SlideShare a Scribd company logo
Bar Bending Schedule:
0
ADGP
Bar Bending Schedule:
 Reinforcement Steel cost is around 20% – 25% of Cost of RCC Structure.
 Wastage of Reinforcement steel is generally noticed only at the end of works,
and the cost implication is huge.
 IS code – “Code of practice for bending and fixing of bars for concrete
reinforcement” – IS 2502 – 1963 (reaffirmed 2004)
 Particular care needed for higher diameter bars while bending. Size of
Mandrel to be as per code else the bars crack at bend location.
 We typically use Mild Steel bars…….. HYSD Bars………?
 HYSD bars can be CT or TMT?
 Available strength – 415 / 500 / 550 / 600 …. With “D”?
1
ADGP
Bar Bending Schedule:
 Bar Bending is a process of cutting and bending reinforcement steel into desired
shape as per structural drawing.
 Bar Bending Schedule (BBS) is a detailed list of reinforcement bars containing bar
mark (for identification), diameter, numbers, shape with size, and cut length of each.
 BBS helps in estimating required quantities of the various diameter of bars, which helps
in Procurement and Stock Management of various diameter of rebar.
 BBS assists in checking the work executed vis-à-vis requirement as per drawing and
the same can be used in billing.
 BBS can be given to factory to get cut & bent steel at site, saving working space,
better wastage control, reducing labour cost and thereby reduction in overall cost.
2
ADGP
Bar Bending Schedule:
 Preparation of BBS:
i. Identification (Bar Mark)
Tag different types of bars in the drawing with a unique id and list it out
in a sheet. Consider the location (Column, Beam, Slab) for tagging.
ii. Diameter
Mention the diameter of steel bar against each Bar Mark.
iii. Numbers required
For Columns and Beam Main Steel, the numbers are usually provided,
however for the Links of Column, Rings of Beam and Slab Main as well
as distribution bars, numbers need to be calculated.
Numbers = (Length – 2xCover / Spacing) + 1
iv. Shape with Sizes
Refer the drawing for making out the correct shape of each type of rebar
and the size of each of the element in shape. For Links and Rings
mostly inner dimension is considered, for others it’s end to end
v. Cut Length
Depend on the diameter, angle & number of bends, laps, type of hooks,
type of steel / concrete and type of stresses.
3
ADGP
Bar Bending Schedule:
 Important points while preparing BBS:
i. Unit weight of various diameter bars
ii. Development Length
End of Column / Beam Bars
iii. Lap Length
Depends on type of steel / concrete / stress and diameter
Staggering of lap - Minimum distance between C/C of Lap = 1.3 X Lap
iv. Lap Location
Columns –
Beams –
Slabs -
v. Bends
Angles of 30, 45, 60
vi. End Hooks
90 degree hooks, 180 degree hooks
4
ADGP
Bar Bending Schedule: Imp. Points
i. Unit weight of various diameter bars:
Use the weight against each diameter as given in the table.
The weight is given in 3 digits beyond decimal for accuracy.
We mostly use rebars of dia 10, 12, 16 and 20. In these;
weight is 0.15% to 0.5% extra considering only 2 digits
beyond decimal.
We deal in 1000’s of metric tonnes of steel in each project.
For every 1000MT, we may loose 1.5 MT to 5 MT.
5
Dia.
(mm)
Unit weight
(Kg/m)
8 0.395
10 0.617
12 0.888
16 1.578
20 2.466
25 3.853
32 6.313
45 12.485
ADGP
Bar Bending Schedule: Imp. Points
ii. Development Length: Extra length of bar provided beyond the required section to
1. Transfer the stresses from steel to concrete
2. Transfer the stresses from one element to other
(From Beams to Columns / Slabs to Beams etc.)
3. Develop sufficient bond strength between rebar surface and concrete
(To avoid failure due to slippage in ultimate load conditions)
In case of bundled bars, development length is increased by 10/20/33 % for 2/3/4 bars in contact
This is also called as an anchorage length in case of axial tension or axial compression
In case we don’t provide the sufficient Development
Length. The failure of junctions / joints will happen
Prior to reaching even the safe load limits.
Development length, normally is more for HYSD bars
And lessor for high strength concrete.
6
ADGP
iii. Lap Length: Lap length is the overlap of two bars to transfer load
For installing the reinforcement steel, when the length of it is not sufficient to cover
the entire stretch, or it is not feasible to transport / lift / install / keep it in position
then the steel is provided with a lap.
Lap is also required, when the diameter of bar has to be changed as per design
requirement.
While providing laps following to be kept in mind:
1. Use proper splicing technique (Lapping / Welding / Mechanical or Threaded splicing)
2. Location of lap to be away from section of high flexural / shear stresses
3. stagger the location of lap for individual bars of a group (Column / Beam / Slab)
If staggering is unavoidable than increase the length of Lap / use spiral rebar over lap
1.3 x Lap Length
Lap Length - Flexural Tension – Ld or 30 Dia
Direct Tension – 2Ld or 30 Dia
Compression – Ld or 24 Dia
In case of 2 different dia – Lap should be calculated for smaller dia bar.
Stagger the lap in bundled bars as well
7
Bar Bending Schedule: Imp. Points
ADGP
iv. Lap Location
Columns – Normally bottom L/4 and Top L/4 are the high stress zones, hence the
lap should be provided in the middle L/2 zone.
However follow, design guideline if specified.
Beams – Normally the bending moment is high in centre and ends in a fixed /
continuous beams. Avoid Laps in bars in tension zone, and provide
laps in compression zone in such locations.
Shear Stress is high in L/3 from support on both sides of beam thus
avoid laps in shear reinforcement, however provide laps for Flexural
tension zone bars as the bending moment is less.
Follow otherwise design guidelines if specified.
Slabs – Avoid laps in locations of high bending moment and high shear stress,
which is normally at the mid span and ends, provide at 1/3 from the
ends.
Follow design guidelines otherwise, if provided
8
Bar Bending Schedule: Imp. Points
ADGP
iv. Lap Location
9
Bar Bending Schedule: Imp. Points
ADGP
v. Bends:
Normally the requirement of Main reinforcement in Beam is at the bottom for Mid Span
and at the top for End span considering the Bending Moment Diagram in Fixed &
Continuous beams. In such case the Main reinforcement is bent and taken up as shown
in figure.
This takes care of the Shear Force Requirement 1/3 span as well.
Refer the sketch – the extra length (i.e. l1-l2) to be considered for cutting length
calculations. Refer the table beside the sketch for considering the extra length based on
angle of bend.
10
Bar Bending Schedule: Imp. Points
Angle
@
D / Sin@ D / Tan@ la = l1-l2
30 D/0.5 D/0.5733 0.27D
45 D/0.707 D/1 0.42D
60 D/0.866 D/1.732 0.58D
ADGP
v. End Anchorage – Hooks & Bends : (in HYSD Steel Bars)
11
Bar Bending Schedule: Imp. Points
Nominal Dia ‘d’ 10 12 16 20 25 32
Hook
Allowance
‘H’ 130 155 210 260 325 415-545
Bend
Allowance
‘B’ 75 75 95 120 150 190-225
Radius ‘kd’ 40 48 64 80 100 128-192
ADGP
End Anchorage
Cut Length = l + B
B=6d
Semi-circular hook
Cut Length = l + H
H=13d
The reinforcement bar shape is prepared based on:
a. Development Length (As per end conditions)
b. Lap Length (As per requirement of Laps)
c. Bends (As per details given in the drawings)
d. End Anchors / Hooks (As per the requirements specified in drawings)
The Cut length is calculated as per various norms given in earlier slides and / or
based on various combination of the above.
As explained earlier about rebar unit weight to be considered up to 3rd digit
after decimal, in case of cutting length also one must consider the reduction
due to bends. Though it’s small value in each bar; the overall impact is huge
considering the huge quantum of work.
12
Bar Bending Schedule: Imp. Points
ADGP
13
Bar Bending Schedule: Imp. Points
ADGP
14
Bar Bending Schedule: Imp. Points
Ultimate Tensile Strength
Yield stress
0.2% proof stress
ADGP
15
Bar Bending Schedule: Splicing / Threading
ADGP
Laps are not always appropriate joint for reinforcement steel.
Space Constraints – specially large dia bars in Columns and Beams
Depend on the strength from concrete / lack structural integrity
Time consuming / Costly for higher diameter bars
Couplers (Crimping / Threading) are the options fro splicing.
Connect quickly at site locations
Reduced congestion of rebars due to splicing
Independent of concrete – integral reinforcement
Cost effective – specially 20mm dia and above.
Coupler should meet 125% of yield strength of rebar.
16
Bar Bending Schedule: Couplers
Rebar Dia.
(MM)
Coupler Details Pitch
(MM)External Dia.
(MM)
Internal Dia.
(MM)
Length (MM)
16 25 13.5 40 2.5
20 32 17.5 48 2.5
25 40 22 60 3.0
32 50 29 72 3.0
40 60 37 90 3.0
ADGP
17
Bar Bending Schedule: Splicing / Threading
ADGP

More Related Content

What's hot

Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Hossam Shafiq II
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
Ar. Aakansha
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
Ali Ishaqi
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structuresRizwan Khurram
 
Bar bending schedule for neck column
Bar bending schedule for neck columnBar bending schedule for neck column
Bar bending schedule for neck column
Shahzad Ali
 
Reinforced Concrete
Reinforced ConcreteReinforced Concrete
Reinforced Concrete
Civil Manage
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)
MachenLink
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc buildinghlksd
 
various connection of steel structure
various connection of steel structurevarious connection of steel structure
various connection of steel structure
mridupawan khanikar
 
Curved beam design
Curved beam designCurved beam design
Curved beam design
Vinayak Patil
 
BOLTED CONNECTION
BOLTED CONNECTIONBOLTED CONNECTION
BOLTED CONNECTION
Rahul Kumar Raj
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
Dr.Subramanian Narayanan
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
Siddiqui Anwar
 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
Ir. David Puen
 
Deep beams
Deep beams Deep beams
Deep beams
Vikas Mehta
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
R VIJAYAKUMAR
 
Strength of concrete (for civil engineering)
Strength of concrete (for civil engineering) Strength of concrete (for civil engineering)
Strength of concrete (for civil engineering)
laxman singh
 
Two way slab
Two way slabTwo way slab
Two way slab
dishant pansuriya
 
Redistribution of moments-Part-1
Redistribution of moments-Part-1Redistribution of moments-Part-1
Redistribution of moments-Part-1
Subhash Patankar
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
ahsanrabbani
 

What's hot (20)

Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
Lec09 Shear in RC Beams (Reinforced Concrete Design I & Prof. Abdelhamid Charif)
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Bar bending schedule for neck column
Bar bending schedule for neck columnBar bending schedule for neck column
Bar bending schedule for neck column
 
Reinforced Concrete
Reinforced ConcreteReinforced Concrete
Reinforced Concrete
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc building
 
various connection of steel structure
various connection of steel structurevarious connection of steel structure
various connection of steel structure
 
Curved beam design
Curved beam designCurved beam design
Curved beam design
 
BOLTED CONNECTION
BOLTED CONNECTIONBOLTED CONNECTION
BOLTED CONNECTION
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
 
Deep beams
Deep beams Deep beams
Deep beams
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
 
Strength of concrete (for civil engineering)
Strength of concrete (for civil engineering) Strength of concrete (for civil engineering)
Strength of concrete (for civil engineering)
 
Two way slab
Two way slabTwo way slab
Two way slab
 
Redistribution of moments-Part-1
Redistribution of moments-Part-1Redistribution of moments-Part-1
Redistribution of moments-Part-1
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 

Similar to BBS Preparation

Rereindetailing
RereindetailingRereindetailing
Rereindetailingarchi2012
 
1228808532(2)
1228808532(2)1228808532(2)
1228808532(2)
rachidlouni1
 
14251 a ch3
14251 a ch314251 a ch3
L1303017175
L1303017175L1303017175
L1303017175
IOSR Journals
 
Engineering science lesson 6 2
Engineering science lesson 6 2Engineering science lesson 6 2
Engineering science lesson 6 2
Shahid Aaqil
 
Rc detailing-to-ec2
Rc detailing-to-ec2Rc detailing-to-ec2
Rc detailing-to-ec2
Luan Truong Van
 
Camber design
Camber designCamber design
Camber design
Sushil Dhungana
 
BBS ppt.pptx
BBS ppt.pptxBBS ppt.pptx
BBS ppt.pptx
KanavSharma201638
 
Prsesntation on Commercial building Project
Prsesntation on Commercial building ProjectPrsesntation on Commercial building Project
Prsesntation on Commercial building Project
MD AFROZ ALAM
 
ASEP Steel Handbook
ASEP Steel HandbookASEP Steel Handbook
ASEP Steel Handbook
Monique Carr
 
Study of Steel Moment Resisting Frame with Reduced Beam Section
Study of Steel Moment Resisting Frame with Reduced Beam SectionStudy of Steel Moment Resisting Frame with Reduced Beam Section
Study of Steel Moment Resisting Frame with Reduced Beam Section
IJERA Editor
 
Tower smart tower_detailing_tips_series_2
Tower smart tower_detailing_tips_series_2Tower smart tower_detailing_tips_series_2
Tower smart tower_detailing_tips_series_2
stan gad
 
4.main content final copy edited (2)
4.main content final copy edited (2)4.main content final copy edited (2)
4.main content final copy edited (2)
MothilalThulasiraman
 
IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...
IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...
IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...
IRJET Journal
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Hossam Shafiq II
 
comparative study of steel I - girder and prestressed steel I - girder as per...
comparative study of steel I - girder and prestressed steel I - girder as per...comparative study of steel I - girder and prestressed steel I - girder as per...
comparative study of steel I - girder and prestressed steel I - girder as per...
Dr. Dhara shah
 
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Hossam Shafiq II
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
Binay Shrestha
 

Similar to BBS Preparation (20)

I Download (1)
I Download (1)I Download (1)
I Download (1)
 
I download
I downloadI download
I download
 
Rereindetailing
RereindetailingRereindetailing
Rereindetailing
 
1228808532(2)
1228808532(2)1228808532(2)
1228808532(2)
 
14251 a ch3
14251 a ch314251 a ch3
14251 a ch3
 
L1303017175
L1303017175L1303017175
L1303017175
 
Engineering science lesson 6 2
Engineering science lesson 6 2Engineering science lesson 6 2
Engineering science lesson 6 2
 
Rc detailing-to-ec2
Rc detailing-to-ec2Rc detailing-to-ec2
Rc detailing-to-ec2
 
Camber design
Camber designCamber design
Camber design
 
BBS ppt.pptx
BBS ppt.pptxBBS ppt.pptx
BBS ppt.pptx
 
Prsesntation on Commercial building Project
Prsesntation on Commercial building ProjectPrsesntation on Commercial building Project
Prsesntation on Commercial building Project
 
ASEP Steel Handbook
ASEP Steel HandbookASEP Steel Handbook
ASEP Steel Handbook
 
Study of Steel Moment Resisting Frame with Reduced Beam Section
Study of Steel Moment Resisting Frame with Reduced Beam SectionStudy of Steel Moment Resisting Frame with Reduced Beam Section
Study of Steel Moment Resisting Frame with Reduced Beam Section
 
Tower smart tower_detailing_tips_series_2
Tower smart tower_detailing_tips_series_2Tower smart tower_detailing_tips_series_2
Tower smart tower_detailing_tips_series_2
 
4.main content final copy edited (2)
4.main content final copy edited (2)4.main content final copy edited (2)
4.main content final copy edited (2)
 
IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...
IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...
IRJET- Buckling Analysis of Corrugated Hollow Columns using Trapezoidal and S...
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
 
comparative study of steel I - girder and prestressed steel I - girder as per...
comparative study of steel I - girder and prestressed steel I - girder as per...comparative study of steel I - girder and prestressed steel I - girder as per...
comparative study of steel I - girder and prestressed steel I - girder as per...
 
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 

Recently uploaded

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
itech2017
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 

Recently uploaded (20)

Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABSDESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
DESIGN AND ANALYSIS OF A CAR SHOWROOM USING E TABS
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 

BBS Preparation

  • 2. Bar Bending Schedule:  Reinforcement Steel cost is around 20% – 25% of Cost of RCC Structure.  Wastage of Reinforcement steel is generally noticed only at the end of works, and the cost implication is huge.  IS code – “Code of practice for bending and fixing of bars for concrete reinforcement” – IS 2502 – 1963 (reaffirmed 2004)  Particular care needed for higher diameter bars while bending. Size of Mandrel to be as per code else the bars crack at bend location.  We typically use Mild Steel bars…….. HYSD Bars………?  HYSD bars can be CT or TMT?  Available strength – 415 / 500 / 550 / 600 …. With “D”? 1 ADGP
  • 3. Bar Bending Schedule:  Bar Bending is a process of cutting and bending reinforcement steel into desired shape as per structural drawing.  Bar Bending Schedule (BBS) is a detailed list of reinforcement bars containing bar mark (for identification), diameter, numbers, shape with size, and cut length of each.  BBS helps in estimating required quantities of the various diameter of bars, which helps in Procurement and Stock Management of various diameter of rebar.  BBS assists in checking the work executed vis-à-vis requirement as per drawing and the same can be used in billing.  BBS can be given to factory to get cut & bent steel at site, saving working space, better wastage control, reducing labour cost and thereby reduction in overall cost. 2 ADGP
  • 4. Bar Bending Schedule:  Preparation of BBS: i. Identification (Bar Mark) Tag different types of bars in the drawing with a unique id and list it out in a sheet. Consider the location (Column, Beam, Slab) for tagging. ii. Diameter Mention the diameter of steel bar against each Bar Mark. iii. Numbers required For Columns and Beam Main Steel, the numbers are usually provided, however for the Links of Column, Rings of Beam and Slab Main as well as distribution bars, numbers need to be calculated. Numbers = (Length – 2xCover / Spacing) + 1 iv. Shape with Sizes Refer the drawing for making out the correct shape of each type of rebar and the size of each of the element in shape. For Links and Rings mostly inner dimension is considered, for others it’s end to end v. Cut Length Depend on the diameter, angle & number of bends, laps, type of hooks, type of steel / concrete and type of stresses. 3 ADGP
  • 5. Bar Bending Schedule:  Important points while preparing BBS: i. Unit weight of various diameter bars ii. Development Length End of Column / Beam Bars iii. Lap Length Depends on type of steel / concrete / stress and diameter Staggering of lap - Minimum distance between C/C of Lap = 1.3 X Lap iv. Lap Location Columns – Beams – Slabs - v. Bends Angles of 30, 45, 60 vi. End Hooks 90 degree hooks, 180 degree hooks 4 ADGP
  • 6. Bar Bending Schedule: Imp. Points i. Unit weight of various diameter bars: Use the weight against each diameter as given in the table. The weight is given in 3 digits beyond decimal for accuracy. We mostly use rebars of dia 10, 12, 16 and 20. In these; weight is 0.15% to 0.5% extra considering only 2 digits beyond decimal. We deal in 1000’s of metric tonnes of steel in each project. For every 1000MT, we may loose 1.5 MT to 5 MT. 5 Dia. (mm) Unit weight (Kg/m) 8 0.395 10 0.617 12 0.888 16 1.578 20 2.466 25 3.853 32 6.313 45 12.485 ADGP
  • 7. Bar Bending Schedule: Imp. Points ii. Development Length: Extra length of bar provided beyond the required section to 1. Transfer the stresses from steel to concrete 2. Transfer the stresses from one element to other (From Beams to Columns / Slabs to Beams etc.) 3. Develop sufficient bond strength between rebar surface and concrete (To avoid failure due to slippage in ultimate load conditions) In case of bundled bars, development length is increased by 10/20/33 % for 2/3/4 bars in contact This is also called as an anchorage length in case of axial tension or axial compression In case we don’t provide the sufficient Development Length. The failure of junctions / joints will happen Prior to reaching even the safe load limits. Development length, normally is more for HYSD bars And lessor for high strength concrete. 6 ADGP
  • 8. iii. Lap Length: Lap length is the overlap of two bars to transfer load For installing the reinforcement steel, when the length of it is not sufficient to cover the entire stretch, or it is not feasible to transport / lift / install / keep it in position then the steel is provided with a lap. Lap is also required, when the diameter of bar has to be changed as per design requirement. While providing laps following to be kept in mind: 1. Use proper splicing technique (Lapping / Welding / Mechanical or Threaded splicing) 2. Location of lap to be away from section of high flexural / shear stresses 3. stagger the location of lap for individual bars of a group (Column / Beam / Slab) If staggering is unavoidable than increase the length of Lap / use spiral rebar over lap 1.3 x Lap Length Lap Length - Flexural Tension – Ld or 30 Dia Direct Tension – 2Ld or 30 Dia Compression – Ld or 24 Dia In case of 2 different dia – Lap should be calculated for smaller dia bar. Stagger the lap in bundled bars as well 7 Bar Bending Schedule: Imp. Points ADGP
  • 9. iv. Lap Location Columns – Normally bottom L/4 and Top L/4 are the high stress zones, hence the lap should be provided in the middle L/2 zone. However follow, design guideline if specified. Beams – Normally the bending moment is high in centre and ends in a fixed / continuous beams. Avoid Laps in bars in tension zone, and provide laps in compression zone in such locations. Shear Stress is high in L/3 from support on both sides of beam thus avoid laps in shear reinforcement, however provide laps for Flexural tension zone bars as the bending moment is less. Follow otherwise design guidelines if specified. Slabs – Avoid laps in locations of high bending moment and high shear stress, which is normally at the mid span and ends, provide at 1/3 from the ends. Follow design guidelines otherwise, if provided 8 Bar Bending Schedule: Imp. Points ADGP
  • 10. iv. Lap Location 9 Bar Bending Schedule: Imp. Points ADGP
  • 11. v. Bends: Normally the requirement of Main reinforcement in Beam is at the bottom for Mid Span and at the top for End span considering the Bending Moment Diagram in Fixed & Continuous beams. In such case the Main reinforcement is bent and taken up as shown in figure. This takes care of the Shear Force Requirement 1/3 span as well. Refer the sketch – the extra length (i.e. l1-l2) to be considered for cutting length calculations. Refer the table beside the sketch for considering the extra length based on angle of bend. 10 Bar Bending Schedule: Imp. Points Angle @ D / Sin@ D / Tan@ la = l1-l2 30 D/0.5 D/0.5733 0.27D 45 D/0.707 D/1 0.42D 60 D/0.866 D/1.732 0.58D ADGP
  • 12. v. End Anchorage – Hooks & Bends : (in HYSD Steel Bars) 11 Bar Bending Schedule: Imp. Points Nominal Dia ‘d’ 10 12 16 20 25 32 Hook Allowance ‘H’ 130 155 210 260 325 415-545 Bend Allowance ‘B’ 75 75 95 120 150 190-225 Radius ‘kd’ 40 48 64 80 100 128-192 ADGP End Anchorage Cut Length = l + B B=6d Semi-circular hook Cut Length = l + H H=13d
  • 13. The reinforcement bar shape is prepared based on: a. Development Length (As per end conditions) b. Lap Length (As per requirement of Laps) c. Bends (As per details given in the drawings) d. End Anchors / Hooks (As per the requirements specified in drawings) The Cut length is calculated as per various norms given in earlier slides and / or based on various combination of the above. As explained earlier about rebar unit weight to be considered up to 3rd digit after decimal, in case of cutting length also one must consider the reduction due to bends. Though it’s small value in each bar; the overall impact is huge considering the huge quantum of work. 12 Bar Bending Schedule: Imp. Points ADGP
  • 14. 13 Bar Bending Schedule: Imp. Points ADGP
  • 15. 14 Bar Bending Schedule: Imp. Points Ultimate Tensile Strength Yield stress 0.2% proof stress ADGP
  • 16. 15 Bar Bending Schedule: Splicing / Threading ADGP
  • 17. Laps are not always appropriate joint for reinforcement steel. Space Constraints – specially large dia bars in Columns and Beams Depend on the strength from concrete / lack structural integrity Time consuming / Costly for higher diameter bars Couplers (Crimping / Threading) are the options fro splicing. Connect quickly at site locations Reduced congestion of rebars due to splicing Independent of concrete – integral reinforcement Cost effective – specially 20mm dia and above. Coupler should meet 125% of yield strength of rebar. 16 Bar Bending Schedule: Couplers Rebar Dia. (MM) Coupler Details Pitch (MM)External Dia. (MM) Internal Dia. (MM) Length (MM) 16 25 13.5 40 2.5 20 32 17.5 48 2.5 25 40 22 60 3.0 32 50 29 72 3.0 40 60 37 90 3.0 ADGP
  • 18. 17 Bar Bending Schedule: Splicing / Threading ADGP