The strategy - in progress - of what the NESMA aims to achieve in the year 2020. Latest version with imput from the Spring conference. Most discussion groups advised the NESMA to aim for topics, rather than isolated products.
The strategy - in progress - of what the NESMA aims to achieve in the year 2020. Latest version with imput from the Spring conference. Most discussion groups advised the NESMA to aim for topics, rather than isolated products.
The processes are the backbones of PMBoK.PMI now in its Fifth Edition has raised them from 9 to 10. This presentation only covers the 9. The10th process on portfolio Management could be obtained from other sources by the reader.
I invite you for PMP® CERTIFICATION PREPARATION CRUISE in Gdańsk. This training course will prepare you to passing PMP® at your first try.
Training is aligned with Fifth Edition of the PMBOK® Guide and will be performed in English.
If you are not interested in the passing PMP®, but you want to learn project management skills, this is a training also for you.
There will be plenty of exercises to ensure gained knowledge stays for a long time. Each knowledge area is followed by a quick test.
The processes are the backbones of PMBoK.PMI now in its Fifth Edition has raised them from 9 to 10. This presentation only covers the 9. The10th process on portfolio Management could be obtained from other sources by the reader.
I invite you for PMP® CERTIFICATION PREPARATION CRUISE in Gdańsk. This training course will prepare you to passing PMP® at your first try.
Training is aligned with Fifth Edition of the PMBOK® Guide and will be performed in English.
If you are not interested in the passing PMP®, but you want to learn project management skills, this is a training also for you.
There will be plenty of exercises to ensure gained knowledge stays for a long time. Each knowledge area is followed by a quick test.
AVEVA World Conference NA - Justin Weaver, Southern CompanyAVEVA-Americas
Digitalization often focuses on engineering and design. But how can digitalization open up opportunities in EPC project performance beyond engineering?
This presentation reviews the potential benefits Southern Company has found in procurement, construction, project controls, and commissioning. It also covers the implementation plan at Southern Company and how it ties into their larger Advanced Work Packaging and Materials Management initiatives.
In many organizations, bottom up estimation of software development projects is still the way to go. Management feels that top-down (parametric) estimation models require too much effort and cost. In this presentation, a random selection of 10 bids are analyzed and the bottom-up estimates and top-down estimates are compared with regard to accuracy and effort spend.
Plataforma inteligente que integra os mais importantes usos do BIM 3D / 4D / 5D / 6D em uma solução única.
Para maiores informações:
www.natecnologia.com.br
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Biological screening of herbal drugs: Introduction and Need for
Phyto-Pharmacological Screening, New Strategies for evaluating
Natural Products, In vitro evaluation techniques for Antioxidants, Antimicrobial and Anticancer drugs. In vivo evaluation techniques
for Anti-inflammatory, Antiulcer, Anticancer, Wound healing, Antidiabetic, Hepatoprotective, Cardio protective, Diuretics and
Antifertility, Toxicity studies as per OECD guidelines
A workshop hosted by the South African Journal of Science aimed at postgraduate students and early career researchers with little or no experience in writing and publishing journal articles.
Acetabularia Information For Class 9 .docxvaibhavrinwa19
Acetabularia acetabulum is a single-celled green alga that in its vegetative state is morphologically differentiated into a basal rhizoid and an axially elongated stalk, which bears whorls of branching hairs. The single diploid nucleus resides in the rhizoid.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
2. Purpose of the Cost Management
Budgeting and controlling the costs so that the
project can be completed within the approved
budget
www.projektor.ee/pm/#cost
27. Cost Control System
• Comparing actual costs with baseline costs
• Reflecting schedule and scope changes in the
budget
• Avoiding non-eligible expenses
• Change communication
• Bringing cost overruns within accepted limit
www.projektor.ee/pm/#cost
28. Earned Value Method
Method that measures
performance of the project and
forecast future performance based
on past performance
work completed ratio × budget price
www.projektor.ee/pm/#cost
29. Earned Value Analysis EVA
• Method for measuring project progress
• Project scope, duration and cost integration
• Enables to estimate project final cost and duration in
the middle of the project
www.projektor.ee/pm/#cost
30. Concept of Earned Value
• Planned value (PV) = planned work × budget price
• Earned value (EV) = work completed ratio × budget
price (actual performance % × budgeted total cost)
• Actual cost (AC) = actual work × actual cost
www.projektor.ee/pm/#cost
31. Planned Value - Earned Value - Actual Value
BMBOK Guide 2009 www.projektor.ee/pm/#cost
32. Earned Value Implementation
• Cost variance (CV) = earned value (EV) – actual cost (AC)
• Schedule variance (SV) = earned value (EV) – planned value
(PV)
• Cost estimation (cost performance index CPI) = earned
value(EV) / actual cost (AC)
• Duration estimation (schedule performance index SPI) =
earned value (EV) / planned value (PV)
www.projektor.ee/pm/#cost
33. Planned task duration 4 d
Planned resource cost 30 $/h
Planned task total cost 960 $/h
Completed duration 2 d
Planned percent complete 50%
Remaining duration estimation 3 d
Actual percent complete 40%
Actual resource cost 25 $/h
How big is:
Planned value 480 $
Earned value 384 $
Actual value 400 $
Estimated total cost 1000 $
www.projektor.ee/pm/#cost
34. Planned task duration 4 d
Planned resource cost 30 $/h
Planned task total cost 960 $/h = 4d x 30 x 8h
Completed duration 2 d
Planned percent complete 50% = 2d / 4d
Remaining duration estimation 3 d
Actual percent complete 40% = 2d / 5d
Actual resource cost 25 $/h
How big is:
Planned value 480 $ = 2d x 30 x 8h
Earned value 384 $ = 960 x 40%
Actual value 400 $ = 2d x 25 x 8h
Estimated total cost 1000 $ = 5d x 8d x 25$/h
www.projektor.ee/pm/#cost
36. Cost Forecasting Method
• CPI - Cost Performance Index (CPI= EV/AC)
• ETC - Estimate to Complete - the remaining cost of
the project
• EAC - Estimate at Completion - the total cost of the
project at the end
www.projektor.ee/pm/#cost
Mostly focus on cost of resources needed in order to complete the project.
Project life-cycle costing = project decision effect on project results (e.g. limiting resign review = decreasing production costs, increasing client’s operational costs)
Estimating – approximate costs (currency or work units) – focus on resources
Budgeting – calculating task, WP and project cost
In smaller projects cost estimating and budgeting are integrated together.
+IN:
Resource calendars
Cost management plan
+MET:
Cost aggregation???
Cost of quality???
Reserve analysis???
Funding limit reconciliation
+OUT:
Requested changes???
Market – what resources are available, what prices
Commercial database as a service
Too general
Parameetriline – näiteks elamu hinna arvutamine ruutmeetrite alusel, tarkvara puhul 13 faktorist koosnev hindamismudel (5 parameetrit igas)
Management puudu
SOW - Statement of Work
Total: 5D x 8H x 25$/h = 1000
Eelmine valem ???: 400 / 384 x 960
Exercises based on equations:
- ETC based on new estimate
- ETC based on Atypical variance ETC = BAC - EVC
- ETC based on typical variance ETC = (BAC - EVC)/CPIC
- EAC using a new estimate EAC = ACC + ETC
- EAC using remaining budget: EAC = ACC + BAC - EV
- EAC using CPIC: EAC = ACC + (BAC – EV)/CPIC
BAC: Budget at completion