Presentation given on March 30, 2010, at Cornell Law School in Ithaca, New York. Titled “Environmental and Regulatory Challenges to Developing Energy Alternatives – a Case Study,” the presentation focused on difficulties companies face when seeking regulatory approvals for proposed solar thermal energy projects in Southern California.
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...Deltares
Presentation by Dr. Alain Pietroniro, Executive Director, National Hydrological Service of Canada, Meteorological Service of Canada, at the Delft-FEWS User Days, during Delft Software Days - Edition 2019. Wednesday, 6 November 2019, Delft.
A letter sent by Rick Webb from the Dominion Pipeline Monitoring Coalition to U.S Forest Service supervisor for the George Washington and Jefferson National Forests, H. Thomas Speaks, Jr. The letter, in essence, requests the USFS to reject Dominion's request to survey a path through 30 miles of the GWNF for the interstate Atlantic Coast Pipeline--a pipeline that will bring abundant, cheap, clean-burning Marcellus Shale gas to Virginia and North Carolina residents.
The Executive Summary of the draft Environmental Impact Statement (EIS) from the Federal Energy Regulatory Commission. It is a review of the potential impacts from building a 125-mile natural gas pipeline from Susquehanna County, PA north into central New York where it will connect with two interstate natural gas transmission pipelines, delivering up to 650,000 dekatherms of natural gas per day to New York and New England--something badly needed. The EIS says there will be negative effects on the environment--but that those effects can be mitigated to "less than significant levels" if certain things are done.
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...Deltares
Presentation by Dr. Alain Pietroniro, Executive Director, National Hydrological Service of Canada, Meteorological Service of Canada, at the Delft-FEWS User Days, during Delft Software Days - Edition 2019. Wednesday, 6 November 2019, Delft.
A letter sent by Rick Webb from the Dominion Pipeline Monitoring Coalition to U.S Forest Service supervisor for the George Washington and Jefferson National Forests, H. Thomas Speaks, Jr. The letter, in essence, requests the USFS to reject Dominion's request to survey a path through 30 miles of the GWNF for the interstate Atlantic Coast Pipeline--a pipeline that will bring abundant, cheap, clean-burning Marcellus Shale gas to Virginia and North Carolina residents.
The Executive Summary of the draft Environmental Impact Statement (EIS) from the Federal Energy Regulatory Commission. It is a review of the potential impacts from building a 125-mile natural gas pipeline from Susquehanna County, PA north into central New York where it will connect with two interstate natural gas transmission pipelines, delivering up to 650,000 dekatherms of natural gas per day to New York and New England--something badly needed. The EIS says there will be negative effects on the environment--but that those effects can be mitigated to "less than significant levels" if certain things are done.
Watershed management along the Colorado River - Michael GabaldonYourAlberta
Michael is an Associate Vice-President with AECOM and a presenter at Alberta’s Watershed Management Symposium: Flood and Drought Mitigation. Using the Colorado River and recent flood events in the State of Colorado as backdrops, Michael talked about bringing diverse stakeholders together to create an effective total watershed management plan.
Society of Wetland Scientists Annual Meeting, The Role of Wetlands in Meeting Global Environmental Challenges: Linking Wetland Science, Policy, and Society
In June 2010, EPA proposed a rule to regulate coal combustion residuals (“CCRs”) under the Resource Conservation and Recovery Act (RCRA). After a lengthy delay, the proposed rule, which set forth two options for the regulation of CCRs, is expected to be finalized by the end of this year.
Information for Cuyahoga County applicants to the State Capital Improvement Program
This presentation was shown at workshops on August 15 and 16, 2017.
http://www.countyplanning.us/services/grant-programs/state-capital-improvement-program/
Update on Hydraulic Fracturing:Preparing for Gasland 2Now Dentons
In this presentation, FMC Law's Alex MacWilliam discusses hydraulic fracturing. The presentation covers the hydraulic fracturing process; the legislative and regulatory management of key issues related to hydraulic fracturing; liability issues in fracturing litigation; finally, lessons and trends related to hydraulic fracturing.
Watershed management along the Colorado River - Michael GabaldonYourAlberta
Michael is an Associate Vice-President with AECOM and a presenter at Alberta’s Watershed Management Symposium: Flood and Drought Mitigation. Using the Colorado River and recent flood events in the State of Colorado as backdrops, Michael talked about bringing diverse stakeholders together to create an effective total watershed management plan.
Society of Wetland Scientists Annual Meeting, The Role of Wetlands in Meeting Global Environmental Challenges: Linking Wetland Science, Policy, and Society
In June 2010, EPA proposed a rule to regulate coal combustion residuals (“CCRs”) under the Resource Conservation and Recovery Act (RCRA). After a lengthy delay, the proposed rule, which set forth two options for the regulation of CCRs, is expected to be finalized by the end of this year.
Information for Cuyahoga County applicants to the State Capital Improvement Program
This presentation was shown at workshops on August 15 and 16, 2017.
http://www.countyplanning.us/services/grant-programs/state-capital-improvement-program/
Update on Hydraulic Fracturing:Preparing for Gasland 2Now Dentons
In this presentation, FMC Law's Alex MacWilliam discusses hydraulic fracturing. The presentation covers the hydraulic fracturing process; the legislative and regulatory management of key issues related to hydraulic fracturing; liability issues in fracturing litigation; finally, lessons and trends related to hydraulic fracturing.
Slides from the presentation by Karen Counsell (University of Glamorgan) at the joint conference Open Educational Resources in the disciplines in October 2010.
Slides from the presentation given by Dale McFadzean (University of the West of Scotland) at the 2010 conference: Moving forward: Legal education in Scotland.
Slides from the presentation given by Paul Maharg (University of Northumbria) at the joint conference Open Educational Resources in the disciplines in October 2010.
Slides for the presentation given by Jude Carroll at the event Assessment and feedback issues for teaching international students in Law on 16 May 2011.
Current Issues Wetland Mitigation_Irow 2009 jlarndt_51
Presents history and current status of wetland mitigation along utility rights-of-way. Presented at the INternational Conference on environmental Concerns in Rights-of-Way Management, 2009, Portland OR.
Per Peterson, chair of nuclear engineering at UC Berkeley, presents on the United States' nuclear waste policy and gives recommendations on future steps.
The NuClean Kick-Off workshop was held on Nov. 7, 2013 at the Handlery Union Square Hotel in San Francisco, CA, co-located with the AIChE 2013 Annual Meeting.
For more information on NuClean, visit: http://www.aiche.org/cei/conferences/nuclean-workshop/2013.
For more information on AIChE's Center for Energy Initiatives (CEI), visit: http://www.aiche.org/cei.
David Kosson, Cornelius Vanderbilt Professor of Engineering at Vanderbilt University, gives an overview of various past and present waste management issues, efforts, technologies and impacts. He also presents some challenges regarding waste management.
The NuClean Kick-Off workshop was held on Nov. 7, 2013 at the Handlery Union Square Hotel in San Francisco, CA, co-located with the AIChE 2013 Annual Meeting.
For more information on NuClean, visit: http://www.aiche.org/cei/conferences/nuclean-workshop/2013.
For more information on AIChE's Center for Energy Initiatives (CEI), visit: http://www.aiche.org/cei.
More than 25 years of proven environmental consulting leadership through key roles with prominent global EPC companies and through long-term business ownership and operation. Demonstrated versatility leading professional teams on critical and highly visible projects for government agencies (e.g., DOD, EPA, various municipalities) and private sector clients (LADWP, Nextera, Solar Reserve, Aerojet General, Waste Management) – from concept to completion. Diverse background as a hydrogeologist, water resource scientist, solid waste/landfill specialist, and permitting and compliance specialist.
Similar to Regulatory Challenges to Alternative Energy (20)
Introduction to the EU REACH Program and California’s Green Chemicals Initiative - REACH & Beyond: Workshop on the Changing Nature of Chemicals Management - December 15, 2008, Sunnyvale, California
1. GENEVA | HOUSTON | KANSAS CITY | LONDON | MIAMI | ORANGE COUNTY | SAN FRANCISCO | TAMPA | WASHINGTON, D.C.
Environmental and Regulatory Challenges to
Developing Energy Alternatives – A Case Study
Seminar Program on Law, Science and Sustainability
Cornell Law School, Ithaca NY – March 30, 2009
2. Disclaimer
This presentation is based in substantial part on publicly-available, non-copyright
protected internet resources, including but not limited to materials published by
the California Energy Commission, the U.S. Bureau of Land Management, and
Solar Millennium LLC. No representation is made herein regarding the accuracy or
completeness of information provided in these materials, nor does any reference
to or reliance on that information constitute an endorsement of the views
expressed by the publishers.
4. California Renewable Portfolio Standard
• California’s Renewable Portfolio Standard Program established in
2002, with the goal of increasing the percentage of renewable
energy in the state's electricity mix to 20 percent by 2010.
• Senate Bill 107 created the California Renewable Portfolio Standard
(RPS), codifying the 20 percent goal and requiring electric utilities to
increase procurement from eligible renewable energy resources by
at least 1 percent of retail sales annually.
• Executive Order S-14-08 (November 17, 2008) requires California
utilities to reach a 33 percent renewables goal by 2020.
• Renewable energy sources utilize many different technologies to
produce electricity (solar (photovoltaic and thermal); large and small
hydroelectricity plants; geothermal; biomass).
• Solar thermal (using reflectors to concentrate sunlight to produce
steam for use in conventional power generation turbines).
7. Ridgecrest Solar Thermal Project
• Applications for certification on file for 12 projects, located in San
Bernardino, Kern, Imperial, Fresno and Riverside counties.
• Total capacity under review: 4,802.8 MW.
• Application of Solar Millennium LLC for Ridgecrest Solar
Development Project (California Energy Commission DOCKET No.
09-AFC-9).
• Located in the high northern Mojave Desert in northeastern Kern
County, California, about five miles southwest of the City of
Ridgecrest, California.
• Utility-scale solar thermal electric power generating will have a
nominal output of 250 megawatts (MW), consisting of a single
power plant utilizing two solar fields.
• Project right-of-way (ROW) will extend across approximately 3,920
acres of public lands owned by the federal government.
9. Solar Thermal Technology
• Solar parabolic trough technology to generate electricity.
• Arrays of parabolic mirrors collect heat energy from the sun and
refocus the radiation on a receiver tube located at the focal point of
the parabola.
• Heat transfer fluid (HTF) is heated to high temperatures (750
degrees Fahrenheit) as it circulates through the receiver tubes.
• Heated HTF is piped through a series of heat exchangers where it
releases its stored heat to generate high pressure steam.
• Steam fed to a traditional steam turbine generator where electricity
is produced.
11. CEC Certification Authority
• State law requires California Energy Commission (CEC) to certify
“sites” for thermal solar power plants with a rated capacity of 50
megawatts or greater.
– Commission has 5 members – 2 appointed as Committee to
conduct the certification process.
– All decisions made solely on the basis of the public record.
• Sites are certified together with their related facilities (i.e.
transmission lines, substations, water supply systems, natural gas
pipelines, waste disposal facilities, access roads, etc.).
• CEC is “lead agency” for California Environmental Quality Act
(CEQA).
• Also monitors compliance with all conditions of certification during
life of the project, including closure and decommissioning.
12. Coordination with BLM
• Federal Bureau of Land Management (BLM).
– Administers public lands under Federal Land Policy and
Management Act (FLPMA) Issuance of right-of-way grants for
use of federal land under 43 CFR Sec. 2800.
– Prepares land use plan (LUP) amendment to authorize proposed
use (power generation and transmission).
– Lead agency for National Environmental Policy Act (NEPA),
National Historic Preservation Act, other Federal laws.
• Major federal action triggering environmental review under NEPA.
– Finding of No Significant Impact (FONSI).
– Preparation of environmental impact statement (EIS).
– Environmental review in conjunction with state law (CEQA).
• BLM and CEC Memorandum of Understanding (MOU) concerning
joint environmental review in a single NEPA)/CEQA process.
13. Coordination with Responsible Agencies
• Local:
– City of Ridgecrest and surrounding communities.
• Regional:
– Regional Water Quality Control Board (RWQCB).
• State:
– Department of Fish and Game.
– State Water Resources Control Water Board (SWRCB).
– Office of Historic Preservation.
– Native American Heritage Commission.
• Federal:
– Environmental Protection Agency (EPA)
– Department of the Interior (Fish and Wildlife Service, National
Parks Service).
14. CEC Certification Process
• Project proponent submits application for CEC certification.
• CEC project staff reviews application to ensure that it meets
minimum requirements and determination to accept application.
• Staff discovery and analyses (data requests and responses; “issues
identification” and public workshops).
• Preliminary and Final Staff Assessment (FSA).
• Committee evidentiary hearing and issuance of Presiding Member’s
Proposed Decision (PMPD), including:
– Findings relating to environmental impacts, public health and
engineering considerations.
– Determination of project’s compliance with Laws, Ordinances,
Regulations and Standards (LORS), potential impacts to the
environment, and related mitigation measures.
– Recommendations regarding conditions of certification.
15. CEC Certification Process (Cont.)
• PMPD hearing and Commission decision.
• Judicial review (30 day CEQA statute of limitations).
16. Ridgecrest Certification Process
TO DATE
• ROW Application – 03/2007
• AFC Submitted – 09/2009
• Data Adequacy – 11/2009
• NOI Published – 11/2009
• Public Workshop – 12/2009
• Scoping Hearing – 01/2010
• Data Requests – 01/2010
GOING FORWARD
• Data Submittal – 01/2010
• BLM ROD – 09/2010
• CEC Decision – 09/2010
• Notice to Proceed – 11/2010
• Begin Construction – 12/2010
• Begin Operations – 07/2013
17. Current Obstacles
• Lack of direction regarding allocation of development in West
Mojave LUP – BLM
• Interim mitigation requirements uncertain – DFG, FWS, BLM
• High level of detail required from applicant – CEC, BLM
• Timing of compliance / combined schedule – CEC, BLM
• Alternatives analysis overly prescriptive – CEC, BLM
• Permitting status and process for network upgrades identified for
renewables – CEC, CPUC, BLM
18. Issue 1 : Individual Impacts (Sacred Lands)
• Mountainous area to the
southwest of project site
known as the El Paso
Mountains Sacred Lands.
• Listed in Native American
Heritage Commission’s
database of Sacred Lands.
• Project could impact view shed
identified by Native Americans
as sacred.
• Exclusive use of no more than
3,926 acres of public land
could eliminate other BLM
authorized land uses.
19. Issue 2 : Individual Impacts (Ground Water)
• Project proposes using high
quality groundwater from wells
located within the Indian Wells
Valley Groundwater Basin.
• Proposed uses include:
– Site construction.
– Plant operations (power
cycle makeup water, mirror
wash water, domestic
potable water, dust.
suppression water, cooling
of ancillary equipment).
• Overdraft in basin will continue
and be exacerbated by the
additional water requirements
of the project.
20. Issue 3 : Cumulative Impacts (Traffic)
• Brown Road/S. China Lake
Blvd./US 395 intersection (post
mile 15) has overall collision
rate 2.8 times higher than the
State-wide average for similar
type facility.
• In both phases of the project
(construction and operational),
additional trips would be
generated by assorted vehicle
types.
• New access point from US 395
is likely a necessity for the
project.
21. Issue 4 : Process (Transmission)
• July 28,
2009 California Independent
System Operator (California
ISO) Phase I Interconnection
Study for project provided
without the generation plant.
• Required to determine the
potential project’s impacts on
existing transmission network.
• CEQA analysis of potential
downstream transmission
upgrades could cause a delay
in the licensing process.
23. ENVIRONMENTAL AND REGULATORY CHALLENGES TO
DEVELOPING ENERGY ALTERNATIVES – A CASE STUDY
Kevin Haroff | Shook Hardy & Bacon LLP | www.shb.com
Geneva | Houston | Kansas City | London | Miami | Orange County | San Francisco | Tampa | Washington D.C.