SlideShare a Scribd company logo
1
I would like present the realization of Vancouver Canada line as example
of risk management for urban tunneling.
The tunnel has been realized by Seli in Vancouver downtown from 2005
to 2008.
2
Some basic concepts of risk management.
The objectives are: to increase the safety during the excavation and to attain the job
targets which are usually time and costs.
The definition of risk is damage times probability.
One can reduce the risk intervening on the damages or on the probability or on both.
The residual risk should be accepted.
A particular case of high, often unacceptable damage, with extremely low probability
is here indicated as Sword of Damocles. As example we can think to the death of the
inhabitants of a building that must be always avoided.
From the types of damages I want to mention the loss of confidence from the
Authority and the public opinion because as we all know it can be really complicated
completing an excavation after unforeseen events, even if without damages.
3
In order to make a risk management we have to: establish al the facts necessary to
identify the hazard scenarios. So we need to know not only the geology and the
tunnel geometry, but also the structural details of the objects interested by the
excavation.
Then it’s fundamental to understand the mechanism governing the hazard in order to
design the appropriate measures.
4
Here we have some photos just to get an idea of the possible damages
due to excessive settlements or to the formation of a sinkhole following
the collapse of the face.
5
Tunneling in soil, cohesive or not, surface settlement cannot be
completely avoid, but using the proper procedures can be mitigated and
maintained within acceptable range.
Indeed uncontrolled excavation may result in excessive subsidence
mainly due to over excavation, which means that a larger volume of
material is excavated by the TBM compared to the required volume for
the tunnel.
In certain cases exceptional over excavation, due for example to
unexpected objects or soils, can also produce a sinkholes on the
surface.
Long term settlements due to water table drawdown must also be
avoided in urban tunneling.
Finally the most dangerous phenomena is the collapse of the face for
insufficient or not uniform support pressure, that often brings to the
formation of a crater on the surface (without warning).
6
Here some data of the twin EPB tunnel of Vancouver Canada Line.
The tunnels have an external diameter of 6m and an interaxis of around
12m.
The geology is characterized by the glacial till, composed by a clay, silt
and sand matrix and the substratum of sedimentary rock with favorable
strength parameters.
The water table is 10 to 15m over the tunnel crown.
In the Till was expected to encounter boulders up to 2m of diameter and
saturated sand lenses.
This presentation is going to focus on two stretch, the first one consist in
crossing a fiord, named False Creek, and the second one in
underpassing with reduced overburden the downtown.
7
The main hazard was to flood the tunnel during the excavation.
Such an event is only possible under the combination of the 2 conditions:
• First it’s necessary an hydraulic connection between the fiord and the face of the
tunnel, for example by rock faults, abandoned unfilled boreholes or the presence
of permeable layers in the till.
• Second the water together with the soil can flow freely through the screw conveyor
only in if the permeability of the muck is to high.
In this condition a proper operation mode of the EPB machine, that means right
conditioning, sufficient support pressure and continuous observation of the
parameters and of the muck, can exclude the possibility of flooding the tunnel
irrespective of the possible presence of a hydraulic connection.
8
A nice picture of the Brava Towers
9
Here we have the plan, the longitudinal and transversal sections of the
original alignment of the tunnel.
As one can see we had really difficult situation, with the tunnels
underpassing the towers very close to the footings and excavating in the
till with about 15m of hydraulic pressure.
10
Based on the geology the main hazards crossing the Till are:
• The presence of high strength boulders that can induce over excavation when
extracted by the TBM head from the soil and also not being destroyed by the
cutting tools they remain in the chamber requiring maintenance and disturbing
the formation of a proper muck.
• The possibility to encounter sand lenses under high hydraulic pressure that could
flow uncontrolled though the screw conveyor causing the collapse of the face.
• The occurrence of external object that similarly to the boulders may damage the
cutting tools.
The most important remedial to reduce the effect of such hazards are:
• Applying the right conditioning to the muck in order to obtain the correct plasticity
and permeability. This is very important since these parameters influence the
capacity of the muck to exert a uniform pressure on the face and to avoid the
inflow of water in the chamber.
• Controlling continuously the TBM parameters such: face pressure, thrust and
torque, to identify quickly changes in ground conditions and therefore to react
properly.
• Finally we applyed a constructive remedial, a thick matter pump that avoided
uncontrolled flow through the screw conveyor reducing the possibility of face
collapse in case of sand lenses.
Screw conveyor: it’s the part of the EPB that controlling the outflow of the material in
form of muck from the chamber, regulate the pressure exerted on the face.
11
Despite all the proposed measures, considering the small distance
between the crown and the footing of the Towers, the first suggestion
was to change the alignment in order to avoid the building.
Unfortunately was only possible to lower the tunnel of 8m.
To cope with potential sand lenses under high hydraulic pressure and
increase the face stability underpassing the towers, higher face pressure
was applied.
Finally monitoring the ground surface before the Towers and the building
provided the information to confirm the design and to intervene to avoid
severe damages.
12
200m before the Brava Towers occurred a sudden change of the
geological conditions, instead of the Till the tunnel encountered a highly
permeable sand layer.
In this conditions was impossible to create an impermeable cake that
allows any intervention in the chamber for ordinary maintenance.
In fact when first it was attempted the presence of a local collapse was
discovered and for stability reasons the chamber was filled again and the
excavation resumed.
The impossibility to replace worn cutting tools involved the risk of TBM
stoppage once reached the mixed face condition or in case of big
boulders, with the difficulty or quite impossibility to intervene for
maintenance underpassing the Towers..
In the end with adequate control of the TBM parameters, they were able
to complete the stretch even if the achieved a slow advancement speed
and major settlements were recorded at the Tower footing.
13
Based on the experience from the 1° drive, it was necessary to reduce
the risk of new settlement that would have caused damage to the
Towers.
The first remedial measure was to increase the interaxis of the tunnels to
reduce the possibility of adverse interaction between the 2 tubes.
A new proper conditioning was studied able to lower the muck
permeability and therefore limit the inflow of water in the chamber.
Finally new boreholes were made to reassess the geology and on this
basis a proper zone was located for maintenance before underpassing
the tower.
14
The new conditioning was partially effective, allowing to refurbish the
cutting head in the located zones.
With cutting tools in good condition the operator was able maintain the
design face support pressure continuously, thus balancing the
hydrostatic pressure and avoiding any inflow in the chamber of extra
ground or water.
This proper execution brought null settlement avoiding any damages to
the Towers.
In the longitudinal section we can see the reassessed geology and the
lowering of the alignment.
One can only imagine what could have happened without a proper risk
management to such high and inhabited building.

More Related Content

What's hot

Presentation st sabya
Presentation st   sabyaPresentation st   sabya
Presentation st sabya
sabyaswain
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
sarojkhadka059
 
2 tunnels
2 tunnels2 tunnels
2 tunnels
Raghav Gadgil
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
Vidhi Khokhani
 
Final
FinalFinal
DAMS
DAMSDAMS
Reservoir Dam Safety
Reservoir Dam SafetyReservoir Dam Safety
Reservoir Dam Safety
Prof. David E. Alexander (UCL)
 
Dam construction
Dam constructionDam construction
Dam construction
alizay41
 
Embankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadEmbankment dam civil 5 th sem upload
Embankment dam civil 5 th sem upload
Meet Soni
 
Dam and types of dam with site selection
Dam and types of dam with site selectionDam and types of dam with site selection
Dam and types of dam with site selection
Jyoti Khatiwada
 
Eg unit v
Eg unit vEg unit v
Eg unit v
shaymaa17
 
Flow diversion and storage
Flow diversion and storageFlow diversion and storage
Flow diversion and storage
shaymaa17
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
jamali husain
 
Ranjith bsr
Ranjith bsrRanjith bsr
Ranjith bsr
Ranjithboda
 
sagar725744
sagar725744sagar725744
sagar725744
Sagar Mandal
 
Dam design
Dam designDam design
Dam design
Mohammed Maina
 
Gravity dam
Gravity damGravity dam
Gravity dam
Tanmoy Mustafi
 
Dams
DamsDams
Tunneling
TunnelingTunneling
Tunneling
jagdish lawadiya
 
Dam presentation
Dam presentationDam presentation
Dam presentation
Abdul Mutakaber Tareen
 

What's hot (20)

Presentation st sabya
Presentation st   sabyaPresentation st   sabya
Presentation st sabya
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
 
2 tunnels
2 tunnels2 tunnels
2 tunnels
 
Embankment lecture 1
Embankment lecture 1Embankment lecture 1
Embankment lecture 1
 
Final
FinalFinal
Final
 
DAMS
DAMSDAMS
DAMS
 
Reservoir Dam Safety
Reservoir Dam SafetyReservoir Dam Safety
Reservoir Dam Safety
 
Dam construction
Dam constructionDam construction
Dam construction
 
Embankment dam civil 5 th sem upload
Embankment dam civil 5 th sem uploadEmbankment dam civil 5 th sem upload
Embankment dam civil 5 th sem upload
 
Dam and types of dam with site selection
Dam and types of dam with site selectionDam and types of dam with site selection
Dam and types of dam with site selection
 
Eg unit v
Eg unit vEg unit v
Eg unit v
 
Flow diversion and storage
Flow diversion and storageFlow diversion and storage
Flow diversion and storage
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Ranjith bsr
Ranjith bsrRanjith bsr
Ranjith bsr
 
sagar725744
sagar725744sagar725744
sagar725744
 
Dam design
Dam designDam design
Dam design
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Dams
DamsDams
Dams
 
Tunneling
TunnelingTunneling
Tunneling
 
Dam presentation
Dam presentationDam presentation
Dam presentation
 

Viewers also liked

510 tunneling safety 2016
510 tunneling safety 2016510 tunneling safety 2016
510 tunneling safety 2016
John Newquist
 
Topik 3 punca kmalangan&pcegahan
Topik 3 punca kmalangan&pcegahanTopik 3 punca kmalangan&pcegahan
Topik 3 punca kmalangan&pcegahan
Wan Nurhidayati Wan Johari
 
lifting operation
lifting operationlifting operation
lifting operation
Salwa Samsudin
 
Pasport Keselamatan Minyak & Gas (OGSP)
Pasport Keselamatan Minyak & Gas (OGSP)Pasport Keselamatan Minyak & Gas (OGSP)
Pasport Keselamatan Minyak & Gas (OGSP)
NioshtechMy
 
LANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJA
LANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJALANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJA
LANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJA
fnurizdian
 
Topik 2 hazard dan risiko
Topik 2 hazard dan risikoTopik 2 hazard dan risiko
Topik 2 hazard dan risiko
Wan Nurhidayati Wan Johari
 
Bab 2 punca & pencegahan kemalangan
Bab 2 punca & pencegahan kemalanganBab 2 punca & pencegahan kemalangan
Bab 2 punca & pencegahan kemalanganSri Devi
 
Keselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaanKeselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaan
Hukaida Hamzah
 
AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514
AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514
AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514
Muhammad Nasrullah
 
Keselamatan di tempat kerja
Keselamatan di tempat kerjaKeselamatan di tempat kerja
Keselamatan di tempat kerja
Kementerian Pengajian Tinggi
 
Kemalangan ditempat kerja
Kemalangan ditempat kerjaKemalangan ditempat kerja
Kemalangan ditempat kerja
syahirahhjsaad
 
Workplace hazards
Workplace hazardsWorkplace hazards
Workplace hazards
safereps
 

Viewers also liked (13)

510 tunneling safety 2016
510 tunneling safety 2016510 tunneling safety 2016
510 tunneling safety 2016
 
Topik 3 punca kmalangan&pcegahan
Topik 3 punca kmalangan&pcegahanTopik 3 punca kmalangan&pcegahan
Topik 3 punca kmalangan&pcegahan
 
lifting operation
lifting operationlifting operation
lifting operation
 
Pasport Keselamatan Minyak & Gas (OGSP)
Pasport Keselamatan Minyak & Gas (OGSP)Pasport Keselamatan Minyak & Gas (OGSP)
Pasport Keselamatan Minyak & Gas (OGSP)
 
LANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJA
LANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJALANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJA
LANGKAH - LANGKAH PENCEGAHAN KEMALANGAN DI TEMPAT KERJA
 
hazard di tempat kerja
hazard di tempat kerjahazard di tempat kerja
hazard di tempat kerja
 
Topik 2 hazard dan risiko
Topik 2 hazard dan risikoTopik 2 hazard dan risiko
Topik 2 hazard dan risiko
 
Bab 2 punca & pencegahan kemalangan
Bab 2 punca & pencegahan kemalanganBab 2 punca & pencegahan kemalangan
Bab 2 punca & pencegahan kemalangan
 
Keselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaanKeselamatan & kesihatan pekerjaan
Keselamatan & kesihatan pekerjaan
 
AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514
AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514
AKTA KESELAMATAN DAN KESIHATAN PEKERJAAN 1994 - AKTA 514
 
Keselamatan di tempat kerja
Keselamatan di tempat kerjaKeselamatan di tempat kerja
Keselamatan di tempat kerja
 
Kemalangan ditempat kerja
Kemalangan ditempat kerjaKemalangan ditempat kerja
Kemalangan ditempat kerja
 
Workplace hazards
Workplace hazardsWorkplace hazards
Workplace hazards
 

Similar to Presentazione torino 5 aprile 2016 vancouver con note

Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
Angelo Indelicato
 
Dams
DamsDams
Dams and Reservoirs -Hydraulics engineering
Dams and Reservoirs -Hydraulics engineeringDams and Reservoirs -Hydraulics engineering
Dams and Reservoirs -Hydraulics engineering
Civil Zone
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
KhawarSakhani
 
OK
OKOK
Cofferdam
CofferdamCofferdam
Cofferdam
sauravsaxena3
 
1115
11151115
291 __0 (1)
291  __0 (1)291  __0 (1)
Earthen dam
Earthen damEarthen dam
Earthen dam
amrutaware2
 
Dam engineering i 5
Dam engineering i 5Dam engineering i 5
Dam engineering i 5
FeteneBefekadu
 
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
Sukesh Nayak
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
AJITA PANDEY
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
SubratDash37
 
Presentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptxPresentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptx
TameneAdugna2
 
Embankment dam by sitaram saini
Embankment dam by sitaram sainiEmbankment dam by sitaram saini
Embankment dam by sitaram saini
SitaramSaini11
 
Lecture 6 p
Lecture 6 pLecture 6 p
underwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptxunderwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptx
Jayachandran68
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
Sahl Buhary
 
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptxDesign-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
LeenaMujahed
 
Tunneling (2).ppt
Tunneling (2).pptTunneling (2).ppt
Tunneling (2).ppt
METRYCMUSICA
 

Similar to Presentazione torino 5 aprile 2016 vancouver con note (20)

Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
Dams
DamsDams
Dams
 
Dams and Reservoirs -Hydraulics engineering
Dams and Reservoirs -Hydraulics engineeringDams and Reservoirs -Hydraulics engineering
Dams and Reservoirs -Hydraulics engineering
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
 
OK
OKOK
OK
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
1115
11151115
1115
 
291 __0 (1)
291  __0 (1)291  __0 (1)
291 __0 (1)
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Dam engineering i 5
Dam engineering i 5Dam engineering i 5
Dam engineering i 5
 
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
ENVIRONMENTAL POLLUTION CONTROL METHOD ADOPTED BY NTPC LTD. IN ASH DYKE (STAR...
 
Constructio underwater
Constructio underwaterConstructio underwater
Constructio underwater
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
Presentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptxPresentation1-hydrolic-st.pptx
Presentation1-hydrolic-st.pptx
 
Embankment dam by sitaram saini
Embankment dam by sitaram sainiEmbankment dam by sitaram saini
Embankment dam by sitaram saini
 
Lecture 6 p
Lecture 6 pLecture 6 p
Lecture 6 p
 
underwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptxunderwater-construction-55849d4caf8cd.pptx
underwater-construction-55849d4caf8cd.pptx
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
 
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptxDesign-of-diversion-dam-in-tarbela-dam-pakistan.pptx
Design-of-diversion-dam-in-tarbela-dam-pakistan.pptx
 
Tunneling (2).ppt
Tunneling (2).pptTunneling (2).ppt
Tunneling (2).ppt
 

Recently uploaded

一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
Dwarkadas J Sanghvi College of Engineering
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
sachin chaurasia
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
ijaia
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
VANDANAMOHANGOUDA
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
Kamal Acharya
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
harshapolam10
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
uqyfuc
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
upoux
 
2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt
abdatawakjira
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
AIRCC Publishing Corporation
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
q30122000
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
ijseajournal
 

Recently uploaded (20)

一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 
Mechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineeringMechatronics material . Mechanical engineering
Mechatronics material . Mechanical engineering
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
ITSM Integration with MuleSoft.pptx
ITSM  Integration with MuleSoft.pptxITSM  Integration with MuleSoft.pptx
ITSM Integration with MuleSoft.pptx
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
Accident detection system project report.pdf
Accident detection system project report.pdfAccident detection system project report.pdf
Accident detection system project report.pdf
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
SCALING OF MOS CIRCUITS m .pptx
SCALING OF MOS CIRCUITS m                 .pptxSCALING OF MOS CIRCUITS m                 .pptx
SCALING OF MOS CIRCUITS m .pptx
 
一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理一比一原版(USF毕业证)旧金山大学毕业证如何办理
一比一原版(USF毕业证)旧金山大学毕业证如何办理
 
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
一比一原版(uofo毕业证书)美国俄勒冈大学毕业证如何办理
 
2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt2. protection of river banks and bed erosion protection works.ppt
2. protection of river banks and bed erosion protection works.ppt
 
AI-Based Home Security System : Home security
AI-Based Home Security System : Home securityAI-Based Home Security System : Home security
AI-Based Home Security System : Home security
 
Height and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdfHeight and depth gauge linear metrology.pdf
Height and depth gauge linear metrology.pdf
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
 

Presentazione torino 5 aprile 2016 vancouver con note

  • 1. 1 I would like present the realization of Vancouver Canada line as example of risk management for urban tunneling. The tunnel has been realized by Seli in Vancouver downtown from 2005 to 2008.
  • 2. 2 Some basic concepts of risk management. The objectives are: to increase the safety during the excavation and to attain the job targets which are usually time and costs. The definition of risk is damage times probability. One can reduce the risk intervening on the damages or on the probability or on both. The residual risk should be accepted. A particular case of high, often unacceptable damage, with extremely low probability is here indicated as Sword of Damocles. As example we can think to the death of the inhabitants of a building that must be always avoided. From the types of damages I want to mention the loss of confidence from the Authority and the public opinion because as we all know it can be really complicated completing an excavation after unforeseen events, even if without damages.
  • 3. 3 In order to make a risk management we have to: establish al the facts necessary to identify the hazard scenarios. So we need to know not only the geology and the tunnel geometry, but also the structural details of the objects interested by the excavation. Then it’s fundamental to understand the mechanism governing the hazard in order to design the appropriate measures.
  • 4. 4 Here we have some photos just to get an idea of the possible damages due to excessive settlements or to the formation of a sinkhole following the collapse of the face.
  • 5. 5 Tunneling in soil, cohesive or not, surface settlement cannot be completely avoid, but using the proper procedures can be mitigated and maintained within acceptable range. Indeed uncontrolled excavation may result in excessive subsidence mainly due to over excavation, which means that a larger volume of material is excavated by the TBM compared to the required volume for the tunnel. In certain cases exceptional over excavation, due for example to unexpected objects or soils, can also produce a sinkholes on the surface. Long term settlements due to water table drawdown must also be avoided in urban tunneling. Finally the most dangerous phenomena is the collapse of the face for insufficient or not uniform support pressure, that often brings to the formation of a crater on the surface (without warning).
  • 6. 6 Here some data of the twin EPB tunnel of Vancouver Canada Line. The tunnels have an external diameter of 6m and an interaxis of around 12m. The geology is characterized by the glacial till, composed by a clay, silt and sand matrix and the substratum of sedimentary rock with favorable strength parameters. The water table is 10 to 15m over the tunnel crown. In the Till was expected to encounter boulders up to 2m of diameter and saturated sand lenses. This presentation is going to focus on two stretch, the first one consist in crossing a fiord, named False Creek, and the second one in underpassing with reduced overburden the downtown.
  • 7. 7 The main hazard was to flood the tunnel during the excavation. Such an event is only possible under the combination of the 2 conditions: • First it’s necessary an hydraulic connection between the fiord and the face of the tunnel, for example by rock faults, abandoned unfilled boreholes or the presence of permeable layers in the till. • Second the water together with the soil can flow freely through the screw conveyor only in if the permeability of the muck is to high. In this condition a proper operation mode of the EPB machine, that means right conditioning, sufficient support pressure and continuous observation of the parameters and of the muck, can exclude the possibility of flooding the tunnel irrespective of the possible presence of a hydraulic connection.
  • 8. 8 A nice picture of the Brava Towers
  • 9. 9 Here we have the plan, the longitudinal and transversal sections of the original alignment of the tunnel. As one can see we had really difficult situation, with the tunnels underpassing the towers very close to the footings and excavating in the till with about 15m of hydraulic pressure.
  • 10. 10 Based on the geology the main hazards crossing the Till are: • The presence of high strength boulders that can induce over excavation when extracted by the TBM head from the soil and also not being destroyed by the cutting tools they remain in the chamber requiring maintenance and disturbing the formation of a proper muck. • The possibility to encounter sand lenses under high hydraulic pressure that could flow uncontrolled though the screw conveyor causing the collapse of the face. • The occurrence of external object that similarly to the boulders may damage the cutting tools. The most important remedial to reduce the effect of such hazards are: • Applying the right conditioning to the muck in order to obtain the correct plasticity and permeability. This is very important since these parameters influence the capacity of the muck to exert a uniform pressure on the face and to avoid the inflow of water in the chamber. • Controlling continuously the TBM parameters such: face pressure, thrust and torque, to identify quickly changes in ground conditions and therefore to react properly. • Finally we applyed a constructive remedial, a thick matter pump that avoided uncontrolled flow through the screw conveyor reducing the possibility of face collapse in case of sand lenses. Screw conveyor: it’s the part of the EPB that controlling the outflow of the material in form of muck from the chamber, regulate the pressure exerted on the face.
  • 11. 11 Despite all the proposed measures, considering the small distance between the crown and the footing of the Towers, the first suggestion was to change the alignment in order to avoid the building. Unfortunately was only possible to lower the tunnel of 8m. To cope with potential sand lenses under high hydraulic pressure and increase the face stability underpassing the towers, higher face pressure was applied. Finally monitoring the ground surface before the Towers and the building provided the information to confirm the design and to intervene to avoid severe damages.
  • 12. 12 200m before the Brava Towers occurred a sudden change of the geological conditions, instead of the Till the tunnel encountered a highly permeable sand layer. In this conditions was impossible to create an impermeable cake that allows any intervention in the chamber for ordinary maintenance. In fact when first it was attempted the presence of a local collapse was discovered and for stability reasons the chamber was filled again and the excavation resumed. The impossibility to replace worn cutting tools involved the risk of TBM stoppage once reached the mixed face condition or in case of big boulders, with the difficulty or quite impossibility to intervene for maintenance underpassing the Towers.. In the end with adequate control of the TBM parameters, they were able to complete the stretch even if the achieved a slow advancement speed and major settlements were recorded at the Tower footing.
  • 13. 13 Based on the experience from the 1° drive, it was necessary to reduce the risk of new settlement that would have caused damage to the Towers. The first remedial measure was to increase the interaxis of the tunnels to reduce the possibility of adverse interaction between the 2 tubes. A new proper conditioning was studied able to lower the muck permeability and therefore limit the inflow of water in the chamber. Finally new boreholes were made to reassess the geology and on this basis a proper zone was located for maintenance before underpassing the tower.
  • 14. 14 The new conditioning was partially effective, allowing to refurbish the cutting head in the located zones. With cutting tools in good condition the operator was able maintain the design face support pressure continuously, thus balancing the hydrostatic pressure and avoiding any inflow in the chamber of extra ground or water. This proper execution brought null settlement avoiding any damages to the Towers. In the longitudinal section we can see the reassessed geology and the lowering of the alignment. One can only imagine what could have happened without a proper risk management to such high and inhabited building.