SlideShare a Scribd company logo
1 of 19
FGD REVIEW
BY CHAIRMAN SIR
on
07.06.2023
ANPARA ‘D’, 2X500 MW
PROJECT SUMMARY
Contract Schedule
As per original NOA dated 4th July2019:
• Unit#6 - 24 months i.e. 3rd July 2021 for Completion of FGD system.
• Unit#7 – 27 months i.e. 3rd October 2021 for Completion of FGD system
Revised dates as per 4th EOT :
• Unit #7 – 30.06.2023
• Unit #6 – 22.09.2023
EXPECTED DATE OF COMPLETION AS PER M/s BEIJING SPC :
• Unit #7 – JUNE 2024
• Unit #6 – SEPTEMBER 2024
• Revised plan for 31.03.2024 for first unit is not submitted by M/s BSPC
FGD PROJECT, ANPARA ‘D’ 2
PROJECT MILE STONE DATES
Sr. No. Activity As Per Actual/
L2-Schedule Expected
1 Notice of Award 04.07.2019 04-07-2019
2 Initial Mobilization for Site enabling activities 23.09.2019 01-09-2019
3 Mobilization for Piling Contractor 20.11.2019 01-06-2020
4 Test Pile Work-Start 30.03.2020 09-08-2020
5 BOI Ordering-Start 20.10.2019 24-02-2020
6 Basic Engineering Completion 30.11.2019 29-04-2020
7 Mobilization for Civil Contractor 06.12.2019 15-01-2021
8 Mechanical Erection Start 01.10.2020 02-07-2021
9 Civil and Structural Works -Completion 30.09.2020 28-02-2024
10 Manufacturing & Supply of Equipment-Completion 30.12.2020 30-11-2023
11 Mechanical & Electrical Erection-Completion (U#1) 30.04.2021 30-06-2024
FGD PROJECT, ANPARA ‘D’ 3
SITE PROGRESS
FGD PROJECT, ANPARA ‘D’ 4
STATUS AS PER ROLLING PLAN (FEB’23 TO MAY’23)
SN ACTIVITY UOM
Target
(From
01.02.2023
to
31.05.2023)
Achieved
upto
31.05.2023
%
Progress
Achieved
Remark
A Ground Improvement
A-1
Stone
coloumn-600
mm dia
NOS 1140 1389 121.84 Sub-Vendor M/s ITD
Cementation stopped work on site
due to internal issue with M/s
BSPC from 23.05.2023
A-2
Piling-600 mm
dia/760mm dia
NOS 294 235 79.93
B Chimney
B-1
Shell slipping/
Casting
CUM 5449 2880 52.85
slow work progress due to
frequent stoppage and non
availability of construction
material
Total Height 54.80/193.5 MTR
completed as on date
SITE PROGRESS
FGD PROJECT, ANPARA ‘D’ 5
SR.
NO
ACTIVITY UOM
Target
(From
01.02.2023
to 31.05.2023)
Achieved
upto
31.05.2023
%
Progress
Achieved
Remark
C
Foundation-Unit#6 &7 Absorber, Inlet Duct, ECB, GDWTR Building, Booster
Fan, Recycle pump, Emergency Tank
C-1 Excavation CUM 16200 11695.5 72.19
work in progress, slow due to
low manpower
C-2 Pile chipping NOS 519 364 70.13
work in progress, slow due to
low manpower
C-3 RCC CUM 3304 735.5 22.26
work in progress, slow due to
low manpower
D Fabrication and Erection
D-1
Fabrication of
Duct
MT 425 23 5.41
Slow work progress due to
unavailability of steel
D-2
Duct Erection
and
Installation
MT 575 0 0.00 Civil front not available
STATUS AS PER ROLLING PLAN (FEB’23 TO MAY’23)
SITE PROGRESS
FGD PROJECT, ANPARA ‘D’ 6
STATUS AS PER ROLLING PLAN (MAY’23)
SN ACTIVITY UOM
Target
in
May 2023
Achieved
in
May 2023
%
Progress
Achieved
Remark
A Ground Improvement
A-1
Stone
coloumn-600
mm dia
NOS 360 286 79.44 Sub-Vendor M/s ITD
Cementation stopped work on site
due to internal issue with M/s
BSPC from 23.05.2023
A-2
Piling-600 mm
dia/760mm dia
NOS 84 27 32.14
B Chimney
B-1
Shell slipping/
Casting
CUM 1470 830 56.46
slow work progress due to
frequent stoppage and non
availability of construction
material
Total Height 54.80/193.5 MTR
completed as on date
SITE PROGRESS
FGD PROJECT, ANPARA ‘D’ 7
SR.
NO
ACTIVITY UOM
Target
in
May 2023
Achieved
in
May 2023
%
Progress
Achieved
Remark
C
Foundation-Unit#6 &7 Absorber, Inlet Duct, ECB, GDWTR Building, Booster
Fan, Recycle pump, Emergency Tank
C-1 Excavation CUM 4000 1870 46.75
work in progress, slow due to
low manpower
C-2 Pile chipping NOS 153 99 64.70
work in progress, slow due to
low manpower
C-3 RCC CUM 600 169 28.16
work in progress, slow due to
low manpower
D Fabrication and Erection
D-1
Fabrication of
Duct
MT 50 26 52.00
Slow work progress due to
unavailability of steel
D-2
Duct Erection
and
Installation
MT 0 0 0 Civil front not available
STATUS AS PER ROLLING PLAN (MAY’23)
STATUS SUMMARY
FGD PROJECT, ANPARA ‘D’ 8
PHYSICAL PROGRESS
Package Current PROGRESS (%)
CIVIL 46%
PROCUREMENT 34%
MECHANICAL AND ELECTRICAL 1%
ENGINEERING 72%
OVERALL 33%
STATUS SUMMARY
FGD PROJECT, ANPARA ‘D’ 9
STONE COLUMNS, BCIS PILING & ENGINEERING
WORK UOM TOTAL COMPLETED
TILL
04.06.2023
BALANCE %
Achieved
STONE COLUMNS 600
MM DIA
NOS. 8344 7138 1206 85.54
STONE COLUMNS 900
MM DIA
NOS. 319 319 0 100.00
BCIS PILE 600 MM DIA NOS. 270 105 165 38.88
BCIS PILE 760 MM DIA NOS. 1532 1448 84 94.51
DUCT FABRICATION
WORK (MT)
MT 2512 1795 717 71.45
ENGINEERING
DRAWING SUBMISSION
FROM BSPC
NOS. 324 233 91 71.91
ENGINEERING
DRAWING APPROVAL
FROM NTPC
NOS. 234 230 4 98.29
SITE PROGRESS
FGD PROJECT, ANPARA ‘D’ 10
MAJOR PACKAGE STATUS as on date
SN ACTIVITY
TOTAL
SCOPE
UOM
PROGRESS
ACHIEVED
%
Achieved
Remarks
A Chimney
1 Shell slipping 8500 CUM 3196.5 37.60
WORK UNDER PROGRESS
2
Chimney
Shell Height
193.5 MTR 54.80 28.32
B
Absrober
#6
Excavation Completed
RCC 542 CUM 445.3 82.15
WALL CASTING COMPLETED,
REST WORK UNDER
PROGRESS
C
Absrober
#7
Excavation 2050 CUM 1750 85.36
LOAD TEST COMPLETED,
SAND FILLING UNDER
PROGRESS FOR PCC
Pile head
work
90 NOS 77 85.55 13 balance left for Elevator
SITE PROGRESS
FGD PROJECT, ANPARA ‘D’ 11
MAJOR PACKAGE STATUS
SN ACTIVITY
SUB
ACTIVITY
TOTAL
SCOPE
UOM
PROGRESS
ACHIEVED
%
Achieved
Remarks
D
GYPSUM
DEWATERING
BUILDING
Excavation 8341 CUM 5010 60.06 WORK PROGRESS SLOW
DUE TO NEAR CHIMNEY
AREA
Pile
Chipping
257 NOS 125 48.63
E
INLET DUCT
SUPPORT
Excavation 6500
CUM
5642 86.80
WORK PROGRESS SLOW
DUE TO INSUFFICIENT
DEPLOYMENT OF
REQUIRED MANPOWER
Pile
Chipping
310 NOS 217 70.00
Foundation 100 NOS 26 26.00
F
ELECTRICAL
CONTROL
BUILDING
Rebar
Fixing
98 MT 28 28.57
WORK UNDER PROGRESS,
STARTED FROM 22.04.2023
G MHS AREA
Stone
Column
2001 NOS 1690 84.45 WORK HALTED
Piling 440 NOS 227 51.51 WORK HALTED
H
BOOSTER
FAN
6 & 7
Pile
Chipping/
Cutting
56 NOS 28 50.00
PILING COMPLETED, PILE
CHIPPING UNDER
PROGRESS
PRESENT MANPOWER
SN Name of Agency
Present
Manpower
WORK
1 M/s Beijing – SPC 13 EPC - FGD Project
2 M/s Balaji 24 Supply of RMC
3 M/s ITD cementation limited 144 Ground Improvement and
Piling works
4 M/s KEEPL 64 Civil foundation works for
FGD
5 M/s Teknow Overseas Pvt. Ltd. 123 Construction of Chimney
6 M/s Shivam Enterprises Pvt. Ltd. 45 Duct fabrication and
erection works
Grand Total 413
FGD PROJECT, ANPARA ‘D’ 12
PRESENT MATERIAL STATUS
SN
Area of
work
Description Size UOM
Closing
Balance
Requirement
1 Chimney
Rebar
16mm MT 72.83 Upto 125 mtr -164 MT
25mm MT 22.20 Upto 125 mtr - 50 MT
12mm MT 15.02 Upto 125 mtr - 30 MT
32mm MT 9.78 Upto 125 mtr - 35 MT
Dala aggregate10 & 20 mm MT 432.35 Upto 125 mtr - 3700 MT
OPC Cement - MT 14.82 Upto 125 mtr -1250MT
2
Other Civil
works
Rebar
8mm MT 17.35
10mm MT 21.88
12mm MT 24.82
16mm MT 21.80
20mm MT 47.20
25mm MT 19.80
32mm MT 29.40
FGD PROJECT, ANPARA ‘D’ 13
PRESENT MATERIAL STATUS
SN Area of work Description Size UOM Closing Balance
3 BCIS Pile work Rebar
8 mm MT 9.705
16mm MT 106.152
20mm MT 41.726
25mm MT 34.399
Total Reinforcement 494.062
4
For BCIS Pile
work
Liner plate MT 21.000
5
For Civil
construction &
BCIS Pile work
Admixture KG 258.280
Cement PPC MT 79.000
Chitrangi
Aggregate
10/20 mm MT 1298.000
FGD PROJECT, ANPARA ‘D’ 14
STATUS SUMMARY
FGD PROJECT, ANPARA ‘D’ 15
FINANCIAL PROGRESS
CONTRACT
CONTRACT
VALUE
Expenditure
till 31.05.2023
FINANCIAL
PROGRESS (%)
OFFSHORE
SUPPLY
USD 10.06 Million INR 7.14 Cr 7.53%
ONSHORE
SUPPLY
INR 181.61 Cr INR 45.71 Cr 19.68%
WORK
EXECUTION
INR 147.50 Cr INR 85.71Cr 49.25%
BOI SUMMARY
SN AREA TOTAL
ITEMS
TOTAL
ORDERED
IMPORTED
ITEMS BOI
DOMESTIC
ITEMS BOI
TOTAL
NO
TOTAL
ORDERED
TOTAL
NO
TOTAL
ORDERED
1 MECHANICAL 27 24 11 10 16 14
2 ELECTRICAL 13 4 0 0 13 4
3 C&I 4 3 0 0 4 3
GRAND TOTAL 44 31 11 10 33 21
16
FGD PROJECT, ANPARA ‘D’
CRITICAL ISSUES
• BSPC Sub-Vendor M/s ITD Cementation stopped work on site from
23.05.2023 due to payment and other contractual issues. Progress of
Ground Improvement i.e. stone column, BCIS piling and other civil
construction work at site is completely hampered.
• Only one Stone column Rig is deployed at present. UNL asked BSPC to
ensure deployment of two more stone column rigs as committed by them
on 05.04.2023 & 17.05.2023 during VC with Chairman UNL in order to
complete the works before monsoon.
• BSPC was to deploy at least 500 nos. manpower by 30.04.2023 as
committed by them on 05.04.2023 during VC with Chairman UNL.
Presently only 413 nos. manpower is deployed at site. BSPC must adhere
to their commitment and enhance the manpower to 500 nos. immediately
and improve the construction material availability as per site requirement.
• Construction material e.g. OPC Cement and Rebar for Chimney shell
casting work and PPC Cement, Rebar and Liner plate for other civil works
should be made available at site in sufficient required quantity by BSPC.
FGD PROJECT, ANPARA ‘D’ 17
CLAIM NOTICE FILED BY BSPC
 BSPC submitted claim notice vide Reference No:
SPC/ANPARA-D/LTR/23-24/277 dated 05.06.2023 received
through email.
 Total Claim Value for Contract-1 USD 10.30 Millions
 Total Claim Value for Contract-2&3 INR 232.04 Crores
 BSPC stated that there was a pressing requirement for UPRVUNL to
proceed for an equitable adjustment of the Contract price, as mandated
and allowed under various clauses of the Contract, including but not limited
to Article 3.1 & 3.2 of the Contract, as well as (among others), Clause 35
(Unforeseen Conditions), Clause 36 (Change in Laws and Regulations),
Clause 37.6 (Force Majeure) and Clause 39 (Change in the Facilities), of
the GCCs
 SETTLEMENT OF DISPUTES / NOTICE OF MUTUAL CONSULTATION,
UNDER CLAUSE 6.1 OF THE GCCs.
FGD PROJECT, ANPARA ‘D’ 18
THANK YOU
FGD PROJECT, ANPARA ‘D’ 19

More Related Content

Similar to ANPARA D FGD PPT 07.06.2023-M (2).pptx

Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxIESGATEWiz
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...muralikrishna317515
 
Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011cmogsc
 
practical training ppt
practical training pptpractical training ppt
practical training pptSagar Shah
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxSaketChandra4
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDFClement Seong
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING Ram1239
 
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxVenkatesh Dontha
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdfsantosobudipray
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxMayankGandhi51
 

Similar to ANPARA D FGD PPT 07.06.2023-M (2).pptx (20)

FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptx
 
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptxFinal Compiled GM Presentation on 18.05.2022 Updated.pptx
Final Compiled GM Presentation on 18.05.2022 Updated.pptx
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
Deep Foundation Technologies for Resurgent India Charotar Basarkar Circulatio...
 
Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011Completed projects july 2010 sept 2011
Completed projects july 2010 sept 2011
 
JAGMOC RESUME
JAGMOC RESUMEJAGMOC RESUME
JAGMOC RESUME
 
practical training ppt
practical training pptpractical training ppt
practical training ppt
 
ICI FINAL REPORT
ICI FINAL REPORTICI FINAL REPORT
ICI FINAL REPORT
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptx
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
 
Sbhep vivek kumar
Sbhep vivek kumarSbhep vivek kumar
Sbhep vivek kumar
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
2024.03.07 PICA Armor Rock_Rev. 05 (Live Doc.)_CPY.pdf
 
PDash,NMDCEDL6.pptx
PDash,NMDCEDL6.pptxPDash,NMDCEDL6.pptx
PDash,NMDCEDL6.pptx
 
CV_Ing_Civil _LEMKEDDEM_Eng
CV_Ing_Civil _LEMKEDDEM_EngCV_Ing_Civil _LEMKEDDEM_Eng
CV_Ing_Civil _LEMKEDDEM_Eng
 
Review of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptxReview of PH-16 With CRB.pptx
Review of PH-16 With CRB.pptx
 

Recently uploaded

Call Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on Delivery
Call Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on DeliveryCall Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on Delivery
Call Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on Deliverybabeytanya
 
VIP Kolkata Call Girl Kestopur 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kestopur 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kestopur 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kestopur 👉 8250192130 Available With Roomdivyansh0kumar0
 
Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Chennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts serviceChennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts servicevipmodelshub1
 
Russian Call girls in Dubai +971563133746 Dubai Call girls
Russian  Call girls in Dubai +971563133746 Dubai  Call girlsRussian  Call girls in Dubai +971563133746 Dubai  Call girls
Russian Call girls in Dubai +971563133746 Dubai Call girlsstephieert
 
Denver Web Design brochure for public viewing
Denver Web Design brochure for public viewingDenver Web Design brochure for public viewing
Denver Web Design brochure for public viewingbigorange77
 
Gram Darshan PPT cyber rural in villages of india
Gram Darshan PPT cyber rural  in villages of indiaGram Darshan PPT cyber rural  in villages of india
Gram Darshan PPT cyber rural in villages of indiaimessage0108
 
Complet Documnetation for Smart Assistant Application for Disabled Person
Complet Documnetation   for Smart Assistant Application for Disabled PersonComplet Documnetation   for Smart Assistant Application for Disabled Person
Complet Documnetation for Smart Assistant Application for Disabled Personfurqan222004
 
VIP Kolkata Call Girls Salt Lake 8250192130 Available With Room
VIP Kolkata Call Girls Salt Lake 8250192130 Available With RoomVIP Kolkata Call Girls Salt Lake 8250192130 Available With Room
VIP Kolkata Call Girls Salt Lake 8250192130 Available With Roomgirls4nights
 
Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)
Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)
Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)Dana Luther
 
VIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call Girladitipandeya
 
Git and Github workshop GDSC MLRITM
Git and Github  workshop GDSC MLRITMGit and Github  workshop GDSC MLRITM
Git and Github workshop GDSC MLRITMgdsc13
 
Russian Call Girls in Kolkata Samaira 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Samaira 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Samaira 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Samaira 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
AlbaniaDreamin24 - How to easily use an API with Flows
AlbaniaDreamin24 - How to easily use an API with FlowsAlbaniaDreamin24 - How to easily use an API with Flows
AlbaniaDreamin24 - How to easily use an API with FlowsThierry TROUIN ☁
 
FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607dollysharma2066
 
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一Fs
 
VIP Kolkata Call Girl Salt Lake 👉 8250192130 Available With Room
VIP Kolkata Call Girl Salt Lake 👉 8250192130  Available With RoomVIP Kolkata Call Girl Salt Lake 👉 8250192130  Available With Room
VIP Kolkata Call Girl Salt Lake 👉 8250192130 Available With Roomishabajaj13
 
Russian Call Girls in Kolkata Ishita 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Ishita 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Ishita 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Ishita 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 

Recently uploaded (20)

Call Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on Delivery
Call Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on DeliveryCall Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on Delivery
Call Girls In Mumbai Central Mumbai ❤️ 9920874524 👈 Cash on Delivery
 
VIP Kolkata Call Girl Kestopur 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kestopur 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kestopur 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kestopur 👉 8250192130 Available With Room
 
Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Uttam Nagar Delhi 💯Call Us 🔝8264348440🔝
 
sasti delhi Call Girls in munirka 🔝 9953056974 🔝 escort Service-
sasti delhi Call Girls in munirka 🔝 9953056974 🔝 escort Service-sasti delhi Call Girls in munirka 🔝 9953056974 🔝 escort Service-
sasti delhi Call Girls in munirka 🔝 9953056974 🔝 escort Service-
 
Chennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts serviceChennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts service
Chennai Call Girls Alwarpet Phone 🍆 8250192130 👅 celebrity escorts service
 
Russian Call girls in Dubai +971563133746 Dubai Call girls
Russian  Call girls in Dubai +971563133746 Dubai  Call girlsRussian  Call girls in Dubai +971563133746 Dubai  Call girls
Russian Call girls in Dubai +971563133746 Dubai Call girls
 
Denver Web Design brochure for public viewing
Denver Web Design brochure for public viewingDenver Web Design brochure for public viewing
Denver Web Design brochure for public viewing
 
Gram Darshan PPT cyber rural in villages of india
Gram Darshan PPT cyber rural  in villages of indiaGram Darshan PPT cyber rural  in villages of india
Gram Darshan PPT cyber rural in villages of india
 
Complet Documnetation for Smart Assistant Application for Disabled Person
Complet Documnetation   for Smart Assistant Application for Disabled PersonComplet Documnetation   for Smart Assistant Application for Disabled Person
Complet Documnetation for Smart Assistant Application for Disabled Person
 
Call Girls In South Ex 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In South Ex 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In South Ex 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In South Ex 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
VIP Kolkata Call Girls Salt Lake 8250192130 Available With Room
VIP Kolkata Call Girls Salt Lake 8250192130 Available With RoomVIP Kolkata Call Girls Salt Lake 8250192130 Available With Room
VIP Kolkata Call Girls Salt Lake 8250192130 Available With Room
 
Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)
Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)
Packaging the Monolith - PHP Tek 2024 (Breaking it down one bite at a time)
 
VIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls LB Nagar high-profile Call Girl
 
Git and Github workshop GDSC MLRITM
Git and Github  workshop GDSC MLRITMGit and Github  workshop GDSC MLRITM
Git and Github workshop GDSC MLRITM
 
Russian Call Girls in Kolkata Samaira 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Samaira 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Samaira 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Samaira 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
AlbaniaDreamin24 - How to easily use an API with Flows
AlbaniaDreamin24 - How to easily use an API with FlowsAlbaniaDreamin24 - How to easily use an API with Flows
AlbaniaDreamin24 - How to easily use an API with Flows
 
FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607
FULL ENJOY Call Girls In Mayur Vihar Delhi Contact Us 8377087607
 
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
定制(Lincoln毕业证书)新西兰林肯大学毕业证成绩单原版一比一
 
VIP Kolkata Call Girl Salt Lake 👉 8250192130 Available With Room
VIP Kolkata Call Girl Salt Lake 👉 8250192130  Available With RoomVIP Kolkata Call Girl Salt Lake 👉 8250192130  Available With Room
VIP Kolkata Call Girl Salt Lake 👉 8250192130 Available With Room
 
Russian Call Girls in Kolkata Ishita 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Ishita 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Ishita 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Ishita 🤌 8250192130 🚀 Vip Call Girls Kolkata
 

ANPARA D FGD PPT 07.06.2023-M (2).pptx

  • 1. FGD REVIEW BY CHAIRMAN SIR on 07.06.2023 ANPARA ‘D’, 2X500 MW
  • 2. PROJECT SUMMARY Contract Schedule As per original NOA dated 4th July2019: • Unit#6 - 24 months i.e. 3rd July 2021 for Completion of FGD system. • Unit#7 – 27 months i.e. 3rd October 2021 for Completion of FGD system Revised dates as per 4th EOT : • Unit #7 – 30.06.2023 • Unit #6 – 22.09.2023 EXPECTED DATE OF COMPLETION AS PER M/s BEIJING SPC : • Unit #7 – JUNE 2024 • Unit #6 – SEPTEMBER 2024 • Revised plan for 31.03.2024 for first unit is not submitted by M/s BSPC FGD PROJECT, ANPARA ‘D’ 2
  • 3. PROJECT MILE STONE DATES Sr. No. Activity As Per Actual/ L2-Schedule Expected 1 Notice of Award 04.07.2019 04-07-2019 2 Initial Mobilization for Site enabling activities 23.09.2019 01-09-2019 3 Mobilization for Piling Contractor 20.11.2019 01-06-2020 4 Test Pile Work-Start 30.03.2020 09-08-2020 5 BOI Ordering-Start 20.10.2019 24-02-2020 6 Basic Engineering Completion 30.11.2019 29-04-2020 7 Mobilization for Civil Contractor 06.12.2019 15-01-2021 8 Mechanical Erection Start 01.10.2020 02-07-2021 9 Civil and Structural Works -Completion 30.09.2020 28-02-2024 10 Manufacturing & Supply of Equipment-Completion 30.12.2020 30-11-2023 11 Mechanical & Electrical Erection-Completion (U#1) 30.04.2021 30-06-2024 FGD PROJECT, ANPARA ‘D’ 3
  • 4. SITE PROGRESS FGD PROJECT, ANPARA ‘D’ 4 STATUS AS PER ROLLING PLAN (FEB’23 TO MAY’23) SN ACTIVITY UOM Target (From 01.02.2023 to 31.05.2023) Achieved upto 31.05.2023 % Progress Achieved Remark A Ground Improvement A-1 Stone coloumn-600 mm dia NOS 1140 1389 121.84 Sub-Vendor M/s ITD Cementation stopped work on site due to internal issue with M/s BSPC from 23.05.2023 A-2 Piling-600 mm dia/760mm dia NOS 294 235 79.93 B Chimney B-1 Shell slipping/ Casting CUM 5449 2880 52.85 slow work progress due to frequent stoppage and non availability of construction material Total Height 54.80/193.5 MTR completed as on date
  • 5. SITE PROGRESS FGD PROJECT, ANPARA ‘D’ 5 SR. NO ACTIVITY UOM Target (From 01.02.2023 to 31.05.2023) Achieved upto 31.05.2023 % Progress Achieved Remark C Foundation-Unit#6 &7 Absorber, Inlet Duct, ECB, GDWTR Building, Booster Fan, Recycle pump, Emergency Tank C-1 Excavation CUM 16200 11695.5 72.19 work in progress, slow due to low manpower C-2 Pile chipping NOS 519 364 70.13 work in progress, slow due to low manpower C-3 RCC CUM 3304 735.5 22.26 work in progress, slow due to low manpower D Fabrication and Erection D-1 Fabrication of Duct MT 425 23 5.41 Slow work progress due to unavailability of steel D-2 Duct Erection and Installation MT 575 0 0.00 Civil front not available STATUS AS PER ROLLING PLAN (FEB’23 TO MAY’23)
  • 6. SITE PROGRESS FGD PROJECT, ANPARA ‘D’ 6 STATUS AS PER ROLLING PLAN (MAY’23) SN ACTIVITY UOM Target in May 2023 Achieved in May 2023 % Progress Achieved Remark A Ground Improvement A-1 Stone coloumn-600 mm dia NOS 360 286 79.44 Sub-Vendor M/s ITD Cementation stopped work on site due to internal issue with M/s BSPC from 23.05.2023 A-2 Piling-600 mm dia/760mm dia NOS 84 27 32.14 B Chimney B-1 Shell slipping/ Casting CUM 1470 830 56.46 slow work progress due to frequent stoppage and non availability of construction material Total Height 54.80/193.5 MTR completed as on date
  • 7. SITE PROGRESS FGD PROJECT, ANPARA ‘D’ 7 SR. NO ACTIVITY UOM Target in May 2023 Achieved in May 2023 % Progress Achieved Remark C Foundation-Unit#6 &7 Absorber, Inlet Duct, ECB, GDWTR Building, Booster Fan, Recycle pump, Emergency Tank C-1 Excavation CUM 4000 1870 46.75 work in progress, slow due to low manpower C-2 Pile chipping NOS 153 99 64.70 work in progress, slow due to low manpower C-3 RCC CUM 600 169 28.16 work in progress, slow due to low manpower D Fabrication and Erection D-1 Fabrication of Duct MT 50 26 52.00 Slow work progress due to unavailability of steel D-2 Duct Erection and Installation MT 0 0 0 Civil front not available STATUS AS PER ROLLING PLAN (MAY’23)
  • 8. STATUS SUMMARY FGD PROJECT, ANPARA ‘D’ 8 PHYSICAL PROGRESS Package Current PROGRESS (%) CIVIL 46% PROCUREMENT 34% MECHANICAL AND ELECTRICAL 1% ENGINEERING 72% OVERALL 33%
  • 9. STATUS SUMMARY FGD PROJECT, ANPARA ‘D’ 9 STONE COLUMNS, BCIS PILING & ENGINEERING WORK UOM TOTAL COMPLETED TILL 04.06.2023 BALANCE % Achieved STONE COLUMNS 600 MM DIA NOS. 8344 7138 1206 85.54 STONE COLUMNS 900 MM DIA NOS. 319 319 0 100.00 BCIS PILE 600 MM DIA NOS. 270 105 165 38.88 BCIS PILE 760 MM DIA NOS. 1532 1448 84 94.51 DUCT FABRICATION WORK (MT) MT 2512 1795 717 71.45 ENGINEERING DRAWING SUBMISSION FROM BSPC NOS. 324 233 91 71.91 ENGINEERING DRAWING APPROVAL FROM NTPC NOS. 234 230 4 98.29
  • 10. SITE PROGRESS FGD PROJECT, ANPARA ‘D’ 10 MAJOR PACKAGE STATUS as on date SN ACTIVITY TOTAL SCOPE UOM PROGRESS ACHIEVED % Achieved Remarks A Chimney 1 Shell slipping 8500 CUM 3196.5 37.60 WORK UNDER PROGRESS 2 Chimney Shell Height 193.5 MTR 54.80 28.32 B Absrober #6 Excavation Completed RCC 542 CUM 445.3 82.15 WALL CASTING COMPLETED, REST WORK UNDER PROGRESS C Absrober #7 Excavation 2050 CUM 1750 85.36 LOAD TEST COMPLETED, SAND FILLING UNDER PROGRESS FOR PCC Pile head work 90 NOS 77 85.55 13 balance left for Elevator
  • 11. SITE PROGRESS FGD PROJECT, ANPARA ‘D’ 11 MAJOR PACKAGE STATUS SN ACTIVITY SUB ACTIVITY TOTAL SCOPE UOM PROGRESS ACHIEVED % Achieved Remarks D GYPSUM DEWATERING BUILDING Excavation 8341 CUM 5010 60.06 WORK PROGRESS SLOW DUE TO NEAR CHIMNEY AREA Pile Chipping 257 NOS 125 48.63 E INLET DUCT SUPPORT Excavation 6500 CUM 5642 86.80 WORK PROGRESS SLOW DUE TO INSUFFICIENT DEPLOYMENT OF REQUIRED MANPOWER Pile Chipping 310 NOS 217 70.00 Foundation 100 NOS 26 26.00 F ELECTRICAL CONTROL BUILDING Rebar Fixing 98 MT 28 28.57 WORK UNDER PROGRESS, STARTED FROM 22.04.2023 G MHS AREA Stone Column 2001 NOS 1690 84.45 WORK HALTED Piling 440 NOS 227 51.51 WORK HALTED H BOOSTER FAN 6 & 7 Pile Chipping/ Cutting 56 NOS 28 50.00 PILING COMPLETED, PILE CHIPPING UNDER PROGRESS
  • 12. PRESENT MANPOWER SN Name of Agency Present Manpower WORK 1 M/s Beijing – SPC 13 EPC - FGD Project 2 M/s Balaji 24 Supply of RMC 3 M/s ITD cementation limited 144 Ground Improvement and Piling works 4 M/s KEEPL 64 Civil foundation works for FGD 5 M/s Teknow Overseas Pvt. Ltd. 123 Construction of Chimney 6 M/s Shivam Enterprises Pvt. Ltd. 45 Duct fabrication and erection works Grand Total 413 FGD PROJECT, ANPARA ‘D’ 12
  • 13. PRESENT MATERIAL STATUS SN Area of work Description Size UOM Closing Balance Requirement 1 Chimney Rebar 16mm MT 72.83 Upto 125 mtr -164 MT 25mm MT 22.20 Upto 125 mtr - 50 MT 12mm MT 15.02 Upto 125 mtr - 30 MT 32mm MT 9.78 Upto 125 mtr - 35 MT Dala aggregate10 & 20 mm MT 432.35 Upto 125 mtr - 3700 MT OPC Cement - MT 14.82 Upto 125 mtr -1250MT 2 Other Civil works Rebar 8mm MT 17.35 10mm MT 21.88 12mm MT 24.82 16mm MT 21.80 20mm MT 47.20 25mm MT 19.80 32mm MT 29.40 FGD PROJECT, ANPARA ‘D’ 13
  • 14. PRESENT MATERIAL STATUS SN Area of work Description Size UOM Closing Balance 3 BCIS Pile work Rebar 8 mm MT 9.705 16mm MT 106.152 20mm MT 41.726 25mm MT 34.399 Total Reinforcement 494.062 4 For BCIS Pile work Liner plate MT 21.000 5 For Civil construction & BCIS Pile work Admixture KG 258.280 Cement PPC MT 79.000 Chitrangi Aggregate 10/20 mm MT 1298.000 FGD PROJECT, ANPARA ‘D’ 14
  • 15. STATUS SUMMARY FGD PROJECT, ANPARA ‘D’ 15 FINANCIAL PROGRESS CONTRACT CONTRACT VALUE Expenditure till 31.05.2023 FINANCIAL PROGRESS (%) OFFSHORE SUPPLY USD 10.06 Million INR 7.14 Cr 7.53% ONSHORE SUPPLY INR 181.61 Cr INR 45.71 Cr 19.68% WORK EXECUTION INR 147.50 Cr INR 85.71Cr 49.25%
  • 16. BOI SUMMARY SN AREA TOTAL ITEMS TOTAL ORDERED IMPORTED ITEMS BOI DOMESTIC ITEMS BOI TOTAL NO TOTAL ORDERED TOTAL NO TOTAL ORDERED 1 MECHANICAL 27 24 11 10 16 14 2 ELECTRICAL 13 4 0 0 13 4 3 C&I 4 3 0 0 4 3 GRAND TOTAL 44 31 11 10 33 21 16 FGD PROJECT, ANPARA ‘D’
  • 17. CRITICAL ISSUES • BSPC Sub-Vendor M/s ITD Cementation stopped work on site from 23.05.2023 due to payment and other contractual issues. Progress of Ground Improvement i.e. stone column, BCIS piling and other civil construction work at site is completely hampered. • Only one Stone column Rig is deployed at present. UNL asked BSPC to ensure deployment of two more stone column rigs as committed by them on 05.04.2023 & 17.05.2023 during VC with Chairman UNL in order to complete the works before monsoon. • BSPC was to deploy at least 500 nos. manpower by 30.04.2023 as committed by them on 05.04.2023 during VC with Chairman UNL. Presently only 413 nos. manpower is deployed at site. BSPC must adhere to their commitment and enhance the manpower to 500 nos. immediately and improve the construction material availability as per site requirement. • Construction material e.g. OPC Cement and Rebar for Chimney shell casting work and PPC Cement, Rebar and Liner plate for other civil works should be made available at site in sufficient required quantity by BSPC. FGD PROJECT, ANPARA ‘D’ 17
  • 18. CLAIM NOTICE FILED BY BSPC  BSPC submitted claim notice vide Reference No: SPC/ANPARA-D/LTR/23-24/277 dated 05.06.2023 received through email.  Total Claim Value for Contract-1 USD 10.30 Millions  Total Claim Value for Contract-2&3 INR 232.04 Crores  BSPC stated that there was a pressing requirement for UPRVUNL to proceed for an equitable adjustment of the Contract price, as mandated and allowed under various clauses of the Contract, including but not limited to Article 3.1 & 3.2 of the Contract, as well as (among others), Clause 35 (Unforeseen Conditions), Clause 36 (Change in Laws and Regulations), Clause 37.6 (Force Majeure) and Clause 39 (Change in the Facilities), of the GCCs  SETTLEMENT OF DISPUTES / NOTICE OF MUTUAL CONSULTATION, UNDER CLAUSE 6.1 OF THE GCCs. FGD PROJECT, ANPARA ‘D’ 18
  • 19. THANK YOU FGD PROJECT, ANPARA ‘D’ 19