Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Action
Client vendor
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either from wall or any fixxed
strcture.at 10m interval and 5m in
curve portion and at changing
width Client Client
6
Pre-level recording
of existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge. Client Vendor
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval . Vendor
8 Fixxation of FRL
Final road level with proper
design should be prepared and
approved sheet should be given
to the Vendors. Client Vendor
9
Checking of HOT MIX
PLANT frequently Client Vendor
a Calibration of plant Every starting of session Client Vendor
10 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 for per day 30% Client Vendor
FIV& EIV 1 for per day 30% Client Vendor
Specific gravity 1 for source Client Vendor
Anti striping Value test 1 for source 95% Client Vendor
b Bitumen T Penetration for grade 1 for per lot VG-30 Client Vendor
T Extraction test 2 test per day Client Vendor
Core cutting & Marshal
stability 2 test per work 9 KN Client Vendor
c Designing of BM Job Mix
At every start of season 1 check
required. Client Vendor
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Bituminous Macadam laying
Name of Road-
Responsibility
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be
cleaned from all debris
and other foreign
material. Regular Vendor
c
Joint within existing
and new surface
At both ends of the
joint 1 to 1.5m of
existing bituminous
surface should be
removed to meet the
regularity of the
surface. Regular vendor
d Trip Challan
Trip challan with
temperature detail and
time of loading
/unloading should be
checked at site and
recorded. Regular Client
Vendor/
Client
e Temperature Laying temperature 110-120 degree centigrade
110-120
degree
centigrade Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level. Client Vendor
12 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm Client Vendor
13 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of pre level and post
level to prepare L-section and C/S
Or as per contract within 3 days
of completion of job. Client Vendor
b Submission of Bill
Vendor will submit the bill with L-
section and C/S with all test
report and other contractual
requirement within 30 days of
completion of Job Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either at wall or any fixxed
strcture.at 10m interval and 5m in
cuve portion and at changing
width Vendor/Client
6
Pre-level recording of
existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge. Vendor/Client
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval . Vendor
8 Fixxation of FRL
Final road level with proper design
should be prepared and approved
sheet should be given to the
Vendors. Vendor/Client
9
Checking of HOT MIX
PLANT frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Dense bituminous Macadam laying
Name of Road-
10 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
T Extraction test 2 test per day Vendor/Client
Core cutting & Marshal
stability 2 test per work 9KN Vendor/Client
d Designing of DBM Job Mix
At every start of season 1 check
required. Vendor/Client
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
a Cleaniness of site
Every site should be
cleaned from all debris
and other foreign
material. Regularly Vendor
b
Joint within existing
and new surface
At both ends of the
joint 1 to 1.5m of
existing bituminous
surface should be
removed to meet the
regularity of the
surface. Regularly vendor
b Trip Challan
Trip challan with
temperature detail and
time of loading
/unloading should be
checked at site and
recorded. Regularly Vendor/Client
b Temperature Laying temperature 110-120 degree centigrade
110-120
degree
centigrade Vendor
c Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
d Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
Vendor/Client
12 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm Vendor/Client
13 Payment Vendor/Client
a
Joint measurement
preparation
Quantity should be caculated on
the basis of pre level and post
level to prepare L-section and C/S
or as per contract within 3 days of
completion of JOB. Vendor/Client
b Submission of Bill
Vendor will submit the bill with L-
section and C/S with all test report
and other requirement as per
contract within 30 days
completion of Job. Vendor
Sr.
no Activity Unit Quantity Testing Required Frequency/plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either at wall or any fixxed
strcture.at 10m interval and 5m
in cuve portion and at changing
width Vendor
6
Pre-level recording
of existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge. Vendor/Client
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval . Vendor
8 Fixxation of FRL
Final road level with proper
design should be prepared and
approved sheet should be given
to the Vendors. Vendor/Client
9
Checking of HOT MIX
PLANT frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
10 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
T Extraction test 2 test per day Vendor/Client
Core cutting & Marshal
stability 2 test per work 9.0 KN Vendor/Client
e Designing of BC Job Mix
At every start of season 1 check
required. Vendor/Client
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Bituminous concrete laying
Name of Road-
b Cleaniness of site
Every site should be
cleaned from all debris
and other foreign
material. Vendor
c
Joint within existing
and new surface
At both ends of the
joint 1 to 1.5m of
existing bituminous
surface should be
removed to meet the
regularity of the
surface. vendor
d Trip Challan
Trip challan with
temperature detail and
time of loading
/unloading should be
checked at site and
recorded. Vendor/Client
e Temperature Laying temperature 110-120 degree centigrade Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
Vendor/Client
12 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm Vendor/Client
13 Payment Vendor/Client
a
Joint measurement
preparation
Quantity should be caculated on
the basis of pre level and post
level to prepare L-section and C/S
or as per contract within 3 days of
completion of JOB. Vendor/Client
b Submission of Bill
Vendor will submit the bill with L-
section and C/S with all test
report and other contractual
requirement within 30 days of
completion of JOB. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either at wall or any fixxed
strcture.at 10m interval and 5m
in cuve portion and at changing
width Vendor
6
Pre-level recording
of existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge. Vendor/Client
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval . Vendor
8 Fixxation of FRL
Final road level with proper
design should be prepared and
approved sheet should be given
to the Vendors. Vendor/Client
9
Checking of HOT MIX
PLANT frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Pre-mix carpet with seal coat laying
Name of Road-
10 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
T Extraction test 2 test per day Vendor/Client
Core cutting & Marshal
stability 2 test per work 9.0 KN Vendor/Client
e Designing of PC-SC Job Mix
At every start of season 1 check
required. Vendor/Client
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
c
Joint within existing
and new surface
At both ends of the joint 1 to
1.5m of existing bituminous
surface should be removed to
meet the regularity of the
surface. vendor
d Trip Challan
Trip challan with temperature
detail and time of loading
/unloading should be checked at
site and recorded. Vendor/Client
e Temperature Laying temperature 110-120 degree centigrade Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
12 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm
13 Payment Vendor/Client
a
Joint measurement
preparation
Quantity should be caculated on
the basis of joint measurement in
(Length)X(Width) and insure the
depth at few interval within 3
days of completion of JOB. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
Joint measurement Record with
required test result within 30
days of completion of Job. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
9
Checking of HOT MIX
PLANT frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
10 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
T Extraction test 2 test per day Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Patch Repairing (small length) Pot holes repairing
Name of Road-
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
c
Joint within existing
and new surface
Pot holes /Patches should be
prepared in square/rectangle size
and Level should be maintained
as existing level of adjoining area. vendor
d Trip Challan
Trip challan with temperature
detail and time of loading
/unloading should be checked at
site and recorded. Vendor/Client
e Temperature Laying temperature 110-120 degree centigrade Vendor
f Compaction Rolling
Hand roller/mini roller/plate
compactor is used for
rolling.Rolling should be carried
till all marks should be cleaned. Vendor
12 Surface Regularity 3m stright edge
3m straight edge is utilised to
check regularity of the road. +/-6mm Vendor/Client
13 Payment Vendor/Client
a
Joint measurement
preparation
Quantity should be caculated to
take the joint measurement in
(Length) X (width) or as contract
within 3 days of completion of
Job. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
Joint measurement Records with
required test result within 30
days of job completion. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either at wall or any fixxed
strcture.at 10m interval and 5m
in cuve portion and at changing
width Vendor
6
Pre-level recording
of existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge. Vendor/Client
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval . Vendor
8 Fixxation of FRL
Final road level with proper
design should be prepared and
approved sheet should be given
to the Vendors. Vendor/Client
9
Checking of HOT MIX
PLANT Frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Mix seal Surfacing
Name of Road-
10 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
T Extraction test 2 test per day Vendor/Client
c Designing of MSS Job Mix
At every start of season 1 check
required. Vendor/Client
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator Once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
c
Joint within existing
and new surface
At both ends of the joint 1 to
1.5m of existing bituminous
surface should be removed to
meet the regularity of the
surface. vendor
d Trip Challan
Trip challan with temperature
detail and time of loading
/unloading should be checked at
site and recorded. Vendor/Client
e Temperature Laying temperature 110-120 degree centigrade Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
Vendor/Client
12 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm Vendor/Client
13 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of joint measurement in
(Length)X(Width) and insure the
depth at few interval within 3
days of Job completion. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
Joint measurement Record,test
results and other contractula
requirement within 30 days of
completion of Job. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5 Bitumen Emulsion T Specific gravity 1 for source Vendor/Client
6 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator Once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
c Fog sealing Bitumen Emulsion
Cracks should be filled with
Bitumen emulsion by sprayer. vendor
7 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of joint measurement in
(Length)X(Width) within 3 days of
completion of JOB. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
Joint measurement Record
,required test result and other
contractual requrement within 30
days of completion of Job. Vendor
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Fog Sealing where cracks occurred.
Name of Road-
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility
Action(
Y/N)
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either at wall or any fixxed
strcture.at 10m interval and 5m in
cuve portion and at changing
width Vendor
6
Pre-level recording of
existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge. Vendor/Client
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval . Vendor
8 Fixxation of FRL
Final road level with proper design
should be prepared and approved
sheet should be given to the
Vendors. Vendor/Client
9 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Bituminous Penetration Macadam laying
Name of Road-
10 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
c
Joint within existing
and new surface
At both ends of the joint 1 to
1.5m of existing bituminous
surface should be removed to
meet the regularity of the surface. vendor
d Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
e Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
Vendor/Client
11 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm Vendor/Client
12 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of pre level and post
level to prepare L-section and C/S
or as per contract within 3 days of
job completion. Vendor/Client
b Submission of Bill
Vendor will submit the bill with L-
section and C/S with all test report
and other contractual
requirement within 30 days of job
completion. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Checking of HOT MIX
PLANT frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
6 Bitumen Mix
a Coarse Aggregate m3 Gradtion 2 test per day
AIV 1 per day 30% Vendor/Client
FI & EI 1 for per day 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Anti striping Value test 1 for source 95% Vendor/Client
b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client
T Extraction test 2 test per day Vendor/Client
Core cutting & Marshal
stability NR NR
e Designing of SC Job Mix
At every start of season 1 check
required. Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Seal coat laying
Name of Road-
7 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
d Trip Challan
Trip challan with temperature detail
and time of loading /unloading
should be checked at site and
recorded. Vendor/Client
e Temperature Laying temperature 110-120 degree centigrade Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
8 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of joint measurement in
(Length)X(Width) within 3 days of
Job completion. Vendor/Client
b Submission of Bill
Vendor will submit the bill with Joint
measurement Record, test result
and other contractual requirement
within 30 days of work. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
Quality of material
Liquid Limit and
Plasticity limit 1 per source
LL not more
than 70 and
PI not more
than 45 or as
discreation of
Client
engineer Vendor/Client
4
Adding or Excavation
of extra earth.
1.If extra earth is
required to be added.
2.If extra earth is need
to excavate,to be
excavated. Regular Vendor
6
loosening and
Recomapacting
If extra earth is need to
add then existing
surface to be loosened
for depth of 150mm Regular Vendor
7 Cross fall or camber %
Shoulder should be
maintained such that
camber should be
3.5% to 4.5% Regular Vendor
8 compaction
Roller of 8-10 tonne
should be used for
rolling Till compaction achieved 90% Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Shoulder laying and maintenance
Name of Road-
11 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
Vendor/Client
12 Surface Regularity
Difference between
design level and Finish
level or difference in
camber plate or
straight edge +/-15mm +/-15mm Vendor/Client
13 Payment Vendor/Client
a
Joint measurement
preparation
Quantity should be calculated on
the basis of sqm for maintenance
work and in cum for new work
Within 3 days of completion of
JOB. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
all test report and other
contractual requirement within
30 days of completion of work. Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Checking of Truck
Mounted MIX PLANT frequently Vendor/Client
a Calibration Every starting of session Vendor/Client
6 Emulsion Mix
a Coarse Aggregate m3 Gradtion 1test per source
Sand equivalent value 1 test per source
more
than50% Vendor/Client
AIV 1 for source 30% Vendor/Client
Specific gravity 1 for source Vendor/Client
Wet striping Value test 1 for source 90% Vendor/Client
Residula on 600
micrometre 1 per source 0.05 Vendor/Client
b Emulsion(SS-2) T Residual penetration 1 per lot 40-100 Vendor/Client
T
Viscosity at 25 dgree
centigrdae 1 per lot 20-100 Vendor/Client
Residual Binder 1 per lot
As design
value Vendor/Client
c Cement Quality of cement Manufacturing Test result Vendor/Client
d Water Quality of water Client water Vendor/Client
e Additives Quality of Additives Hincol Retarder Vendor/Client
PH Value 1 per lot 1-1.2 Vendor/Client
f Designing of MIX Job Mix
At every start of season 1 check
required. Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Microsurfacing(Seal coat with Emulsion)
Name of Road-
7 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
c Traffic movement
Open the traffic after
microsurfacing
Traffic should be blocked by
barrigading for 2 hour for setting
the Mix on site,before leaving the
traffic Vendor
d Surface Finish Surface regularity
Regular surface should be
checked by joint inspection with
Vendor and Client. Vendor/Client
8 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of joint measurement in
(Length)X(Width) within 3 days
of job completion. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
Joint measurement Record ,test
result and other contractual
requirement before 30 days of
completion of job Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit
Responsi
bility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 GIS survey Not required
5
Fixxing the BM and
chainage marking
TBM should fixxed at any fixxed
place. Chaining should be carried
either from wall or any fixxed
strcture.at 10m interval and 5m in
curve portion and at changing
width
Client/ve
ndor
6
Pre-level recording
of existing surface.
At minimum of 10m interval or
lesser in longitudinal and at every
three point in cross sectional that
is centre and both edge.
Client/Ve
ndor
7
Preparation of L-
section and C/S
L-section should be prepared for
centre point level and c/s is
prepared at every 10m interval
interval .
Client/Ve
ndor
8 Fixxation of FRL
Final road level with proper
design should be prepared and
approved sheet should be given
to the Vendors.
Client/Ve
ndor
9 Paver Block
Client/Ve
ndor
a Coarse Aggregate m3 Gradtion 2 test per day
Client/Ve
ndor
AIV 1 for per day 30%
Client/Ve
ndor
FIV& EIV 1 for per day 30%
Client/Ve
ndor
Specific gravity 1 for source
Client/Ve
ndor
b Cement T Fineness 1 for per lot
Client/Ve
ndor
c
Strength of Paver
Block Compressive strength 1 test per 200 sqm
Client/Ve
ndor
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Paver Block Laying
Name of Road-
10 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work
Client/Ve
ndor
b Cleaniness of site
Every site should be
cleaned from all debris
and other foreign
material. Regular
Client/Ve
ndor
f Compaction Rolling Compactor should used for rolling
Client/Ve
ndor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level.
Client/Ve
ndor
11 Surface Regularity
Difference between
design level and Finish
level +/-6mm +/-6mm
Client/Ve
ndor
12 Payment
a
Joint measurement
preparation
Quantity should be caculated on
the basis of joint measurement in
(Length)X(Width) within 3 days
of job completion.
Client/Ve
ndor
b Submission of Bill
Vendor will submit the bill with L-
section and C/S with all test
report and other contractual
requirement within 30 days of
completion of Job Vendor
Sr.
no. Activity Unit Quantity Testing Required Frequency/Plan
Required
Limit Responsibility Action
1
Labour licence
submission 1 time Vendor
2
C1 &C2 format
submission 1 time Vendor
3
Safety training at
site,Gate
Pass/Identity cards 1 time Vendor
4 Quality of material
Liquid Limit and
Plasticity limit 1 per source
LL not more
than 70 and
PI not more
than 45 or as
discreation of
Client
engineer Vendor/Client
5 Cross fall or camber %
Shoulder should be
maintained such that
camber should be
2.5% to 3.5% or as
designed Regular Vendor
6 compaction
Roller of 8-10 tonne
should be used for
rolling Till compaction achieved 90% Vendor/Client
QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY
Name of Work - Sub-Grade Preparation
Name of Road-
7 Construction at site
a Safety
Barrigading,Flag man
with whistle,Indicator
Board for Work in
progress,Lighting
ararangement for night
work,PPE,seat
belt,vehicle back horn
and licence for
operator once At every start of work Vendor
b Cleaniness of site
Every site should be cleaned from
all debris and other foreign
material. Vendor
f Compaction Rolling
Rolling should be carried till all
marks should be cleaned. Vendor
g Final level Finished Level
Finished level to be recorded at
same interval as pre level. Vendor/Client
Vendor/Client
8 Surface Regularity
Difference between
design level and Finish
level or difference in
camber plate or
straight edge +/-15mm +/-15mm Vendor/Client
9 Payment Vendor/Client
a
Joint measurement
preparation
Quantity should be calculated on
the basis of sqm for maintenance
work and in cum for new work
Within 3 days of completion of
JOB. Vendor/Client
b Submission of Bill
Vendor will submit the bill with
all test report and other
contractual requirement within
30 days of completion of work. Vendor
Sr.no Details of Activity Time Limit
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
TIME LINE FOR BILLING AND PAYMENT

Qap ,checklist and responsibility

  • 1.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Action Client vendor 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either from wall or any fixxed strcture.at 10m interval and 5m in curve portion and at changing width Client Client 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Client Vendor 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Vendor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Client Vendor 9 Checking of HOT MIX PLANT frequently Client Vendor a Calibration of plant Every starting of session Client Vendor 10 Bitumen Mix a Coarse Aggregate m3 Gradtion 2 test per day AIV 1 for per day 30% Client Vendor FIV& EIV 1 for per day 30% Client Vendor Specific gravity 1 for source Client Vendor Anti striping Value test 1 for source 95% Client Vendor b Bitumen T Penetration for grade 1 for per lot VG-30 Client Vendor T Extraction test 2 test per day Client Vendor Core cutting & Marshal stability 2 test per work 9 KN Client Vendor c Designing of BM Job Mix At every start of season 1 check required. Client Vendor QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Bituminous Macadam laying Name of Road- Responsibility
  • 2.
    11 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Regular Vendor c Joint within existing and new surface At both ends of the joint 1 to 1.5m of existing bituminous surface should be removed to meet the regularity of the surface. Regular vendor d Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Regular Client Vendor/ Client e Temperature Laying temperature 110-120 degree centigrade 110-120 degree centigrade Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor g Final level Finished Level Finished level to be recorded at same interval as pre level. Client Vendor 12 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm Client Vendor 13 Payment a Joint measurement preparation Quantity should be caculated on the basis of pre level and post level to prepare L-section and C/S Or as per contract within 3 days of completion of job. Client Vendor b Submission of Bill Vendor will submit the bill with L- section and C/S with all test report and other contractual requirement within 30 days of completion of Job Vendor
  • 3.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either at wall or any fixxed strcture.at 10m interval and 5m in cuve portion and at changing width Vendor/Client 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Vendor/Client 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Vendor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Vendor/Client 9 Checking of HOT MIX PLANT frequently Vendor/Client a Calibration Every starting of session Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Dense bituminous Macadam laying Name of Road-
  • 4.
    10 Bitumen Mix aCoarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client T Extraction test 2 test per day Vendor/Client Core cutting & Marshal stability 2 test per work 9KN Vendor/Client d Designing of DBM Job Mix At every start of season 1 check required. Vendor/Client 11 Construction at site a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor a Cleaniness of site Every site should be cleaned from all debris and other foreign material. Regularly Vendor b Joint within existing and new surface At both ends of the joint 1 to 1.5m of existing bituminous surface should be removed to meet the regularity of the surface. Regularly vendor b Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Regularly Vendor/Client b Temperature Laying temperature 110-120 degree centigrade 110-120 degree centigrade Vendor c Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor d Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client Vendor/Client 12 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm Vendor/Client 13 Payment Vendor/Client a Joint measurement preparation Quantity should be caculated on the basis of pre level and post level to prepare L-section and C/S or as per contract within 3 days of completion of JOB. Vendor/Client b Submission of Bill Vendor will submit the bill with L- section and C/S with all test report and other requirement as per contract within 30 days completion of Job. Vendor
  • 5.
    Sr. no Activity UnitQuantity Testing Required Frequency/plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either at wall or any fixxed strcture.at 10m interval and 5m in cuve portion and at changing width Vendor 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Vendor/Client 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Vendor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Vendor/Client 9 Checking of HOT MIX PLANT frequently Vendor/Client a Calibration Every starting of session Vendor/Client 10 Bitumen Mix a Coarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client T Extraction test 2 test per day Vendor/Client Core cutting & Marshal stability 2 test per work 9.0 KN Vendor/Client e Designing of BC Job Mix At every start of season 1 check required. Vendor/Client 11 Construction at site a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Bituminous concrete laying Name of Road-
  • 6.
    b Cleaniness ofsite Every site should be cleaned from all debris and other foreign material. Vendor c Joint within existing and new surface At both ends of the joint 1 to 1.5m of existing bituminous surface should be removed to meet the regularity of the surface. vendor d Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Vendor/Client e Temperature Laying temperature 110-120 degree centigrade Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor g Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client Vendor/Client 12 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm Vendor/Client 13 Payment Vendor/Client a Joint measurement preparation Quantity should be caculated on the basis of pre level and post level to prepare L-section and C/S or as per contract within 3 days of completion of JOB. Vendor/Client b Submission of Bill Vendor will submit the bill with L- section and C/S with all test report and other contractual requirement within 30 days of completion of JOB. Vendor
  • 7.
    Sr. no. Activity UnitQuantity Testing Required Frequency/plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either at wall or any fixxed strcture.at 10m interval and 5m in cuve portion and at changing width Vendor 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Vendor/Client 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Vendor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Vendor/Client 9 Checking of HOT MIX PLANT frequently Vendor/Client a Calibration Every starting of session Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Pre-mix carpet with seal coat laying Name of Road-
  • 8.
    10 Bitumen Mix aCoarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client T Extraction test 2 test per day Vendor/Client Core cutting & Marshal stability 2 test per work 9.0 KN Vendor/Client e Designing of PC-SC Job Mix At every start of season 1 check required. Vendor/Client 11 Construction at site a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor c Joint within existing and new surface At both ends of the joint 1 to 1.5m of existing bituminous surface should be removed to meet the regularity of the surface. vendor d Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Vendor/Client e Temperature Laying temperature 110-120 degree centigrade Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor g Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client 12 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm 13 Payment Vendor/Client a Joint measurement preparation Quantity should be caculated on the basis of joint measurement in (Length)X(Width) and insure the depth at few interval within 3 days of completion of JOB. Vendor/Client b Submission of Bill Vendor will submit the bill with Joint measurement Record with required test result within 30 days of completion of Job. Vendor
  • 9.
    Sr. no. Activity UnitQuantity Testing Required Frequency/plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 9 Checking of HOT MIX PLANT frequently Vendor/Client a Calibration Every starting of session Vendor/Client 10 Bitumen Mix a Coarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client T Extraction test 2 test per day Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Patch Repairing (small length) Pot holes repairing Name of Road-
  • 10.
    11 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor c Joint within existing and new surface Pot holes /Patches should be prepared in square/rectangle size and Level should be maintained as existing level of adjoining area. vendor d Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Vendor/Client e Temperature Laying temperature 110-120 degree centigrade Vendor f Compaction Rolling Hand roller/mini roller/plate compactor is used for rolling.Rolling should be carried till all marks should be cleaned. Vendor 12 Surface Regularity 3m stright edge 3m straight edge is utilised to check regularity of the road. +/-6mm Vendor/Client 13 Payment Vendor/Client a Joint measurement preparation Quantity should be caculated to take the joint measurement in (Length) X (width) or as contract within 3 days of completion of Job. Vendor/Client b Submission of Bill Vendor will submit the bill with Joint measurement Records with required test result within 30 days of job completion. Vendor
  • 11.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either at wall or any fixxed strcture.at 10m interval and 5m in cuve portion and at changing width Vendor 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Vendor/Client 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Vendor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Vendor/Client 9 Checking of HOT MIX PLANT Frequently Vendor/Client a Calibration Every starting of session Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Mix seal Surfacing Name of Road-
  • 12.
    10 Bitumen Mix aCoarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client T Extraction test 2 test per day Vendor/Client c Designing of MSS Job Mix At every start of season 1 check required. Vendor/Client 11 Construction at site a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator Once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor c Joint within existing and new surface At both ends of the joint 1 to 1.5m of existing bituminous surface should be removed to meet the regularity of the surface. vendor d Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Vendor/Client e Temperature Laying temperature 110-120 degree centigrade Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor g Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client Vendor/Client 12 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm Vendor/Client 13 Payment a Joint measurement preparation Quantity should be caculated on the basis of joint measurement in (Length)X(Width) and insure the depth at few interval within 3 days of Job completion. Vendor/Client b Submission of Bill Vendor will submit the bill with Joint measurement Record,test results and other contractula requirement within 30 days of completion of Job. Vendor
  • 13.
    Sr. no. Activity UnitQuantity Testing Required Frequency/plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Bitumen Emulsion T Specific gravity 1 for source Vendor/Client 6 Construction at site a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator Once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor c Fog sealing Bitumen Emulsion Cracks should be filled with Bitumen emulsion by sprayer. vendor 7 Payment a Joint measurement preparation Quantity should be caculated on the basis of joint measurement in (Length)X(Width) within 3 days of completion of JOB. Vendor/Client b Submission of Bill Vendor will submit the bill with Joint measurement Record ,required test result and other contractual requrement within 30 days of completion of Job. Vendor QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Fog Sealing where cracks occurred. Name of Road-
  • 14.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action( Y/N) 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either at wall or any fixxed strcture.at 10m interval and 5m in cuve portion and at changing width Vendor 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Vendor/Client 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Vendor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Vendor/Client 9 Bitumen Mix a Coarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Bituminous Penetration Macadam laying Name of Road-
  • 15.
    10 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor c Joint within existing and new surface At both ends of the joint 1 to 1.5m of existing bituminous surface should be removed to meet the regularity of the surface. vendor d Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor e Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client Vendor/Client 11 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm Vendor/Client 12 Payment a Joint measurement preparation Quantity should be caculated on the basis of pre level and post level to prepare L-section and C/S or as per contract within 3 days of job completion. Vendor/Client b Submission of Bill Vendor will submit the bill with L- section and C/S with all test report and other contractual requirement within 30 days of job completion. Vendor
  • 16.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Checking of HOT MIX PLANT frequently Vendor/Client a Calibration Every starting of session Vendor/Client 6 Bitumen Mix a Coarse Aggregate m3 Gradtion 2 test per day AIV 1 per day 30% Vendor/Client FI & EI 1 for per day 30% Vendor/Client Specific gravity 1 for source Vendor/Client Anti striping Value test 1 for source 95% Vendor/Client b Bitumen T Penetration for grade 1 for per day VG-30 Vendor/Client T Extraction test 2 test per day Vendor/Client Core cutting & Marshal stability NR NR e Designing of SC Job Mix At every start of season 1 check required. Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Seal coat laying Name of Road-
  • 17.
    7 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor d Trip Challan Trip challan with temperature detail and time of loading /unloading should be checked at site and recorded. Vendor/Client e Temperature Laying temperature 110-120 degree centigrade Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor 8 Payment a Joint measurement preparation Quantity should be caculated on the basis of joint measurement in (Length)X(Width) within 3 days of Job completion. Vendor/Client b Submission of Bill Vendor will submit the bill with Joint measurement Record, test result and other contractual requirement within 30 days of work. Vendor
  • 18.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor Quality of material Liquid Limit and Plasticity limit 1 per source LL not more than 70 and PI not more than 45 or as discreation of Client engineer Vendor/Client 4 Adding or Excavation of extra earth. 1.If extra earth is required to be added. 2.If extra earth is need to excavate,to be excavated. Regular Vendor 6 loosening and Recomapacting If extra earth is need to add then existing surface to be loosened for depth of 150mm Regular Vendor 7 Cross fall or camber % Shoulder should be maintained such that camber should be 3.5% to 4.5% Regular Vendor 8 compaction Roller of 8-10 tonne should be used for rolling Till compaction achieved 90% Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Shoulder laying and maintenance Name of Road-
  • 19.
    11 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor g Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client Vendor/Client 12 Surface Regularity Difference between design level and Finish level or difference in camber plate or straight edge +/-15mm +/-15mm Vendor/Client 13 Payment Vendor/Client a Joint measurement preparation Quantity should be calculated on the basis of sqm for maintenance work and in cum for new work Within 3 days of completion of JOB. Vendor/Client b Submission of Bill Vendor will submit the bill with all test report and other contractual requirement within 30 days of completion of work. Vendor
  • 20.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Checking of Truck Mounted MIX PLANT frequently Vendor/Client a Calibration Every starting of session Vendor/Client 6 Emulsion Mix a Coarse Aggregate m3 Gradtion 1test per source Sand equivalent value 1 test per source more than50% Vendor/Client AIV 1 for source 30% Vendor/Client Specific gravity 1 for source Vendor/Client Wet striping Value test 1 for source 90% Vendor/Client Residula on 600 micrometre 1 per source 0.05 Vendor/Client b Emulsion(SS-2) T Residual penetration 1 per lot 40-100 Vendor/Client T Viscosity at 25 dgree centigrdae 1 per lot 20-100 Vendor/Client Residual Binder 1 per lot As design value Vendor/Client c Cement Quality of cement Manufacturing Test result Vendor/Client d Water Quality of water Client water Vendor/Client e Additives Quality of Additives Hincol Retarder Vendor/Client PH Value 1 per lot 1-1.2 Vendor/Client f Designing of MIX Job Mix At every start of season 1 check required. Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Microsurfacing(Seal coat with Emulsion) Name of Road-
  • 21.
    7 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor c Traffic movement Open the traffic after microsurfacing Traffic should be blocked by barrigading for 2 hour for setting the Mix on site,before leaving the traffic Vendor d Surface Finish Surface regularity Regular surface should be checked by joint inspection with Vendor and Client. Vendor/Client 8 Payment a Joint measurement preparation Quantity should be caculated on the basis of joint measurement in (Length)X(Width) within 3 days of job completion. Vendor/Client b Submission of Bill Vendor will submit the bill with Joint measurement Record ,test result and other contractual requirement before 30 days of completion of job Vendor
  • 22.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsi bility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 GIS survey Not required 5 Fixxing the BM and chainage marking TBM should fixxed at any fixxed place. Chaining should be carried either from wall or any fixxed strcture.at 10m interval and 5m in curve portion and at changing width Client/ve ndor 6 Pre-level recording of existing surface. At minimum of 10m interval or lesser in longitudinal and at every three point in cross sectional that is centre and both edge. Client/Ve ndor 7 Preparation of L- section and C/S L-section should be prepared for centre point level and c/s is prepared at every 10m interval interval . Client/Ve ndor 8 Fixxation of FRL Final road level with proper design should be prepared and approved sheet should be given to the Vendors. Client/Ve ndor 9 Paver Block Client/Ve ndor a Coarse Aggregate m3 Gradtion 2 test per day Client/Ve ndor AIV 1 for per day 30% Client/Ve ndor FIV& EIV 1 for per day 30% Client/Ve ndor Specific gravity 1 for source Client/Ve ndor b Cement T Fineness 1 for per lot Client/Ve ndor c Strength of Paver Block Compressive strength 1 test per 200 sqm Client/Ve ndor QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Paver Block Laying Name of Road-
  • 23.
    10 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Client/Ve ndor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Regular Client/Ve ndor f Compaction Rolling Compactor should used for rolling Client/Ve ndor g Final level Finished Level Finished level to be recorded at same interval as pre level. Client/Ve ndor 11 Surface Regularity Difference between design level and Finish level +/-6mm +/-6mm Client/Ve ndor 12 Payment a Joint measurement preparation Quantity should be caculated on the basis of joint measurement in (Length)X(Width) within 3 days of job completion. Client/Ve ndor b Submission of Bill Vendor will submit the bill with L- section and C/S with all test report and other contractual requirement within 30 days of completion of Job Vendor
  • 24.
    Sr. no. Activity UnitQuantity Testing Required Frequency/Plan Required Limit Responsibility Action 1 Labour licence submission 1 time Vendor 2 C1 &C2 format submission 1 time Vendor 3 Safety training at site,Gate Pass/Identity cards 1 time Vendor 4 Quality of material Liquid Limit and Plasticity limit 1 per source LL not more than 70 and PI not more than 45 or as discreation of Client engineer Vendor/Client 5 Cross fall or camber % Shoulder should be maintained such that camber should be 2.5% to 3.5% or as designed Regular Vendor 6 compaction Roller of 8-10 tonne should be used for rolling Till compaction achieved 90% Vendor/Client QUALITY ASSURANCE PLAN CHECKLIST AND RESPONSIBILITY Name of Work - Sub-Grade Preparation Name of Road-
  • 25.
    7 Construction atsite a Safety Barrigading,Flag man with whistle,Indicator Board for Work in progress,Lighting ararangement for night work,PPE,seat belt,vehicle back horn and licence for operator once At every start of work Vendor b Cleaniness of site Every site should be cleaned from all debris and other foreign material. Vendor f Compaction Rolling Rolling should be carried till all marks should be cleaned. Vendor g Final level Finished Level Finished level to be recorded at same interval as pre level. Vendor/Client Vendor/Client 8 Surface Regularity Difference between design level and Finish level or difference in camber plate or straight edge +/-15mm +/-15mm Vendor/Client 9 Payment Vendor/Client a Joint measurement preparation Quantity should be calculated on the basis of sqm for maintenance work and in cum for new work Within 3 days of completion of JOB. Vendor/Client b Submission of Bill Vendor will submit the bill with all test report and other contractual requirement within 30 days of completion of work. Vendor
  • 26.
    Sr.no Details ofActivity Time Limit 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 TIME LINE FOR BILLING AND PAYMENT