SlideShare a Scribd company logo
Figuring Out:
        Where Are You?
                    &
Does your Contractor Agree?



Roger D. H. Warburton, PhD, PMP
           Associate Professor,
  Metropolitan College, Boston University
The
        “How ya doin?”
           Problem
Contractor:   We’re a little behind, but
              it’s not a problem.
              We’ll make it up.


What do you say?
Route 93 Re-Paving Problem
We Have a Plan

From 128/I93 to I90-I93 is 7.7 miles.

Plan:       0.77 miles each month
Schedule:   10 months.
Cost:       $1,470,000.
What Actually Happened?

Month 1:

Contractor: We’re a little behind,
            but it’s not a problem.
            We’ll make it up.
What Actually Happened?

Month 2:

Contractor: We’re a little behind,
            but it’s not a problem.
            We’ll make it up.
What Actually Happened?

Month 3:   We’re a little behind,
           but it’s not a problem.
           We’ll make it up.



     Enough Already!
Here’s the bill!
       Month 11
  Budget       Actual
$1,470,000   $1,869,000

There is a better way!
How Do We Measure
     “Progress?”
Against the plan …..
   Planned 0.77 miles



   Actual 0.66 miles



 You can always measure something!
What Was Accomplished?
   Miles of Roadway
   Lines of code
    designed, written, tested
   Drawings completed          WBS:
   Reports delivered        Deliverable
   Units delivered           Oriented
    Square Meters of Paint
                              Hierarchy


   Feet of Steel Erected
   Cubic Yards of Tunnel Dug Out
You Already Have The Data

You are the PM.
The Mayor wants to know the
status of the project.

  Monthly Reports:
     What was planned?
     What was accomplished?
     What did it cost?
End of Month 2
1)   Measure Progress:
         Planned 1.54 miles


         Actual 1.49 miles


2)   Report Costs:
         Planned $294,000


         Actual $329,000
The “Value” of a Mile

Plan:      7.7 miles
Cost:      $1,470,000

Planned Cost / Mile = $190,909

Complete ½ mile:
   “Value” = $190,909 ÷ 2
           =     $95,455
The “Value” of a Mile

Plan:      7.7 miles
Cost:      $1,470,000

Planned Cost / Mile = $190,909

Complete ½ mile:
   “Value” = $190,909 / 2
                          Earned
           =     $95,455
                          Value
Glossary
   Planned Value, PV
       The sum of the value of the work planned


   Earned Value, EV
       The sum of the value of work performed


   Actual Cost, AC
        The sum of the costs incurred
Glossary
   Budget At Completion,    BAC
   Estimated At Completion, EAC
   Estimate To Complete,    ETC               EAC
                         Time Now
           Budget, BAC                        Estimate
                                            To Complete
                                                ETC

       $
                             Actual Costs
                             To Date
Glossary
   Cost Performance Index, CPI




   Schedule Performance Index, SPI
CPI: Cost Efficiency





                             Planned 1.54 miles


    Cost / Mile = $190,909   Actual 1.43 miles
SPI: Schedule Efficiency
   Schedule Performance Index, SPI
                      Planned 1.54 miles


                      Actual 1.43 miles




      You are behind schedule
How Much Behind?
   Schedule Variance, SV
                      Planned 1.54 miles


                      Actual 1.43 miles




    You are $21,000 behind schedule!
Route 93 Status: Month 4
You are the PM.
The Mayor wants to know the status of
the project.
         (Miles Completed)                Cost

Month   Planned    Completed    Planned          Actual
  1         0.77         0.77     $147,000       $181,000
  2         0.77         0.66     $147,000       $161,000
  3         0.77         0.62     $147,000       $187,000
  4         0.77         0.58     $147,000       $177,000


             Plot Everything!
What actually happened?




         Months
Add the Cost




    Months
Cumulative Costs




       Months
Efficiency




   Months
Graphs vs. Tables



                    Month   CPI
                      1     0.81
                      2     0.80
                      3     0.74
                      4     0.71



  Months
Typical CPI & SPI




   CPI falls & Levels off
   SPI falls & rises → 1.0
How Much Will It Cost?
Estimate at
Completion

BAC = $1,470,000




CPI = 0.8 → EAC = $1,838,000
Estimate at Completion #2




    #1: EAC = $1,838,000
Plot EAC (t)
Earned Value Management (EVM)
   Provides early warning of trouble
   EAC reliable ~ 20% into a project
   Christensen & Heise, 1992
      DOD experience >400 programs since 1977

      Without exception:


         The cumulative CPI does not
          significantly improve during the
          period of 15% through 85% of the
          contract
         In fact it tends to decline!
“I did not use EVM because …”
   “Not needed on small projects”
   “Hard to apply” (Kim, 2000)
   “The implementation
    requirements, terminology, and the countless
                  Contractor
    rules and interpretations, are perceived as
                     Excuses
    overly restrictive” (Fleming & Koppelman, 2005)
   It is difficult to find a balance between the utility
    of the EV technique . . . versus the effort it takes
    to implement (Quentin & Koppelman, 2005)
From Earned Value
       to
      TCPI
PMBOK        4th   Edition

The to-complete performance index
(TCPI) is the calculated projection of
cost performance that must be
achieved on the remaining work to
meet a specified management goal,
such as the BAC or the EAC.
TCPI
A simple formula to change
        the world!

   “Once our customers start
  calculating TCPI, we will no
longer be able to fudge project
             cost!”
What is TCPI?
TCPI: Month 4
   Work Remaining:
       BAC – EV(t) = $1,470,000 – $546,000
   Funds Remaining:
       BAC – AC(t) = $1,470,000 – $681,000
You:
You need a 17% improvement.

Contractor:
No problem!

Trust me, we’ll make it up.

Everything will be OK.
Really?!
Your current efficiency is 80%

Your TCPI is 117%

    You need a 37%
     improvement!
It’s Getting Worse!

            37%




You need a 37% improvement!
You Can’t Win!

 You need
 to be here!




    TCPI → ∞!
Admit it,



            You’re here
The “Modus” Project
Cumulative Doesn’t Help
Modus: CPI & SPI
We Know the Cost
Guidance

Conclusion

  Earned Value is the
Public Sector Manager’s
         Friend
Thank
   You

rwarb@bu.edu
PMBOK to the Rescue!
If it becomes obvious that the BAC
is no longer viable, the EAC
supersedes the BAC
TCPI with EAC




Required efficiency is just the CPI!
Admit it,



            You’re here
Schedule Prediction

More Related Content

Viewers also liked

Trabajo final taller Intel Aprender. Telecentro Arturo Prat Buin
Trabajo final taller Intel Aprender. Telecentro Arturo Prat BuinTrabajo final taller Intel Aprender. Telecentro Arturo Prat Buin
Trabajo final taller Intel Aprender. Telecentro Arturo Prat Buin
Intel Aprender Chile
 
El sentimiento del Tango - opening photos
El sentimiento del Tango - opening photosEl sentimiento del Tango - opening photos
El sentimiento del Tango - opening photos
Alfonso Caputo
 
Animals are awesome
Animals are awesomeAnimals are awesome
Animals are awesome
Drew Wilson
 
1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο
1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο
1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωροart-stella
 
La gestion du cycle de projet
La gestion du cycle de projetLa gestion du cycle de projet
La gestion du cycle de projet
Institut Pasteur de Madagascar
 
ACEROS INOXIDABLES
ACEROS INOXIDABLESACEROS INOXIDABLES
Control seguridad alimentaria y sincronización operaciones
Control seguridad alimentaria y sincronización operacionesControl seguridad alimentaria y sincronización operaciones
Control seguridad alimentaria y sincronización operaciones
ainia centro tecnológico
 
Deideologizaciya -novaya_ideiologiya
Deideologizaciya  -novaya_ideiologiyaDeideologizaciya  -novaya_ideiologiya
Deideologizaciya -novaya_ideiologiyaпрофессор
 
Question 4
Question 4Question 4
Question 4
longroadthriller13
 
Plan Económico y Financiero
Plan Económico y FinancieroPlan Económico y Financiero
Plan Económico y Financiero
Catherine Torres
 
1.2 tatiana
1.2 tatiana1.2 tatiana
1.2 tatiana
percantinoplacito
 

Viewers also liked (11)

Trabajo final taller Intel Aprender. Telecentro Arturo Prat Buin
Trabajo final taller Intel Aprender. Telecentro Arturo Prat BuinTrabajo final taller Intel Aprender. Telecentro Arturo Prat Buin
Trabajo final taller Intel Aprender. Telecentro Arturo Prat Buin
 
El sentimiento del Tango - opening photos
El sentimiento del Tango - opening photosEl sentimiento del Tango - opening photos
El sentimiento del Tango - opening photos
 
Animals are awesome
Animals are awesomeAnimals are awesome
Animals are awesome
 
1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο
1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο
1ο Γυμνάσιο Καρπενησίου - αντικειμενα στον χωρο
 
La gestion du cycle de projet
La gestion du cycle de projetLa gestion du cycle de projet
La gestion du cycle de projet
 
ACEROS INOXIDABLES
ACEROS INOXIDABLESACEROS INOXIDABLES
ACEROS INOXIDABLES
 
Control seguridad alimentaria y sincronización operaciones
Control seguridad alimentaria y sincronización operacionesControl seguridad alimentaria y sincronización operaciones
Control seguridad alimentaria y sincronización operaciones
 
Deideologizaciya -novaya_ideiologiya
Deideologizaciya  -novaya_ideiologiyaDeideologizaciya  -novaya_ideiologiya
Deideologizaciya -novaya_ideiologiya
 
Question 4
Question 4Question 4
Question 4
 
Plan Económico y Financiero
Plan Económico y FinancieroPlan Económico y Financiero
Plan Económico y Financiero
 
1.2 tatiana
1.2 tatiana1.2 tatiana
1.2 tatiana
 

Similar to Figuring out where you are and does your contractor agree?

Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
Manish Purwar
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
Fahad Ali
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
sajidkhan82714
 
Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
Roger H. Mandel
 
Logic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without MathLogic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without Math
Martin Bailey
 
Earned value management
Earned value managementEarned value management
Earned value management
whizkris
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
haroldtaylor1113
 
Understanding_EVA_V2.pptx
Understanding_EVA_V2.pptxUnderstanding_EVA_V2.pptx
Understanding_EVA_V2.pptx
FasiHaider3
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
Association for Project Management
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
Qais Ur Rehman Rasooli, PMP
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
Glen Alleman
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
DILIP KUMAR M.Tech (ACT)
 
Earned value management
Earned value managementEarned value management
Earned value management
Ar. Faisal Husaini
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
Anand Bobade
 

Similar to Figuring out where you are and does your contractor agree? (20)

Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
Earned Value Management Project Analysis
Earned Value Management Project Analysis Earned Value Management Project Analysis
Earned Value Management Project Analysis
 
Logic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without MathLogic of Formulas - how to answer EVM questions without Math
Logic of Formulas - how to answer EVM questions without Math
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Understanding_EVA_V2.pptx
Understanding_EVA_V2.pptxUnderstanding_EVA_V2.pptx
Understanding_EVA_V2.pptx
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
 
Earned value management
Earned value managementEarned value management
Earned value management
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 

Recently uploaded

A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
ControlCase
 
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
SOFTTECHHUB
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Aggregage
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
Aftab Hussain
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
DianaGray10
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
Uni Systems S.M.S.A.
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
mikeeftimakis1
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
DianaGray10
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Vladimir Iglovikov, Ph.D.
 
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
Neo4j
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Paige Cruz
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
Alpen-Adria-Universität
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
Edge AI and Vision Alliance
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
Kumud Singh
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
KAMESHS29
 

Recently uploaded (20)

A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
PCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase TeamPCI PIN Basics Webinar from the Controlcase Team
PCI PIN Basics Webinar from the Controlcase Team
 
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!
 
Generative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to ProductionGenerative AI Deep Dive: Advancing from Proof of Concept to Production
Generative AI Deep Dive: Advancing from Proof of Concept to Production
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Removing Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software FuzzingRemoving Uninteresting Bytes in Software Fuzzing
Removing Uninteresting Bytes in Software Fuzzing
 
Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1Communications Mining Series - Zero to Hero - Session 1
Communications Mining Series - Zero to Hero - Session 1
 
Microsoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdfMicrosoft - Power Platform_G.Aspiotis.pdf
Microsoft - Power Platform_G.Aspiotis.pdf
 
Introduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - CybersecurityIntroduction to CHERI technology - Cybersecurity
Introduction to CHERI technology - Cybersecurity
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
 
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AIEnchancing adoption of Open Source Libraries. A case study on Albumentations.AI
Enchancing adoption of Open Source Libraries. A case study on Albumentations.AI
 
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
GraphSummit Singapore | Neo4j Product Vision & Roadmap - Q2 2024
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
Video Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the FutureVideo Streaming: Then, Now, and in the Future
Video Streaming: Then, Now, and in the Future
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
“Building and Scaling AI Applications with the Nx AI Manager,” a Presentation...
 
Mind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AIMind map of terminologies used in context of Generative AI
Mind map of terminologies used in context of Generative AI
 
RESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for studentsRESUME BUILDER APPLICATION Project for students
RESUME BUILDER APPLICATION Project for students
 

Figuring out where you are and does your contractor agree?

  • 1. Figuring Out: Where Are You? & Does your Contractor Agree? Roger D. H. Warburton, PhD, PMP Associate Professor, Metropolitan College, Boston University
  • 2. The “How ya doin?” Problem Contractor: We’re a little behind, but it’s not a problem. We’ll make it up. What do you say?
  • 4. We Have a Plan From 128/I93 to I90-I93 is 7.7 miles. Plan: 0.77 miles each month Schedule: 10 months. Cost: $1,470,000.
  • 5. What Actually Happened? Month 1: Contractor: We’re a little behind, but it’s not a problem. We’ll make it up.
  • 6. What Actually Happened? Month 2: Contractor: We’re a little behind, but it’s not a problem. We’ll make it up.
  • 7. What Actually Happened? Month 3: We’re a little behind, but it’s not a problem. We’ll make it up. Enough Already!
  • 8. Here’s the bill! Month 11 Budget Actual $1,470,000 $1,869,000 There is a better way!
  • 9. How Do We Measure “Progress?” Against the plan ….. Planned 0.77 miles Actual 0.66 miles You can always measure something!
  • 10. What Was Accomplished?  Miles of Roadway  Lines of code designed, written, tested  Drawings completed WBS:  Reports delivered Deliverable  Units delivered Oriented Square Meters of Paint Hierarchy   Feet of Steel Erected  Cubic Yards of Tunnel Dug Out
  • 11. You Already Have The Data You are the PM. The Mayor wants to know the status of the project. Monthly Reports: What was planned? What was accomplished? What did it cost?
  • 12. End of Month 2 1) Measure Progress: Planned 1.54 miles Actual 1.49 miles 2) Report Costs: Planned $294,000 Actual $329,000
  • 13. The “Value” of a Mile Plan: 7.7 miles Cost: $1,470,000 Planned Cost / Mile = $190,909 Complete ½ mile: “Value” = $190,909 ÷ 2 = $95,455
  • 14. The “Value” of a Mile Plan: 7.7 miles Cost: $1,470,000 Planned Cost / Mile = $190,909 Complete ½ mile: “Value” = $190,909 / 2 Earned = $95,455 Value
  • 15. Glossary  Planned Value, PV  The sum of the value of the work planned  Earned Value, EV  The sum of the value of work performed  Actual Cost, AC  The sum of the costs incurred
  • 16. Glossary  Budget At Completion, BAC  Estimated At Completion, EAC  Estimate To Complete, ETC EAC Time Now Budget, BAC Estimate To Complete ETC $ Actual Costs To Date
  • 17. Glossary  Cost Performance Index, CPI  Schedule Performance Index, SPI
  • 18. CPI: Cost Efficiency  Planned 1.54 miles Cost / Mile = $190,909 Actual 1.43 miles
  • 19. SPI: Schedule Efficiency  Schedule Performance Index, SPI Planned 1.54 miles Actual 1.43 miles You are behind schedule
  • 20. How Much Behind?  Schedule Variance, SV Planned 1.54 miles Actual 1.43 miles You are $21,000 behind schedule!
  • 21. Route 93 Status: Month 4 You are the PM. The Mayor wants to know the status of the project. (Miles Completed) Cost Month Planned Completed Planned Actual 1 0.77 0.77 $147,000 $181,000 2 0.77 0.66 $147,000 $161,000 3 0.77 0.62 $147,000 $187,000 4 0.77 0.58 $147,000 $177,000 Plot Everything!
  • 23. Add the Cost Months
  • 25. Efficiency Months
  • 26. Graphs vs. Tables Month CPI 1 0.81 2 0.80 3 0.74 4 0.71 Months
  • 27. Typical CPI & SPI  CPI falls & Levels off  SPI falls & rises → 1.0
  • 28. How Much Will It Cost? Estimate at Completion BAC = $1,470,000 CPI = 0.8 → EAC = $1,838,000
  • 29. Estimate at Completion #2 #1: EAC = $1,838,000
  • 31. Earned Value Management (EVM)  Provides early warning of trouble  EAC reliable ~ 20% into a project  Christensen & Heise, 1992  DOD experience >400 programs since 1977  Without exception:  The cumulative CPI does not significantly improve during the period of 15% through 85% of the contract  In fact it tends to decline!
  • 32. “I did not use EVM because …”  “Not needed on small projects”  “Hard to apply” (Kim, 2000)  “The implementation requirements, terminology, and the countless Contractor rules and interpretations, are perceived as Excuses overly restrictive” (Fleming & Koppelman, 2005)  It is difficult to find a balance between the utility of the EV technique . . . versus the effort it takes to implement (Quentin & Koppelman, 2005)
  • 33. From Earned Value to TCPI
  • 34. PMBOK 4th Edition The to-complete performance index (TCPI) is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC.
  • 35. TCPI A simple formula to change the world! “Once our customers start calculating TCPI, we will no longer be able to fudge project cost!”
  • 37. TCPI: Month 4  Work Remaining:  BAC – EV(t) = $1,470,000 – $546,000  Funds Remaining:  BAC – AC(t) = $1,470,000 – $681,000
  • 38. You: You need a 17% improvement. Contractor: No problem! Trust me, we’ll make it up. Everything will be OK.
  • 39. Really?! Your current efficiency is 80% Your TCPI is 117% You need a 37% improvement!
  • 40. It’s Getting Worse! 37% You need a 37% improvement!
  • 41. You Can’t Win! You need to be here! TCPI → ∞!
  • 42. Admit it, You’re here
  • 46. We Know the Cost
  • 48. Conclusion Earned Value is the Public Sector Manager’s Friend
  • 49. Thank You rwarb@bu.edu
  • 50. PMBOK to the Rescue! If it becomes obvious that the BAC is no longer viable, the EAC supersedes the BAC
  • 51. TCPI with EAC Required efficiency is just the CPI!
  • 52. Admit it, You’re here