Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted1
Primavera Gateway
John Pikovskiy – Principal Product Manager PGBU Strategy
April 2014
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted2
The following is intended to outline our general product direction.
It is intended for information purposes only, and may not be
incorporated into any contract. It is not a commitment to deliver
any material, code, or functionality, and should not be relied upon
in making purchasing decisions. The development, release, and
timing of any features or functionality described for Oracle’s
products remains at the sole discretion of Oracle.
Safe Harbor Statement
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted3
Outline
 Integration Strategy Overview
 Current Capabilities in PG 1.1
 Roadmap and Planned Features
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted4
Gateway Overview
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted5
Oracle Primavera Integration Strategy
Integrating Primavera with 3rd Party Product
 Complete
– Spans across all asset intensive industries
– Supports all project driven use cases
– ERP agnostic design
 Extensible
– Adjustable to customer specific needs and requirements
 Supported
– All Oracle Solution
– On-going development to enhance the Gateway and stay current with platforms and current
versions of integrated products
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted6
Integration Strategy
Architectural Overview
Primavera Gateway
NonPrimavera
Applications
PrimaveraEPPM
Integration Broker
Graphical User Interface
Configuration ; Role-based security; Ad-hoc
synchronizations; Monitoring
Maximo
Provider
by Pipeline
SAP
Provider
Unifier
Provider*
EBS Provider
by Project
Partners
EAM
Provider^
JDE Provider
by Morpheus
P6 Provider
VCP
Provider^
PublicAPI
IntegrationSynchServices
Compare
Industry-Specific Flows and Data Maps
Routine Maintenance; Shutdown and turnaround; Capital
Project
Logging
Scheduling Audit
Customizations
Sample
Provider
Ventyx
Provider
by Pipeline
EnterpriseTrack
Provider
* Not available in Primavera Gateway v1.1. Planned for next major version of Primavera Gateway
^ Not included in Primavera Gateway v1.1. Will be developed by partners after initial release of Primavera Gateway
“Prime”
(CPM)
Provider
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted7
System Breakdown
Technical Overview
Web Tier
Business Tier
Database
Client
Browser based (HTML, JQuery, Bootstrap, RequireJS)
Primavera Gateway
J2EE / Weblogic
ERP Specific Oracle
Oracle,
SQL Server
P6ERP/EAM
Integration Broker
Java Interface definitions for providers, Canonical
data model, Orchestration of flows, Job scheduling
P6 ProviderERP Provider
HTTP / HTTPS
JPA Eclipse link
Vendor
Specific
API
SOAP – based
Web Services
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted8
Complete
Framework Features
 Flexible Data Exchange
– Definition of data ownership – separate flows for import vs. export
– Customer defined attribute mappings for each flow
– Support for non-common attributes – UDFs, Codes.
 Error Handling
– Automatic notifications
– Partial error handling
 Scalability and Ease-of-Use
– Synch by entity (resource assignments, Activities, WBS, etc.)
– Synch changed data only
– Synch for a range of projects
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted9
Extensible
Integration Strategy
 Primavera Framework provides common/standard integration
– Support for recommended / best practice flows
– Support for commonly shared attributes
– Configuration and scheduling
 Consulting Services or Custom Work should be expected and
planned
– ERP Providers
– Custom Flows
– Mapping of user defined attributes and non-common attributes
– Logic to handle data exceptions and specific business rules
• On-going development to enhance integration solution
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted10
Supported
Overall Framework Benefits
 Reduced cost of ownership
– Licensing, Installation, Hardware, Maintenance, Customization, Support
– Customizations require standard Java skills
 Time To Market
– Pre-build industry-specific flows and data maps
– Providers for each version of Primavera and ERP which ensures compatibility.
– 6-8 month development cycle
 Performance and Scalability
– Java versus XML based payloads are much quicker
– Less layers data has to pass through
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted11
Data Flow Example
ERP to P6 flow
ERP
P6PI Data
ERP
Data
P6 Data
P6 Data
Parallel
Read
Canonical Data
Format &
Compare
Service
Delta Only
Writes
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted12
Common Integration Flows
Conceptual Object Data Map
Resource Dictionary
Project / WBS / Work Orders
Tasks / Operations
Resource Assignments
Material Component
Budget / Forecast
Actual Cost
Resource Dictionary
Project / WBS / UDF
Activities
Activities / Assignment
Budget / Progress
Cost / UDF
Resource Assignments
ERP/EAM P6
Actual Hours Actual Hours
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted13
Primavera Gateway 1.1
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted14
Primavera Gateway v1.1: What is new
Target: FY 2014
• Global Calendars
• Cost Accounts
• “Prime” Provider
• Instantis Provider
Additional Data
• Fixed WBS level synchronization
• Flexible synchronization based on User ‘tagging” WBS node in p6 for synchronization
• Activities and assignment spread over time – calendar (week, month) or financial periods. Expose
additional Spread Data objects: Expense Costs, Role
Project Summary
• Filtering capabilities for synchronization and monitoring page
• E-mail notifications
• Enhanced installation
• New UI consistent with Oracle Primavera Prime
Usability Enhancements
• Ability to designate field map as “create only” or “update only” or both
• Export Global Data from P6
• Cloud Ready: Groovy scriptable customization, UI for data maps configuration
• Support to register multiple providers.
Advanced Features
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted15
SAP Provider for PG v1.1: What is new
Target: FY 2014
•Additional selection criteria as ‘Cost Center’ for Employee Resource Master
•Transferring Workcenter Resource CalendarGlobal Data
•Milestone Synchronization
•Synchronization of SAP ‘System Status’ and ‘User Status’ at Project and WBS level
•Option for the user to create activities with different SAP Control Key from P6 to SAP
using P6 Activity Code Assignment
•Option of defining range of SAP Project ID’s in the selection criteria for Project
Synchronization
•Synchronizing specific WBS hierarchy from SAP to P6
Project Structures
•Additional PM Order Selection Options, like Functional Location, Company Code,
Business Area, Asset, Basic and Actual Dates, etc.Plant Maintenance
•Support for the latest SAP ECC Ehp 7SAP Platform
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted16
Data Dictionary
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted17
Data Mapping
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted18
Data Flows
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted19
Synchronization Definitions
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted20
Automatic Synchronization Scheduling
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted21
Import Calendar
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted22
WBS Filtering
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted23
Export Spread Data Flow
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted24
E-mail Notification
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted25
Filtering on Synchronizations Page
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted26
Filtering on Monitoring Page
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted27
Asset Management
SAP Oracle Primavera
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted28
Project Management
SAP Oracle Primavera
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted29
Materials Management Integration – In-Stock Materials
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted30
Materials Management Integration – Non-Stock Materials
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted31
Supported Versions and Platform
Primavera Gateway 1.1
OS Software Comments
Database MS Win 2k8 R2 SP1 x64
Ora11g R2 v3 and v4
Oracle 12c
MS Win 2k8 SP2 x32 ,x64
MS Win 2012 x64
OEL 5.9 and 6.3 x32,x64
Application MS Win 2k8 R2 SP1x64
Oracle Weblogic 11g (10.3.6)
Oracle Weblogic 12c (12.1.2)
Sun JDK 1.7.0.51MS Win 2k8 SP2 x32 ,x64
MS Win 2012 R2 x64
OEL 6.3 x32,x64
Client MS Win 7 SP1 x32,x64,
MS Win 8 x32, x64
Any platform running supported
browser
IE9, IE10, IE11 Supported Languages:
English, German, French, Simpl.
Chinese, Japanese, Russian, Spanish,
Trad. Chinese, Brazilian Portuguese,
Italian, Korean
Firefox 24.2+
Chrome 32 +
Authentication LDAP, OID 11g, AD 2k8, AD 2012
Providers
Primavera P6 EPPM v 8.2, EPPM v 8.3 Requires adapter for Web Services
SAP ECC 6.0 All Enhancement Packs up to version 7
Oracle Primavera Prime V 14.1
EnterpriseTrack V 8.7
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted32
Roadmap
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted33
Primavera Gateway Backlog
 Planned releases
– Primavera Gateway v1.1 – FY 2014 – Enhance integration capability for P6
– Primavera Gateway v2.0 – FY 2015 – Support additional Primavera Products(Unifier 10, Instantis 8.8)
– Primavera Gateway v2.x – FY 2015 – Advanced OOTB capabilities for Project Driven Supply Chain
 Primavera Framework Enhancements
– Cloud Support– Oracle continues push towards cloud enable offerings, integration has to support this model as well
– Providers– the library of pre-built integration has to continue to grow
– API – need to allow connecting Primavera Gateway using application native UI or other integration platforms
– Usability Improvement – make Primavera Gateway easier to use, more robust, and competitive
 On-going development of Providers for External Applications
– EBS – adapter for Project Costing / Project Management (work started for 2.0 release)
– PDSC – adapter for VCP (work started for 2.0 release)
– JDE – adapter for Enterprise One
• Partner Involvement
– Work with partners to develop providers for specific ERPs and Use Case – IFS, PSFT, WAM, EAM, etc
– Existing integrations : EBS PA by Project Partners; JDE E1 by Morpheus; SAP/Maximo/Ventyx by Pipeline
– Certify partner’s providers through OVI
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted34
Primavera Gateway v2.0: Complex Integration Scenarios
Target: FY 2015
• Fully Scriptable updates
• UI for user provisioning
• Cloud-enabled external providers
Cloud Support
• Unifier provider. Continue to enhance P6 , Instantis , and “Prime” providers
• EBS Projects provider; VCP / ASCP provider
• Ability to “chain” multiple jobs together
Additional Providers Support
• Exposing job status and job execution progress via WS
• Ability to set synchronization job in native UI (PM staring synch in P6)API
• Near Real Time” synchronizations – ability to trigger synchronization job based on application events and triggers
• Data Level Security – allow to differentiate flows and synchronization definitions by User
• Enhanced filtering capabilities – allow to synchronize part of the project (for example, only activities with specific activity code)
• UI for “metadata” manipulation (configuring maps)
• Dynamic lookups for synchronization parameters
Usability Enhancements
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted35
Q / A
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted36
Copyright © 2014, Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted39

Primavera Gateway overview - Oracle Primavera P6 Collaborate 14

  • 1.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted1 Primavera Gateway John Pikovskiy – Principal Product Manager PGBU Strategy April 2014
  • 2.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted2 The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material, code, or functionality, and should not be relied upon in making purchasing decisions. The development, release, and timing of any features or functionality described for Oracle’s products remains at the sole discretion of Oracle. Safe Harbor Statement
  • 3.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted3 Outline  Integration Strategy Overview  Current Capabilities in PG 1.1  Roadmap and Planned Features
  • 4.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted4 Gateway Overview
  • 5.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted5 Oracle Primavera Integration Strategy Integrating Primavera with 3rd Party Product  Complete – Spans across all asset intensive industries – Supports all project driven use cases – ERP agnostic design  Extensible – Adjustable to customer specific needs and requirements  Supported – All Oracle Solution – On-going development to enhance the Gateway and stay current with platforms and current versions of integrated products
  • 6.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted6 Integration Strategy Architectural Overview Primavera Gateway NonPrimavera Applications PrimaveraEPPM Integration Broker Graphical User Interface Configuration ; Role-based security; Ad-hoc synchronizations; Monitoring Maximo Provider by Pipeline SAP Provider Unifier Provider* EBS Provider by Project Partners EAM Provider^ JDE Provider by Morpheus P6 Provider VCP Provider^ PublicAPI IntegrationSynchServices Compare Industry-Specific Flows and Data Maps Routine Maintenance; Shutdown and turnaround; Capital Project Logging Scheduling Audit Customizations Sample Provider Ventyx Provider by Pipeline EnterpriseTrack Provider * Not available in Primavera Gateway v1.1. Planned for next major version of Primavera Gateway ^ Not included in Primavera Gateway v1.1. Will be developed by partners after initial release of Primavera Gateway “Prime” (CPM) Provider
  • 7.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted7 System Breakdown Technical Overview Web Tier Business Tier Database Client Browser based (HTML, JQuery, Bootstrap, RequireJS) Primavera Gateway J2EE / Weblogic ERP Specific Oracle Oracle, SQL Server P6ERP/EAM Integration Broker Java Interface definitions for providers, Canonical data model, Orchestration of flows, Job scheduling P6 ProviderERP Provider HTTP / HTTPS JPA Eclipse link Vendor Specific API SOAP – based Web Services
  • 8.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted8 Complete Framework Features  Flexible Data Exchange – Definition of data ownership – separate flows for import vs. export – Customer defined attribute mappings for each flow – Support for non-common attributes – UDFs, Codes.  Error Handling – Automatic notifications – Partial error handling  Scalability and Ease-of-Use – Synch by entity (resource assignments, Activities, WBS, etc.) – Synch changed data only – Synch for a range of projects
  • 9.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted9 Extensible Integration Strategy  Primavera Framework provides common/standard integration – Support for recommended / best practice flows – Support for commonly shared attributes – Configuration and scheduling  Consulting Services or Custom Work should be expected and planned – ERP Providers – Custom Flows – Mapping of user defined attributes and non-common attributes – Logic to handle data exceptions and specific business rules • On-going development to enhance integration solution
  • 10.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted10 Supported Overall Framework Benefits  Reduced cost of ownership – Licensing, Installation, Hardware, Maintenance, Customization, Support – Customizations require standard Java skills  Time To Market – Pre-build industry-specific flows and data maps – Providers for each version of Primavera and ERP which ensures compatibility. – 6-8 month development cycle  Performance and Scalability – Java versus XML based payloads are much quicker – Less layers data has to pass through
  • 11.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted11 Data Flow Example ERP to P6 flow ERP P6PI Data ERP Data P6 Data P6 Data Parallel Read Canonical Data Format & Compare Service Delta Only Writes
  • 12.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted12 Common Integration Flows Conceptual Object Data Map Resource Dictionary Project / WBS / Work Orders Tasks / Operations Resource Assignments Material Component Budget / Forecast Actual Cost Resource Dictionary Project / WBS / UDF Activities Activities / Assignment Budget / Progress Cost / UDF Resource Assignments ERP/EAM P6 Actual Hours Actual Hours
  • 13.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted13 Primavera Gateway 1.1
  • 14.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted14 Primavera Gateway v1.1: What is new Target: FY 2014 • Global Calendars • Cost Accounts • “Prime” Provider • Instantis Provider Additional Data • Fixed WBS level synchronization • Flexible synchronization based on User ‘tagging” WBS node in p6 for synchronization • Activities and assignment spread over time – calendar (week, month) or financial periods. Expose additional Spread Data objects: Expense Costs, Role Project Summary • Filtering capabilities for synchronization and monitoring page • E-mail notifications • Enhanced installation • New UI consistent with Oracle Primavera Prime Usability Enhancements • Ability to designate field map as “create only” or “update only” or both • Export Global Data from P6 • Cloud Ready: Groovy scriptable customization, UI for data maps configuration • Support to register multiple providers. Advanced Features
  • 15.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted15 SAP Provider for PG v1.1: What is new Target: FY 2014 •Additional selection criteria as ‘Cost Center’ for Employee Resource Master •Transferring Workcenter Resource CalendarGlobal Data •Milestone Synchronization •Synchronization of SAP ‘System Status’ and ‘User Status’ at Project and WBS level •Option for the user to create activities with different SAP Control Key from P6 to SAP using P6 Activity Code Assignment •Option of defining range of SAP Project ID’s in the selection criteria for Project Synchronization •Synchronizing specific WBS hierarchy from SAP to P6 Project Structures •Additional PM Order Selection Options, like Functional Location, Company Code, Business Area, Asset, Basic and Actual Dates, etc.Plant Maintenance •Support for the latest SAP ECC Ehp 7SAP Platform
  • 16.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted16 Data Dictionary
  • 17.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted17 Data Mapping
  • 18.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted18 Data Flows
  • 19.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted19 Synchronization Definitions
  • 20.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted20 Automatic Synchronization Scheduling
  • 21.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted21 Import Calendar
  • 22.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted22 WBS Filtering
  • 23.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted23 Export Spread Data Flow
  • 24.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted24 E-mail Notification
  • 25.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted25 Filtering on Synchronizations Page
  • 26.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted26 Filtering on Monitoring Page
  • 27.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted27 Asset Management SAP Oracle Primavera
  • 28.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted28 Project Management SAP Oracle Primavera
  • 29.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted29 Materials Management Integration – In-Stock Materials
  • 30.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted30 Materials Management Integration – Non-Stock Materials
  • 31.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted31 Supported Versions and Platform Primavera Gateway 1.1 OS Software Comments Database MS Win 2k8 R2 SP1 x64 Ora11g R2 v3 and v4 Oracle 12c MS Win 2k8 SP2 x32 ,x64 MS Win 2012 x64 OEL 5.9 and 6.3 x32,x64 Application MS Win 2k8 R2 SP1x64 Oracle Weblogic 11g (10.3.6) Oracle Weblogic 12c (12.1.2) Sun JDK 1.7.0.51MS Win 2k8 SP2 x32 ,x64 MS Win 2012 R2 x64 OEL 6.3 x32,x64 Client MS Win 7 SP1 x32,x64, MS Win 8 x32, x64 Any platform running supported browser IE9, IE10, IE11 Supported Languages: English, German, French, Simpl. Chinese, Japanese, Russian, Spanish, Trad. Chinese, Brazilian Portuguese, Italian, Korean Firefox 24.2+ Chrome 32 + Authentication LDAP, OID 11g, AD 2k8, AD 2012 Providers Primavera P6 EPPM v 8.2, EPPM v 8.3 Requires adapter for Web Services SAP ECC 6.0 All Enhancement Packs up to version 7 Oracle Primavera Prime V 14.1 EnterpriseTrack V 8.7
  • 32.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted32 Roadmap
  • 33.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted33 Primavera Gateway Backlog  Planned releases – Primavera Gateway v1.1 – FY 2014 – Enhance integration capability for P6 – Primavera Gateway v2.0 – FY 2015 – Support additional Primavera Products(Unifier 10, Instantis 8.8) – Primavera Gateway v2.x – FY 2015 – Advanced OOTB capabilities for Project Driven Supply Chain  Primavera Framework Enhancements – Cloud Support– Oracle continues push towards cloud enable offerings, integration has to support this model as well – Providers– the library of pre-built integration has to continue to grow – API – need to allow connecting Primavera Gateway using application native UI or other integration platforms – Usability Improvement – make Primavera Gateway easier to use, more robust, and competitive  On-going development of Providers for External Applications – EBS – adapter for Project Costing / Project Management (work started for 2.0 release) – PDSC – adapter for VCP (work started for 2.0 release) – JDE – adapter for Enterprise One • Partner Involvement – Work with partners to develop providers for specific ERPs and Use Case – IFS, PSFT, WAM, EAM, etc – Existing integrations : EBS PA by Project Partners; JDE E1 by Morpheus; SAP/Maximo/Ventyx by Pipeline – Certify partner’s providers through OVI
  • 34.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted34 Primavera Gateway v2.0: Complex Integration Scenarios Target: FY 2015 • Fully Scriptable updates • UI for user provisioning • Cloud-enabled external providers Cloud Support • Unifier provider. Continue to enhance P6 , Instantis , and “Prime” providers • EBS Projects provider; VCP / ASCP provider • Ability to “chain” multiple jobs together Additional Providers Support • Exposing job status and job execution progress via WS • Ability to set synchronization job in native UI (PM staring synch in P6)API • Near Real Time” synchronizations – ability to trigger synchronization job based on application events and triggers • Data Level Security – allow to differentiate flows and synchronization definitions by User • Enhanced filtering capabilities – allow to synchronize part of the project (for example, only activities with specific activity code) • UI for “metadata” manipulation (configuring maps) • Dynamic lookups for synchronization parameters Usability Enhancements
  • 35.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted35 Q / A
  • 36.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted36
  • 37.
    Copyright © 2014,Oracle and/or its affiliates. All rights reserved. Confidential – Oracle Restricted39