CITY OF CAPE TOWN
Creating Sustainable Value in a
  multi service municipality

   André Stelzner / Mehboob Foflonker
             Dir: ERP Business Transformation
                      Dir: ERP Implementation
Agenda




         Background.

         SAP Implementation - the City’s ERP system.

         SAP-ISU – the City’s Utility solution.

         Creating Value

         Conclusion.
Background:
Significant Political Events in South Africa during
the past decade have changed the face of Local
Government in Cape Town.

              Pre- 1994: South Africa internationally isolated and
              communities segregated on racial grounds.
              April 1994: first democratic election and government
              of national unity established.
              3-Tier government structure: National, Provincial and
              Local Government
              Legislation passed restructuring Local Government:
                  Mergers of 7 previous autonomous
                  Municipalities into a single Metropolitan Uni-City
                  Powers and Duties of Local Authorities changed
              Next Wave of Restructuring – Establishment of
              Regional Electricity Distributors.
Background:

The City of Cape Town had to merge 7 previously
autonomous local government administrations and
become a single integrated metropolitan City, but it found
that creating a Unicity to be complex due to:

•   “Lack of standardised financial
    policies and procedures”

•   “Each administration ran its own
    IT systems, many of which did not
    meet business requirements”

•   “Back-office systems were
    deemed (by large) to be outdated,
    functionally inadequate and not
    properly integrated”

•   “Difficulty in merging these
    systems was in fact hindering the
    merger of the administrations and
    undermining the objectives which
    motivated the creation of the
    Unicity”
Background:
      Demographics of Cape Town
                Population:                3.2 million

                Share of National GDP:               10.5 %
                Share of Provincial GDP:             75 %

                Area:                      215 900 ha

                Rateable Properties:       800 000

                Employees:                 24 579

                Annual budget 2004/05:
                 Operating: R 11,3 billion
                 Capital:   R 1,5 billion

                Annual Income 2004/05:
                 From Utility Services: R 4,36 billion (38,6 %)
                 From Tax and Levies: R 3,14 billiion (27,8 %)
Background:

Local Government – the delivery arm of Government
        Governance closest to the people – providing the following
        services:
            Electricity / distribution and peak load generating
            Water and Sanitation / storage, treatment and distribution
            Solid Waste / landfill, removal and area cleaning
            Roads, Stormwater and transport
            Public Housing
            Local Economic Development
            Social - and primary health services
            Emergency Services
            Municipal Policing
            Urban Planning and Environment
            Sport and Recreation
            City Administration
Agenda




         Background.

         Implementation SAP - the City’s ERP system.

         SAP-ISU – the City’s Utility solution.

         Creating Value

         Conclusion.
Project Implementation: Selection Process



                                                                             2004 & beyond
                                                      2002 & 2003
   2000                         2001

                                                                              The years of
                                                      The years of
The year of                 The year of
                                                                                Benefits
                                                     Implementation
  Strategy                   Selection


Projects undertaken during 2001: Resulted in the
SAP system and Accenture being selected.
                                                    Project # 4
                            Project # 3                                    Project # 5
Project # 2
• The consultant                                    • The enterprise
                            • The software                                 • The ERP systems
  selection                                           system integrator
                              selection                                      implementation
  (March – April 2001)                                selection (July -
                              (April - June 2001)                            blueprint planning
                                                      November 2001)
• Gartner was chosen                                                         phase
                            • SAP was selected
  to assist with software                                                    (November 2001 -
                                                    • Accenture was
                              as software
  and systems                                                                January 2002)
                                                      chosen as the
                              providers
  integrator selection
                                                      preferred ERP        • Accenture confirms
  processes
                                                      system integration     their cost & scope
                                                      partner                of implementation
Project Objectives:




                                         CA PE
                                     METROPOLITA N
                   Blaauwberg            AREA




                                                           City of
                                Tygerberg

                                                           City of
                                      Oostenberg
                      Cape

                                                         Cape Town
                                                         Cape Town
                      Town




                                            Helderberg
                     South
                   Penins ula




           “To Implement a functionally rich ERP
             system, in a manner that will ensure
         integration, facilitate the merger and bring
            about organisational transformation.”
         Thereby, enabling the City to deliver on its
                     Strategic Objectives”
What is an ERP




                                                          MAINTENANCE Processes
An ERPsystem offers organizations a




                                                                                                                              ASSET MANAGEMENT Processes
                                                                                                      PROCUREMENT Processes
                                                                                  REVENUE Processes
comprehensive and integrated solution for managing
services such as financial, revenue, human resources,
maintenance, procurement, leasing, customer care on a
single integrated IT system.




                                                                                                                                                           PROJECT Processes
                                                                                  HR processes




                                                                                                                                                                               CUSTOMER Processes
It is not so much about the technology as it is
                                                         PLANNING processes
about the integration of business processes.

                                                        ACCOUNTING processes
Workflow provides the means of automating
business processes and system integration
ensures that only a single record of master data is
held – but shared across the application.

Debate is whether to implement an ERP system
vrs. so called ‘best of breed’ systems.

SAP is a specific ERP vendors.
Successful Organizations are able to align:



                                  STRATEGY:
          Strategy
          Organisation
                                  What must we do ?




                                                               TECHNOLOGY
                                  PROCESS:
                                  How are we going to do it?

Process                  People
                                  People:
                                  Who is going to do it ?
Project Scope:

       The City of Cape Town: Scope of implementation

 - Billing to sundry
                                                                                                                                - Financial Accounting
   debtors
                                                             SD                            FI
                                                             Sales &                     Financial
                                                           Distribution                 Accounting
                                                                                                                                 - Management
                                               MM                                                     CO
 - Procurement &                                                                                                                   Accounting
                                               Materials                                             Controlling
   Inventory           SCADA*                   Mgmt.

                                                                   R/3 (4.6c) and                                  AM
                                    PP
   Management
                                                                                                                 Fixed Assets
                                  Production

                                                                  IS-U/CCS (4.63)                                    Mgmt
                                   Planning



                       EDI                                        Number of Users
 - Plant Maintenance               QM                                                                               PS                  - Asset
                                                                       6 500
                                    Quality                                                                         Project
                                                                                                                                          Management
                                  Management                                                                        System
                                                PM                                                     WF
                                              Plant
                         Field                                                                        Workflow
                                           Maintenance
                                                                                                                                     - Project
                        Service
                                                                                           IS
                                                             HR
                        Support
                                                                                                                                       Accounting
                                                                                                                         IS-RE
                                                                                         Industry
                                     Work                   Human
                                                                                         Solutions
                                                           Resources
                                  Clearance*
                                                                                                            IS-U /
                                                                                                                                       - Real Estate
                                                                                                            FERC
                                                SM
 - Human Resources &                                                            GIS
                                                                          CAD                                                            Management
   Payroll                                     Service                          AM/FM
                                                Mgmt
                                                                                                IS-U/
                                                                                                CCS
                                                                                                                                 - Customer Care &
                                                                                                                                   Revenue Management
Systems to be Replaced
Original – Replaced = Final
240 – 138 = 102 systems
198 – 128 = 70 interfaces
ERP Program –
    Past and Future Release dates.

    Release 1 & 2
    GAMAP /GRAP
    SAP_BW

                                                                                  2005                       2006
    Program                    2003                          2004
                                                                          F   A    J AA M
                                                                                        O        D   F   A   J   OA NO   D
                      F    A   J   A   O   D   F    A    J   A   O    D       F    M             J           S           D
                                                                                                     J   A
  System Support                                        Support to 6300 system users

    Release 1                                               Original Project Scope:
                                                   Release 1 – Expenditure (Go-live Dec 2002)
                                                    Release 2 – Revenue (Go-live Sept 2003)
    Release 2      Revenue Release
                                                 Implement GAMAP
                          GAMAP
     GAMAP                                     GAMAP compliance as of
                                                    1 July 2003


System Enhancements        Monthly Releases of new Reports and Functionality
                                                                                    Upgrade of
     Upgrade
                                                                                    R3 and ISU

     Business
                                                                                                SAP-BW
    Warehouse
                                                                  Go-live dates
Agenda




         Background.

         Implementation SAP - the City’s ERP system.

         SAP-ISU – the City’s Utility solution.

         Creating Value

         Conclusion.
Challenges faced by the Cape Town Municipal Utilities


    Social responsibilities of Government in conflict with
    Commercial Objectives of Utility Business units.

    Aging Infrastructure with a lack of investment in proactive
    maintenance.

    Need to rapidly expand access to basic services in order to –
               keep track with high rate of urbanisation and
               eliminate the historical backlog.

    Many Citizen can not afford basic Utilities.

    Unbundling of Utility Services from Local Authorities.

    Managing limited Natural Resources.

Initial steps to overcome many of these challenges have been enabled
 through the implementation of the City SAP-ERP system
Social responsibilities of Local Government vrs.
      Commercial objectives

      Unlocking scarce financial resources for social up-liftment
      and improved service delivery :

                                   R extracted, used to improve …
             Create
            financial
              value                                       Preferential procurement
                                                              Employment equity

                        R extracted, used for …                        Socially
                                                  Supports …
                                                                      conscious
                                                                       policies
                              Advance social
  R extracted, used to
                                upliftment                                                    Improve
educate staff and provide                               lower cost, more pervasive
                                                                                          service delivery
     better working                                     service delivery supports …
    environment …
                                 improved decision making
                        allowing matching of supply and demand …


                              Information
                             transparency
                                                    motivated, better educated
               Enhance
                                                      and more productive             Enabled by SAP
                human
                                                          employees…
             performance
Infrastructure Maintenance: Plant Maintenance


  Maintenance Management has been enabled through the
implementation of SAP-PM (Plant Maintenance)
       All infrastructural assets have been created on SAP within a functional
       location hierarchy.
          2 million pieces of equipment (fixed installations, distributed Infrastructure,
                                                  equipment and plant)
          100’s proactive maintenance schedules created.
          2 163 PM users across 500 Maintenance Depots and Workshops
   Centralised call centre for Defect Notification via ISU-CIC and PM
   Accurate job costing - Integration with Ledger and Asset Register
Infrastructure Provision: Project Systems (PS)

  Provision of Services to previously disadvantaged communities
  necessitates an aggressive infrastructure expansion programme.

  Financial management of projects via PS and Investment
  Management structures to administer various funding sources.

  Integration of Project Systems with the Asset Register.

  Asset Depreciation and Interest Simulation.
Utility Billing: Consolidated billing for various services.


Number of Contracts and Devices managed through SAP ISU:

Division:                                        Number of Meter Reading
                          Number of    Billing
                                                           interval
                          Contracts   Interval    Devices
                                                             Prop. value assessed
                           671 388                  n/a
Property Taxes:                       Annual
                                                                 every 5 yrs.

                           633 183                577 148
Water Services:                       Monthly                      Monthly

                           616 923                569 821
Sewerage Services:                    Monthly                      Monthly

                           658 306                529 611
Refuse Removal:                       Monthly                   Fixed Charge

                                                  364 779          Monthly
                           451 894
Electricity:                          Monthly
                                                                   Pre-paid
                                                  423 527
                  Total   3 031 694              2 464 886

          Number of ISU users = 2 243            Number of PM users = 2 163
Revenue Solution: Progressive Tariff Structures
  Large disparity in the socio-economic status of citizens
        Identifying citizens which can – but don’t pay versus
        Citizens which do not have the means to pay.

  Implementation of social and resource responsible tariff
structures:
    Property Tax: first R50 000 of property value exempt from tax - then
    property tax based on % of remainder of property value.
    Water: first 6 kl free and then step tariff based on property zoning.
    Sewerage: Availability charge based on property value and consumptive
    charges as a % of water consumption
    Refuse: Availability charge based on property value and consumptive
    charge based on bins removed by week.
    Electricity: first 50 KwH free and then step tariff per category of user.

        Rebate system for citizens which are proven to be indigent.
        Debt payment via arrangement with the raising of interest being suspended for
        period whilst arrangement is being adhered to.
        Various other progressive messages to help address arrears.
        Invoicing in all 3 Official Languages of the Western Cape Province.
Revenue Solution: Consolidated and Itemised Billing

Extract of Municipal Account – front page (Balances)
Revenue Solution: Consolidated and Itemised Billing

Extract of Utility Bill - City of Cape Town (in Afrikaans):
- Property Tax: instalment Plan
- Electricity and Water : Step Tariffs with actual Consumption for billing
                           period and availability charges shown in detail.
- Sewerage and Waste Removal plus Sundry Charges not shown………
Single view of the citizen                               Consumption History
                                                         Click for Graphic View and
                                                         details of Meter Readings
                      Account Balance.
                                                         and Period Consumption.
                   Click for current and future
                   amounts raised and details
                     of payments received.



                           Monthly Consolidated
                                Account.                 History of Customer
                             Click for copy of Invoice        Contacts
                                                         No further action required
                                                              Click for details




Details of Each Service
Tab for details of each Utility
    and Rates Service.
                                                              Service Orders
                                                                  Raised
                                                          Instruction to Operational
                                                            Units to perform work.
                                                            Click for Progress and
                                                             Costing Information
Turning the Tide against Non-payment:
    Payment Ratio
                                       How was the benefit realised?
                                       • Improved visibility and transparency of information on the new invoice, the
                                         ability for citizens to pay their accounts at any municipal pay point and the
                                         implementation of a call center to address billing queries.
                                       • Revenue Services performed significant data alignment duties in converting
                                         data to SAP.
                                       • Revenue enhancement interventions have received priority attention.




       Payment Ratio : 12 month moving average                             Calculation:

                                                                           • 1% increase in the payment ration =
100.0%                                                                       R6,05 mil per month.
95.0%                                                                      • Increasing the payment ration since
                                                                             go-live of ISU has increased revenue
90.0%
                                                                             by R698 mil.
85.0%                                                                      • Only 10% of this payment benefit has
                                                                             been accredited as a direct ERP
80.0%
                                                                             benefit – a very conservative approach
75.0%                                                                        has been adopted in the ROI model.
               03




                                                4
                              4
                       04




                                       4
         3




                                                      4
                                            l- 0
                             -0

                                     -0
       0




                                                       0
             v-

                    n-




                                                    p-
    p-




                            ar

                                  ay

                                           Ju
           No

                  Ja
  Se




                                                Se
                         M

                                 M




             % Payments vs Billings        (12 month moving average)
Cash flow.

It’s all about Cash in the Bank:
Net increase of R667mil between Sept ’03 (SAP go-live)
and Sept ’04.

                            Cash Balance

                                        SAP
              1,600
                                         go-
              1,400                      live
              1,200
 R '000 000




              1,000
                800
                                                             Planned loan of
                600                                           R300 mil not
                400                                           taken up
                200
                  0




               Au 4
               Au 3
               Au 2




               Ap 4
               Ap 3




               O3




                     04
                    03
               Fe 2
               O2




               Ju 4
               Ju 3




               De 3
               De 2




                     0
                     0




                     0
                     0




                  r- 0

                     0
                     0
                  r- 0
                     0




                    0




                   -0
                   -0




                  n-




                  n-
                  n-




                 b-
                 b-




                  c-




                 g-
                  c-




                 g-
                 g-




                ct
                ct
               Ju




               Fe     Budgeted Cash Balance     Actual Cash Balance
Creating Confidence in utility-billing:
    Starts with accurate meter readings.
                                                     Number of Repeated
Reason for no meter reading– (SAP / GIS Reporting)
                                                            Estimates
                                                      Number
                                                         OF       Number
                                                     estimates OF meters
                                                          2         2612
                                                          3         1591
                                                          4          755
                                                          5          519
                                                          6          416
                                                          7          303
                                                          8          243
                                                          9         1433
                                                         10          224
Managing scarce Natural Resources

Water Consumption Monitoring
Cape Town is in the mits of a
sever draught.

SAP – Spacial reporting
Agenda




         Background.

         Implementation SAP - the City’s ERP system.

         SAP-ISU – the City’s Utility solution.

         Creating Value

         Conclusion.
Value Creating Opportunities Identified
  A compelling business case was built by only
       quantifying       “ the tip of the iceberg ”




           Quantified, financial VCOs that are directly attributable to SAP (4)

               Those financial VCOs that we have managed to quantify (10)

       Those financial VCOs that can be quantified (managers willing AND data is available)

                      Those VCOs that have a direct financial benefit (45)

               Those VCOs that we have documented (74 unique of the127 identified)

Those VCOs that are known to the City of Cape Town due to a vision and strategy having been defined

               All value creating opportunities (VCOs) that can be enabled by an ERP
Project Benefits: Financial (CoCT ROI Study)
                                                                                      Value of Benefit:                        2002 - 2004
R 300,000,000
                                                                                      • Reduction in costs of support staff = R87,5mil
R 250,000,000
                                                                                      • Increased Revenue through improved collection
R 200,000,000                                              Staff Costs
                                                                                        and daily billing = R192,6 mil
                                                           Revenue
R 150,000,000
                                                                                      • Reduction in Inventory Holdings and increase in
                                                           Inventory Benefits
                                                                                        stock turns = R1,02 mil
R 100,000,000                                              IT Value Opportunity

 R 50,000,000                                                                         • IT value. The cost of supporting SAP with more
                                                                                        functionality = cost of supporting legacy
          R0
                                                                                        systems
                2001/2   2002/3    2003/4   2004/5


                 Project break-even will be achieved before the end of the current financial year
                 R 300,000,000
                    Project Implementation Costs = R 350 mil ($ 58,3 mil)
                 R 200,000,000                                                                                                      Cos ts




                 R 100,000,000
                                                                                                                                    Benefits
                                                                                                                                    Realis ed
                           R0


                                                                                                                                    Net ROI
                -R 100,000,000



                                                                                                                /8




                                                                                                                          /9
                                                 /3




                                                                                         /6




                                                                                                     /7
                                       /2




                                                             /4




                                                                          /5




                                                                                                              07




                                                                                                                        08
                                               02




                                                                                                   06
                                     01




                                                           03




                                                                        04




                                                                                       05




                                                                                                           20




                                                                                                                     20
                                            20




                                                                                    20




                                                                                                20
                                  20




                                                        20




                                                                     20




                -R 200,000,000
                                                                                                                                    Expected
                                                                               Future value of Realised Benefits
                                                                                                                                    Cas e
                                              Actuals
                                                                                                                                    Feb2002
                -R 300,000,000
Project Benefits: E-Government – the next wave
   Bridging the digital divide:
   ERP project critical enabler to the “smart city”
   strategy

SAP will provide the
solid foundation on
which the
eGovernment strategy
of the City will be
deployed.

eGovernment flip
flops relationships:

Citizen     Citizen


Official      IT


  IT        Official
Agenda




         Background.

         Implementation SAP - the City’s ERP system.

         SAP-ISU – the City’s Utility solution.

         Creating Value

         Conclusion.
Support Organisation – Driving out Business Value




Accredited SAP Competence Center Established.

Support Team = 150 (Coct = 90, Accenture = 20, Empowerment = 40)
With a 3 year strategy to become self sufficient.

Business appointed Process Owners and User Groups established.

Monthly release strategy implemented
Conclusion:

In conclusion, implementing ‘SAP in the City’ has …
 Helped to align the operational activities of the organisation to its strategic
 imperatives - basic free services for the ‘poorest of the poor’

 Provided a robust technical platform to integrate and standardise business
 processes across the organisation

 Significantly impacted the city’s operating model, organisational structure and
 human performance considerations - Services closer to the People.

 Provides effective management reporting capabilities, encouraging fairness,
 accountability, responsibility and transparency

 Enables financial, as well as non-financial benefits

 Enabled performance management
Questions ?




City of Cape Town: ERP project room (August 2002)

More Related Content

What's hot

Jesse robredo on mainstreaming meaningful stakeholdership in governance
Jesse robredo on mainstreaming meaningful stakeholdership in governanceJesse robredo on mainstreaming meaningful stakeholdership in governance
Jesse robredo on mainstreaming meaningful stakeholdership in governanceGreen Minds
 
Western cape broadband strategy (industry briefing)
Western cape broadband strategy (industry briefing)Western cape broadband strategy (industry briefing)
Western cape broadband strategy (industry briefing)Nirvesh Sooful
 
Information Society SA, Public Sector ICT CeBIT 2013 presentation
Information Society SA, Public Sector ICT CeBIT 2013 presentationInformation Society SA, Public Sector ICT CeBIT 2013 presentation
Information Society SA, Public Sector ICT CeBIT 2013 presentationInformation Society SA
 
EOH Local Government Services
EOH Local Government ServicesEOH Local Government Services
EOH Local Government ServicesNirvesh Sooful
 
CSI Piemonte international
CSI Piemonte internationalCSI Piemonte international
CSI Piemonte internationalDebora Colò
 
Framework For Smart E India Insyder
Framework For Smart E India   InsyderFramework For Smart E India   Insyder
Framework For Smart E India InsyderRoy Antony Arnold G
 
Sheffield city region cdi overview
Sheffield city region cdi overviewSheffield city region cdi overview
Sheffield city region cdi overviewSheffieldCityRegion
 
Report of the Committee on NOFN
Report of the Committee on NOFNReport of the Committee on NOFN
Report of the Committee on NOFNVishal Sharma
 
The Internet & Rural Development ME 216 Information & Communication Technolog...
The Internet & Rural Development ME 216 Information & Communication Technolog...The Internet & Rural Development ME 216 Information & Communication Technolog...
The Internet & Rural Development ME 216 Information & Communication Technolog...Jo Balucanag - Bitonio
 
Tutorial 2 arvo ott
Tutorial 2 arvo ottTutorial 2 arvo ott
Tutorial 2 arvo ottegovernment
 
Dews ict haro_debrief_v3
Dews ict haro_debrief_v3Dews ict haro_debrief_v3
Dews ict haro_debrief_v3Jennifer Chan
 
Broad band 14march2012-pgw_cindustrypresentation
Broad band 14march2012-pgw_cindustrypresentationBroad band 14march2012-pgw_cindustrypresentation
Broad band 14march2012-pgw_cindustrypresentationNirvesh Sooful
 
Pearl River Delta 2020
Pearl River Delta 2020Pearl River Delta 2020
Pearl River Delta 2020Dinah Saw
 
Measuring digital development for policy-making: Models, stages, characterist...
Measuring digital development for policy-making: Models, stages, characterist...Measuring digital development for policy-making: Models, stages, characterist...
Measuring digital development for policy-making: Models, stages, characterist...Ismael Peña-López
 
Understanding e government in kortrijk
Understanding e government in kortrijkUnderstanding e government in kortrijk
Understanding e government in kortrijkSmart Cities Project
 
An ANT exploration of mParticipation in the city of Cape Town
An ANT exploration of mParticipation in the city of Cape TownAn ANT exploration of mParticipation in the city of Cape Town
An ANT exploration of mParticipation in the city of Cape TownLaban Bagui
 

What's hot (20)

Jesse robredo on mainstreaming meaningful stakeholdership in governance
Jesse robredo on mainstreaming meaningful stakeholdership in governanceJesse robredo on mainstreaming meaningful stakeholdership in governance
Jesse robredo on mainstreaming meaningful stakeholdership in governance
 
Western cape broadband strategy (industry briefing)
Western cape broadband strategy (industry briefing)Western cape broadband strategy (industry briefing)
Western cape broadband strategy (industry briefing)
 
Jan5 pack
Jan5 packJan5 pack
Jan5 pack
 
Information Society SA, Public Sector ICT CeBIT 2013 presentation
Information Society SA, Public Sector ICT CeBIT 2013 presentationInformation Society SA, Public Sector ICT CeBIT 2013 presentation
Information Society SA, Public Sector ICT CeBIT 2013 presentation
 
EOH Local Government Services
EOH Local Government ServicesEOH Local Government Services
EOH Local Government Services
 
Arm overview
Arm overviewArm overview
Arm overview
 
Microsoft_overview
Microsoft_overviewMicrosoft_overview
Microsoft_overview
 
Tcdc scrlep overview
Tcdc scrlep overviewTcdc scrlep overview
Tcdc scrlep overview
 
CSI Piemonte international
CSI Piemonte internationalCSI Piemonte international
CSI Piemonte international
 
Framework For Smart E India Insyder
Framework For Smart E India   InsyderFramework For Smart E India   Insyder
Framework For Smart E India Insyder
 
Sheffield city region cdi overview
Sheffield city region cdi overviewSheffield city region cdi overview
Sheffield city region cdi overview
 
Report of the Committee on NOFN
Report of the Committee on NOFNReport of the Committee on NOFN
Report of the Committee on NOFN
 
The Internet & Rural Development ME 216 Information & Communication Technolog...
The Internet & Rural Development ME 216 Information & Communication Technolog...The Internet & Rural Development ME 216 Information & Communication Technolog...
The Internet & Rural Development ME 216 Information & Communication Technolog...
 
Tutorial 2 arvo ott
Tutorial 2 arvo ottTutorial 2 arvo ott
Tutorial 2 arvo ott
 
Dews ict haro_debrief_v3
Dews ict haro_debrief_v3Dews ict haro_debrief_v3
Dews ict haro_debrief_v3
 
Broad band 14march2012-pgw_cindustrypresentation
Broad band 14march2012-pgw_cindustrypresentationBroad band 14march2012-pgw_cindustrypresentation
Broad band 14march2012-pgw_cindustrypresentation
 
Pearl River Delta 2020
Pearl River Delta 2020Pearl River Delta 2020
Pearl River Delta 2020
 
Measuring digital development for policy-making: Models, stages, characterist...
Measuring digital development for policy-making: Models, stages, characterist...Measuring digital development for policy-making: Models, stages, characterist...
Measuring digital development for policy-making: Models, stages, characterist...
 
Understanding e government in kortrijk
Understanding e government in kortrijkUnderstanding e government in kortrijk
Understanding e government in kortrijk
 
An ANT exploration of mParticipation in the city of Cape Town
An ANT exploration of mParticipation in the city of Cape TownAn ANT exploration of mParticipation in the city of Cape Town
An ANT exploration of mParticipation in the city of Cape Town
 

Viewers also liked

Accelerate Cape Town
Accelerate Cape TownAccelerate Cape Town
Accelerate Cape Townguylundy
 
Vision 2030 Indaba Presentation by Guy Lundy
Vision 2030 Indaba Presentation by Guy LundyVision 2030 Indaba Presentation by Guy Lundy
Vision 2030 Indaba Presentation by Guy Lundyguylundy
 
Creative Cape Town Design Indaba 2009
Creative Cape Town Design Indaba 2009Creative Cape Town Design Indaba 2009
Creative Cape Town Design Indaba 2009Cape Town Partnership
 
Cape Town for World Design Capital Bid 2014
Cape Town for World Design Capital Bid 2014Cape Town for World Design Capital Bid 2014
Cape Town for World Design Capital Bid 2014Cape Town Partnership
 
Brand Cape Town - May 2011.
Brand Cape Town - May 2011.Brand Cape Town - May 2011.
Brand Cape Town - May 2011.guylundy
 
Cape Town - South Africa
Cape Town - South AfricaCape Town - South Africa
Cape Town - South AfricaJohn *
 
Central City Development Strategy 2008
Central City Development Strategy 2008Central City Development Strategy 2008
Central City Development Strategy 2008Mike Perk
 
Planning and Design Issues: Eric Keune
Planning and Design Issues: Eric KeunePlanning and Design Issues: Eric Keune
Planning and Design Issues: Eric Keuneurbansystemssymposium
 
Stadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of StadiumsStadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of Stadiumssoumya2492
 
A Brief Intro to Scramjet Engines
A Brief Intro to Scramjet EnginesA Brief Intro to Scramjet Engines
A Brief Intro to Scramjet Enginesishan patel
 

Viewers also liked (12)

Accelerate Cape Town
Accelerate Cape TownAccelerate Cape Town
Accelerate Cape Town
 
Cape Town Partnership 2009 Feedback
Cape Town Partnership 2009 FeedbackCape Town Partnership 2009 Feedback
Cape Town Partnership 2009 Feedback
 
Vision 2030 Indaba Presentation by Guy Lundy
Vision 2030 Indaba Presentation by Guy LundyVision 2030 Indaba Presentation by Guy Lundy
Vision 2030 Indaba Presentation by Guy Lundy
 
Creative Cape Town Design Indaba 2009
Creative Cape Town Design Indaba 2009Creative Cape Town Design Indaba 2009
Creative Cape Town Design Indaba 2009
 
Cape Town for World Design Capital Bid 2014
Cape Town for World Design Capital Bid 2014Cape Town for World Design Capital Bid 2014
Cape Town for World Design Capital Bid 2014
 
Cape Town is open for business
Cape Town is open for businessCape Town is open for business
Cape Town is open for business
 
Brand Cape Town - May 2011.
Brand Cape Town - May 2011.Brand Cape Town - May 2011.
Brand Cape Town - May 2011.
 
Cape Town - South Africa
Cape Town - South AfricaCape Town - South Africa
Cape Town - South Africa
 
Central City Development Strategy 2008
Central City Development Strategy 2008Central City Development Strategy 2008
Central City Development Strategy 2008
 
Planning and Design Issues: Eric Keune
Planning and Design Issues: Eric KeunePlanning and Design Issues: Eric Keune
Planning and Design Issues: Eric Keune
 
Stadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of StadiumsStadiums That Changed The Game - Structure Development Of Stadiums
Stadiums That Changed The Game - Structure Development Of Stadiums
 
A Brief Intro to Scramjet Engines
A Brief Intro to Scramjet EnginesA Brief Intro to Scramjet Engines
A Brief Intro to Scramjet Engines
 

Similar to Presentation to DPLG May2006

eGovernment interoperability
eGovernment interoperabilityeGovernment interoperability
eGovernment interoperabilityLuis Guijarro
 
Towards an evidence-based approach to local intervention : The ECAMP tool
Towards an evidence-based approach to local intervention : The ECAMP toolTowards an evidence-based approach to local intervention : The ECAMP tool
Towards an evidence-based approach to local intervention : The ECAMP toolClaus Rabe
 
Road To Responsibility
Road To ResponsibilityRoad To Responsibility
Road To ResponsibilityMatsBerglind
 
Enabling the next generation airport at DXB
Enabling the next generation airport at DXBEnabling the next generation airport at DXB
Enabling the next generation airport at DXBAmor Group
 
How to successfully implement sap ami
How to successfully implement sap amiHow to successfully implement sap ami
How to successfully implement sap amirobgirvan
 
Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...
Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...
Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...Shane Mitchell
 
City of Cape Town Automated Metering Infrastructure (AMI)
City of Cape Town Automated Metering Infrastructure (AMI) City of Cape Town Automated Metering Infrastructure (AMI)
City of Cape Town Automated Metering Infrastructure (AMI) Rudy Abrahams
 
Data center -_james_lindauer_v2
Data center -_james_lindauer_v2Data center -_james_lindauer_v2
Data center -_james_lindauer_v2James Lindauer
 
SPAN IFMIS Project in Indonesia
SPAN IFMIS Project in IndonesiaSPAN IFMIS Project in Indonesia
SPAN IFMIS Project in Indonesiaicgfmconference
 
Impact of the Program IDABC in Spain (interoperable delivery of services to a...
Impact of the Program IDABC in Spain (interoperable delivery of services to a...Impact of the Program IDABC in Spain (interoperable delivery of services to a...
Impact of the Program IDABC in Spain (interoperable delivery of services to a...Miguel A. Amutio
 
Next genits closing_event
Next genits closing_eventNext genits closing_event
Next genits closing_eventimec.archive
 
2040 RTP Leadership Symposium 8.24.12
2040 RTP Leadership Symposium 8.24.122040 RTP Leadership Symposium 8.24.12
2040 RTP Leadership Symposium 8.24.12CHCRPA
 
City of Ottawa Success Stories Using FME
City of Ottawa Success Stories Using FMECity of Ottawa Success Stories Using FME
City of Ottawa Success Stories Using FMESafe Software
 
2010 koneps brochure
2010 koneps brochure2010 koneps brochure
2010 koneps brochureHai Nguyen
 
Dan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network WebinarDan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network Webinarunitedwaterslides
 
S&T for Homeland Security 2011 Framework For Safe and Secure City
S&T for Homeland Security 2011 Framework For Safe and Secure CityS&T for Homeland Security 2011 Framework For Safe and Secure City
S&T for Homeland Security 2011 Framework For Safe and Secure CityADGP, Public Grivences, Bangalore
 
Itac benoit long deck final eng - feb 12 2013
Itac benoit long deck   final eng - feb 12 2013Itac benoit long deck   final eng - feb 12 2013
Itac benoit long deck final eng - feb 12 2013KBIZEAU
 
SAUG 2010 EA101 Session
SAUG 2010 EA101 SessionSAUG 2010 EA101 Session
SAUG 2010 EA101 SessionPhil Gleadhill
 

Similar to Presentation to DPLG May2006 (20)

eGovernment interoperability
eGovernment interoperabilityeGovernment interoperability
eGovernment interoperability
 
Towards an evidence-based approach to local intervention : The ECAMP tool
Towards an evidence-based approach to local intervention : The ECAMP toolTowards an evidence-based approach to local intervention : The ECAMP tool
Towards an evidence-based approach to local intervention : The ECAMP tool
 
Road To Responsibility
Road To ResponsibilityRoad To Responsibility
Road To Responsibility
 
Enabling the next generation airport at DXB
Enabling the next generation airport at DXBEnabling the next generation airport at DXB
Enabling the next generation airport at DXB
 
How to successfully implement sap ami
How to successfully implement sap amiHow to successfully implement sap ami
How to successfully implement sap ami
 
Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...
Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...
Volker Buscher, Arup - Urban Information Architecture: From Digital to Smart ...
 
City of Cape Town Automated Metering Infrastructure (AMI)
City of Cape Town Automated Metering Infrastructure (AMI) City of Cape Town Automated Metering Infrastructure (AMI)
City of Cape Town Automated Metering Infrastructure (AMI)
 
Data center -_james_lindauer_v2
Data center -_james_lindauer_v2Data center -_james_lindauer_v2
Data center -_james_lindauer_v2
 
SPAN IFMIS Project in Indonesia
SPAN IFMIS Project in IndonesiaSPAN IFMIS Project in Indonesia
SPAN IFMIS Project in Indonesia
 
Impact of the Program IDABC in Spain (interoperable delivery of services to a...
Impact of the Program IDABC in Spain (interoperable delivery of services to a...Impact of the Program IDABC in Spain (interoperable delivery of services to a...
Impact of the Program IDABC in Spain (interoperable delivery of services to a...
 
Next genits closing_event
Next genits closing_eventNext genits closing_event
Next genits closing_event
 
2040 RTP Leadership Symposium 8.24.12
2040 RTP Leadership Symposium 8.24.122040 RTP Leadership Symposium 8.24.12
2040 RTP Leadership Symposium 8.24.12
 
Presentation
PresentationPresentation
Presentation
 
City of Ottawa Success Stories Using FME
City of Ottawa Success Stories Using FMECity of Ottawa Success Stories Using FME
City of Ottawa Success Stories Using FME
 
2010 koneps brochure
2010 koneps brochure2010 koneps brochure
2010 koneps brochure
 
York Region Rapid Transit
York Region Rapid TransitYork Region Rapid Transit
York Region Rapid Transit
 
Dan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network WebinarDan Sugarman Sustainable City Network Webinar
Dan Sugarman Sustainable City Network Webinar
 
S&T for Homeland Security 2011 Framework For Safe and Secure City
S&T for Homeland Security 2011 Framework For Safe and Secure CityS&T for Homeland Security 2011 Framework For Safe and Secure City
S&T for Homeland Security 2011 Framework For Safe and Secure City
 
Itac benoit long deck final eng - feb 12 2013
Itac benoit long deck   final eng - feb 12 2013Itac benoit long deck   final eng - feb 12 2013
Itac benoit long deck final eng - feb 12 2013
 
SAUG 2010 EA101 Session
SAUG 2010 EA101 SessionSAUG 2010 EA101 Session
SAUG 2010 EA101 Session
 

More from Nirvesh Sooful

Safety and security summit launch
Safety and security summit launchSafety and security summit launch
Safety and security summit launchNirvesh Sooful
 
African Urban Matters - African Ideas - Connected Cities
African Urban Matters - African Ideas - Connected CitiesAfrican Urban Matters - African Ideas - Connected Cities
African Urban Matters - African Ideas - Connected CitiesNirvesh Sooful
 
Bridging the digital divide – access. content and skills.
Bridging the digital divide – access. content and skills.Bridging the digital divide – access. content and skills.
Bridging the digital divide – access. content and skills.Nirvesh Sooful
 
Improving Local Government Procurement through the use of technology
Improving Local Government Procurement through the use of technology Improving Local Government Procurement through the use of technology
Improving Local Government Procurement through the use of technology Nirvesh Sooful
 
Western Cape Broadband Briefing to Cape Chamber ICT Committee
Western Cape Broadband Briefing to Cape Chamber ICT CommitteeWestern Cape Broadband Briefing to Cape Chamber ICT Committee
Western Cape Broadband Briefing to Cape Chamber ICT CommitteeNirvesh Sooful
 
Western cape broadband strategy (industry briefing leadership)
Western cape broadband strategy (industry briefing   leadership)Western cape broadband strategy (industry briefing   leadership)
Western cape broadband strategy (industry briefing leadership)Nirvesh Sooful
 
Case study: ICT as the key ingredient of your city development strategy
Case study: ICT as the key ingredient of your city development strategyCase study: ICT as the key ingredient of your city development strategy
Case study: ICT as the key ingredient of your city development strategyNirvesh Sooful
 
Using ICT to enable government supply chain and procurement processes
Using ICT to enable government supply chain and procurement processesUsing ICT to enable government supply chain and procurement processes
Using ICT to enable government supply chain and procurement processesNirvesh Sooful
 
Some Random Thoughts On My Departure
Some Random Thoughts On My DepartureSome Random Thoughts On My Departure
Some Random Thoughts On My DepartureNirvesh Sooful
 
The Emerging Role Of The Cio
The Emerging Role Of The CioThe Emerging Role Of The Cio
The Emerging Role Of The CioNirvesh Sooful
 
Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...
Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...
Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...Nirvesh Sooful
 

More from Nirvesh Sooful (11)

Safety and security summit launch
Safety and security summit launchSafety and security summit launch
Safety and security summit launch
 
African Urban Matters - African Ideas - Connected Cities
African Urban Matters - African Ideas - Connected CitiesAfrican Urban Matters - African Ideas - Connected Cities
African Urban Matters - African Ideas - Connected Cities
 
Bridging the digital divide – access. content and skills.
Bridging the digital divide – access. content and skills.Bridging the digital divide – access. content and skills.
Bridging the digital divide – access. content and skills.
 
Improving Local Government Procurement through the use of technology
Improving Local Government Procurement through the use of technology Improving Local Government Procurement through the use of technology
Improving Local Government Procurement through the use of technology
 
Western Cape Broadband Briefing to Cape Chamber ICT Committee
Western Cape Broadband Briefing to Cape Chamber ICT CommitteeWestern Cape Broadband Briefing to Cape Chamber ICT Committee
Western Cape Broadband Briefing to Cape Chamber ICT Committee
 
Western cape broadband strategy (industry briefing leadership)
Western cape broadband strategy (industry briefing   leadership)Western cape broadband strategy (industry briefing   leadership)
Western cape broadband strategy (industry briefing leadership)
 
Case study: ICT as the key ingredient of your city development strategy
Case study: ICT as the key ingredient of your city development strategyCase study: ICT as the key ingredient of your city development strategy
Case study: ICT as the key ingredient of your city development strategy
 
Using ICT to enable government supply chain and procurement processes
Using ICT to enable government supply chain and procurement processesUsing ICT to enable government supply chain and procurement processes
Using ICT to enable government supply chain and procurement processes
 
Some Random Thoughts On My Departure
Some Random Thoughts On My DepartureSome Random Thoughts On My Departure
Some Random Thoughts On My Departure
 
The Emerging Role Of The Cio
The Emerging Role Of The CioThe Emerging Role Of The Cio
The Emerging Role Of The Cio
 
Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...
Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...
Digital Cities Conference 2007 - The Social and Economic Impact of a Metropol...
 

Recently uploaded

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 

Recently uploaded (20)

Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 

Presentation to DPLG May2006

  • 1. CITY OF CAPE TOWN Creating Sustainable Value in a multi service municipality André Stelzner / Mehboob Foflonker Dir: ERP Business Transformation Dir: ERP Implementation
  • 2. Agenda Background. SAP Implementation - the City’s ERP system. SAP-ISU – the City’s Utility solution. Creating Value Conclusion.
  • 3. Background: Significant Political Events in South Africa during the past decade have changed the face of Local Government in Cape Town. Pre- 1994: South Africa internationally isolated and communities segregated on racial grounds. April 1994: first democratic election and government of national unity established. 3-Tier government structure: National, Provincial and Local Government Legislation passed restructuring Local Government: Mergers of 7 previous autonomous Municipalities into a single Metropolitan Uni-City Powers and Duties of Local Authorities changed Next Wave of Restructuring – Establishment of Regional Electricity Distributors.
  • 4. Background: The City of Cape Town had to merge 7 previously autonomous local government administrations and become a single integrated metropolitan City, but it found that creating a Unicity to be complex due to: • “Lack of standardised financial policies and procedures” • “Each administration ran its own IT systems, many of which did not meet business requirements” • “Back-office systems were deemed (by large) to be outdated, functionally inadequate and not properly integrated” • “Difficulty in merging these systems was in fact hindering the merger of the administrations and undermining the objectives which motivated the creation of the Unicity”
  • 5. Background: Demographics of Cape Town Population: 3.2 million Share of National GDP: 10.5 % Share of Provincial GDP: 75 % Area: 215 900 ha Rateable Properties: 800 000 Employees: 24 579 Annual budget 2004/05: Operating: R 11,3 billion Capital: R 1,5 billion Annual Income 2004/05: From Utility Services: R 4,36 billion (38,6 %) From Tax and Levies: R 3,14 billiion (27,8 %)
  • 6. Background: Local Government – the delivery arm of Government Governance closest to the people – providing the following services: Electricity / distribution and peak load generating Water and Sanitation / storage, treatment and distribution Solid Waste / landfill, removal and area cleaning Roads, Stormwater and transport Public Housing Local Economic Development Social - and primary health services Emergency Services Municipal Policing Urban Planning and Environment Sport and Recreation City Administration
  • 7. Agenda Background. Implementation SAP - the City’s ERP system. SAP-ISU – the City’s Utility solution. Creating Value Conclusion.
  • 8. Project Implementation: Selection Process 2004 & beyond 2002 & 2003 2000 2001 The years of The years of The year of The year of Benefits Implementation Strategy Selection Projects undertaken during 2001: Resulted in the SAP system and Accenture being selected. Project # 4 Project # 3 Project # 5 Project # 2 • The consultant • The enterprise • The software • The ERP systems selection system integrator selection implementation (March – April 2001) selection (July - (April - June 2001) blueprint planning November 2001) • Gartner was chosen phase • SAP was selected to assist with software (November 2001 - • Accenture was as software and systems January 2002) chosen as the providers integrator selection preferred ERP • Accenture confirms processes system integration their cost & scope partner of implementation
  • 9. Project Objectives: CA PE METROPOLITA N Blaauwberg AREA City of Tygerberg City of Oostenberg Cape Cape Town Cape Town Town Helderberg South Penins ula “To Implement a functionally rich ERP system, in a manner that will ensure integration, facilitate the merger and bring about organisational transformation.” Thereby, enabling the City to deliver on its Strategic Objectives”
  • 10. What is an ERP MAINTENANCE Processes An ERPsystem offers organizations a ASSET MANAGEMENT Processes PROCUREMENT Processes REVENUE Processes comprehensive and integrated solution for managing services such as financial, revenue, human resources, maintenance, procurement, leasing, customer care on a single integrated IT system. PROJECT Processes HR processes CUSTOMER Processes It is not so much about the technology as it is PLANNING processes about the integration of business processes. ACCOUNTING processes Workflow provides the means of automating business processes and system integration ensures that only a single record of master data is held – but shared across the application. Debate is whether to implement an ERP system vrs. so called ‘best of breed’ systems. SAP is a specific ERP vendors.
  • 11. Successful Organizations are able to align: STRATEGY: Strategy Organisation What must we do ? TECHNOLOGY PROCESS: How are we going to do it? Process People People: Who is going to do it ?
  • 12. Project Scope: The City of Cape Town: Scope of implementation - Billing to sundry - Financial Accounting debtors SD FI Sales & Financial Distribution Accounting - Management MM CO - Procurement & Accounting Materials Controlling Inventory SCADA* Mgmt. R/3 (4.6c) and AM PP Management Fixed Assets Production IS-U/CCS (4.63) Mgmt Planning EDI Number of Users - Plant Maintenance QM PS - Asset 6 500 Quality Project Management Management System PM WF Plant Field Workflow Maintenance - Project Service IS HR Support Accounting IS-RE Industry Work Human Solutions Resources Clearance* IS-U / - Real Estate FERC SM - Human Resources & GIS CAD Management Payroll Service AM/FM Mgmt IS-U/ CCS - Customer Care & Revenue Management Systems to be Replaced Original – Replaced = Final 240 – 138 = 102 systems 198 – 128 = 70 interfaces
  • 13. ERP Program – Past and Future Release dates. Release 1 & 2 GAMAP /GRAP SAP_BW 2005 2006 Program 2003 2004 F A J AA M O D F A J OA NO D F A J A O D F A J A O D F M J S D J A System Support Support to 6300 system users Release 1 Original Project Scope: Release 1 – Expenditure (Go-live Dec 2002) Release 2 – Revenue (Go-live Sept 2003) Release 2 Revenue Release Implement GAMAP GAMAP GAMAP GAMAP compliance as of 1 July 2003 System Enhancements Monthly Releases of new Reports and Functionality Upgrade of Upgrade R3 and ISU Business SAP-BW Warehouse Go-live dates
  • 14. Agenda Background. Implementation SAP - the City’s ERP system. SAP-ISU – the City’s Utility solution. Creating Value Conclusion.
  • 15. Challenges faced by the Cape Town Municipal Utilities Social responsibilities of Government in conflict with Commercial Objectives of Utility Business units. Aging Infrastructure with a lack of investment in proactive maintenance. Need to rapidly expand access to basic services in order to – keep track with high rate of urbanisation and eliminate the historical backlog. Many Citizen can not afford basic Utilities. Unbundling of Utility Services from Local Authorities. Managing limited Natural Resources. Initial steps to overcome many of these challenges have been enabled through the implementation of the City SAP-ERP system
  • 16. Social responsibilities of Local Government vrs. Commercial objectives Unlocking scarce financial resources for social up-liftment and improved service delivery : R extracted, used to improve … Create financial value Preferential procurement Employment equity R extracted, used for … Socially Supports … conscious policies Advance social R extracted, used to upliftment Improve educate staff and provide lower cost, more pervasive service delivery better working service delivery supports … environment … improved decision making allowing matching of supply and demand … Information transparency motivated, better educated Enhance and more productive Enabled by SAP human employees… performance
  • 17. Infrastructure Maintenance: Plant Maintenance Maintenance Management has been enabled through the implementation of SAP-PM (Plant Maintenance) All infrastructural assets have been created on SAP within a functional location hierarchy. 2 million pieces of equipment (fixed installations, distributed Infrastructure, equipment and plant) 100’s proactive maintenance schedules created. 2 163 PM users across 500 Maintenance Depots and Workshops Centralised call centre for Defect Notification via ISU-CIC and PM Accurate job costing - Integration with Ledger and Asset Register
  • 18. Infrastructure Provision: Project Systems (PS) Provision of Services to previously disadvantaged communities necessitates an aggressive infrastructure expansion programme. Financial management of projects via PS and Investment Management structures to administer various funding sources. Integration of Project Systems with the Asset Register. Asset Depreciation and Interest Simulation.
  • 19. Utility Billing: Consolidated billing for various services. Number of Contracts and Devices managed through SAP ISU: Division: Number of Meter Reading Number of Billing interval Contracts Interval Devices Prop. value assessed 671 388 n/a Property Taxes: Annual every 5 yrs. 633 183 577 148 Water Services: Monthly Monthly 616 923 569 821 Sewerage Services: Monthly Monthly 658 306 529 611 Refuse Removal: Monthly Fixed Charge 364 779 Monthly 451 894 Electricity: Monthly Pre-paid 423 527 Total 3 031 694 2 464 886 Number of ISU users = 2 243 Number of PM users = 2 163
  • 20. Revenue Solution: Progressive Tariff Structures Large disparity in the socio-economic status of citizens Identifying citizens which can – but don’t pay versus Citizens which do not have the means to pay. Implementation of social and resource responsible tariff structures: Property Tax: first R50 000 of property value exempt from tax - then property tax based on % of remainder of property value. Water: first 6 kl free and then step tariff based on property zoning. Sewerage: Availability charge based on property value and consumptive charges as a % of water consumption Refuse: Availability charge based on property value and consumptive charge based on bins removed by week. Electricity: first 50 KwH free and then step tariff per category of user. Rebate system for citizens which are proven to be indigent. Debt payment via arrangement with the raising of interest being suspended for period whilst arrangement is being adhered to. Various other progressive messages to help address arrears. Invoicing in all 3 Official Languages of the Western Cape Province.
  • 21. Revenue Solution: Consolidated and Itemised Billing Extract of Municipal Account – front page (Balances)
  • 22. Revenue Solution: Consolidated and Itemised Billing Extract of Utility Bill - City of Cape Town (in Afrikaans): - Property Tax: instalment Plan - Electricity and Water : Step Tariffs with actual Consumption for billing period and availability charges shown in detail. - Sewerage and Waste Removal plus Sundry Charges not shown………
  • 23. Single view of the citizen Consumption History Click for Graphic View and details of Meter Readings Account Balance. and Period Consumption. Click for current and future amounts raised and details of payments received. Monthly Consolidated Account. History of Customer Click for copy of Invoice Contacts No further action required Click for details Details of Each Service Tab for details of each Utility and Rates Service. Service Orders Raised Instruction to Operational Units to perform work. Click for Progress and Costing Information
  • 24. Turning the Tide against Non-payment: Payment Ratio How was the benefit realised? • Improved visibility and transparency of information on the new invoice, the ability for citizens to pay their accounts at any municipal pay point and the implementation of a call center to address billing queries. • Revenue Services performed significant data alignment duties in converting data to SAP. • Revenue enhancement interventions have received priority attention. Payment Ratio : 12 month moving average Calculation: • 1% increase in the payment ration = 100.0% R6,05 mil per month. 95.0% • Increasing the payment ration since go-live of ISU has increased revenue 90.0% by R698 mil. 85.0% • Only 10% of this payment benefit has been accredited as a direct ERP 80.0% benefit – a very conservative approach 75.0% has been adopted in the ROI model. 03 4 4 04 4 3 4 l- 0 -0 -0 0 0 v- n- p- p- ar ay Ju No Ja Se Se M M % Payments vs Billings (12 month moving average)
  • 25. Cash flow. It’s all about Cash in the Bank: Net increase of R667mil between Sept ’03 (SAP go-live) and Sept ’04. Cash Balance SAP 1,600 go- 1,400 live 1,200 R '000 000 1,000 800 Planned loan of 600 R300 mil not 400 taken up 200 0 Au 4 Au 3 Au 2 Ap 4 Ap 3 O3 04 03 Fe 2 O2 Ju 4 Ju 3 De 3 De 2 0 0 0 0 r- 0 0 0 r- 0 0 0 -0 -0 n- n- n- b- b- c- g- c- g- g- ct ct Ju Fe Budgeted Cash Balance Actual Cash Balance
  • 26. Creating Confidence in utility-billing: Starts with accurate meter readings. Number of Repeated Reason for no meter reading– (SAP / GIS Reporting) Estimates Number OF Number estimates OF meters 2 2612 3 1591 4 755 5 519 6 416 7 303 8 243 9 1433 10 224
  • 27. Managing scarce Natural Resources Water Consumption Monitoring Cape Town is in the mits of a sever draught. SAP – Spacial reporting
  • 28. Agenda Background. Implementation SAP - the City’s ERP system. SAP-ISU – the City’s Utility solution. Creating Value Conclusion.
  • 29. Value Creating Opportunities Identified A compelling business case was built by only quantifying “ the tip of the iceberg ” Quantified, financial VCOs that are directly attributable to SAP (4) Those financial VCOs that we have managed to quantify (10) Those financial VCOs that can be quantified (managers willing AND data is available) Those VCOs that have a direct financial benefit (45) Those VCOs that we have documented (74 unique of the127 identified) Those VCOs that are known to the City of Cape Town due to a vision and strategy having been defined All value creating opportunities (VCOs) that can be enabled by an ERP
  • 30. Project Benefits: Financial (CoCT ROI Study) Value of Benefit: 2002 - 2004 R 300,000,000 • Reduction in costs of support staff = R87,5mil R 250,000,000 • Increased Revenue through improved collection R 200,000,000 Staff Costs and daily billing = R192,6 mil Revenue R 150,000,000 • Reduction in Inventory Holdings and increase in Inventory Benefits stock turns = R1,02 mil R 100,000,000 IT Value Opportunity R 50,000,000 • IT value. The cost of supporting SAP with more functionality = cost of supporting legacy R0 systems 2001/2 2002/3 2003/4 2004/5 Project break-even will be achieved before the end of the current financial year R 300,000,000 Project Implementation Costs = R 350 mil ($ 58,3 mil) R 200,000,000 Cos ts R 100,000,000 Benefits Realis ed R0 Net ROI -R 100,000,000 /8 /9 /3 /6 /7 /2 /4 /5 07 08 02 06 01 03 04 05 20 20 20 20 20 20 20 20 -R 200,000,000 Expected Future value of Realised Benefits Cas e Actuals Feb2002 -R 300,000,000
  • 31. Project Benefits: E-Government – the next wave Bridging the digital divide: ERP project critical enabler to the “smart city” strategy SAP will provide the solid foundation on which the eGovernment strategy of the City will be deployed. eGovernment flip flops relationships: Citizen Citizen Official IT IT Official
  • 32. Agenda Background. Implementation SAP - the City’s ERP system. SAP-ISU – the City’s Utility solution. Creating Value Conclusion.
  • 33. Support Organisation – Driving out Business Value Accredited SAP Competence Center Established. Support Team = 150 (Coct = 90, Accenture = 20, Empowerment = 40) With a 3 year strategy to become self sufficient. Business appointed Process Owners and User Groups established. Monthly release strategy implemented
  • 34. Conclusion: In conclusion, implementing ‘SAP in the City’ has … Helped to align the operational activities of the organisation to its strategic imperatives - basic free services for the ‘poorest of the poor’ Provided a robust technical platform to integrate and standardise business processes across the organisation Significantly impacted the city’s operating model, organisational structure and human performance considerations - Services closer to the People. Provides effective management reporting capabilities, encouraging fairness, accountability, responsibility and transparency Enables financial, as well as non-financial benefits Enabled performance management
  • 35. Questions ? City of Cape Town: ERP project room (August 2002)