Railway Track Gauge
Mr MANIVEL M
FACULTY,CIVIL ENGINEERING
SCHOOL OF TECHNOLOGY
PANDIT DEENDAYAL PETROLEUM UNIVERSITY
GANDHINAGAR
Introduction
• Gauge is defined as the minimum distance
between inner face two rails. Indian Railways
follows this standard practice and the gauge is
measured as the clear minimum distance
between the running faces of the two rails as
shown in Fig. 2.1.
TYPES OF GAUGES IN INDIA
The different gauges in India are of the following
these types :-
1. Broad gauge (1676),
2. Meter gauge (1000),
3. Narrow gauge (762 mm & 610 mm).
In India, efforts are being made to convert all N.G. and M.G. lines
to B.G. lines on important sections as and when funds are
available.
Permanent Way
Permanent way: The combination of rails, fitted
on sleepers with the help of fixtures and
fastenings and resting on ballast and subgrade
is called the railway track or permanent way.
Choice of Gauge
• The choice of gauge is very limited, as each
country has a fixed gauge and all new railway
lines are constructed to adhere to the
standard gauge. However, the following
factors theoretically influence the choice of
the gauge.
1.Cost Considerations:
There is only a marginal increase in the cost of the track if
a wider gauge is adopted. In this connection, the
following points are important.
(a) There is a proportional increase in the cost of
acquisition of land, earthwork, rails, sleepers, ballast,
and other track items when constructing a wider gauge.
(b) The cost of building bridges, culverts, and tunnels
increases only marginally due to a wider gauge.
(c) The cost of constructing station buildings, platforms,
staff quarters, level crossings, signals, etc. associated
with the railway network is more or less the same for all
gauges.
(d) The cost of rolling stock is independent of the gauge of
the track for carrying the same volume of traffic.
2. Traffic Considerations:
The volume of traffic depends upon the size of
wagons and the speed and hauling capacity of the
train.
(a) As a wider gauge can carry larger wagons and
coaches, it can theoretically carry more traffic.
(b) A wider gauge has a greater potential at higher
speeds, because speed is a function of the
diameter of the wheel, which in turn is limited by
the width of the gauge.
(c) The type of traction and signalling equipment
required are independent of the gauge.
3. Physical Features of the Country:
It is possible to adopt steeper gradients and
sharper curves for a narrow gauge a compared
to a wider gauge.
4. Uniformity of Gauge:
The existence of a uniform gauge in a country
enables smooth, speedy, and efficient
operation of trains. Therefore a single gauge
should be adopted irrespective of the minor
advantages of a wider gauge and the few
limitations of a narrower gauge.
Problems Caused by Change of Gauge
The need for uniformity of gauge has been
recognized by all the advanced countries of
the world. A number of problems have
cropped up in the operation of Indian Railways
because of the use of three gauges. The ill
effects of change of gauge (more popularly
known as break of gauge) are numerous;
some of these are enumerated here.
1.Inconvenience to Passengers:
Due to change of gauge, passengers have to change
trains mid-journey along with their luggage, which
causes inconvenience such as the following.
(a) Climbing stairs and crossing bridges
(b) Finding seats in the compartments of the later
trains
(c) Missing connections with the later trains in case
the earlier train is late
(d) Harassment caused by porters
(e) Transporting luggage
(f) Uncertainty and delay in reaching the destination
2. Difficulty in Trans-shipment of Goods:
Goods have to be trans-shipped at the point where
the change of gauge takes place. This causes the
following problems.
(a) Damage to goods during trans-shipment.
(b) Considerable delay in receipt of goods at the
destination.
(c) Theft or misplacement of goods during trans-
shipment and the subsequent claims.
(d) Non-availability of adequate and specialized
trans-shipment labour and staff, particularly
during strikes.
3. Inefficient Use of Rolling Stock:
As wagons have to move empty in the direction
of the trans-shipment point, they are not fully
utilized. Similarly, idle wagons of one gauge
cannot be moved on another gauge.
4. Hindrance to Fast Movement of Goods and
Passenger Traffic:
Due to change in the gauge, traffic cannot move
fast which becomes a major problem
particularly during emergencies such as war,
floods, and accidents.
5. Additional Facilities at Stations and Yards:
(a) Costly sheds and additional facilities need to be
provided for handling the large volume of goods
at trans-shipment points.
(b) Duplicate equipment and facilities such as yards
and platforms need to be provided for both
gauges at trans-shipment points.
6. Difficulties in Balanced Economic Growth:
• The difference in gauge also leads unbalanced
economic growth. This happens because
industries set up near MG/NG stations cannot
send their goods economically and efficiently to
areas being served by BG stations.
7. Difficulties in Future Gauge Conversion
Projects:
Gauge conversion is quite difficult, as it requires
enormous effort to widen existing tracks.
Widening the gauge involves heavy civil
engineering work such as widening of the
embankment, the bridges and tunnels, as well
as the tracks; additionally, a wider rolling stock
is also required. During the gauge conversion
period, there are operational problems as well
since the traffic has to be slowed down and
even suspended for a certain period is order to
execute the work.
Uni-gauge Policy of Indian Railways
The multi-gauge system is not only costly and
cumbersome but also causes serious
bottlenecks in the operation of the Railways
and hinders the balanced development of the
country. Indian Railways therefore took the
bold decision in 1992 of getting rid of the
multi-gauge system and following the unigauge
policy of adopting the broad gauge (1676 mm)
uniformly.
Benefits of Adopting BG (1676 mm) as
the Uniform Gauge
The uni-gauge system will be highly beneficial to
rail users, the railway administration, as well
as to the nation as described below.
1.No Transport Bottlenecks:
There will be no transport bottlenecks after a
uniform gauge is adopted and this will lead to
improved operational efficiency resulting in
fast movement of goods and passengers.
2.No Trans-shipment Hazards:
There will no hazards of trans-shipment and as
such no delays, no damage to goods, no
inconvenience to passengers of transfer from
one train to another train.
3.Provisions of Alternate Routes:
Through a uni-gauge policy, alternate routes will
be available for free movement of traffic and
there will be less pressure on the existing BG
network. This is expected to result in long-haul
road traffic reverting to the railways.
4.Better Turn round:
There will be a better turn round of wagons and
locomotives, and their usage will improve the
operating ratio of the railway system as a whole. As a
result the community will be benefited immensely.
5.Improved Utilization of Track:
There will be improved utilization of tracks and
reduction in the operating expenses of the railway.
6.Balanced Economic Growth:
7.No Multiple Tracking Works:
The uni-gauge project will eliminate the need for
certain traffic facilities and multiple tracking
works, which will offset the cost of gauge
conversions to a certain extent.
8.Better Transport Infrastructure:
Some of the areas served by the MG have the
potential of becoming highly industrialized;
skilled manpower is also available. The uni-
gauge policy will help in providing these areas
a better transportation infrastructure.
9.Boosting Investor’s Confidence:
With the liberalization of the economic policy,
the uni-gauge projects of the Indian Railways
have come to play a significant role. This will
help in boosting the investors’ confidence that
their goods will be distributed throughout the
country in time and without any hindrance.
This will also help in setting up industries in
areas not yet exploited because of the lack of
infrastructure facilities.
Loading gauge
 A loading gauge defines the maximum
height and width for railway vehicles and
their loads to ensure safe passage through
bridges, tunnels and other structures.
 The loading gauge determines the sizes of
passenger trains and the size of shipping
containers that can be conveyed on a
section of railway line and varies across the
world and often within a single railway
system.
Loading gauge
Construction gauge.
 By adding suitable clearance at the top
side of the loading gauge construction
gauge is obtained.
 It decides the dimensions such as
height and width of structures in
bridges and tunnels along the track
so that all wagons may pass through
them without damage to the
structures
• Thanks

More Related Content

What's hot

modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
krishnacp
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
KHUSHBU SHAH
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
RAMPRASAD KUMAWAT
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
Latif Hyder Wadho
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
Gowtham G
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
Mani Vel
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
Bhavya Jaiswal
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
Eddy Ankit Gangani
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
RAMPRASAD KUMAWAT
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
Aaquib ansari
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
TVijayaGowri
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
Mani Vel
 
Hill road
Hill roadHill road
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
T.Naga Anusha
 
Corrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in railsCorrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in rails
Sagar Kaptan
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
dhara dattani
 
Sleepers and Their types
Sleepers and Their typesSleepers and Their types
Sleepers and Their types
17CE67
 
classification of indian railway
classification of indian railway classification of indian railway
classification of indian railway
addavidson
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
Arbaz Kazi
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
Deven Diran
 

What's hot (20)

modern methods of railway track maintanence
modern methods of railway track maintanencemodern methods of railway track maintanence
modern methods of railway track maintanence
 
Chapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway trackChapter 7 Maintenance of railway track
Chapter 7 Maintenance of railway track
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 
Alignment of railway tracks
Alignment of railway tracksAlignment of railway tracks
Alignment of railway tracks
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
 
Hill road
Hill roadHill road
Hill road
 
Geometric design of the track
Geometric design of the trackGeometric design of the track
Geometric design of the track
 
Corrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in railsCorrugated (roaring), Hogging, Buckling, Kinks in rails
Corrugated (roaring), Hogging, Buckling, Kinks in rails
 
Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
 
Sleepers and Their types
Sleepers and Their typesSleepers and Their types
Sleepers and Their types
 
classification of indian railway
classification of indian railway classification of indian railway
classification of indian railway
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
 
Rail fastenings and joints
Rail fastenings and jointsRail fastenings and joints
Rail fastenings and joints
 

Similar to 2.railway track gauge

Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Tushar Sonawane
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gauge
Jangid Devendra
 
Types of tracks in pakistan
Types of tracks in pakistanTypes of tracks in pakistan
Types of tracks in pakistan
AYAZ AHMAD
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gauge
Gaurav Jagad
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
RESHMAFEGADE
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
RESHMAFEGADE
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
Malyar Talash
 
Railway.pdf
Railway.pdfRailway.pdf
Railway.pdf
abhijitsaha99
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
IRJET Journal
 
railway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxrailway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptx
RESHMAFEGADE
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieering
Mani Vel
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
Mani Vel
 
Rail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMateRail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMate
Civil TechMate
 
Introduction, alignment & surveys
Introduction, alignment & surveysIntroduction, alignment & surveys
Introduction, alignment & surveys
GARRE RAVI KUMAR
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminal
KapilLamba6
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
2018kumaranurag
 
Transport poster
Transport posterTransport poster
Transport posterGordon Best
 
Railway Engineering Introduction
Railway Engineering IntroductionRailway Engineering Introduction
Railway Engineering Introduction
T.Naga Anusha
 
D012531923
D012531923D012531923
D012531923
IOSR Journals
 

Similar to 2.railway track gauge (20)

Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
Rail Gauges and Rail standards [Useful for Civil Engineering Students IECT SPPU]
 
TRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gaugeTRANSPORTATION ENGINEERING railway track gauge
TRANSPORTATION ENGINEERING railway track gauge
 
Types of tracks in pakistan
Types of tracks in pakistanTypes of tracks in pakistan
Types of tracks in pakistan
 
1. railway track gauge
1. railway track gauge1. railway track gauge
1. railway track gauge
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
railway and bridge engineering.pdf
railway and bridge engineering.pdfrailway and bridge engineering.pdf
railway and bridge engineering.pdf
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Railway.pdf
Railway.pdfRailway.pdf
Railway.pdf
 
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai MonorailTime Overrun in Transportation Project - A Case Study of Mumbai Monorail
Time Overrun in Transportation Project - A Case Study of Mumbai Monorail
 
Railway Gauge
Railway GaugeRailway Gauge
Railway Gauge
 
railway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptxrailway and bridge engineering ppt.pptx
railway and bridge engineering ppt.pptx
 
1.railway engnieering
1.railway engnieering1.railway engnieering
1.railway engnieering
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
 
Rail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMateRail Gauge | Types of Rail Gauges | Civil TechMate
Rail Gauge | Types of Rail Gauges | Civil TechMate
 
Introduction, alignment & surveys
Introduction, alignment & surveysIntroduction, alignment & surveys
Introduction, alignment & surveys
 
Rail yard container terminal
Rail yard container terminalRail yard container terminal
Rail yard container terminal
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Transport poster
Transport posterTransport poster
Transport poster
 
Railway Engineering Introduction
Railway Engineering IntroductionRailway Engineering Introduction
Railway Engineering Introduction
 
D012531923
D012531923D012531923
D012531923
 

Recently uploaded

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 

Recently uploaded (20)

power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 

2.railway track gauge

  • 1. Railway Track Gauge Mr MANIVEL M FACULTY,CIVIL ENGINEERING SCHOOL OF TECHNOLOGY PANDIT DEENDAYAL PETROLEUM UNIVERSITY GANDHINAGAR
  • 2. Introduction • Gauge is defined as the minimum distance between inner face two rails. Indian Railways follows this standard practice and the gauge is measured as the clear minimum distance between the running faces of the two rails as shown in Fig. 2.1.
  • 3. TYPES OF GAUGES IN INDIA The different gauges in India are of the following these types :- 1. Broad gauge (1676), 2. Meter gauge (1000), 3. Narrow gauge (762 mm & 610 mm). In India, efforts are being made to convert all N.G. and M.G. lines to B.G. lines on important sections as and when funds are available.
  • 4. Permanent Way Permanent way: The combination of rails, fitted on sleepers with the help of fixtures and fastenings and resting on ballast and subgrade is called the railway track or permanent way.
  • 5.
  • 6. Choice of Gauge • The choice of gauge is very limited, as each country has a fixed gauge and all new railway lines are constructed to adhere to the standard gauge. However, the following factors theoretically influence the choice of the gauge.
  • 7. 1.Cost Considerations: There is only a marginal increase in the cost of the track if a wider gauge is adopted. In this connection, the following points are important. (a) There is a proportional increase in the cost of acquisition of land, earthwork, rails, sleepers, ballast, and other track items when constructing a wider gauge. (b) The cost of building bridges, culverts, and tunnels increases only marginally due to a wider gauge. (c) The cost of constructing station buildings, platforms, staff quarters, level crossings, signals, etc. associated with the railway network is more or less the same for all gauges. (d) The cost of rolling stock is independent of the gauge of the track for carrying the same volume of traffic.
  • 8. 2. Traffic Considerations: The volume of traffic depends upon the size of wagons and the speed and hauling capacity of the train. (a) As a wider gauge can carry larger wagons and coaches, it can theoretically carry more traffic. (b) A wider gauge has a greater potential at higher speeds, because speed is a function of the diameter of the wheel, which in turn is limited by the width of the gauge. (c) The type of traction and signalling equipment required are independent of the gauge.
  • 9. 3. Physical Features of the Country: It is possible to adopt steeper gradients and sharper curves for a narrow gauge a compared to a wider gauge. 4. Uniformity of Gauge: The existence of a uniform gauge in a country enables smooth, speedy, and efficient operation of trains. Therefore a single gauge should be adopted irrespective of the minor advantages of a wider gauge and the few limitations of a narrower gauge.
  • 10. Problems Caused by Change of Gauge The need for uniformity of gauge has been recognized by all the advanced countries of the world. A number of problems have cropped up in the operation of Indian Railways because of the use of three gauges. The ill effects of change of gauge (more popularly known as break of gauge) are numerous; some of these are enumerated here.
  • 11. 1.Inconvenience to Passengers: Due to change of gauge, passengers have to change trains mid-journey along with their luggage, which causes inconvenience such as the following. (a) Climbing stairs and crossing bridges (b) Finding seats in the compartments of the later trains (c) Missing connections with the later trains in case the earlier train is late (d) Harassment caused by porters (e) Transporting luggage (f) Uncertainty and delay in reaching the destination
  • 12. 2. Difficulty in Trans-shipment of Goods: Goods have to be trans-shipped at the point where the change of gauge takes place. This causes the following problems. (a) Damage to goods during trans-shipment. (b) Considerable delay in receipt of goods at the destination. (c) Theft or misplacement of goods during trans- shipment and the subsequent claims. (d) Non-availability of adequate and specialized trans-shipment labour and staff, particularly during strikes.
  • 13. 3. Inefficient Use of Rolling Stock: As wagons have to move empty in the direction of the trans-shipment point, they are not fully utilized. Similarly, idle wagons of one gauge cannot be moved on another gauge. 4. Hindrance to Fast Movement of Goods and Passenger Traffic: Due to change in the gauge, traffic cannot move fast which becomes a major problem particularly during emergencies such as war, floods, and accidents.
  • 14. 5. Additional Facilities at Stations and Yards: (a) Costly sheds and additional facilities need to be provided for handling the large volume of goods at trans-shipment points. (b) Duplicate equipment and facilities such as yards and platforms need to be provided for both gauges at trans-shipment points. 6. Difficulties in Balanced Economic Growth: • The difference in gauge also leads unbalanced economic growth. This happens because industries set up near MG/NG stations cannot send their goods economically and efficiently to areas being served by BG stations.
  • 15. 7. Difficulties in Future Gauge Conversion Projects: Gauge conversion is quite difficult, as it requires enormous effort to widen existing tracks. Widening the gauge involves heavy civil engineering work such as widening of the embankment, the bridges and tunnels, as well as the tracks; additionally, a wider rolling stock is also required. During the gauge conversion period, there are operational problems as well since the traffic has to be slowed down and even suspended for a certain period is order to execute the work.
  • 16. Uni-gauge Policy of Indian Railways The multi-gauge system is not only costly and cumbersome but also causes serious bottlenecks in the operation of the Railways and hinders the balanced development of the country. Indian Railways therefore took the bold decision in 1992 of getting rid of the multi-gauge system and following the unigauge policy of adopting the broad gauge (1676 mm) uniformly.
  • 17. Benefits of Adopting BG (1676 mm) as the Uniform Gauge The uni-gauge system will be highly beneficial to rail users, the railway administration, as well as to the nation as described below. 1.No Transport Bottlenecks: There will be no transport bottlenecks after a uniform gauge is adopted and this will lead to improved operational efficiency resulting in fast movement of goods and passengers.
  • 18. 2.No Trans-shipment Hazards: There will no hazards of trans-shipment and as such no delays, no damage to goods, no inconvenience to passengers of transfer from one train to another train. 3.Provisions of Alternate Routes: Through a uni-gauge policy, alternate routes will be available for free movement of traffic and there will be less pressure on the existing BG network. This is expected to result in long-haul road traffic reverting to the railways.
  • 19. 4.Better Turn round: There will be a better turn round of wagons and locomotives, and their usage will improve the operating ratio of the railway system as a whole. As a result the community will be benefited immensely. 5.Improved Utilization of Track: There will be improved utilization of tracks and reduction in the operating expenses of the railway. 6.Balanced Economic Growth:
  • 20. 7.No Multiple Tracking Works: The uni-gauge project will eliminate the need for certain traffic facilities and multiple tracking works, which will offset the cost of gauge conversions to a certain extent. 8.Better Transport Infrastructure: Some of the areas served by the MG have the potential of becoming highly industrialized; skilled manpower is also available. The uni- gauge policy will help in providing these areas a better transportation infrastructure.
  • 21. 9.Boosting Investor’s Confidence: With the liberalization of the economic policy, the uni-gauge projects of the Indian Railways have come to play a significant role. This will help in boosting the investors’ confidence that their goods will be distributed throughout the country in time and without any hindrance. This will also help in setting up industries in areas not yet exploited because of the lack of infrastructure facilities.
  • 22. Loading gauge  A loading gauge defines the maximum height and width for railway vehicles and their loads to ensure safe passage through bridges, tunnels and other structures.  The loading gauge determines the sizes of passenger trains and the size of shipping containers that can be conveyed on a section of railway line and varies across the world and often within a single railway system.
  • 24. Construction gauge.  By adding suitable clearance at the top side of the loading gauge construction gauge is obtained.  It decides the dimensions such as height and width of structures in bridges and tunnels along the track so that all wagons may pass through them without damage to the structures