign-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdf
 
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0CSAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
SAMPLE REVIT DRAWINGS-SUNIT K DHINGRA-COMPLETE - E0C
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
 
Design of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfDesign of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdf
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
 
Design Of Flat Slab
Design Of Flat Slab Design Of Flat Slab
Design Of Flat Slab
 

Recently uploaded

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 

Recently uploaded (20)

Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 

Reinforced Concrete Frame Structure

  • 2. MEASUREMENT OF RC FRAMED STRUCTURE Framed concrete structure in building consists of the following components: 1. Columns/Stiffeners 2. Floor/Roof beams 3. Floor/Roof Slab 2
  • 3. COLUMNS ■ Items to be measured: a. Concrete to column (VRC Grade 20 –30, etc) b. Formwork to sides of columns c. Reinforcement i) Main bar ii) Links 3
  • 4. COLUMNS ■ Measurement of the items above are similar to the principles of measurements of column stumps. ■ For the purpose of measurement, the height of column is taken from the upper surface of ground beam (upper surface of column stump) to the upper surface of the floor/roof beams above. 4
  • 5. ■ Starter bar must be added at (41d) from the column height (if the measurement was not appeared in drawings, however, this is not common with CAD drawings provided nowadays). ■ Link bend formula (6d) for each bend x 4 (with bend cannot less than 900 angle), 4x6d ■ Note: Stirrups will end only at beam length. Not in intersection area which only links will be available in that area. 5
  • 6. Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described: Columns m3 0.80 0.80 3.15 6 TK Clause F3.1 & F3.15 2.02 2 L W D TK ALWAYS ADHERE TO THIS PRINCIPLES OF MEASUREMENT RULE
  • 7. b. Formwork ■ Formwork is measured to sides of columns. ■ Formwork to column is measured in SQUARE METRE (F.15.1 and F.15.4 and F.10.3). 7
  • 8. 8 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sawn formwork Grade C timber as described to: Sides of columns 0.80 3.15 4 TK m2 Clause (F.15.1 and F.15.4 and F.10.3) TK 10.08 10
  • 9. c. Reinforcement ■ Reinforcement to columns shall be measures in m which later be converted to kg. ■ Consisting of two(2) types: i) Main bars ( High tensile). (F8.4)-according to elements ii) Links (Mild steel). (F8.3) 9
  • 10. 10 Study reinforceme nt layouts according to your building technology textbooks!
  • 13. Measurement of links- do this calculation on your side cast. ■ Length of ONE link: 4/300 less 4/25 100 (cover) 1,100 add 4/6d (24d) 144 (say 6mm) 1,244 (4/6d also acceptable in links/stirrups bends which is equivalent to 24d) (Ahmad Abdullah;2012) 13
  • 14. Number of links in columns: ■ Assuming the height of column= 3.00 m Centre to centre of links = 150 mm c/c No. of link = 3,000 + 1 150 = 21 nos 14
  • 15. Measurement of main bar ■ The length of main bar are measured based on the height of column together with all laps and bends. ■ Normally, there are four(4) main bars in a columns and high tensile steel are used. 15
  • 16. 16
  • 17. 17
  • 18. 18 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate 20mm Diameter high tensile reinforcement as described to: Columns 3.60 5 TK m C5 (at 5 location), marks according to grid in drawings TK 3.60 Convert to kg after finish measuring all 20mm dia for columns
  • 19. 19 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate 6mm Diameter mild steel reinforcement as described to: Links to columns 0.80 21 TK m Assuming the height of column= 3.00 m Centre to centre of links = 150 mm c/c No. of link = 3000 + 1 150 = 21 nos 5 84.00 Convert to kg after finish measuring all 6mm dia for columns
  • 20. FLOOR BEAM/ROOF BEAM Items to be measured: a. Concrete to floor/roof beams ■ Uses Vibrated Reinforced Concrete Grade 20 etc. ■ Measurement of concrete in beams is in CUBIC METRE (volume) in accordance to F.3.1 and F.3.14. ■ Length is measured between the columns. 20
  • 21. How to measure beam length? 21 Column Beam Length of beam is taken between columns
  • 22. 22 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described: Upper floor/roof beams 5.00 0.45 0.45 TK m3 Clause F3.2, F3.14 L W D Take note on the arrangement of dimension placement, arrangement differs from columns to beams
  • 23. b. Formwork ■ Formwork are required at both sides and soffit of the beam since it is suspended. ■ F.14.1 Formwork to sides and soffit of beam is measured in SQUARE METRE according to the following classification: a. Horizontal b. Sloping not exc. 150 from horizontal c. Sloping over 150 from horizontal 23
  • 24. b. Formwork ■ F.14.3 Formwork to secondary beam shall be measured up to the sides of main beams but NO DEDUCTION shall be made from the formwork of the main beam where the secondary beam intersects it. ■ F.14.4 Formwork to beam which intersect with column shall be measured up to them on all sides. (stop at end of columns) 24
  • 27. 27 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sawn formwork Grade C timber as described: To sides and soffit of floor/roof beam 5.00 0.45 TK m2 Clause F14.1
  • 28. c. Reinforcement i) Main bar – high tensile steel ■ Top main bar ■ Bottom main bar ii) Stirrups – mild steel ■ Measurement of main bar and stirrups in floor/roof beams are similar to the principles of measurement of reinforcement in ground beams. 28
  • 29. MEASUREMENT OF CONCRETE SUSPENDED SLAB Items to be measured: a. Concrete to suspended floor slab. b. Formwork i) To soffit of slab ii) To edge of slab ( not associated to beams) iii) To top of slab ( exc. 150 from horizontal) c. Reinforcement d. Expansion joint (if any) 29
  • 30. Concrete to floor slab ■ Uses vibrated reinforced concrete Grade 20 etc. ■ Measured in CUBIC METRE which shall include thickening but excludes upstands stating the thickness according to F.2.1. (F.3.1 and F.3.9 ). 30
  • 31. Concrete to upper floor slab ■ If the slab is laid sloping, this shall be stated in the description according to: i) Sloping not exceeding 150 from horizontal ii) Sloping over 150 from horizontal ( Refer F.1.7 ) ■ Usually the measurement to find the area of slab is taken ACROSS THE BEAM. 31
  • 32. 32 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described to: Suspended floor slab exceeding 100 mm not exceeding 150 mm thick 25.00 10.00 0.15 TK m3 Clause F.3.1 & F.3.9 L W D
  • 33. 33 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Vibrated reinforced concrete Grade 25 as described to: Suspended floor slab exceeding 100 mm not exceeding 150 mm thick laid sloping not exc. 150 25.00 10.00 0.15 TK m3 Clause F.3.1 & F.3.14
  • 34. Concrete to floor slab Formwork ■ Formwork to soffit of slab is measured in SQUARE METRE and classified as follows (F.12.1 ): a. Horizontal b. Sloping not exceeding 150 from horizontal c. Sloping over 150 from horizontal. 34
  • 35. Concrete to floor slab ■ Formwork to soffit of solid slab exceeding 200 mm thick shall be measured separately in SQUARE METRE and the thickness in stages of 100 mm ( F.12.2 ). ■ Formwork to upper sloping surfaces of slabs where more than 150 from horizontal shall be measured in SQUARE METRES (F.12.3 ). 35
  • 36. Concrete to floor slab Formwork to edges of slabs (not associated with downstand beams or projecting eaves), shall be measured in LINEAR METRE according the following categories (F.12.5) : ■ Not exceeding 250 mm deep ■ 250 – 500 mm deep Where exceeding 500 mm deep, the depth shall be stated. 36
  • 37. Concrete to floor slab Formwork to ends and perimeter of openings exceeding 1.00m girth shall be measured in LINEAR METRE according the following categories ( F.12.6): – Not exceeding 250 mm wide – 250 – 500 mm wide Where exceeding 500 mm wide, the width shall be stated. 37
  • 38. Concrete to floor slab Note: ■ F.10.9 Formwork to soffits or soffits of beams over 3.50 m high shall be so described stating the height in further stages of 1.50m. ■ If the soffit of floor slab exceeds 3.50m high then it is subjected to this clause. 38
  • 39. 39 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sawn formwork Grade C timber as described to: Soffit of suspended floor slab exceeding 200 mm thick; exc. 3.50m but not exc. 5.00m high 25.00 10.00 TK m2 (Clause F.3.1, F10.9 & F12.2)
  • 40. Concrete to floor slab Reinforcement ■ The type of reinforcement used in suspended slab are normally high tensile bar reinforcement even though fabric reinforcement can also be used. ■ F.8.4 Classification of bar reinforcement shall be as follows: a. In foundation which shall include column bases (pad foundation), ground beams, pile caps and the like. b. In ground slab which shall include beds, roads, footpaths and paving. c. In suspended slab which shall include attached beams, upstand, kerbs and lintels. d. In walls which shall include columns. 40
  • 41. Concrete to floor slab ■ Therefore based on F.8.4(c) , principally the measurement of reinforcements in suspended slab should be done together with the reinforcements for suspended floor/roof beams. ■ Typical layout of reinforcement in suspended slab is as shown in the following transparencies. ■ The most important thing to do before starting the process of taking off is to understand the layout of the reinforcements and if possible sketches of the layout be made to avoid confusion due to the several layers of the reinforcements. 41
  • 42. Concrete to floor slab ■ Measurements if bar reinforcement follows the same principles of other bar reinforcement according to: i) Type of steel used ii) Diameter of steel bar 42
  • 43. Expansion joints ■ Expansion joint is sometimes incorporated in the design of suspended slab for the purpose for providing a mechanism to cater for the expansion and compression of the slab due to heat. ■ F.4.2 Designed joints including those required to be a special profile or which incorporate water stops, EXPANSION OR COMPRESSION jointing materials which are required in the formation of bays shall be measured in LINEAR METRE. 43
  • 44. 44 Project Element/Trade Slip No Heading Description: Unit Quantity Taker Off Squaring Chk. Squaring Rate Sundries: Expansion joint, 25mm wide in 100mm thick slab filled with and approved non-shrinking grout and pointed on both sides with aluminium strip 20mm x 4mm thick including all necessary formwork and any necessary treatment to the reinforcement 21.00 TK m Clause F4.3 Length 8,000 add 7,000 add 6,000 21,000 Side Cast
  • 45. Concrete to floor slab ■ Particulars of the following shall be stated in the description: i. Any necessary formwork. ii. Treatment of reinforcement crossing the joint. iii. Water stop, expansion or compression jointing and pointing materials. 45
  • 46. 46