SlideShare a Scribd company logo
Railway Engineering
Submitted by:
Akshay Kaushal (110134)
Jaspreet Singh (110138)
https://www.youtube.com/watch?v=pvg3e2P2TAo
History of Indian Railway
Railway Engineering
• It is a branch of civil engineering concerned with the design,
construction, maintenance, and operation of railways.
• Railway engineering includes elements of civil, mechanical,
industrial, and electrical engineering.
• Railway engineers handle the design, construction, and operation
of railroads and mass transit systems that use a fixed guideway
(such as light rail or even monorails).
• Typical tasks would include determining horizontal and vertical
alignment design, station location and design, construction cost
estimating, and establishment of signaling & controlling system.
• Railroad engineers can also move into the specialized field of
train dispatching which focuses on train movement control.
Section of Permanent Way
RAIL GAUGE
The gauge of a railway track is defined as the
clear minimum perpendicular distance between
the inner faces of the two rails.
Dimension of gauges
1. Broad Gauge(BG) 1676mm(5’6”)
2. Standard Gauge(SG) 1435mm
3. Metre Gauge(MG) 1000mm
4. Narrow Gauge(NG) 762mm(2’6”)
5. Light Gauge 610mm
Coning of Wheels
• Coning of wheels – The distance between the inside edges of
wheel flanges is generally kept less than the gauge. Gap is
about 38 mm on Either side. Normally the tyre is absolutely
ahead centre on the head of the rail, as the wheel is coned to
keep it in this central position automatically. These wheel are
coned at a slope
• Theory of coning:- On a level track, as soon as the axle moves
towards one rail, the diameter of the wheel tread over the rail
increases, while It decreases over the other rail. This prevents
to further movement And axle retreats back to its original
position (with equal dia or both rails and equal pressure on
both rails).
Coning of Wheel on Level-track
RAILS
The high carbon rolled steel sections, which are laid
end-to-end, in two parallel lines over sleepers to
provide continuous and leveled surface for the trains
to move and for carrying axle loads of the rolling
stock are called rails.
`
Functions of the rails:
To provide continuous and level surface for the
movement of trains with minimum friction with
steel wheels of the rolling stock;
Provide strength, durability and lateral guidance
to the track;
Transmit the axle loads to sleepers which transfer
the same load to the underlying ballast and
formation;
Bear the stresses developed due to heavy vertical
loads, breaking forces and temperature variance.
RAILS
Types of rails:
1. Double Headed Rails (DH Rails)
2. Bull Headed Rails (BH Rails)
3. Flat-footed Rails (FF Rails)
Length of Rails
On Indian Railways the standard lengths are the following:
Length = 12.80 m. (42 ft.) for BG (say 13 m) and
Length = 11.89 m. (39 ft.) for MG (say 12 m)
Corrugated or Roaring Rails
In certain places, head of rails are found to be
corrugated rather than smooth and straight,
when the vehicles pass over such rails, a roaring
sound is created which is intense enough to be
unpleasant.
Hogged Rails
Due to battering action of wheels over the end of the rails, the
rails get bent down and get deflected at the ends. These rails are
called hogged rails.
Measures taken to rectify the hogged rails are:
1. Cropping
2. Replacing
3. Welding
4. Dehogging
Reason of Hogging!
https://www.youtube.com/watch?v=9njqDgjIcWQ
Kinks In Rails
When the ends of adjoining rails move slightly out of position,
“shoulders” or “kinks” are formed.
Measures taken to rectify kinks in rails:
1. By correcting alignment at joints and at curved locations.
2. Proper packing of joints.
3. Proper maintenance of the track periodically in repect of
cross levels, gauge, alignment, welding of worn out portions
etc.
Buckling of Rails
Buckling means the track has gone out of its original position or
alignment due to prevention of expansion of rails in hot weather
on account of temperature variations.
Damaged Rails
These are the rails which should be removed on
account of their becoming unsafe for a railway
track.
Rail Features
• Crushed Heads
• Square or Angular Break
• Split Heads
• Split Web
• Horizontal Fissures
• Transverse Fissures
• Flowing Metal in Heads
• Horizontal Cracks
Crushed Head
Split Heads
Horizontal and Transverse Fissures
Flowing Metal in Heads
Rail Joints
• Supported Rail Joint
• Suspended Rail Joint
• Bridge Joint
• Base Joint
• Welded Rail Joint
• Staggered or Broken Joint
• Square or Even Joint
• Compromise Joint
• Insulated Joint
• Expansion Joint`
Rail Joint
Insulated Joint
Expansion Joint
Creep of Rails
Creep is defined as the longitudinal movement
of the rail with respect to the sleepers.
Defects of Creep
(i) Sleepers move out of position thereby the rail gauge.
(ii) Position of points and crossings are disturbed.
(iii) Interlocking mechanism gets
disturbed.
Remedies or Prevention of Creep
• Pulling back of rails
• Provision of Anchors or Anticreepers.
• Use of steel sleepers.
Anticreeper
Sleepers
Sleepers are the transverse ties that are laid to
support the rails. They transmit wheel load from
the rails to the ballast.
Classification of sleepers
(i) Wooden sleeper
(ii) Metal sleeper
Cast iron sleeper
Steel sleeper
(iii) Concrete sleeper
Reinforced concrete
Sleeper (R.C.C)
Prestressed Concrete
Sleeper .
Wooden Sleepers
• Hard wood such as, sal and teak
• Soft wood such as, chir and deodar
Metal Sleepers
Concrete Sleepers
Sleeper Density
Sleeper density is the number of sleepers Per
rail length. It is specified as (M+x) or (N+x),
where M or N is the length of the rail in meters
and x is a number that varies according to
factors such as axle load, speed, type & section
of the rail etc.
It varies in India from M+4 to M+7 for main
tracks.
Track Fittings & Fastenings
• Fish plates
• Spikes
– Dog spikes
– Screw spikes
– Round spikes
– Standard spikes
– Elastic spikes
• Bolts
– Dog or Hook bolt
– Fish bolt
– Rag bolt
– Fang nut and bolt
• Keys
– Wooden key for C.I. Chair
– M.S. key and steel trough
sleepers
– Stuart’s key
– Morgan key
– Cotter and tie bars
• Chairs
– Cast steel chairs
– Mild steel and Cast Iron
Slide Chairs
• Blocks
– Heel blocks
– Distance blocks
– Crossing blocks
– Check blocks
• Plates
– Bearing Plates
– Saddle Plates
Track Fittings & Fastenings contd..
Fish Plate
Dog Spike
Screw spikes
Chair
Bearing Plate
Ballast
To provide structural support for
the track, holding it in good line
and surface
To distribute the load evenly to the
subballast and subgrade and thus
help to provide stability
Provide for drainage
Ballast in railroad terminology is durable granular material placed between
the crosstie and the sub ballast to hold the track in line and grade.
The primary purposes of ballast are:
BALLAST
SUBBALLAST SUBGRADE
BALLAST SECTION
Types of Ballast
• Broken Stone
• Gravel or River Pebbles or Shingle
• Ashes or Cinders
• Sand
• Mooram
• Kankar
• Brick Ballast
• Blast Furnace Slag
• Selected Earth
Ballast Size
• For wooden sleepers = 5.1 cm
• For steel sleepers = 3.8 cm
• For under switches & crossings = 2.54 cm
Points & Crossings
• Points and crossings provide flexibility of
movement by connecting one line to another
according to requirements.
• They also help for imposing restrictions over
turnouts which necessarily retard the
movements.
• From safety aspect, it is also important as points
and crossings are weak kinks or points in the
track and vehicles are susceptible to derailments
at these places.
Turnouts
• It’s the simplest combination of points and crossings which
enables one track either a branch line or a siding, to take
off from another track.
• Parts of a turnout:
– A pair of points or switches
– A pair of stockrails
– A Vee crossing
– Two check rails
– Four lead rails
– Switch tie plate
– Studs or stops
– Bearing plates, slide chairs, stretcher bars etc.
– For operating the points – rods, cranks, levers etc.
– For locking system – locking box, lock bar, plunger bar etc.
Types of Switches
Crossings
A crossing or a frog is a device which provides two flangeways
through which the wheels of the flanges may move, when two
rails intersect each other at an angle.
Acute Angle Crossing
Diamond Crossing
Square Crossing
Track Junctions
• Turnouts
• Symmetrical split
• Three throw switch
• Double turnout or Tandem
• Diamond crossing
• Cross overs
• Single slip and double slip
• Gauntlet track and ladder tracks
• Temporary diversion
• Triangle
• Double junctions
Turnout
Symmetrical split
https://www.youtube.com/watch?v=L_wOPY5Pu-A
How Railway Track Changes
Signalling
It consists of the systems, devices and means by
which trains are operated efficiently and tracks
are used to maximum extent, maintaining the
safety of the passengers, the staff and the rolling
stock.
On the basis of Operating
Characteristics:
• Detonating Signals (Fog or audible signals)
• Hand signals (Visual Indication signals)
• Fixed signals (Visual Indication signals)
Detonating Signal
Hand Signals
Fixed Signals
• Stop or Semaphore type Signals
• Warner Signals
• Shunting Signals (Disc or Ground Signals)
• Coloured-light Signals
On the basis of Functional
Characteristics:
Semaphore type signals
Warner Signals
Shunting Signals
Coloured-light Signals
• Reception Signals
– Outer signals
– Home signals
• Departure Signals
– Starter
– Advance Starter
On the basis of Locational
Characteristics:
Departure Signals
• Repeater or Co-acting signals
• Routing Signals
• Calling on signals
• Point indicator
• Modified lower quadrant semaphore signal
• Miscellaneous signals
On the basis of Special Characteristics:
High Speed Bullet Train
https://www.youtube.com/watch?v=2-_yS60NhyM
THANK YOU

More Related Content

What's hot

Points and crossings
Points and crossingsPoints and crossings
Points and crossings
srinivas2036
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
RAMPRASAD KUMAWAT
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail Creep
RAMPRASAD KUMAWAT
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
Mani Vel
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
Aaquib ansari
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
Arbaz Kazi
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast
T.Naga Anusha
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
Gowtham G
 
Railway Engineering: Points and crossings
Railway Engineering: Points and crossingsRailway Engineering: Points and crossings
Railway Engineering: Points and crossings
Bathla Tuition Centre
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gauge
Mani Vel
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
KHUSHBU SHAH
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failures
Sunil Kumar Meena
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
Deven Diran
 
Points and crossing
Points and crossingPoints and crossing
Points and crossing
Akash Patel
 
Railway Signalling by Aditi Shah
Railway Signalling by Aditi ShahRailway Signalling by Aditi Shah
Railway Signalling by Aditi Shah
Aditi Shah
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
Mani Vel
 
Railway engineering part3
Railway engineering part3Railway engineering part3
Railway engineering part3
GARRE RAVI KUMAR
 
Highway Engineering Introduction: Lecture 1
Highway Engineering  Introduction: Lecture 1Highway Engineering  Introduction: Lecture 1
Highway Engineering Introduction: Lecture 1
Raghubir Singh
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
Irfan Nasir
 

What's hot (20)

Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Coning of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail CreepConing of Wheels in Railways & Rail Creep
Coning of Wheels in Railways & Rail Creep
 
11.track junctions and layouts
11.track junctions and layouts11.track junctions and layouts
11.track junctions and layouts
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
 
Sleepers and Ballast
Sleepers and Ballast Sleepers and Ballast
Sleepers and Ballast
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
 
Railway Engineering: Points and crossings
Railway Engineering: Points and crossingsRailway Engineering: Points and crossings
Railway Engineering: Points and crossings
 
2.railway track gauge
2.railway track gauge2.railway track gauge
2.railway track gauge
 
Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failures
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
 
Points and crossing
Points and crossingPoints and crossing
Points and crossing
 
Railway Signalling by Aditi Shah
Railway Signalling by Aditi ShahRailway Signalling by Aditi Shah
Railway Signalling by Aditi Shah
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
 
Railway engineering part3
Railway engineering part3Railway engineering part3
Railway engineering part3
 
3rd unit
3rd unit3rd unit
3rd unit
 
Highway Engineering Introduction: Lecture 1
Highway Engineering  Introduction: Lecture 1Highway Engineering  Introduction: Lecture 1
Highway Engineering Introduction: Lecture 1
 
Defects in rails. Railway Engineering
Defects in rails. Railway EngineeringDefects in rails. Railway Engineering
Defects in rails. Railway Engineering
 

Viewers also liked

Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
srinivas2036
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
sharda university
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.
ashrafdgrt
 
Unit 1. introduction to Railway Engineering
Unit 1. introduction to Railway EngineeringUnit 1. introduction to Railway Engineering
Unit 1. introduction to Railway Engineering
nkocet
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
Latif Hyder Wadho
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway Engineering
Latif Hyder Wadho
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
Prem Prakash Kumar
 
Presentation on indian railway
Presentation on indian railwayPresentation on indian railway
Presentation on indian railway
Khusro_khan
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
jmaghade99
 
railway presentation Ppt
railway presentation Pptrailway presentation Ppt
railway presentation Ppt
Sachin Singh
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
Mani Vel
 
Meter gauge, broad gauge and narrow gauge
Meter gauge, broad gauge and narrow gaugeMeter gauge, broad gauge and narrow gauge
Meter gauge, broad gauge and narrow gaugeParv Garg
 
Indian Railways ppt.
Indian Railways ppt.Indian Railways ppt.
Indian Railways ppt.
vinaybidarimath
 
RAILWAY ENGINEERING
RAILWAY ENGINEERINGRAILWAY ENGINEERING
RAILWAY ENGINEERING
fye7884
 
03 superelevation and spiral curves
03 superelevation and spiral curves03 superelevation and spiral curves
03 superelevation and spiral curves
Vivek Kumar
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Shanmugaraj M
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 

Viewers also liked (20)

Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)Introduction to railway engineering (T.E 2)
Introduction to railway engineering (T.E 2)
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.
 
Unit 1. introduction to Railway Engineering
Unit 1. introduction to Railway EngineeringUnit 1. introduction to Railway Engineering
Unit 1. introduction to Railway Engineering
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway Engineering
 
Railway track:An Introduction
Railway track:An IntroductionRailway track:An Introduction
Railway track:An Introduction
 
Presentation on indian railway
Presentation on indian railwayPresentation on indian railway
Presentation on indian railway
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
railway presentation Ppt
railway presentation Pptrailway presentation Ppt
railway presentation Ppt
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
 
Left hand turnout
Left hand turnoutLeft hand turnout
Left hand turnout
 
Meter gauge, broad gauge and narrow gauge
Meter gauge, broad gauge and narrow gaugeMeter gauge, broad gauge and narrow gauge
Meter gauge, broad gauge and narrow gauge
 
Indian Railways ppt.
Indian Railways ppt.Indian Railways ppt.
Indian Railways ppt.
 
RAILWAY ENGINEERING
RAILWAY ENGINEERINGRAILWAY ENGINEERING
RAILWAY ENGINEERING
 
03 superelevation and spiral curves
03 superelevation and spiral curves03 superelevation and spiral curves
03 superelevation and spiral curves
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 

Similar to Railway engineering

1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
MayuriPatel90
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
MuhammadAdeel269
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport Engineering
Emaan Sharma
 
railwaypartPPT
railwaypartPPTrailwaypartPPT
railwaypartPPT
SamratRoy57
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
dhara dattani
 
Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1
AJEETH B
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
TURUMELLAVIJAYAGOWRI
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
TVijayaGowri
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
Dnyaneshwar More
 
Points and crossings.ppt
Points and crossings.pptPoints and crossings.ppt
Points and crossings.ppt
samatha6
 
P.way
P.wayP.way
P.way
vaignan
 
Railway track
Railway trackRailway track
Railway track
Dewang Agrawal
 
Escalators uol (1)
Escalators uol (1)Escalators uol (1)
Escalators uol (1)
Hashimammar
 
Railway and highways, Airways material.pptx
Railway and highways, Airways material.pptxRailway and highways, Airways material.pptx
Railway and highways, Airways material.pptx
Rajuyadav437367
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
ssuser75acc8
 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
ishwar dhakad
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
Bathla Tuition Centre
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
hiranrathva
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
Arun G
 
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
Dr. BASWESHWAR JIRWANKAR
 

Similar to Railway engineering (20)

1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway and Airport Engineering
Railway and Airport EngineeringRailway and Airport Engineering
Railway and Airport Engineering
 
railwaypartPPT
railwaypartPPTrailwaypartPPT
railwaypartPPT
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
 
Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
 
Points and crossings.ppt
Points and crossings.pptPoints and crossings.ppt
Points and crossings.ppt
 
P.way
P.wayP.way
P.way
 
Railway track
Railway trackRailway track
Railway track
 
Escalators uol (1)
Escalators uol (1)Escalators uol (1)
Escalators uol (1)
 
Railway and highways, Airways material.pptx
Railway and highways, Airways material.pptxRailway and highways, Airways material.pptx
Railway and highways, Airways material.pptx
 
lecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdflecturenote_1888016911chapter-3 track.pdf
lecturenote_1888016911chapter-3 track.pdf
 
Railway track design ppt 2018
Railway track design ppt 2018Railway track design ppt 2018
Railway track design ppt 2018
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
 
Points and crossings ( special assigments )
Points and crossings ( special assigments )Points and crossings ( special assigments )
Points and crossings ( special assigments )
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
 
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-II INFRASTRUCTURE ENGINEERING BTCVC702
 

More from Akshay D Nicator

The Effect of Rise Husk Ash on Strength and Permeability of Concrete
The Effect of Rise Husk Ash on Strength and Permeability of ConcreteThe Effect of Rise Husk Ash on Strength and Permeability of Concrete
The Effect of Rise Husk Ash on Strength and Permeability of Concrete
Akshay D Nicator
 
Energy Conservation Through Green Buildings
Energy Conservation Through Green BuildingsEnergy Conservation Through Green Buildings
Energy Conservation Through Green Buildings
Akshay D Nicator
 
Paperspace in AutoCAD
Paperspace in AutoCADPaperspace in AutoCAD
Paperspace in AutoCAD
Akshay D Nicator
 
Wind loads
Wind loadsWind loads
Wind loads
Akshay D Nicator
 
An unpayable debt
An unpayable debt An unpayable debt
An unpayable debt
Akshay D Nicator
 
Recycled Concrete Aggregate - A Solid Wealth
Recycled Concrete Aggregate - A Solid WealthRecycled Concrete Aggregate - A Solid Wealth
Recycled Concrete Aggregate - A Solid Wealth
Akshay D Nicator
 
Use of Nanotechnology in Civil Engineering
Use of Nanotechnology in Civil EngineeringUse of Nanotechnology in Civil Engineering
Use of Nanotechnology in Civil Engineering
Akshay D Nicator
 
I Wish We Could Run Away
I Wish We Could Run AwayI Wish We Could Run Away
I Wish We Could Run Away
Akshay D Nicator
 
Manmade Disasters
Manmade DisastersManmade Disasters
Manmade Disasters
Akshay D Nicator
 

More from Akshay D Nicator (9)

The Effect of Rise Husk Ash on Strength and Permeability of Concrete
The Effect of Rise Husk Ash on Strength and Permeability of ConcreteThe Effect of Rise Husk Ash on Strength and Permeability of Concrete
The Effect of Rise Husk Ash on Strength and Permeability of Concrete
 
Energy Conservation Through Green Buildings
Energy Conservation Through Green BuildingsEnergy Conservation Through Green Buildings
Energy Conservation Through Green Buildings
 
Paperspace in AutoCAD
Paperspace in AutoCADPaperspace in AutoCAD
Paperspace in AutoCAD
 
Wind loads
Wind loadsWind loads
Wind loads
 
An unpayable debt
An unpayable debt An unpayable debt
An unpayable debt
 
Recycled Concrete Aggregate - A Solid Wealth
Recycled Concrete Aggregate - A Solid WealthRecycled Concrete Aggregate - A Solid Wealth
Recycled Concrete Aggregate - A Solid Wealth
 
Use of Nanotechnology in Civil Engineering
Use of Nanotechnology in Civil EngineeringUse of Nanotechnology in Civil Engineering
Use of Nanotechnology in Civil Engineering
 
I Wish We Could Run Away
I Wish We Could Run AwayI Wish We Could Run Away
I Wish We Could Run Away
 
Manmade Disasters
Manmade DisastersManmade Disasters
Manmade Disasters
 

Recently uploaded

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 

Recently uploaded (20)

Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 

Railway engineering

  • 1. Railway Engineering Submitted by: Akshay Kaushal (110134) Jaspreet Singh (110138)
  • 3. Railway Engineering • It is a branch of civil engineering concerned with the design, construction, maintenance, and operation of railways. • Railway engineering includes elements of civil, mechanical, industrial, and electrical engineering. • Railway engineers handle the design, construction, and operation of railroads and mass transit systems that use a fixed guideway (such as light rail or even monorails). • Typical tasks would include determining horizontal and vertical alignment design, station location and design, construction cost estimating, and establishment of signaling & controlling system. • Railroad engineers can also move into the specialized field of train dispatching which focuses on train movement control.
  • 5. RAIL GAUGE The gauge of a railway track is defined as the clear minimum perpendicular distance between the inner faces of the two rails.
  • 6. Dimension of gauges 1. Broad Gauge(BG) 1676mm(5’6”) 2. Standard Gauge(SG) 1435mm 3. Metre Gauge(MG) 1000mm 4. Narrow Gauge(NG) 762mm(2’6”) 5. Light Gauge 610mm
  • 7. Coning of Wheels • Coning of wheels – The distance between the inside edges of wheel flanges is generally kept less than the gauge. Gap is about 38 mm on Either side. Normally the tyre is absolutely ahead centre on the head of the rail, as the wheel is coned to keep it in this central position automatically. These wheel are coned at a slope • Theory of coning:- On a level track, as soon as the axle moves towards one rail, the diameter of the wheel tread over the rail increases, while It decreases over the other rail. This prevents to further movement And axle retreats back to its original position (with equal dia or both rails and equal pressure on both rails).
  • 8. Coning of Wheel on Level-track
  • 9. RAILS The high carbon rolled steel sections, which are laid end-to-end, in two parallel lines over sleepers to provide continuous and leveled surface for the trains to move and for carrying axle loads of the rolling stock are called rails. `
  • 10. Functions of the rails: To provide continuous and level surface for the movement of trains with minimum friction with steel wheels of the rolling stock; Provide strength, durability and lateral guidance to the track; Transmit the axle loads to sleepers which transfer the same load to the underlying ballast and formation; Bear the stresses developed due to heavy vertical loads, breaking forces and temperature variance.
  • 11. RAILS Types of rails: 1. Double Headed Rails (DH Rails) 2. Bull Headed Rails (BH Rails) 3. Flat-footed Rails (FF Rails)
  • 12. Length of Rails On Indian Railways the standard lengths are the following: Length = 12.80 m. (42 ft.) for BG (say 13 m) and Length = 11.89 m. (39 ft.) for MG (say 12 m)
  • 13. Corrugated or Roaring Rails In certain places, head of rails are found to be corrugated rather than smooth and straight, when the vehicles pass over such rails, a roaring sound is created which is intense enough to be unpleasant.
  • 14. Hogged Rails Due to battering action of wheels over the end of the rails, the rails get bent down and get deflected at the ends. These rails are called hogged rails. Measures taken to rectify the hogged rails are: 1. Cropping 2. Replacing 3. Welding 4. Dehogging
  • 16. Kinks In Rails When the ends of adjoining rails move slightly out of position, “shoulders” or “kinks” are formed. Measures taken to rectify kinks in rails: 1. By correcting alignment at joints and at curved locations. 2. Proper packing of joints. 3. Proper maintenance of the track periodically in repect of cross levels, gauge, alignment, welding of worn out portions etc.
  • 17. Buckling of Rails Buckling means the track has gone out of its original position or alignment due to prevention of expansion of rails in hot weather on account of temperature variations.
  • 18. Damaged Rails These are the rails which should be removed on account of their becoming unsafe for a railway track.
  • 19. Rail Features • Crushed Heads • Square or Angular Break • Split Heads • Split Web • Horizontal Fissures • Transverse Fissures • Flowing Metal in Heads • Horizontal Cracks
  • 24.
  • 25. Rail Joints • Supported Rail Joint • Suspended Rail Joint • Bridge Joint • Base Joint • Welded Rail Joint • Staggered or Broken Joint • Square or Even Joint • Compromise Joint • Insulated Joint • Expansion Joint`
  • 27.
  • 30. Creep of Rails Creep is defined as the longitudinal movement of the rail with respect to the sleepers.
  • 31. Defects of Creep (i) Sleepers move out of position thereby the rail gauge. (ii) Position of points and crossings are disturbed. (iii) Interlocking mechanism gets disturbed.
  • 32. Remedies or Prevention of Creep • Pulling back of rails • Provision of Anchors or Anticreepers. • Use of steel sleepers. Anticreeper
  • 33. Sleepers Sleepers are the transverse ties that are laid to support the rails. They transmit wheel load from the rails to the ballast.
  • 34. Classification of sleepers (i) Wooden sleeper (ii) Metal sleeper Cast iron sleeper Steel sleeper (iii) Concrete sleeper Reinforced concrete Sleeper (R.C.C) Prestressed Concrete Sleeper .
  • 35. Wooden Sleepers • Hard wood such as, sal and teak • Soft wood such as, chir and deodar
  • 38. Sleeper Density Sleeper density is the number of sleepers Per rail length. It is specified as (M+x) or (N+x), where M or N is the length of the rail in meters and x is a number that varies according to factors such as axle load, speed, type & section of the rail etc. It varies in India from M+4 to M+7 for main tracks.
  • 39. Track Fittings & Fastenings • Fish plates • Spikes – Dog spikes – Screw spikes – Round spikes – Standard spikes – Elastic spikes • Bolts – Dog or Hook bolt – Fish bolt – Rag bolt – Fang nut and bolt • Keys – Wooden key for C.I. Chair – M.S. key and steel trough sleepers – Stuart’s key – Morgan key – Cotter and tie bars • Chairs – Cast steel chairs – Mild steel and Cast Iron Slide Chairs
  • 40. • Blocks – Heel blocks – Distance blocks – Crossing blocks – Check blocks • Plates – Bearing Plates – Saddle Plates Track Fittings & Fastenings contd..
  • 44. Chair
  • 46. Ballast To provide structural support for the track, holding it in good line and surface To distribute the load evenly to the subballast and subgrade and thus help to provide stability Provide for drainage Ballast in railroad terminology is durable granular material placed between the crosstie and the sub ballast to hold the track in line and grade. The primary purposes of ballast are:
  • 48. Types of Ballast • Broken Stone • Gravel or River Pebbles or Shingle • Ashes or Cinders • Sand • Mooram • Kankar • Brick Ballast • Blast Furnace Slag • Selected Earth
  • 49. Ballast Size • For wooden sleepers = 5.1 cm • For steel sleepers = 3.8 cm • For under switches & crossings = 2.54 cm
  • 50. Points & Crossings • Points and crossings provide flexibility of movement by connecting one line to another according to requirements. • They also help for imposing restrictions over turnouts which necessarily retard the movements. • From safety aspect, it is also important as points and crossings are weak kinks or points in the track and vehicles are susceptible to derailments at these places.
  • 51. Turnouts • It’s the simplest combination of points and crossings which enables one track either a branch line or a siding, to take off from another track. • Parts of a turnout: – A pair of points or switches – A pair of stockrails – A Vee crossing – Two check rails – Four lead rails – Switch tie plate – Studs or stops – Bearing plates, slide chairs, stretcher bars etc. – For operating the points – rods, cranks, levers etc. – For locking system – locking box, lock bar, plunger bar etc.
  • 52.
  • 53.
  • 55. Crossings A crossing or a frog is a device which provides two flangeways through which the wheels of the flanges may move, when two rails intersect each other at an angle.
  • 59. Track Junctions • Turnouts • Symmetrical split • Three throw switch • Double turnout or Tandem • Diamond crossing • Cross overs • Single slip and double slip • Gauntlet track and ladder tracks • Temporary diversion • Triangle • Double junctions
  • 63. Signalling It consists of the systems, devices and means by which trains are operated efficiently and tracks are used to maximum extent, maintaining the safety of the passengers, the staff and the rolling stock.
  • 64. On the basis of Operating Characteristics: • Detonating Signals (Fog or audible signals) • Hand signals (Visual Indication signals) • Fixed signals (Visual Indication signals)
  • 68. • Stop or Semaphore type Signals • Warner Signals • Shunting Signals (Disc or Ground Signals) • Coloured-light Signals On the basis of Functional Characteristics:
  • 73. • Reception Signals – Outer signals – Home signals • Departure Signals – Starter – Advance Starter On the basis of Locational Characteristics:
  • 75. • Repeater or Co-acting signals • Routing Signals • Calling on signals • Point indicator • Modified lower quadrant semaphore signal • Miscellaneous signals On the basis of Special Characteristics:
  • 76. High Speed Bullet Train https://www.youtube.com/watch?v=2-_yS60NhyM