SlideShare a Scribd company logo
1
Project Performance
Measurement -
Earned Value
Simon Robertson
© 2010 Robertson Consulting Ltd June 2010
2
Benefits of EVM
• An up-to-date accurate status of the
project
• Solid input to proactively make corrections
• Allows managing stakeholder expectations
• Historic reference for future estimates
• No surprises to the customer
• More accurate representation of on-time
completion
© 2010 Robertson Consulting Ltd 2
3
MSProject 2010 & EVM
© 2010 Robertson Consulting Ltd When? Just after you develop the Schedule….. 3
4
MSProject 2010 & EVM
• Important Issue
Indicators
o Cost overrun – may be
working additional hours to
keep timeline
o Time overrun – may be
availability of resources
limited
o Cost and Time overrun –
may be project control,
poor quality, rework was
necessary
© 2010 Robertson Consulting Ltd
• Steps to prepare
o Ensure all Resources and
Materials are in MSProject
o Ensure all planning complete
and schedule agreed
o Establish project baseline from
where the variances will be
calculated and presented
o Add Columns to reflect the EV
measures
o Prepare project management
documents to meet the
tracking and reporting
requirements from the various
project stakeholders
o Set expectations with the
project team, address any
concerns and get buy-in
4
5
MSProject 2010 & EVM
Typical Measures
o Planned Value (PV) – amount budgeted
to be spent between task’s start date and
the status date
o Actual Cost (AC) – amount spent while
preforming work on a task during a given
period
o Earned Value (EV) – amount that that
should have been spent for a given
percentage of work performed on a task
© 2010 Robertson Consulting Ltd 5
6
MSProject 2010 & EVM
Typical Variance Metrics
oCost Variance(CV) – links spending
to earned value
CV = EV – AC or BCWP - ACWP
oSchedule Variance (SV) – links the
work accomplished (earned) with
planned
SV = EV – PV or BCWP - BCWS
© 2010 Robertson Consulting Ltd 6
7
MSProject 2010 & EVM
Typical Performance Indicators
o Cost Performance Index
CPI = EV/AC or BCWP/ACWP
o Schedule Performance Index
SPI = EV/PV or BCWP/BCWS
o Critical Ratio (?)
CR = CPI x SPI or BCWP2/ACWP x
BCWS
© 2010 Robertson Consulting Ltd 7
8
MSProject 2010 & EVM
Typical Forecasting Metrics
o Estimate at Completion (EAC)– apply CPI and SPI
as performance factors (PF)
o Mathematical EAC (uses PF = 1)
EACm = (BAC – EV) + AC
or EACm = BAC – CV
o Low End EAC (uses PF = CPI)
EACL= [(BAC-EV)/ (CPI)] + AC
Or EACL = (BAC)/ (CPI)
o High End EAC (uses PF = CPI x SPI)
EACH = [(BAC – EV)/(CPI x SPI)] + AC
© 2010 Robertson Consulting Ltd 8
9
MSProject 2010 & EVM
Typical Cost Corrective Action Metrics
o To Complete Performance Index (TCPI)
TCPI = (Work remaining)/ (Funds Remaining)
o To stay within original BAC
TCPI = (BAC – EV) / (BAC – AC)
o To stay within newly forecasted LRE where
baseline remains at original BAC
TCPI = (BAC – EV) / (LRE – AC )
Where LRE (Latest Revised Estimate)
LRE (or EACE) = ETC + AC
© 2010 Robertson Consulting Ltd 9
10
MSProject 2010 & EVM
Typical Schedule Corrective Action Metrics
o To Complete Schedule Performance Index
(TCSPI)
TCSPI = (Unearned Duration Remaining)/ (Actual
Duration Remaining)
o To stay within original PMB
TCSPI = [PD – (AD)(SPI)] / [(PD - AD)]
o To stay within the latest revised Schedule (LRS)
where baseline remains at original PMB
TCSPI = ([PD – (AD)(SPI)] / [(LRS - AD)]
© 2010 Robertson Consulting Ltd 10
11
Typical Information Collection Table
Values Variance Performance Index
WBS Element
Planned
Value (PV)
Earned
Value
Actual
Cost
(AC)
Schedule
EV-PV
Cost
EV-AC
Schedule
EV/PV
Cost
EV/AC
1.0 Pre-Pilot
Plan
63,000 58,000 62,500 (5,000) (4,500) 0.92 0.93
2.0 Checklists 64,000 48,000 46,800 (16,000) 1,200 0.75 1.03
3.0 Curriculum 23,000 20,000 23,500 (3,000) (3,500) 0.87 0.85
4.0 Mid-Term
Evaluation
68,000 68,000 72,500 - (4,500) 1.00 0.94
5.0
Implementation
Support
12,000 10,000 10,000 (2,000) - 0.83 1.00
6.0 Practice
Manual
7,000 6,200 6,000 (800) 200 0.89 1.03
7.0 Roll-out
Plan
20,000 13,500 18,100 (6,500) (4,600) 0.68 0.75
Totals 257,000 223,700 239,400 (33,000) (15,700) 0.87 0.93
© 2010 Robertson Consulting Ltd 11
12
Earned Value Analysis
0
1
2
3
4
5
6
7
Initiation Planning Execution Close Down
Actual
Budgetted
Earned Value
CV
SV
CV = EV – AC (BCWP – ACWP)
CPI = EV/ AC ( BCWP / ACWP)
SV = EV – PV (BCWP – BCWS)
SPI = EV/PV (BCWP/BCWS)
CR = CPI x SPI ((BCWP2 / (ACWP x BCWS))
STATUS
DATE
12© 2010 Robertson Consulting Ltd
Analysis Design Develop Deploy Operate
13
Earned Value Useful Notes
Main EV measures:
 CV = EV – AC (BCWP- ACWP)
 SV = EV – PV (BCWP-BCWS)
 Above result “0” is on target
 CPI = EV/AC (BCWP/ACWP)
 SPI = EV/PV (BCWP/BCWS)
 CPI, SPI = 1 is on target
 CR = CPI x SPI
 CR >= 1.0 is good
Integrates Scope, Time and Cost
• Cost Variance (CV)
• Schedule Variance (SV)
• Time Variance (TV)
• Earned Value (EV = BCWP)
• Actual Cost (AC = ACWP) – (if per time
= Burn rate)
• Planned Value (PV = BCWS)
• Budget at Completion (BAC)
• Schedule at Completion (SAC)
• Cost Performance Index (CPI)
• Schedule Performance Index (SPI)
• Critical Ratio (CR)
13© 2010 Robertson Consulting Ltd
14
Can I help further?
• Training in Earned Value
• PMI Training
• Project Consultancy – making it work on the ground
• Project Management Maturity Model Assessment
• Organisational Maturity Model Assessment
• Bespoke Training or facilitation solutions
Simon Robertson
+44 (0)7967300344
simon@robertsonconsulting.co.uk
14

More Related Content

What's hot

Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
Glen Alleman
 
Estimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulationEstimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulation
Glen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
Glen Alleman
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
Glen Alleman
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
Glen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
Glen Alleman
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
Glen Alleman
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
JustAcademy
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
Glen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
Glen Alleman
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
Glen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
Glen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
Glen Alleman
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
project management
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
Glen Alleman
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
Glen Alleman
 
SE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of SuccessSE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of Success
Glen Alleman
 
Program Management Office Services
Program Management Office ServicesProgram Management Office Services
Program Management Office Services
Glen Alleman
 

What's hot (20)

Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
 
Estimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulationEstimating cost and schedule for monte carlo simulation
Estimating cost and schedule for monte carlo simulation
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess5 Immutable Principles of Capital Project SUccess
5 Immutable Principles of Capital Project SUccess
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Scrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise LevelsScrum Lifecycle At Enterprise Levels
Scrum Lifecycle At Enterprise Levels
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...Five Immutable Principles of Program Success and Their Supporting Processes a...
Five Immutable Principles of Program Success and Their Supporting Processes a...
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?What Makes a Good Concept of Operations?
What Makes a Good Concept of Operations?
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
IMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is ParamountIMP & WBS - Getting Both Right is Paramount
IMP & WBS - Getting Both Right is Paramount
 
SE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of SuccessSE1 - Integrating SE and PPM to Increase the Probability of Success
SE1 - Integrating SE and PPM to Increase the Probability of Success
 
Program Management Office Services
Program Management Office ServicesProgram Management Office Services
Program Management Office Services
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 

Viewers also liked

Performance management
Performance managementPerformance management
Performance management
Emma Yaks
 
Measurement Techniques V1.01 S
Measurement Techniques V1.01 SMeasurement Techniques V1.01 S
Measurement Techniques V1.01 S
Pawoot (Pom) Pongvitayapanu
 
Advanced network performance measurement techniques
Advanced network performance measurement techniquesAdvanced network performance measurement techniques
Advanced network performance measurement techniques
Martin Geddes
 
Project Performance Reporting
Project Performance ReportingProject Performance Reporting
Project Performance Reporting
Association for Project Management
 
Techniques for measurement of productivity
Techniques for measurement of productivityTechniques for measurement of productivity
Techniques for measurement of productivity
ANSHUL AHUJA
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performance
liviu00
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
Glen Alleman
 
Project performance tracking analysis and reporting
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reporting
Charles Cotter, PhD
 
Project-performance appraisal
Project-performance appraisalProject-performance appraisal
Project-performance appraisal
abhisaxena
 
Measurement and scaling techniques
Measurement  and  scaling  techniquesMeasurement  and  scaling  techniques
Measurement and scaling techniquesUjjwal 'Shanu'
 
Performance Management
Performance ManagementPerformance Management
Performance Management
Gautam Ghosh
 
Project Management KPIs
Project Management KPIsProject Management KPIs
Project Management KPIs
Tom Tsongas, PMP, CSM
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
SlideShare
 

Viewers also liked (15)

Performance management
Performance managementPerformance management
Performance management
 
Measurement Techniques V1.01 S
Measurement Techniques V1.01 SMeasurement Techniques V1.01 S
Measurement Techniques V1.01 S
 
Advanced network performance measurement techniques
Advanced network performance measurement techniquesAdvanced network performance measurement techniques
Advanced network performance measurement techniques
 
Project Performance Reporting
Project Performance ReportingProject Performance Reporting
Project Performance Reporting
 
Techniques for measurement of productivity
Techniques for measurement of productivityTechniques for measurement of productivity
Techniques for measurement of productivity
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performance
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
 
performance measures
performance measuresperformance measures
performance measures
 
Project performance - some thoughts and reflections
Project performance - some thoughts and reflectionsProject performance - some thoughts and reflections
Project performance - some thoughts and reflections
 
Project performance tracking analysis and reporting
Project performance tracking analysis and reportingProject performance tracking analysis and reporting
Project performance tracking analysis and reporting
 
Project-performance appraisal
Project-performance appraisalProject-performance appraisal
Project-performance appraisal
 
Measurement and scaling techniques
Measurement  and  scaling  techniquesMeasurement  and  scaling  techniques
Measurement and scaling techniques
 
Performance Management
Performance ManagementPerformance Management
Performance Management
 
Project Management KPIs
Project Management KPIsProject Management KPIs
Project Management KPIs
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Similar to Project Performance Measurement Earned Value A Starter

Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
PMI-Montréal
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Russell Taylor BEng CEng FAPM FIET
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
 
Earned value
Earned valueEarned value
Earned value
Oliver
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
Dhamo daran
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
Aquamarine Emerald
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
Association for Project Management
 
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset managementWebinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
Stork
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
Association for Project Management
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
Dr Mohamed Elfarran
 
project-management-process
project-management-processproject-management-process
project-management-processJose P. Banuelos
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
Sayed Ahmed
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
G K, BE,MS,ISTQB Certified Expert
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
vitumbikokhoswe1
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
yogeshagrawal84
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
Ejaz Bhatti
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdf
Elyes ELEBRI
 
An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...
Association for Project Management
 

Similar to Project Performance Measurement Earned Value A Starter (20)

Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned value
Earned valueEarned value
Earned value
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9   lon...
PGBM01 - MBA Financial Management And Control (2015-16 Trm1 A)Lecture 9 lon...
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset managementWebinar - Slimme besluitvorming over project-portfolio’s in asset management
Webinar - Slimme besluitvorming over project-portfolio’s in asset management
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
project-management-process
project-management-processproject-management-process
project-management-process
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Lecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.pptLecture 5- Monitoring and Controlling Projects.ppt
Lecture 5- Monitoring and Controlling Projects.ppt
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdf
 
An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...An introduction to an effective earned value management system (EVMS) webinar...
An introduction to an effective earned value management system (EVMS) webinar...
 

Recently uploaded

Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
Fwdays
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
CatarinaPereira64715
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
Product School
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
Abida Shariff
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 

Recently uploaded (20)

Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 

Project Performance Measurement Earned Value A Starter

  • 1. 1 Project Performance Measurement - Earned Value Simon Robertson © 2010 Robertson Consulting Ltd June 2010
  • 2. 2 Benefits of EVM • An up-to-date accurate status of the project • Solid input to proactively make corrections • Allows managing stakeholder expectations • Historic reference for future estimates • No surprises to the customer • More accurate representation of on-time completion © 2010 Robertson Consulting Ltd 2
  • 3. 3 MSProject 2010 & EVM © 2010 Robertson Consulting Ltd When? Just after you develop the Schedule….. 3
  • 4. 4 MSProject 2010 & EVM • Important Issue Indicators o Cost overrun – may be working additional hours to keep timeline o Time overrun – may be availability of resources limited o Cost and Time overrun – may be project control, poor quality, rework was necessary © 2010 Robertson Consulting Ltd • Steps to prepare o Ensure all Resources and Materials are in MSProject o Ensure all planning complete and schedule agreed o Establish project baseline from where the variances will be calculated and presented o Add Columns to reflect the EV measures o Prepare project management documents to meet the tracking and reporting requirements from the various project stakeholders o Set expectations with the project team, address any concerns and get buy-in 4
  • 5. 5 MSProject 2010 & EVM Typical Measures o Planned Value (PV) – amount budgeted to be spent between task’s start date and the status date o Actual Cost (AC) – amount spent while preforming work on a task during a given period o Earned Value (EV) – amount that that should have been spent for a given percentage of work performed on a task © 2010 Robertson Consulting Ltd 5
  • 6. 6 MSProject 2010 & EVM Typical Variance Metrics oCost Variance(CV) – links spending to earned value CV = EV – AC or BCWP - ACWP oSchedule Variance (SV) – links the work accomplished (earned) with planned SV = EV – PV or BCWP - BCWS © 2010 Robertson Consulting Ltd 6
  • 7. 7 MSProject 2010 & EVM Typical Performance Indicators o Cost Performance Index CPI = EV/AC or BCWP/ACWP o Schedule Performance Index SPI = EV/PV or BCWP/BCWS o Critical Ratio (?) CR = CPI x SPI or BCWP2/ACWP x BCWS © 2010 Robertson Consulting Ltd 7
  • 8. 8 MSProject 2010 & EVM Typical Forecasting Metrics o Estimate at Completion (EAC)– apply CPI and SPI as performance factors (PF) o Mathematical EAC (uses PF = 1) EACm = (BAC – EV) + AC or EACm = BAC – CV o Low End EAC (uses PF = CPI) EACL= [(BAC-EV)/ (CPI)] + AC Or EACL = (BAC)/ (CPI) o High End EAC (uses PF = CPI x SPI) EACH = [(BAC – EV)/(CPI x SPI)] + AC © 2010 Robertson Consulting Ltd 8
  • 9. 9 MSProject 2010 & EVM Typical Cost Corrective Action Metrics o To Complete Performance Index (TCPI) TCPI = (Work remaining)/ (Funds Remaining) o To stay within original BAC TCPI = (BAC – EV) / (BAC – AC) o To stay within newly forecasted LRE where baseline remains at original BAC TCPI = (BAC – EV) / (LRE – AC ) Where LRE (Latest Revised Estimate) LRE (or EACE) = ETC + AC © 2010 Robertson Consulting Ltd 9
  • 10. 10 MSProject 2010 & EVM Typical Schedule Corrective Action Metrics o To Complete Schedule Performance Index (TCSPI) TCSPI = (Unearned Duration Remaining)/ (Actual Duration Remaining) o To stay within original PMB TCSPI = [PD – (AD)(SPI)] / [(PD - AD)] o To stay within the latest revised Schedule (LRS) where baseline remains at original PMB TCSPI = ([PD – (AD)(SPI)] / [(LRS - AD)] © 2010 Robertson Consulting Ltd 10
  • 11. 11 Typical Information Collection Table Values Variance Performance Index WBS Element Planned Value (PV) Earned Value Actual Cost (AC) Schedule EV-PV Cost EV-AC Schedule EV/PV Cost EV/AC 1.0 Pre-Pilot Plan 63,000 58,000 62,500 (5,000) (4,500) 0.92 0.93 2.0 Checklists 64,000 48,000 46,800 (16,000) 1,200 0.75 1.03 3.0 Curriculum 23,000 20,000 23,500 (3,000) (3,500) 0.87 0.85 4.0 Mid-Term Evaluation 68,000 68,000 72,500 - (4,500) 1.00 0.94 5.0 Implementation Support 12,000 10,000 10,000 (2,000) - 0.83 1.00 6.0 Practice Manual 7,000 6,200 6,000 (800) 200 0.89 1.03 7.0 Roll-out Plan 20,000 13,500 18,100 (6,500) (4,600) 0.68 0.75 Totals 257,000 223,700 239,400 (33,000) (15,700) 0.87 0.93 © 2010 Robertson Consulting Ltd 11
  • 12. 12 Earned Value Analysis 0 1 2 3 4 5 6 7 Initiation Planning Execution Close Down Actual Budgetted Earned Value CV SV CV = EV – AC (BCWP – ACWP) CPI = EV/ AC ( BCWP / ACWP) SV = EV – PV (BCWP – BCWS) SPI = EV/PV (BCWP/BCWS) CR = CPI x SPI ((BCWP2 / (ACWP x BCWS)) STATUS DATE 12© 2010 Robertson Consulting Ltd Analysis Design Develop Deploy Operate
  • 13. 13 Earned Value Useful Notes Main EV measures:  CV = EV – AC (BCWP- ACWP)  SV = EV – PV (BCWP-BCWS)  Above result “0” is on target  CPI = EV/AC (BCWP/ACWP)  SPI = EV/PV (BCWP/BCWS)  CPI, SPI = 1 is on target  CR = CPI x SPI  CR >= 1.0 is good Integrates Scope, Time and Cost • Cost Variance (CV) • Schedule Variance (SV) • Time Variance (TV) • Earned Value (EV = BCWP) • Actual Cost (AC = ACWP) – (if per time = Burn rate) • Planned Value (PV = BCWS) • Budget at Completion (BAC) • Schedule at Completion (SAC) • Cost Performance Index (CPI) • Schedule Performance Index (SPI) • Critical Ratio (CR) 13© 2010 Robertson Consulting Ltd
  • 14. 14 Can I help further? • Training in Earned Value • PMI Training • Project Consultancy – making it work on the ground • Project Management Maturity Model Assessment • Organisational Maturity Model Assessment • Bespoke Training or facilitation solutions Simon Robertson +44 (0)7967300344 simon@robertsonconsulting.co.uk 14