SlideShare a Scribd company logo
Severn Tidal Power Feasibility StudySevern Tidal Power Feasibility Study
Severn Estuary Forum 2009Severn Estuary Forum 2009
Juliet Austin – Environmental workstream lead, STP study,Juliet Austin – Environmental workstream lead, STP study,
Department of Energy & Climate ChangeDepartment of Energy & Climate Change
Background: Two-year
Government Feasibility study
• Government decision in response to Sustainable Development
Commission’s 2007 report ‘Turning the Tide’ and increasing UK
need for renewable energy
• To enable Government to decide whether it could support tidal
power scheme in the Severn Estuary, and if so, on what terms?
• 10 long-listed options – 5 shortlisted after 2009 public consultation
• 3-5 year planning and, if consented, 5-10 year construction periods
• Issues being addressed:
- strategic case for Severn power compared with alternatives, and in
what timescale (2020/2050…?)
- impacts and benefits, and balance between the two?
- costs and risks, who bears them, legal compliance
- preferred scheme/s? Multiple options under consideration
Map of 10 originally-
proposed options
5 Short-listed schemes
… Following 2009 public consultation…
Beachley Barrage (625 MW, £2.3bn construction cost)
Shoots Barrage (1.05 GW, £3.2bn)
Cardiff-Weston Barrage (8.6 GW, £20.9bn)
Welsh Fleming Lagoon (1.36 GW, £4bn)
Bridgwater Bay Lagoon (1.36 GW, £3.8bn cost)
… individually, and some potentially in combination
Short listed options
Decisions next year
• Advice to ministers April 2010, subject to election
• Public consultation (in addition to one in Jan-April 09)
• Decision late 2010 – either:
- to offer package of support for preferred scheme/s to
go ahead, and move to full feasibility work leading to
planning application OR
- to wait until uncertainties are clearer, and potentially
for new technologies to be deployable in the Severn OR
- not to support a scheme
Public consultation
Issues for consultation – Jan-April 2009
1. Shortlist of scheme options
2. Scope of Strategic Environmental Assessment (SEA)
3. Scope of overall work of feasibility study
What replies did we get?
Good response – over 730 replies:
• Lots of views, full range of views
• How assessing environmental impact?
• Short-listing – questions on why and how
• Regional economic DTZ report – assumptions made?
Government response
• Explains how scheme options are being considered
• Confirms shortlist of 5 schemes for impact assessment
• Confirms £534,000 funding for 3 new Severn Estuary
technology schemes (SETS):
- Atkins/Rolls Royce: low head barrage
- Severn Tidal Fence Consortium – tidal stream
- VerdErg: tidal stream array
• ‘Feedback loop’ – apply learning and shortlist SETS and
non-shortlisted schemes if feasibility study criteria met
• Confirm SEA scope, with minor changes
• Peer review of DTZ study
Non short-listed
Schemes
Apply learning and
short-list if feasibility
criteria are met
Embryonic
Schemes
Develop and assess via
SETS. Short-list if feasibility
criteria are met. Consider in
study conclusions if not.
Short-listed
schemes
Feasibility study conclusions
Developing evidence base/
optimisation of scheme design and operation
Consideration of scheme options –
feedback loop
Embryonic technologies
3 schemes being funded: less environmentally damaging/cost
effective?
Low head barrage – Rolls Royce/Atkins
– ‘low head’ barrage with new types of turbine than traditional barrage design
– Draws on both tidal stream and range technology
– Tides held back for less time = should reduce potential impact on intertidal/fish
Severn tidal fence – Severn tidal fence Consortium
- Tidal stream array
- Does not hold back water to generate electricity – turbines use movement of
water rather than height difference
Severn tidal fence - VerdErg
- Radical new fence design using tidal stream technology – water passes through
tubes that in turn drive turbines
- Minimal moving parts – potentially less damage to fish and intertidal habitat
Wider context
• Government’s Low-carbon Transition Plan and Renewable Energy
Strategy
• Aim: 40% low carbon electricity, 30% renewables by 2020
- renewable electricity - mainly offshore wind
- Severn tidal power?? Depends on wind – plus cost of energy,
certainties, impacts, cost and risk
• Longer term:
- 80% decarbonisation electricity supply by 2050. Demand will rise
- include mix of renewables, nuclear, carbon capture and storage
- Severn tidal power?? More work needed on longer term, also on
Severn power options
Work areas…
Economic & Commercial
• Strategic and economic case
• Impact assessment
• Risk assessment and risk management
• Subsidy mechanism, public role & costs, delivery
timescale
• Transfer of risk – public vs private?
• Timing implications
• Cost – environment, compensatory measures
• Affordability / impact on consumers
• Regional economic impact
Environmental studies
(more detail later)
• Gathering evidence for Strategic Environmental Assessment (SEA)
of environmental and regional impacts – report in 2010
• Impacts on flooding, birds, fish, other habitats and species,
water quality, geomorphology (shape of estuary and moving
sediments)
• Series of technical workshops in the autumn comprising specialists
to advise on the SEA studies
• Environmental legislation – can we comply? Studies include
Habitats Directive, Water Framework Directive
• Ecosystem valuation report – to illustrate the value of the
environment to society, in monetary terms
• All part of consultation in 2010
Technical & Engineering
- Optimisation of shortlisted barrages and lagoons – getting best
out of options against different feasibility study objectives (cost,
environmental impact, amount of energy)
- Mitigation against environmental damage: cross-checking
against SEA impacts
- Grid Study
- Supply Chain Study
- Severn Estuary Embryonic Technology Schemes assessment
Regional impact assessment
• Commissioned independent peer reviewer to look at
DTZ report (strategic-level assessment of economic and
social impact) in light of public consultation comments
• Conclusions of review expected this Autumn
• SEA, supply chain study and ecosystems valuation work
contribute to picture on regional impact
• Will take a view on whether more work is necessary after
peer review
• Regulatory overview:
assessment of compliance with
relevant regulations and policies
• Assessment of various potential
consenting procedures
• Analysis of the methodology of
consenting compensatory
habitats
• Analysis of risk and who bears it
Consenting
Route /
Risk Analysis
Consenting
Compensatory
Habitats
Regulatory
Overview
Timeline
Planning And Consents
Engaging stakeholders & public
• Public consultation Jan-April 2009
• Regular stakeholder meetings, multilateral and bilateral
• SEA workshops for technical experts
• Sciencewise public dialogue sessions:
– Intended to provide early view on priority issues for people and
how best to communicate information in the consultation
– Small scale meetings for invited members of the public
• Information on DECC website and regular e-mail bulletins
• Encouraging organisations to communicate to your stakeholders
• Public consultation (likely to be in 2010)
– Include public meetings on both sides of the Estuary
Environmental studies (more
detail)
• Strategic Environmental Assessment (SEA) – high-level social and
environmental impacts – a requirement of large project plans.
Majority of scientific evidence base.
• Pre-consultation – high-level. May09 – Jan10 – more detailed.
• Engaging stakeholders: Decc environmental workstream
(Environment Agency, Natural England, Countryside Council for
Wales, Defra, Welsh Assembly Govt), SEA Steering Group (NGOs,
regional interests incl. Bristol Port), individual stakeholder meetings
High level
environmental issues
• Environmental benefit - annual saving of up to 11Mt CO2.
• Range of effects on estuarine, marine and freshwater
ecosystems.
• Studies on the value of the services they provide – eg
fishing, flood defence, aggregates.
• Severn Estuary, River Wye and River Usk (and beyond)
– protected international importance for their biodiversity.
• Compliance with Habitats Directive, Water Framework
Directive, other environmental legislation, policies.
• Uncertainty in results given short timescales, whether
desk or field-based, different specialist opinions.
Impacts?
Hydraulics and geomorphology
• H&G: Shape/ structure of estuary, currents, sediment
movements
• High tidal range = complicated environmental system
• Sediment deposition in channels, build up on foreshore or
erosion, flood risk?
• Estuary is extreme high energy environment.
• Removing energy changes environment.
• Understanding physical response drives many other
topics – water quality, flooding, biodiversity; affects
engineering
• Looking at range of potential complex physical scenarios
Other impacts?
• Reduced tidal range – loss of salt marsh and mudflat habitats.
Effects on habitats and their value as flood defence?
• Flood risk?
• Birds – displacement, loss of birds from Severn, national effects?
• Fish and fishing – declines and/or local extinctions?
• Water quality – salinity, pollutants, temperature.
• Other sea users – aggregate, other energy production, tourism and
recreation.
• Historic environment/seascape?
• Navigation?
Environmental studies
- SEA
SEA
ENVIRONMENTAL
REPORT
Physico-Chemical
THEME
Society & Economy
THEME
Landscape &
Historic Env
THEME
Biodiversity
THEME
Carbon Footprint,
Resources &
Waste THEME
Hydraulics and
Geomorphology
Marine Water
Quality
Freshwater Env. &
Assoc. Interfaces
Flood Risk and
Land Drainage
Society &Economy
Navigation
Other Sea Uses
Noise & Vibration
Marine Ecology
Ornithology
Migratory &
Estuarine Fish
Terrestrial &
Fresh. Ecology
Historic
Environment
Landscape and
Seascape
Carbon
Footprinting
Resources and
Waste
Habitats Directive compliance
and compensatory measures
• Following steps laid down in EU Regulations
• Process: Scoping and Appropriate Assessment on
designated sites, assessing for likely significant adverse
effects. If so, look to mitigate. Is the project of IROPI?
If so, determine feasibility of providing compensatory
measures.
• Investigating feasibility / cost of different types of
compensatory measures. E.g. managed realignment for
lost mudflat/saltmarsh, impacts on fish.
• Do not yet know enough to say whether compensatory
measures possible for any of the habitats/species lost
under short-listed schemes.
2010: Phase 2 public consultation on recommendations
Scheme assessment: Individual costs, benefits, risks, impacts
of each scheme against key areas identified in study objectives
(regional, economic, environmental, regulatory requirements,
energy and climate change goals) using quantitative and
qualitative data from evidence gathered across feasibility study
Decision by Ministers: Stop, wait, go ahead?
Response to phase 2 consultation
2009/10 - environment:
Results of SEA studies, impact on
environmental legislation, ecosystem
valuation
Strategic case
Results of Severn
Embryonic
Technology
Schemes
Contact information –
getting in touch
Web:
www.decc.gov.uk/severntidalpower
Email:
severntidalpowerunit@decc.gsi.gov.uk

More Related Content

What's hot

Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Robert Muir
 
Mitigation Symposium - Kim Sturgess
Mitigation Symposium - Kim SturgessMitigation Symposium - Kim Sturgess
Mitigation Symposium - Kim Sturgess
YourAlberta
 
Mitigation Symposium - Scott Edelman
Mitigation Symposium - Scott EdelmanMitigation Symposium - Scott Edelman
Mitigation Symposium - Scott Edelman
YourAlberta
 
Mitigation Symposium - Dave Ardell
Mitigation Symposium - Dave ArdellMitigation Symposium - Dave Ardell
Mitigation Symposium - Dave Ardell
YourAlberta
 
Peatland rewetting for carbon credits – Experience from Belarus
Peatland rewetting for carbon credits – Experience from BelarusPeatland rewetting for carbon credits – Experience from Belarus
Peatland rewetting for carbon credits – Experience from Belarus
Aberdeen CES
 
Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...
Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...
Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...
Robert Muir
 
3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...
3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...
3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...
Environmental Protection Agency, Ireland
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Robert Muir
 
Hydropower Siting, Design, Operations in Changing Climate
Hydropower Siting, Design, Operations in Changing ClimateHydropower Siting, Design, Operations in Changing Climate
Hydropower Siting, Design, Operations in Changing Climate
Water, Land and Ecosystems (WLE)
 
An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019
An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019
An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019
Robert Muir
 
26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures
Environmental Protection Agency, Ireland
 
Cost Effectiveness of LID Implementation
Cost Effectiveness of LID ImplementationCost Effectiveness of LID Implementation
Cost Effectiveness of LID Implementation
Robert Muir
 
IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...
IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...
IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...
Robert Muir
 
Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...
Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...
Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...
Robert Muir
 
Nam Ngiep Hydropower Dam -- Climate Risk Assessment
Nam Ngiep Hydropower Dam -- Climate Risk Assessment Nam Ngiep Hydropower Dam -- Climate Risk Assessment
Nam Ngiep Hydropower Dam -- Climate Risk Assessment
ICEM - International Centre for Environmental Management
 
Regulatory Overview of Stormwater Management
Regulatory Overview of Stormwater ManagementRegulatory Overview of Stormwater Management
Regulatory Overview of Stormwater Management
Andrew T. Der & Associates, LLC
 
International Water Resources and Wetlands Conference, Tulcea, Romania
International Water Resources and Wetlands Conference, Tulcea, RomaniaInternational Water Resources and Wetlands Conference, Tulcea, Romania
International Water Resources and Wetlands Conference, Tulcea, Romania
Andrew T. Der & Associates, LLC
 
Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...
Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...
Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...
Andrew T. Der & Associates, LLC
 
Presentation 1: Intro and Methodology
Presentation 1: Intro and MethodologyPresentation 1: Intro and Methodology
Presentation 1: Intro and Methodology
ICEM - International Centre for Environmental Management
 

What's hot (20)

Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
 
Mitigation Symposium - Kim Sturgess
Mitigation Symposium - Kim SturgessMitigation Symposium - Kim Sturgess
Mitigation Symposium - Kim Sturgess
 
Mitigation Symposium - Scott Edelman
Mitigation Symposium - Scott EdelmanMitigation Symposium - Scott Edelman
Mitigation Symposium - Scott Edelman
 
SuRCASE
SuRCASESuRCASE
SuRCASE
 
Mitigation Symposium - Dave Ardell
Mitigation Symposium - Dave ArdellMitigation Symposium - Dave Ardell
Mitigation Symposium - Dave Ardell
 
Peatland rewetting for carbon credits – Experience from Belarus
Peatland rewetting for carbon credits – Experience from BelarusPeatland rewetting for carbon credits – Experience from Belarus
Peatland rewetting for carbon credits – Experience from Belarus
 
Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...
Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...
Storm Warts, The Floods Awaken, A New Hope for Cost-Effective Investment in F...
 
3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...
3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...
3. Catchment Management of Irish rivers and the role of hydromorphology - Emm...
 
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
Clean Air Partnership Green Infrastructure CAC Meeting - Don Mills Channel Fl...
 
Hydropower Siting, Design, Operations in Changing Climate
Hydropower Siting, Design, Operations in Changing ClimateHydropower Siting, Design, Operations in Changing Climate
Hydropower Siting, Design, Operations in Changing Climate
 
An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019
An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019
An Economic Analysis of Green and Grey Infrastructure - TRIECA Conference 2019
 
26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures26. Floods Directive & Hydromorpholgy Measures
26. Floods Directive & Hydromorpholgy Measures
 
Cost Effectiveness of LID Implementation
Cost Effectiveness of LID ImplementationCost Effectiveness of LID Implementation
Cost Effectiveness of LID Implementation
 
IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...
IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...
IDF Trend Analysis, Future Climate Projections & System Design for Extreme We...
 
Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...
Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...
Robert Muir Level of Service Upgrades and Climate Change Adaptation NRC Works...
 
Nam Ngiep Hydropower Dam -- Climate Risk Assessment
Nam Ngiep Hydropower Dam -- Climate Risk Assessment Nam Ngiep Hydropower Dam -- Climate Risk Assessment
Nam Ngiep Hydropower Dam -- Climate Risk Assessment
 
Regulatory Overview of Stormwater Management
Regulatory Overview of Stormwater ManagementRegulatory Overview of Stormwater Management
Regulatory Overview of Stormwater Management
 
International Water Resources and Wetlands Conference, Tulcea, Romania
International Water Resources and Wetlands Conference, Tulcea, RomaniaInternational Water Resources and Wetlands Conference, Tulcea, Romania
International Water Resources and Wetlands Conference, Tulcea, Romania
 
Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...
Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...
Balancing Nonpoint Source Water Quality Management with Wetland and Stream Pr...
 
Presentation 1: Intro and Methodology
Presentation 1: Intro and MethodologyPresentation 1: Intro and Methodology
Presentation 1: Intro and Methodology
 

Similar to 2009 06 Department of Energy and Climate Change - Juliet Austin

Local Highways and Climate Change Event 9th july 2013
Local Highways and Climate Change Event 9th july 2013Local Highways and Climate Change Event 9th july 2013
Local Highways and Climate Change Event 9th july 2013
Sustainability East
 
Current Issues Wetland Mitigation_Irow 2009
Current Issues Wetland Mitigation_Irow 2009 Current Issues Wetland Mitigation_Irow 2009
Current Issues Wetland Mitigation_Irow 2009
jlarndt_51
 
Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017
Sustainable Severn
 
2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff
2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff 2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff
2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff
SevernEstuary
 
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 -Project professionals: Ready for the future? Climate change, Leigh Woodcock -Project professionals: Ready for the future? Climate change, Leigh Woodcock
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
APMDonotuse
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
SonikaPawar
 
Northampton, MA Climate Adaptation
Northampton, MA Climate AdaptationNorthampton, MA Climate Adaptation
Northampton, MA Climate Adaptation
American Institute of Architects
 
The Rivers Trust Autumn Conference: Day 2 - Session 3
The Rivers Trust Autumn Conference: Day 2 - Session 3The Rivers Trust Autumn Conference: Day 2 - Session 3
The Rivers Trust Autumn Conference: Day 2 - Session 3
Westcountry Rivers Trust
 
Stephen Cook - Renewable Energy
Stephen Cook - Renewable EnergyStephen Cook - Renewable Energy
Stephen Cook - Renewable Energy
PAS_Team
 
2009 09 IMCORE - Rhoda Ballinger
2009 09 IMCORE - Rhoda Ballinger 2009 09 IMCORE - Rhoda Ballinger
2009 09 IMCORE - Rhoda Ballinger
SevernEstuary
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Toronto Public Consultation Unit
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
NaturalEngland
 
Eia for railway project
Eia for railway projectEia for railway project
Eia for railway project
GARRE RAVI KUMAR
 
Case studies on economic appraisal of adaptation options in some countries
Case studies on economic appraisal of adaptation options in some countriesCase studies on economic appraisal of adaptation options in some countries
Case studies on economic appraisal of adaptation options in some countries
NAP Events
 
State action plans on climate change_Preeti Soni, UNDP_15 October 2014
State action plans on climate change_Preeti Soni, UNDP_15 October 2014State action plans on climate change_Preeti Soni, UNDP_15 October 2014
State action plans on climate change_Preeti Soni, UNDP_15 October 2014
India Water Portal
 
The Energy Water Nexus. By Daryl Fields.
The Energy Water Nexus. By Daryl Fields.The Energy Water Nexus. By Daryl Fields.
The Energy Water Nexus. By Daryl Fields.
Global Water Partnership
 
DSD-INT 2015 - Tools to optimise power production and environmental effects -...
DSD-INT 2015 - Tools to optimise power production and environmental effects -...DSD-INT 2015 - Tools to optimise power production and environmental effects -...
DSD-INT 2015 - Tools to optimise power production and environmental effects -...
Deltares
 
Planning and sustainable energy (February 2013)
Planning and sustainable energy (February 2013)Planning and sustainable energy (February 2013)
Planning and sustainable energy (February 2013)
PAS_Team
 
2013 06 bristol deep sea container terminal - jerry stanford
2013   06 bristol deep sea container terminal - jerry stanford2013   06 bristol deep sea container terminal - jerry stanford
2013 06 bristol deep sea container terminal - jerry stanford
SevernEstuary
 

Similar to 2009 06 Department of Energy and Climate Change - Juliet Austin (20)

Local Highways and Climate Change Event 9th july 2013
Local Highways and Climate Change Event 9th july 2013Local Highways and Climate Change Event 9th july 2013
Local Highways and Climate Change Event 9th july 2013
 
Current Issues Wetland Mitigation_Irow 2009
Current Issues Wetland Mitigation_Irow 2009 Current Issues Wetland Mitigation_Irow 2009
Current Issues Wetland Mitigation_Irow 2009
 
Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017Gino Bawn - Sustainable Severn Forum 2017
Gino Bawn - Sustainable Severn Forum 2017
 
2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff
2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff 2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff
2008 03 Tidal Power: The Options Peter Kydd, Parsons Brinckerhoff
 
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 -Project professionals: Ready for the future? Climate change, Leigh Woodcock -Project professionals: Ready for the future? Climate change, Leigh Woodcock
-Project professionals: Ready for the future? Climate change, Leigh Woodcock
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Northampton, MA Climate Adaptation
Northampton, MA Climate AdaptationNorthampton, MA Climate Adaptation
Northampton, MA Climate Adaptation
 
The Rivers Trust Autumn Conference: Day 2 - Session 3
The Rivers Trust Autumn Conference: Day 2 - Session 3The Rivers Trust Autumn Conference: Day 2 - Session 3
The Rivers Trust Autumn Conference: Day 2 - Session 3
 
Stephen Cook - Renewable Energy
Stephen Cook - Renewable EnergyStephen Cook - Renewable Energy
Stephen Cook - Renewable Energy
 
Natural gas
Natural gasNatural gas
Natural gas
 
2009 09 IMCORE - Rhoda Ballinger
2009 09 IMCORE - Rhoda Ballinger 2009 09 IMCORE - Rhoda Ballinger
2009 09 IMCORE - Rhoda Ballinger
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
4 sarah nightingale decc offshore wind seminar 18 19  march 20144 sarah nightingale decc offshore wind seminar 18 19  march 2014
4 sarah nightingale decc offshore wind seminar 18 19 march 2014
 
Eia for railway project
Eia for railway projectEia for railway project
Eia for railway project
 
Case studies on economic appraisal of adaptation options in some countries
Case studies on economic appraisal of adaptation options in some countriesCase studies on economic appraisal of adaptation options in some countries
Case studies on economic appraisal of adaptation options in some countries
 
State action plans on climate change_Preeti Soni, UNDP_15 October 2014
State action plans on climate change_Preeti Soni, UNDP_15 October 2014State action plans on climate change_Preeti Soni, UNDP_15 October 2014
State action plans on climate change_Preeti Soni, UNDP_15 October 2014
 
The Energy Water Nexus. By Daryl Fields.
The Energy Water Nexus. By Daryl Fields.The Energy Water Nexus. By Daryl Fields.
The Energy Water Nexus. By Daryl Fields.
 
DSD-INT 2015 - Tools to optimise power production and environmental effects -...
DSD-INT 2015 - Tools to optimise power production and environmental effects -...DSD-INT 2015 - Tools to optimise power production and environmental effects -...
DSD-INT 2015 - Tools to optimise power production and environmental effects -...
 
Planning and sustainable energy (February 2013)
Planning and sustainable energy (February 2013)Planning and sustainable energy (February 2013)
Planning and sustainable energy (February 2013)
 
2013 06 bristol deep sea container terminal - jerry stanford
2013   06 bristol deep sea container terminal - jerry stanford2013   06 bristol deep sea container terminal - jerry stanford
2013 06 bristol deep sea container terminal - jerry stanford
 

More from SevernEstuary

Explore the Severn
Explore the SevernExplore the Severn
Explore the Severn
SevernEstuary
 
Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...
Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...
Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...
SevernEstuary
 
Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...
Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...
Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...
SevernEstuary
 
Alex Bellisario - Citizan in the Severn
Alex Bellisario - Citizan in the SevernAlex Bellisario - Citizan in the Severn
Alex Bellisario - Citizan in the Severn
SevernEstuary
 
2006 09 10,000 Years of Change, Richard Brunning
2006 09 10,000 Years of Change, Richard Brunning2006 09 10,000 Years of Change, Richard Brunning
2006 09 10,000 Years of Change, Richard Brunning
SevernEstuary
 
2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...
2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...
2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...
SevernEstuary
 
2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...
2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...
2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...
SevernEstuary
 
2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine
2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine 2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine
2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine
SevernEstuary
 
2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency
2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency 2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency
2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency
SevernEstuary
 
2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...
2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...
2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...
SevernEstuary
 
2006 03 National Predictions - David Woolf, National Oceanographic Centre
2006 03 National Predictions - David Woolf, National Oceanographic Centre 2006 03 National Predictions - David Woolf, National Oceanographic Centre
2006 03 National Predictions - David Woolf, National Oceanographic Centre
SevernEstuary
 
2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...
2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...
2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...
SevernEstuary
 
2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...
2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...
2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...
SevernEstuary
 
2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...
2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...
2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...
SevernEstuary
 
2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre
2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre
2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre
SevernEstuary
 
2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...
2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...
2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...
SevernEstuary
 
2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...
2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...
2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...
SevernEstuary
 
2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...
2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...
2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...
SevernEstuary
 
2007 05 Severn River Basin District - Working together - Mark Scott, Environm...
2007 05 Severn River Basin District - Working together - Mark Scott, Environm...2007 05 Severn River Basin District - Working together - Mark Scott, Environm...
2007 05 Severn River Basin District - Working together - Mark Scott, Environm...
SevernEstuary
 
2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales
2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales
2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales
SevernEstuary
 

More from SevernEstuary (20)

Explore the Severn
Explore the SevernExplore the Severn
Explore the Severn
 
Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...
Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...
Sue Kidd - Cross-border Marine Planning in the North West - Challenges and Op...
 
Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...
Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...
Claire Sweeney - Delivering Sustainable Network Rail Improvement Schemes for ...
 
Alex Bellisario - Citizan in the Severn
Alex Bellisario - Citizan in the SevernAlex Bellisario - Citizan in the Severn
Alex Bellisario - Citizan in the Severn
 
2006 09 10,000 Years of Change, Richard Brunning
2006 09 10,000 Years of Change, Richard Brunning2006 09 10,000 Years of Change, Richard Brunning
2006 09 10,000 Years of Change, Richard Brunning
 
2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...
2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...
2006 08 Tidal Severn Flood Risk Management Strategy and Avonmouth Scheme - Ni...
 
2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...
2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...
2006 07 Avonmouth Renewable Energy Project - Patrick Kearon, The Bristol Port...
 
2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine
2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine 2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine
2006 06 Severn Barrage: Is the Tide Turning? - David Kerr, Sir Robert McAlpine
 
2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency
2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency 2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency
2006 05 Severn Estuary Perspective - Roger Wade, Environment Agency
 
2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...
2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...
2006 04 Regional Perspective - Sarah Hendell-Blackford, SW Climate Change Imp...
 
2006 03 National Predictions - David Woolf, National Oceanographic Centre
2006 03 National Predictions - David Woolf, National Oceanographic Centre 2006 03 National Predictions - David Woolf, National Oceanographic Centre
2006 03 National Predictions - David Woolf, National Oceanographic Centre
 
2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...
2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...
2006 02 Intergrated Management and the Severn Estuary - Peter Burbridge, Newc...
 
2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...
2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...
2006 01 The Dynamic Severn: Points of View - Chris Wooldridge, Cariff Univers...
 
2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...
2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...
2006 00 Severn Estuary Forum: Changing times and tides: the future of the Sev...
 
2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre
2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre
2007 09 The Severn Bridges - Andrew Hewett, Severn Bridges Visitor Centre
 
2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...
2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...
2007 08 Public Engagement with Tidal Power Options - Mervyn Bramley, Universi...
 
2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...
2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...
2007 07 Working Together for Coastal Planning - Tim Stojanovic, EU Corepoint ...
 
2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...
2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...
2007 06 Climate Change Research Advisory Group - Rhoda Ballinger, Cardiff Uni...
 
2007 05 Severn River Basin District - Working together - Mark Scott, Environm...
2007 05 Severn River Basin District - Working together - Mark Scott, Environm...2007 05 Severn River Basin District - Working together - Mark Scott, Environm...
2007 05 Severn River Basin District - Working together - Mark Scott, Environm...
 
2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales
2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales
2007 04 Newport Wetlands Centre - Sue Rice, Countryside Council for Wales
 

Recently uploaded

Sustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.pptSustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.ppt
chaitaliambole
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
CIFOR-ICRAF
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
Open Access Research Paper
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
sidjena70
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
rohankumarsinghrore1
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
yasmindemoraes1
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
AhmadKhan917612
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
laozhuseo02
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
greendigital
 
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
zm9ajxup
 
alhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptxalhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptx
CECOS University Peshawar, Pakistan
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Innovation and Technology for Development Centre
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
Robin Grant
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
chaitaliambole
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
punit537210
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
RaniJaiswal16
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
MMariSelvam4
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
Robin Grant
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
a0966109726
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
BanitaDsouza
 

Recently uploaded (20)

Sustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.pptSustainable Rain water harvesting in india.ppt
Sustainable Rain water harvesting in india.ppt
 
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian AmazonAlert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
Alert-driven Community-based Forest monitoring: A case of the Peruvian Amazon
 
Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...Characterization and the Kinetics of drying at the drying oven and with micro...
Characterization and the Kinetics of drying at the drying oven and with micro...
 
Natural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptxNatural farming @ Dr. Siddhartha S. Jena.pptx
Natural farming @ Dr. Siddhartha S. Jena.pptx
 
Celebrating World-environment-day-2024.pdf
Celebrating  World-environment-day-2024.pdfCelebrating  World-environment-day-2024.pdf
Celebrating World-environment-day-2024.pdf
 
Summary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of AustraliaSummary of the Climate and Energy Policy of Australia
Summary of the Climate and Energy Policy of Australia
 
Environmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. SinghEnvironmental Science Book By Dr. Y.K. Singh
Environmental Science Book By Dr. Y.K. Singh
 
International+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shopInternational+e-Commerce+Platform-www.cfye-commerce.shop
International+e-Commerce+Platform-www.cfye-commerce.shop
 
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business VenturesWillie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Ventures
 
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
一比一原版(UMTC毕业证书)明尼苏达大学双城分校毕业证如何办理
 
alhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptxalhambra case study Islamic gardens part-2.pptx
alhambra case study Islamic gardens part-2.pptx
 
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdfPresentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
Presentación Giulio Quaggiotto-Diálogo improbable .pptx.pdf
 
NRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation StrategyNRW Board Paper - DRAFT NRW Recreation Strategy
NRW Board Paper - DRAFT NRW Recreation Strategy
 
Sustainable farming practices in India .pptx
Sustainable farming  practices in India .pptxSustainable farming  practices in India .pptx
Sustainable farming practices in India .pptx
 
Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024Artificial Reefs by Kuddle Life Foundation - May 2024
Artificial Reefs by Kuddle Life Foundation - May 2024
 
ppt on beauty of the nature by Palak.pptx
ppt on  beauty of the nature by Palak.pptxppt on  beauty of the nature by Palak.pptx
ppt on beauty of the nature by Palak.pptx
 
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for..."Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...
 
DRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving togetherDRAFT NRW Recreation Strategy - People and Nature thriving together
DRAFT NRW Recreation Strategy - People and Nature thriving together
 
Daan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like itDaan Park Hydrangea flower season I like it
Daan Park Hydrangea flower season I like it
 
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptxAGRICULTURE Hydrophonic FERTILISER PPT.pptx
AGRICULTURE Hydrophonic FERTILISER PPT.pptx
 

2009 06 Department of Energy and Climate Change - Juliet Austin

  • 1. Severn Tidal Power Feasibility StudySevern Tidal Power Feasibility Study Severn Estuary Forum 2009Severn Estuary Forum 2009 Juliet Austin – Environmental workstream lead, STP study,Juliet Austin – Environmental workstream lead, STP study, Department of Energy & Climate ChangeDepartment of Energy & Climate Change
  • 2. Background: Two-year Government Feasibility study • Government decision in response to Sustainable Development Commission’s 2007 report ‘Turning the Tide’ and increasing UK need for renewable energy • To enable Government to decide whether it could support tidal power scheme in the Severn Estuary, and if so, on what terms? • 10 long-listed options – 5 shortlisted after 2009 public consultation • 3-5 year planning and, if consented, 5-10 year construction periods • Issues being addressed: - strategic case for Severn power compared with alternatives, and in what timescale (2020/2050…?) - impacts and benefits, and balance between the two? - costs and risks, who bears them, legal compliance - preferred scheme/s? Multiple options under consideration
  • 3. Map of 10 originally- proposed options
  • 4. 5 Short-listed schemes … Following 2009 public consultation… Beachley Barrage (625 MW, £2.3bn construction cost) Shoots Barrage (1.05 GW, £3.2bn) Cardiff-Weston Barrage (8.6 GW, £20.9bn) Welsh Fleming Lagoon (1.36 GW, £4bn) Bridgwater Bay Lagoon (1.36 GW, £3.8bn cost) … individually, and some potentially in combination
  • 6. Decisions next year • Advice to ministers April 2010, subject to election • Public consultation (in addition to one in Jan-April 09) • Decision late 2010 – either: - to offer package of support for preferred scheme/s to go ahead, and move to full feasibility work leading to planning application OR - to wait until uncertainties are clearer, and potentially for new technologies to be deployable in the Severn OR - not to support a scheme
  • 7. Public consultation Issues for consultation – Jan-April 2009 1. Shortlist of scheme options 2. Scope of Strategic Environmental Assessment (SEA) 3. Scope of overall work of feasibility study What replies did we get? Good response – over 730 replies: • Lots of views, full range of views • How assessing environmental impact? • Short-listing – questions on why and how • Regional economic DTZ report – assumptions made?
  • 8. Government response • Explains how scheme options are being considered • Confirms shortlist of 5 schemes for impact assessment • Confirms £534,000 funding for 3 new Severn Estuary technology schemes (SETS): - Atkins/Rolls Royce: low head barrage - Severn Tidal Fence Consortium – tidal stream - VerdErg: tidal stream array • ‘Feedback loop’ – apply learning and shortlist SETS and non-shortlisted schemes if feasibility study criteria met • Confirm SEA scope, with minor changes • Peer review of DTZ study
  • 9. Non short-listed Schemes Apply learning and short-list if feasibility criteria are met Embryonic Schemes Develop and assess via SETS. Short-list if feasibility criteria are met. Consider in study conclusions if not. Short-listed schemes Feasibility study conclusions Developing evidence base/ optimisation of scheme design and operation Consideration of scheme options – feedback loop
  • 10. Embryonic technologies 3 schemes being funded: less environmentally damaging/cost effective? Low head barrage – Rolls Royce/Atkins – ‘low head’ barrage with new types of turbine than traditional barrage design – Draws on both tidal stream and range technology – Tides held back for less time = should reduce potential impact on intertidal/fish Severn tidal fence – Severn tidal fence Consortium - Tidal stream array - Does not hold back water to generate electricity – turbines use movement of water rather than height difference Severn tidal fence - VerdErg - Radical new fence design using tidal stream technology – water passes through tubes that in turn drive turbines - Minimal moving parts – potentially less damage to fish and intertidal habitat
  • 11. Wider context • Government’s Low-carbon Transition Plan and Renewable Energy Strategy • Aim: 40% low carbon electricity, 30% renewables by 2020 - renewable electricity - mainly offshore wind - Severn tidal power?? Depends on wind – plus cost of energy, certainties, impacts, cost and risk • Longer term: - 80% decarbonisation electricity supply by 2050. Demand will rise - include mix of renewables, nuclear, carbon capture and storage - Severn tidal power?? More work needed on longer term, also on Severn power options
  • 12. Work areas… Economic & Commercial • Strategic and economic case • Impact assessment • Risk assessment and risk management • Subsidy mechanism, public role & costs, delivery timescale • Transfer of risk – public vs private? • Timing implications • Cost – environment, compensatory measures • Affordability / impact on consumers • Regional economic impact
  • 13. Environmental studies (more detail later) • Gathering evidence for Strategic Environmental Assessment (SEA) of environmental and regional impacts – report in 2010 • Impacts on flooding, birds, fish, other habitats and species, water quality, geomorphology (shape of estuary and moving sediments) • Series of technical workshops in the autumn comprising specialists to advise on the SEA studies • Environmental legislation – can we comply? Studies include Habitats Directive, Water Framework Directive • Ecosystem valuation report – to illustrate the value of the environment to society, in monetary terms • All part of consultation in 2010
  • 14. Technical & Engineering - Optimisation of shortlisted barrages and lagoons – getting best out of options against different feasibility study objectives (cost, environmental impact, amount of energy) - Mitigation against environmental damage: cross-checking against SEA impacts - Grid Study - Supply Chain Study - Severn Estuary Embryonic Technology Schemes assessment
  • 15. Regional impact assessment • Commissioned independent peer reviewer to look at DTZ report (strategic-level assessment of economic and social impact) in light of public consultation comments • Conclusions of review expected this Autumn • SEA, supply chain study and ecosystems valuation work contribute to picture on regional impact • Will take a view on whether more work is necessary after peer review
  • 16. • Regulatory overview: assessment of compliance with relevant regulations and policies • Assessment of various potential consenting procedures • Analysis of the methodology of consenting compensatory habitats • Analysis of risk and who bears it Consenting Route / Risk Analysis Consenting Compensatory Habitats Regulatory Overview Timeline Planning And Consents
  • 17. Engaging stakeholders & public • Public consultation Jan-April 2009 • Regular stakeholder meetings, multilateral and bilateral • SEA workshops for technical experts • Sciencewise public dialogue sessions: – Intended to provide early view on priority issues for people and how best to communicate information in the consultation – Small scale meetings for invited members of the public • Information on DECC website and regular e-mail bulletins • Encouraging organisations to communicate to your stakeholders • Public consultation (likely to be in 2010) – Include public meetings on both sides of the Estuary
  • 18. Environmental studies (more detail) • Strategic Environmental Assessment (SEA) – high-level social and environmental impacts – a requirement of large project plans. Majority of scientific evidence base. • Pre-consultation – high-level. May09 – Jan10 – more detailed. • Engaging stakeholders: Decc environmental workstream (Environment Agency, Natural England, Countryside Council for Wales, Defra, Welsh Assembly Govt), SEA Steering Group (NGOs, regional interests incl. Bristol Port), individual stakeholder meetings
  • 19. High level environmental issues • Environmental benefit - annual saving of up to 11Mt CO2. • Range of effects on estuarine, marine and freshwater ecosystems. • Studies on the value of the services they provide – eg fishing, flood defence, aggregates. • Severn Estuary, River Wye and River Usk (and beyond) – protected international importance for their biodiversity. • Compliance with Habitats Directive, Water Framework Directive, other environmental legislation, policies. • Uncertainty in results given short timescales, whether desk or field-based, different specialist opinions.
  • 20. Impacts? Hydraulics and geomorphology • H&G: Shape/ structure of estuary, currents, sediment movements • High tidal range = complicated environmental system • Sediment deposition in channels, build up on foreshore or erosion, flood risk? • Estuary is extreme high energy environment. • Removing energy changes environment. • Understanding physical response drives many other topics – water quality, flooding, biodiversity; affects engineering • Looking at range of potential complex physical scenarios
  • 21. Other impacts? • Reduced tidal range – loss of salt marsh and mudflat habitats. Effects on habitats and their value as flood defence? • Flood risk? • Birds – displacement, loss of birds from Severn, national effects? • Fish and fishing – declines and/or local extinctions? • Water quality – salinity, pollutants, temperature. • Other sea users – aggregate, other energy production, tourism and recreation. • Historic environment/seascape? • Navigation?
  • 22. Environmental studies - SEA SEA ENVIRONMENTAL REPORT Physico-Chemical THEME Society & Economy THEME Landscape & Historic Env THEME Biodiversity THEME Carbon Footprint, Resources & Waste THEME Hydraulics and Geomorphology Marine Water Quality Freshwater Env. & Assoc. Interfaces Flood Risk and Land Drainage Society &Economy Navigation Other Sea Uses Noise & Vibration Marine Ecology Ornithology Migratory & Estuarine Fish Terrestrial & Fresh. Ecology Historic Environment Landscape and Seascape Carbon Footprinting Resources and Waste
  • 23. Habitats Directive compliance and compensatory measures • Following steps laid down in EU Regulations • Process: Scoping and Appropriate Assessment on designated sites, assessing for likely significant adverse effects. If so, look to mitigate. Is the project of IROPI? If so, determine feasibility of providing compensatory measures. • Investigating feasibility / cost of different types of compensatory measures. E.g. managed realignment for lost mudflat/saltmarsh, impacts on fish. • Do not yet know enough to say whether compensatory measures possible for any of the habitats/species lost under short-listed schemes.
  • 24. 2010: Phase 2 public consultation on recommendations Scheme assessment: Individual costs, benefits, risks, impacts of each scheme against key areas identified in study objectives (regional, economic, environmental, regulatory requirements, energy and climate change goals) using quantitative and qualitative data from evidence gathered across feasibility study Decision by Ministers: Stop, wait, go ahead? Response to phase 2 consultation 2009/10 - environment: Results of SEA studies, impact on environmental legislation, ecosystem valuation Strategic case Results of Severn Embryonic Technology Schemes
  • 25. Contact information – getting in touch Web: www.decc.gov.uk/severntidalpower Email: severntidalpowerunit@decc.gsi.gov.uk

Editor's Notes

  1. This slide shows how 3 different groupings of scheme options will be considered.: Centre – position for short-listed schemes. Still under consideration what these are, following consultation On right – position just described for SETS-support schemes On left – intend to introduce a feedback loop for non-short-listed schemes to check that feasibility assessments made now are still valid.
  2. Position as set out in consultation paper. Won’t go into detail on assessment process, though may want to come back to this in discussion. Neither reef nor fence proposed for shortlist, nor offshore lagoons (cost of energy assessed as £269-317 MWh against £200 threshold) Considering short-list in light of responses, including Atkins report. Following slides assume neither reef or fence is short-listed, on a without prejudice basis.
  3. [NB: All the deliverables will go through multiple iterations (as expressed by the arrows) and are all due in Nov 09. Workstream reviews are pencilled in for June 09 and September 09 before taking delivery in November.] Regulatory Overview: Assessment of pertinent national and EU regulations, acts, laws, etc. This includes our ability to meet, costs of meeting, risk of not meeting, including areas where optimisation could ease compliance with regulations and assessment framework (scheme feasibility/desirability). It also includes procedure overview on how we meet the regs so as to de-risk for developers (proposal-specific). Final document both a deliverable in its own right and feeds into second Public Consultation. Will include scope for P&C work in Phase 3. At present, we have identified over 70 regulations in this work covering environmental, regional, devolutionary and decommissioning aspects of the projects. Memo on Consenting Options: Assessment of various potential consenting procedures, including NPS, IPC, Bills, etc. Includes potential procedure (proposal-specific). Timeline for Consenting Process: Analysing the different timescales and deliverable points for various consenting routes (includes time needed for regulations not covered within the consenting processes) Regulatory Risk Analysis: Analysing the risks of various regulations and consenting routes, analysing the impact on STP of navigating/manoeuvring (might be rolled into the memo on consenting options…) Memo on Consenting Compensatory Habitats: As it says on the tin – relies heavily on regulatory overview and consenting route selection. (Potentially significant impacts on timeline and 2020 targets.)
  4. In 2007 Government asked the SDC to investigate tidal power opportunities across the UK. Wilst the Commission also considered other UK estauaries (mersey wyre thames) its report concluded, with conditions (full compliance with European directives on habs and birds) that there is a strong case for a sustainable Severn barrage. In response Government launched a 2-year feasibility study in Jan 2008 to investigate whether Government could support a severn scheme and if so, on what terms. If, following the feasibility study conclusion the decision was to proceed with a STP project it would still be subject to a full process of planning and consent-grating before construction could begin. This will probably take 3-5 years and construction a further 5-7 years depending on the scheme or combination of schemes selected.