© 2013 Oracle Corporation
Oracle Primavera
Roadmap & Future
Direction
Collaborate 13
April 2013
Primavera Product Strategy
February 2013
© 2013 Oracle Corporation
The following information is intended to outline our general
product direction.
It is intended for information purposes only, and may not be
incorporated into any contract. It is not a commitment to
deliver any material, code, or functionality, and should not be
relied upon in making purchasing decisions.
The development, release, and timing of any features or
functionality described for Oracle’s products remains at the
sole discretion of Oracle.
© 2013 Oracle Corporation
trends
© 2013 Oracle Corporation
PPM IS THE FASTEST GROWING SAAS SEGMENT
*Source: IDC, Gartner
41% ANNUAL GROWTH,
PROJECTED TO GROW FROM
$241 MILLION IN 2011 TO
$952 MILLION IN 2015
PILLAR CAGR
PPM 41%
SCM 13.7%
ERP 10%
CRM 12.9%
© 2013 Oracle Corporation
*Source: Oracle
INTEGRATED INTO THE ENTERPRISE
20 OF THE TOP 20
PRIMAVERA CUSTOMERS
INTEGRATE WITH MISSION
CRITICAL APPLICATIONS
© 2013 Oracle Corporation
*Source: The Productivity Imperative, McKinsey June 2010
85% OF NEW JOBS CREATED
IN THE PAST DECADE
REQUIRED COMPLEX
KNOWLEDGE SKILLS
INNOVATION WORKER & THE RISE OF SOCIAL TOOLS
© 2013 Oracle Corporation
*Source: IDC Worldwide Mobile Worker Population 2009-2013 Forecast
GLOBAL MOBILE WORKER
POPULATION EXPECTED TO
SURPASS 1 BILLION IN 2013,
WHICH ACCOUNTS FOR 35% OF
THE WORKFORCE
MOBILE
© 2013 Oracle Corporation
PROLIFERATION OF PPM IN THE ENTERPRISE
IT 66%
Sales 33%
Product Dev
47%
Operations 59%
Marketing
41%
Finance
41%
*Source: Forrestor
© 2013 Oracle Corporation
© 2013 Oracle Corporation
© 2013 Oracle Corporation
Microsoft Excel
Salesforce
Clarizen
Project.net
ProjectPlace
Evernote
Basecamp
Zoho Projects
Asana
Mavenlink
Powersteering
Sopheon Accolade
Planview
Planisware
GenSight
Daptiv
AtTask
Sciforma
LiquidPlanner
Siemens Teamcenter
CA Clarity
Planview
HP
Compuware
Innotas
Serena
BMC
IBM Rational
Version One
Rally
SAP
Deltek
Artemis
Dekker Tracker
Acumen Fuse
One point
Sciforma PSNext
PDware
Planta
Planisware
SAP
Artemis
IBM Maximo
Prometheus
Click Software
Viziya
ABB Ventyx
Pasta
Logica ARM Suite
Knowledge Relay
Trimble Meridian
CMiC
PMWeb
PowerPlant
eBuilder
Asta
Accruent
Ares Prism
US Cost
IBM Tririga
© 2013 Oracle Corporation
vision
© 2013 Oracle Corporation
IT
NPD
Manufacturing
ETO
Owner
Capital Projects
EPC
Contractor
Routine
Maintenance
Process
Improvement / LSS
Earned Value
Program Management
Shutdown /
Turnaround /
Outage
Installation
Services
#1 MULTI-INITIATIVE PPM SOLUTION
© 2013 Oracle Corporation
how?
© 2013 Oracle Corporation
skire
© 2013 Oracle Corporation
Oracle Primavera + Skire
A complete Construction Lifecycle Management Solution
Capital
Planning
Project
Funding
Plan and
Schedule
Cost
Controls
Manage
Resourc
e & Risk
Change
Mgmt.
Deliver
Projects
Manage
&
Operate
Assets
Initiate
Projects
Prioritize
Projects
Plan
Build
Operate
=
Visibility
Automation
Integration
• Plan
• Shorten cycle time with collaboration between
planning, design and procurement teams
• Complete visibility from project initiation to
capital planning
• Build
• Improve project accountability and regulatory
compliance with proper audit controls
• Control costs and accurately predict cash flow
with integrated and detailed tracking
• Operate
• Improve operation and maintenance with
integrated scheduling tools
• Balance assignment of resources based on
system-wide demands=
© 2013 Oracle Corporation
The Primavera Unifier Solution
Facilities and Real Estate Management
•Complete visibility to all real estate properties –
owned and leased
•Facility management tools that enable enterprises
to operate efficiently
•Streamlines the process to shorten operational
cycle times
Capital Project and Program Management
• Best-in-class cloud-based and on-premise
enterprise solution
• Built for the specialized needs of asset-
intensive industries
• Simple to deploy and use, and proven with
large-scale global enterprises
Key Benefits
• Rapid project execution helps
accelerate the construction and
bid process to meet project
timelines and budgets
• Increases visibility to all projects
to ensure field resources are
allocated appropriately
• Standardization of workflows,
improve coordination between
multiple work sites, reducing
cycle time and costs
© 2013 Oracle Corporation
IT
NPD
Manufacturing
ETO
Owner
Capital Projects
EPC
Contractor
Routine
Maintenance
Process
Improvement / LSS
Earned Value
Program Management
Shutdown /
Turnaround /
Outage
Installation
Services
Delivering on Vision of #1 Multi-Initiative Solution
© 2013 Oracle Corporation
instantis
© 2013 Oracle Corporation
Oracle Primavera + Instantis
Delivers Industry Leading Solution for IT, NPD & LSS
 Purpose Built
Top-down, resource driven environments
with light project management needs
 Cloud Enabled
Instantis is built from the ground up using
cloud native technology
 Seamless PPM
Instantis offers top-down portfolio
capabilities seamlessly integrated
with just enough project execution
.
P6 &
Unifier
Strategies
Tasks
Work Orders
Portfolios
Resources
Deliverables
Projects
Instantis
Corporate Capital ProjectsR & D IT Manufacturing Maintenance
© 2013 Oracle Corporation
IT
NPD
Manufacturing
ETO
Owner
Capital Projects
EPC
Contractor
Routine
Maintenance
Process
Improvement / LSS
Earned Value
Program Management
Shutdown /
Turnaround /
Outage
Installation
Services
Delivering on Vision of #1 Multi-Initiative Solution
© 2012 Oracle Corporation
roadmap
© 2013 Oracle Corporation
OVERARCHING STRATEGY
• P6 EPPM R8.X
• Primavera Unifier 9.X
• Instantis 8.x
• Contract Management
• OPPM 9.X
• P6 Analytics 3.1
• AutoVue
• Crystal Ball
• Risk Analysis
• Gateway
1.
Deliver Customer Value With
Existing Products
© 2013 Oracle Corporation
P6 ANALYTICS 3.1 – Released January 2013
• Shutdown/Outage /Turnaround
• Routine/On-Line Maintenance
• Daily Trending:
• Activity and Assignment History
• Burn Down Charts
• Emergent Work
• INPO AP-928 Support
• Slowly Changing Dimensions
• More UDFs and UDF Types
• Code Hierarchy Support
© 2013 Oracle Corporation
PRIMAVERA GATEWAY – Released March 2013
• Reduced TCO
• Industry specific data flows and
maps
• Pre-build Integrations
and Flows
• Flexible data exchange
• Error handling
• Scalability and ease-of-use
• Quickly build new integration
adaptors
© 2013 Oracle Corporation
PRIMAVERA UNIFIER 9.12 – Released March 2013
• Improved P6 integration
• Content repository support
• CMIS
• UCM
• Red Stack uptake
• Autovue version update
• Security improvements
© 2013 Oracle Corporation
P6 EPPM 8.3 – Released March 2013
• Improved Unifier integration
• Usability and adoption features
• UN/CEFACT XML
• Improved XML import control
• Improvements to Gantt & TSLD
© 2013 Oracle Corporation
P6 EPPM 8.3 – Released March 2013
Rename Columns
Landing page for users
© 2013 Oracle Corporation
P6 EPPM 8.3 – Released March 2013
Select multiple values
from pick lists
Advanced print options
© 2013 Oracle Corporation
• New Graphics Engine
• Gantt & Time-Scaled Logic
Diagrams
• Share graphics
• Run without full PM installed
• Configurable
• Field Stacking
• Text Wrapping
• Variable Timeline
• Connector Blocks
• Batching Reports
P6 EPPM 8.3 Visualizer – Released March 2013
© 2013 Oracle Corporation
Extensive configurability
P6 EPPM 8.3 Visualizer – Released March 2013
© 2013 Oracle Corporation
• Enhanced assignment distribution
• Collaborate via discussion threads
• View Notebooks
• Search & filter tasks
• View documents
• Update codes and UDFs
• iPhone multi-language support
• Email push capability
P6 EPPM 8.3 Team Member – Released March 2013
© 2013 Oracle Corporation
P6 EPPM 8.3 Team Member – Released March 2013
Discussions /
collaboration
© 2013 Oracle Corporation
Update Activity
Codes & UDFs
P6 EPPM 8.3 Team Member – Released March 2013
© 2013 Oracle Corporation
• Enhanced Facilities & Real
Estate mgmt. capabilities
• Recurrence pattern templates
• Improved auto-creation of
preventive maintenance work
orders
PRIMAVERA UNIFIER 9.13 – Planned CY2013
© 2013 Oracle Corporation
UNIFIER MOBILE – Planned CY2013
• Initial focus on tablets (iPad).
• Native mobile application
• Leverage device hardware
• Multi-language support
© 2013 Oracle Corporation
INSTANTIS 8.5 – Planned CY2013
• Resource calendars
• Project request staffing
improvements
• Activity labor cost capitalization
• MS Project 2010 support
• Timesheets enhancements
• Variable resource rates for project
labor costing
• UI and Navigation improvements
© 2013 Oracle Corporation
P6 ANALYTICS 3.2 – Planned CY2013
• Additional P6 dimensional data:
• Resource hierarchies
• Role hierarchies
• Project Owner
• Risk exposure start and finish dates
• Enhanced geospatial mapping support
• Catalog improvements
© 2013 Oracle Corporation
OPPM 9.0 SP2 – Planned CY2013
• Update Bridge to support MS
Project Server 2010
• Configure # of Workflow approvers
• ALL approvers must approve or
ANY approver can approve
• Certification of Oracle database
11.2.0.3
• P1 Defect fixes
© 2013 Oracle Corporation
OPPM 9.1 – Planned CY2014
• Additional types of graphs for dashboards and improved
output controls
• Multi-select and purge workflow instances
• Enable workflow task email notifications to include a
embedded link
• Ability to move items from one portfolio to another via
workflow
• Customer Enhancements
© 2013 Oracle Corporation
CONTRACT MANAGEMENT 14.2 – Planned CY2014
• Enable admins to specify user specific
layouts
• Link submittals and drawings
• Specify Sharepoint site per project rather
than globally
• Create proxy for action items
• Build out web services
• Customer enhancements
© 2013 Oracle Corporation
OVERARCHING STRATEGY
• P6 EPPM R8.X
• Primavera Unifier 9.X
• Instantis 8.5
• Contract Management
• OPPM 9.X
• P6 Analytics
• AutoVue
• Crystal Ball
• Risk Analysis
• Gateway
1.
Deliver customer value With
existing products
• Common UI & Navigation
• More integration of
Schedule, Costs.
Contracts, Changes
• Common Reports / BI
• Common Integration
layer
• Native P6 workflow
• Risk Management
• I18N & Localizations
2.
Integrate and build out P6,
Unifier and Instantis applications
• Mobile, Mobile, Mobile
• ANSI EVMS
• Portfolio Mgmt. +
• Core PM Professional
focus
• Offline Client
• Social / Crowd-sourcing
/ Gamification
3.
Consolidate and extend the
Primavera platform
© 2013 Oracle Corporation
CLOUD & ON-PREMISE PRIMAVERA GATEWAY
ANALYTICS
WORKFLOW
MODERN UI
ORACLE SOCIAL
STREAMS
CROWD SOURCING
GAMIFICATION
NATIVE MOBILE
MULTI-PLATFORM
ORGANIC DEVELOPMENT
ACQUISITONS
IP CONSOLIDATION
CLOUD INTEGRATION SOCIAL MOBILE PPM PROLIFERATION
© 2013 Oracle Corporation
The preceding information is intended to outline our general product
direction.
It is intended for information purposes only, and may not be incorporated
into any contract. It is not a commitment to deliver any material, code, or
functionality, and should not be relied upon in making purchasing
decisions.
The development, release, and timing of any features or functionality
described for Oracle’s products remains at the sole discretion of Oracle.
© 2013 Oracle Corporation
© 2013 Oracle Corporation

Primavera vision & roadmap collaborate13 april 2013

  • 1.
    © 2013 OracleCorporation Oracle Primavera Roadmap & Future Direction Collaborate 13 April 2013 Primavera Product Strategy February 2013
  • 2.
    © 2013 OracleCorporation The following information is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.
  • 3.
    © 2013 OracleCorporation trends
  • 4.
    © 2013 OracleCorporation PPM IS THE FASTEST GROWING SAAS SEGMENT *Source: IDC, Gartner 41% ANNUAL GROWTH, PROJECTED TO GROW FROM $241 MILLION IN 2011 TO $952 MILLION IN 2015 PILLAR CAGR PPM 41% SCM 13.7% ERP 10% CRM 12.9%
  • 5.
    © 2013 OracleCorporation *Source: Oracle INTEGRATED INTO THE ENTERPRISE 20 OF THE TOP 20 PRIMAVERA CUSTOMERS INTEGRATE WITH MISSION CRITICAL APPLICATIONS
  • 6.
    © 2013 OracleCorporation *Source: The Productivity Imperative, McKinsey June 2010 85% OF NEW JOBS CREATED IN THE PAST DECADE REQUIRED COMPLEX KNOWLEDGE SKILLS INNOVATION WORKER & THE RISE OF SOCIAL TOOLS
  • 7.
    © 2013 OracleCorporation *Source: IDC Worldwide Mobile Worker Population 2009-2013 Forecast GLOBAL MOBILE WORKER POPULATION EXPECTED TO SURPASS 1 BILLION IN 2013, WHICH ACCOUNTS FOR 35% OF THE WORKFORCE MOBILE
  • 8.
    © 2013 OracleCorporation PROLIFERATION OF PPM IN THE ENTERPRISE IT 66% Sales 33% Product Dev 47% Operations 59% Marketing 41% Finance 41% *Source: Forrestor
  • 9.
    © 2013 OracleCorporation
  • 10.
    © 2013 OracleCorporation
  • 11.
    © 2013 OracleCorporation Microsoft Excel Salesforce Clarizen Project.net ProjectPlace Evernote Basecamp Zoho Projects Asana Mavenlink Powersteering Sopheon Accolade Planview Planisware GenSight Daptiv AtTask Sciforma LiquidPlanner Siemens Teamcenter CA Clarity Planview HP Compuware Innotas Serena BMC IBM Rational Version One Rally SAP Deltek Artemis Dekker Tracker Acumen Fuse One point Sciforma PSNext PDware Planta Planisware SAP Artemis IBM Maximo Prometheus Click Software Viziya ABB Ventyx Pasta Logica ARM Suite Knowledge Relay Trimble Meridian CMiC PMWeb PowerPlant eBuilder Asta Accruent Ares Prism US Cost IBM Tririga
  • 12.
    © 2013 OracleCorporation vision
  • 13.
    © 2013 OracleCorporation IT NPD Manufacturing ETO Owner Capital Projects EPC Contractor Routine Maintenance Process Improvement / LSS Earned Value Program Management Shutdown / Turnaround / Outage Installation Services #1 MULTI-INITIATIVE PPM SOLUTION
  • 14.
    © 2013 OracleCorporation how?
  • 15.
    © 2013 OracleCorporation skire
  • 16.
    © 2013 OracleCorporation Oracle Primavera + Skire A complete Construction Lifecycle Management Solution Capital Planning Project Funding Plan and Schedule Cost Controls Manage Resourc e & Risk Change Mgmt. Deliver Projects Manage & Operate Assets Initiate Projects Prioritize Projects Plan Build Operate = Visibility Automation Integration • Plan • Shorten cycle time with collaboration between planning, design and procurement teams • Complete visibility from project initiation to capital planning • Build • Improve project accountability and regulatory compliance with proper audit controls • Control costs and accurately predict cash flow with integrated and detailed tracking • Operate • Improve operation and maintenance with integrated scheduling tools • Balance assignment of resources based on system-wide demands=
  • 17.
    © 2013 OracleCorporation The Primavera Unifier Solution Facilities and Real Estate Management •Complete visibility to all real estate properties – owned and leased •Facility management tools that enable enterprises to operate efficiently •Streamlines the process to shorten operational cycle times Capital Project and Program Management • Best-in-class cloud-based and on-premise enterprise solution • Built for the specialized needs of asset- intensive industries • Simple to deploy and use, and proven with large-scale global enterprises Key Benefits • Rapid project execution helps accelerate the construction and bid process to meet project timelines and budgets • Increases visibility to all projects to ensure field resources are allocated appropriately • Standardization of workflows, improve coordination between multiple work sites, reducing cycle time and costs
  • 18.
    © 2013 OracleCorporation IT NPD Manufacturing ETO Owner Capital Projects EPC Contractor Routine Maintenance Process Improvement / LSS Earned Value Program Management Shutdown / Turnaround / Outage Installation Services Delivering on Vision of #1 Multi-Initiative Solution
  • 19.
    © 2013 OracleCorporation instantis
  • 20.
    © 2013 OracleCorporation Oracle Primavera + Instantis Delivers Industry Leading Solution for IT, NPD & LSS  Purpose Built Top-down, resource driven environments with light project management needs  Cloud Enabled Instantis is built from the ground up using cloud native technology  Seamless PPM Instantis offers top-down portfolio capabilities seamlessly integrated with just enough project execution . P6 & Unifier Strategies Tasks Work Orders Portfolios Resources Deliverables Projects Instantis Corporate Capital ProjectsR & D IT Manufacturing Maintenance
  • 21.
    © 2013 OracleCorporation IT NPD Manufacturing ETO Owner Capital Projects EPC Contractor Routine Maintenance Process Improvement / LSS Earned Value Program Management Shutdown / Turnaround / Outage Installation Services Delivering on Vision of #1 Multi-Initiative Solution
  • 22.
    © 2012 OracleCorporation roadmap
  • 23.
    © 2013 OracleCorporation OVERARCHING STRATEGY • P6 EPPM R8.X • Primavera Unifier 9.X • Instantis 8.x • Contract Management • OPPM 9.X • P6 Analytics 3.1 • AutoVue • Crystal Ball • Risk Analysis • Gateway 1. Deliver Customer Value With Existing Products
  • 24.
    © 2013 OracleCorporation P6 ANALYTICS 3.1 – Released January 2013 • Shutdown/Outage /Turnaround • Routine/On-Line Maintenance • Daily Trending: • Activity and Assignment History • Burn Down Charts • Emergent Work • INPO AP-928 Support • Slowly Changing Dimensions • More UDFs and UDF Types • Code Hierarchy Support
  • 25.
    © 2013 OracleCorporation PRIMAVERA GATEWAY – Released March 2013 • Reduced TCO • Industry specific data flows and maps • Pre-build Integrations and Flows • Flexible data exchange • Error handling • Scalability and ease-of-use • Quickly build new integration adaptors
  • 26.
    © 2013 OracleCorporation PRIMAVERA UNIFIER 9.12 – Released March 2013 • Improved P6 integration • Content repository support • CMIS • UCM • Red Stack uptake • Autovue version update • Security improvements
  • 27.
    © 2013 OracleCorporation P6 EPPM 8.3 – Released March 2013 • Improved Unifier integration • Usability and adoption features • UN/CEFACT XML • Improved XML import control • Improvements to Gantt & TSLD
  • 28.
    © 2013 OracleCorporation P6 EPPM 8.3 – Released March 2013 Rename Columns Landing page for users
  • 29.
    © 2013 OracleCorporation P6 EPPM 8.3 – Released March 2013 Select multiple values from pick lists Advanced print options
  • 30.
    © 2013 OracleCorporation • New Graphics Engine • Gantt & Time-Scaled Logic Diagrams • Share graphics • Run without full PM installed • Configurable • Field Stacking • Text Wrapping • Variable Timeline • Connector Blocks • Batching Reports P6 EPPM 8.3 Visualizer – Released March 2013
  • 31.
    © 2013 OracleCorporation Extensive configurability P6 EPPM 8.3 Visualizer – Released March 2013
  • 32.
    © 2013 OracleCorporation • Enhanced assignment distribution • Collaborate via discussion threads • View Notebooks • Search & filter tasks • View documents • Update codes and UDFs • iPhone multi-language support • Email push capability P6 EPPM 8.3 Team Member – Released March 2013
  • 33.
    © 2013 OracleCorporation P6 EPPM 8.3 Team Member – Released March 2013 Discussions / collaboration
  • 34.
    © 2013 OracleCorporation Update Activity Codes & UDFs P6 EPPM 8.3 Team Member – Released March 2013
  • 35.
    © 2013 OracleCorporation • Enhanced Facilities & Real Estate mgmt. capabilities • Recurrence pattern templates • Improved auto-creation of preventive maintenance work orders PRIMAVERA UNIFIER 9.13 – Planned CY2013
  • 36.
    © 2013 OracleCorporation UNIFIER MOBILE – Planned CY2013 • Initial focus on tablets (iPad). • Native mobile application • Leverage device hardware • Multi-language support
  • 37.
    © 2013 OracleCorporation INSTANTIS 8.5 – Planned CY2013 • Resource calendars • Project request staffing improvements • Activity labor cost capitalization • MS Project 2010 support • Timesheets enhancements • Variable resource rates for project labor costing • UI and Navigation improvements
  • 38.
    © 2013 OracleCorporation P6 ANALYTICS 3.2 – Planned CY2013 • Additional P6 dimensional data: • Resource hierarchies • Role hierarchies • Project Owner • Risk exposure start and finish dates • Enhanced geospatial mapping support • Catalog improvements
  • 39.
    © 2013 OracleCorporation OPPM 9.0 SP2 – Planned CY2013 • Update Bridge to support MS Project Server 2010 • Configure # of Workflow approvers • ALL approvers must approve or ANY approver can approve • Certification of Oracle database 11.2.0.3 • P1 Defect fixes
  • 40.
    © 2013 OracleCorporation OPPM 9.1 – Planned CY2014 • Additional types of graphs for dashboards and improved output controls • Multi-select and purge workflow instances • Enable workflow task email notifications to include a embedded link • Ability to move items from one portfolio to another via workflow • Customer Enhancements
  • 41.
    © 2013 OracleCorporation CONTRACT MANAGEMENT 14.2 – Planned CY2014 • Enable admins to specify user specific layouts • Link submittals and drawings • Specify Sharepoint site per project rather than globally • Create proxy for action items • Build out web services • Customer enhancements
  • 42.
    © 2013 OracleCorporation OVERARCHING STRATEGY • P6 EPPM R8.X • Primavera Unifier 9.X • Instantis 8.5 • Contract Management • OPPM 9.X • P6 Analytics • AutoVue • Crystal Ball • Risk Analysis • Gateway 1. Deliver customer value With existing products • Common UI & Navigation • More integration of Schedule, Costs. Contracts, Changes • Common Reports / BI • Common Integration layer • Native P6 workflow • Risk Management • I18N & Localizations 2. Integrate and build out P6, Unifier and Instantis applications • Mobile, Mobile, Mobile • ANSI EVMS • Portfolio Mgmt. + • Core PM Professional focus • Offline Client • Social / Crowd-sourcing / Gamification 3. Consolidate and extend the Primavera platform
  • 43.
    © 2013 OracleCorporation CLOUD & ON-PREMISE PRIMAVERA GATEWAY ANALYTICS WORKFLOW MODERN UI ORACLE SOCIAL STREAMS CROWD SOURCING GAMIFICATION NATIVE MOBILE MULTI-PLATFORM ORGANIC DEVELOPMENT ACQUISITONS IP CONSOLIDATION CLOUD INTEGRATION SOCIAL MOBILE PPM PROLIFERATION
  • 44.
    © 2013 OracleCorporation The preceding information is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle.
  • 45.
    © 2013 OracleCorporation
  • 46.
    © 2013 OracleCorporation