POWER FACTOR
IMPROVEMENT
IN GRID USING SMALL HYDRO
GENERATING STATION
PRESENTED BY,
AKHIL.A.G TJAKEEE003
ANUSHA.K.BINO TJAKEEE010
VIJISHA.E.V
TJAKEEE051
VISHAG RAVEENDAN TJAKEEE052
Guide: Anil sir
27-03-2014 1
INTRODUCTION
 Power
 Power factor
 Synchronization
 Synchronous machine
 Synchronous condenser
 Current situation
27-03-2014 2
PF IMPROVEMENT EQUIPMENT
Static capacitor
 Synchronous condenser
 Phase advancers
27-03-2014 3
ACT :SYN. GENERATOR
27-03-2014 4
ACT :SYN.CONDENSER
27-03-2014 5
11
K
V
11/110KV
TRANSFOMER
110KV
SUBSTATION
110/33KV
TRANSFOMER
33KV
SUBSTATION
33/11KV
TRANSFORMER
11KV/415V
TRANSFORMER
LOAD
LOAD LOAD LOAD LOAD
11KV
LINE
PRIMARY
TRANSMISSION
SECONDARY
TRANSMISSION
GENERATING
STATION
PRIMARY
DISTRIBUTI
ON
POWER
SYSTEM
NETWORK
LOAD
27-03-2014 6
11
K
V
11/110KV
TRANSFOMER
110KV
SUBSTATION
110/33KV
TRANSFOMER
33KV
SUBSTATION
33/11KV
TRANSFORMER
LOAD
11KV/415V
TRANSFORMER
LOAD
LOAD LOAD LOAD LOAD
SYNCHRONO
US
SCOPE
3.3/11KV
TRANSFORM
ER
3.3
KV
11KV
LINE
PRIMARY
TRANSMISSION
SECONDARY
TRANSMISSION
SMALL
GENERATING
STATION
GENERATING
STATION
PRIMARY
DISTRIBUTION
PRIMARY
DISTRIBUTI
ON
27-03-2014 7
11
K
V
11/110KV
TRANSFOMER
110KV
SUBSTATION
110/33KV
TRANSFOMER
33kV
SUBSTATION
33/11KV
TRANSFORMER
LOAD
11KV/415V
TRANSFORMER
LOAD
LOAD LOAD LOAD LOAD
SYNCHRONO
US
SCOPE
3.3/11KV
TRANSFORM
ER
SYNCH
RONOU
S
CONDE
NSER
11KV
LINE
PRIMARY
TRANSMISSION
SECONDARY
TRANSMISSION
GENERATING
STATION
PRIMARY
DISTRIBUTION
PRIMARY
DISTRIBUTI
ON
27-03-2014 8
SYNCHRONOUS MACHINE
27-03-2014 9
27-03-2014 10
DESIGN
Generating capacity of Peechi generating station is
1.25MW. The. We know that ,
If act as generator
Active power = 3 𝑉𝐼 𝐶𝑜𝑠∅ = 1.250MW.
PF=0.9 lagging; ∅ = 25.840
Apparent power = 3 𝑉𝐼 = 1.388𝑀𝑉𝐴.
Reactive power = 3 𝑉𝐼 𝑆𝑖𝑛 ∅ = 0.604𝑀𝑉𝐴𝑅
Full load current I = 1.388MVA = 243 A
3 ∗ 3.3 KV
Full load active current = 218.70A.
Full load reactive current = 105.91A.
27-03-2014 11
If act as synchronous condenser
An over excited synchronous motor operated at no load
called synchronous condenser. This MVA we are going to
run as synchronous condenser with 0.1pf leading.
Apparent power = 1.388 MVA.
cos−1
(.1) = 84.260
27-03-2014 12
This 1.388 MVA can be supplied to 33KV Substation in
kannara where Load =3Mw, pf = .6 that means it draws 5
MVA from feeding Ollur 33kV Substation
Pf =0.6
∅ = 53.130
27-03-2014 13
Power factor = cos⁡
〖(39.72)= 0.769.〗
So Power factor improved from 0.6 to 0.769. With 3 MW
= 0.169.
5MVA – 4.08MVA = .92 MVA.
I.e. The working of synchronous motor produces .92
MVA as profit.
27-03-2014 14
Consider now a machine that:
1 Is operated at successively smaller and
smaller torque angle
2. Greater and greater field excitation
27-03-2014 15
FULL LOAD
We know that,
Output of AC Generator = 1250000 MW
3 𝑉𝐼 𝑐𝑜𝑠∅ = 1250000.
Full load current IA =243A
Input of AC Generator = 1314434MW
𝟑 ∗ 𝑬 ∗ 𝑰 ∗ 𝒄𝒐𝒔ɸ =1306200
E = 3.44 kV
Voltage drop across the generator = .147kV
27-03-2014 16
75% LOAD
Assume ɸ= 20º
Output of AC Generator = 9375000 MW
√3 VI cos∅=9375000
IA = 174.54A
Excitation current = 165.5A
Voltage drop across the generator = jIaX = 0.082 kV
27-03-2014 17
50% LOAD
Assume ɸ =150
Output of AC Generator = 625000 MW
3 𝑉𝐼 𝑐𝑜𝑠∅ = 625000
3 ∗ 3.3 ∗ 𝐼A*.96 = 625000
IA = 113A
Excitation current = 147A
Voltage drop across the generator = jIaX = 29.24*1.38
= 0.043 kV
27-03-2014 18
25% LOAD
Assume ɸ=100
Output of AC Generator = 312500 MW
3 𝑉𝐼 𝑐𝑜𝑠∅ = 312500
3 ∗ 3.3 ∗ 𝐼A*.98 = 312500
IA = 55.51A
Excitation current = 128.50A
Voltage drop across the generator = jIaX = 9.63*1.38
= 0.013 kV
27-03-2014 19
NO LOAD
Assume ɸ= 20
Output of AC Generator = 17136.85 MW
3 ∗ 3.3 ∗ 𝐼A*.99 = 17136.85
IA = 3A
Excitation current = 110A
Voltage drop across the generator = jIaX = 0.10*1.38
= 0.000138 kV
27-03-2014 20
SYNCHRONOUS CONDENSER OPERATION
Synchronous generator has the capability of operating
as a synchronous condenser. Increasing the field
excitation causes E to increase.
We know that
Vt = E + jIaX
27-03-2014 21
SUCCESSIVELY GREATER FIELD EXCITATION
Case1
Apparent Power = 317320.81MW
Active Power = 31736.65 MVA
Reactive Power = 315729.76 MVAR
Let we assume that 0.1 power factor ie, ɸ = 84.260
Ia, act =5.50 A Ia, react =54.72 A
Resultant current I =55A
Voltage drop across the generator, jIaX = 1.38 * 54.72 =75.51 V
27-03-2014 22
Case 2
Apparent Power = 647047.61MW
Active Power = 64714.08 MVA
Reactive Power = 643803.30MVAR
Assume ɸ = 84.260
Ia, act =11.30 A
Ia, react =112.43 A
Resultant current I =113A
Voltage drop across the generator, jIaX = 1.38 * 113 =155.15 V
27-03-2014 23
Case 3
Apparent Power = 997666.66 MW
Active Power = 99781.03 MVA
Reactive Power = 992664.34MVAR
Assume ɸ = 84.260
Ia, act =17.45 A
Ia, react=173.66 A
Resultant current I =174.54A
Voltage drop across the generator, jIaX = 1.38 * 173.66
=239.65V
27-03-2014 24
Case 4
Apparent Power = 1388866.19MW
Active Power = 138906.62 MVA
Reactive Power = 1381902.4MVAR
Assume ɸ = 84.260
Ia , act =24.30A Ia, react =241.76 A
Resultant current I =242.98A
Voltage drop across the generator, jIaX =155.15 V
27-03-2014 25
STARTING & EXCITATION CONTROL
27-03-2014 26
SYNCHRONOUS MACHINE & REGULATOR
27-03-2014 27
SIMULATION RESULT
27-03-2014 28
27-03-2014 29
CONCLUSION
 Low power factor problems in the power system
network can be analysed.
 Power factor improved from 0.6 to 0.769. With
3MW
 The working of synchronous motor produces .92
MVA as profit.
27-03-2014 30
REFERENCE
 C.JAYARAMAN – Concept of reactive
power compensation
 Juan Dixon and Luis Moran -“ Reactive
Power Compensation Technologies”.
 T.J Millen- “ Reactive Power Control in
Electrical Systems.”
 RICARDO DOMKE -Power factor
improvement
27-03-2014 31
THANKS
27-03-2014 32

Power factor improvement method using synchronous condenser

  • 1.
    POWER FACTOR IMPROVEMENT IN GRIDUSING SMALL HYDRO GENERATING STATION PRESENTED BY, AKHIL.A.G TJAKEEE003 ANUSHA.K.BINO TJAKEEE010 VIJISHA.E.V TJAKEEE051 VISHAG RAVEENDAN TJAKEEE052 Guide: Anil sir 27-03-2014 1
  • 2.
    INTRODUCTION  Power  Powerfactor  Synchronization  Synchronous machine  Synchronous condenser  Current situation 27-03-2014 2
  • 3.
    PF IMPROVEMENT EQUIPMENT Staticcapacitor  Synchronous condenser  Phase advancers 27-03-2014 3
  • 4.
  • 5.
  • 6.
    11 K V 11/110KV TRANSFOMER 110KV SUBSTATION 110/33KV TRANSFOMER 33KV SUBSTATION 33/11KV TRANSFORMER 11KV/415V TRANSFORMER LOAD LOAD LOAD LOADLOAD 11KV LINE PRIMARY TRANSMISSION SECONDARY TRANSMISSION GENERATING STATION PRIMARY DISTRIBUTI ON POWER SYSTEM NETWORK LOAD 27-03-2014 6
  • 7.
    11 K V 11/110KV TRANSFOMER 110KV SUBSTATION 110/33KV TRANSFOMER 33KV SUBSTATION 33/11KV TRANSFORMER LOAD 11KV/415V TRANSFORMER LOAD LOAD LOAD LOADLOAD SYNCHRONO US SCOPE 3.3/11KV TRANSFORM ER 3.3 KV 11KV LINE PRIMARY TRANSMISSION SECONDARY TRANSMISSION SMALL GENERATING STATION GENERATING STATION PRIMARY DISTRIBUTION PRIMARY DISTRIBUTI ON 27-03-2014 7
  • 8.
    11 K V 11/110KV TRANSFOMER 110KV SUBSTATION 110/33KV TRANSFOMER 33kV SUBSTATION 33/11KV TRANSFORMER LOAD 11KV/415V TRANSFORMER LOAD LOAD LOAD LOADLOAD SYNCHRONO US SCOPE 3.3/11KV TRANSFORM ER SYNCH RONOU S CONDE NSER 11KV LINE PRIMARY TRANSMISSION SECONDARY TRANSMISSION GENERATING STATION PRIMARY DISTRIBUTION PRIMARY DISTRIBUTI ON 27-03-2014 8
  • 9.
  • 10.
  • 11.
    DESIGN Generating capacity ofPeechi generating station is 1.25MW. The. We know that , If act as generator Active power = 3 𝑉𝐼 𝐶𝑜𝑠∅ = 1.250MW. PF=0.9 lagging; ∅ = 25.840 Apparent power = 3 𝑉𝐼 = 1.388𝑀𝑉𝐴. Reactive power = 3 𝑉𝐼 𝑆𝑖𝑛 ∅ = 0.604𝑀𝑉𝐴𝑅 Full load current I = 1.388MVA = 243 A 3 ∗ 3.3 KV Full load active current = 218.70A. Full load reactive current = 105.91A. 27-03-2014 11
  • 12.
    If act assynchronous condenser An over excited synchronous motor operated at no load called synchronous condenser. This MVA we are going to run as synchronous condenser with 0.1pf leading. Apparent power = 1.388 MVA. cos−1 (.1) = 84.260 27-03-2014 12
  • 13.
    This 1.388 MVAcan be supplied to 33KV Substation in kannara where Load =3Mw, pf = .6 that means it draws 5 MVA from feeding Ollur 33kV Substation Pf =0.6 ∅ = 53.130 27-03-2014 13
  • 14.
    Power factor =cos⁡ 〖(39.72)= 0.769.〗 So Power factor improved from 0.6 to 0.769. With 3 MW = 0.169. 5MVA – 4.08MVA = .92 MVA. I.e. The working of synchronous motor produces .92 MVA as profit. 27-03-2014 14
  • 15.
    Consider now amachine that: 1 Is operated at successively smaller and smaller torque angle 2. Greater and greater field excitation 27-03-2014 15
  • 16.
    FULL LOAD We knowthat, Output of AC Generator = 1250000 MW 3 𝑉𝐼 𝑐𝑜𝑠∅ = 1250000. Full load current IA =243A Input of AC Generator = 1314434MW 𝟑 ∗ 𝑬 ∗ 𝑰 ∗ 𝒄𝒐𝒔ɸ =1306200 E = 3.44 kV Voltage drop across the generator = .147kV 27-03-2014 16
  • 17.
    75% LOAD Assume ɸ=20º Output of AC Generator = 9375000 MW √3 VI cos∅=9375000 IA = 174.54A Excitation current = 165.5A Voltage drop across the generator = jIaX = 0.082 kV 27-03-2014 17
  • 18.
    50% LOAD Assume ɸ=150 Output of AC Generator = 625000 MW 3 𝑉𝐼 𝑐𝑜𝑠∅ = 625000 3 ∗ 3.3 ∗ 𝐼A*.96 = 625000 IA = 113A Excitation current = 147A Voltage drop across the generator = jIaX = 29.24*1.38 = 0.043 kV 27-03-2014 18
  • 19.
    25% LOAD Assume ɸ=100 Outputof AC Generator = 312500 MW 3 𝑉𝐼 𝑐𝑜𝑠∅ = 312500 3 ∗ 3.3 ∗ 𝐼A*.98 = 312500 IA = 55.51A Excitation current = 128.50A Voltage drop across the generator = jIaX = 9.63*1.38 = 0.013 kV 27-03-2014 19
  • 20.
    NO LOAD Assume ɸ=20 Output of AC Generator = 17136.85 MW 3 ∗ 3.3 ∗ 𝐼A*.99 = 17136.85 IA = 3A Excitation current = 110A Voltage drop across the generator = jIaX = 0.10*1.38 = 0.000138 kV 27-03-2014 20
  • 21.
    SYNCHRONOUS CONDENSER OPERATION Synchronousgenerator has the capability of operating as a synchronous condenser. Increasing the field excitation causes E to increase. We know that Vt = E + jIaX 27-03-2014 21
  • 22.
    SUCCESSIVELY GREATER FIELDEXCITATION Case1 Apparent Power = 317320.81MW Active Power = 31736.65 MVA Reactive Power = 315729.76 MVAR Let we assume that 0.1 power factor ie, ɸ = 84.260 Ia, act =5.50 A Ia, react =54.72 A Resultant current I =55A Voltage drop across the generator, jIaX = 1.38 * 54.72 =75.51 V 27-03-2014 22
  • 23.
    Case 2 Apparent Power= 647047.61MW Active Power = 64714.08 MVA Reactive Power = 643803.30MVAR Assume ɸ = 84.260 Ia, act =11.30 A Ia, react =112.43 A Resultant current I =113A Voltage drop across the generator, jIaX = 1.38 * 113 =155.15 V 27-03-2014 23
  • 24.
    Case 3 Apparent Power= 997666.66 MW Active Power = 99781.03 MVA Reactive Power = 992664.34MVAR Assume ɸ = 84.260 Ia, act =17.45 A Ia, react=173.66 A Resultant current I =174.54A Voltage drop across the generator, jIaX = 1.38 * 173.66 =239.65V 27-03-2014 24
  • 25.
    Case 4 Apparent Power= 1388866.19MW Active Power = 138906.62 MVA Reactive Power = 1381902.4MVAR Assume ɸ = 84.260 Ia , act =24.30A Ia, react =241.76 A Resultant current I =242.98A Voltage drop across the generator, jIaX =155.15 V 27-03-2014 25
  • 26.
    STARTING & EXCITATIONCONTROL 27-03-2014 26
  • 27.
    SYNCHRONOUS MACHINE &REGULATOR 27-03-2014 27
  • 28.
  • 29.
  • 30.
    CONCLUSION  Low powerfactor problems in the power system network can be analysed.  Power factor improved from 0.6 to 0.769. With 3MW  The working of synchronous motor produces .92 MVA as profit. 27-03-2014 30
  • 31.
    REFERENCE  C.JAYARAMAN –Concept of reactive power compensation  Juan Dixon and Luis Moran -“ Reactive Power Compensation Technologies”.  T.J Millen- “ Reactive Power Control in Electrical Systems.”  RICARDO DOMKE -Power factor improvement 27-03-2014 31
  • 32.