Seminar On
PLACING AND COMPACTION OF
CONCERTE
By,
Chiranthan y
Department of Civil Engineering
MAHARAJA INSTITUTE OF TECHNOLOGY
THANDAVAPURA
PLACING
It is a process of depositing a fresh
concrete on its final position.
• Before placing concrete form work must be
checked for its rigidity and cleanliness .
• Concrete should not be dropped from height as
it causes segregation or piled up in heaps .
• The wheel barrow or vibrating needle should
not be allowed to run over the placed concrete.
The cautious to be taken for
placing .
• The concrete broadly categorized according to type
of work
1. Foundation bed
To construct a foundation we have to
excavate earth trenches.
After excavation of trenches we check
the bed of the earth trench
The bed of the trench should be free
from roots, organic matters and loose
earth
Trenche is wetted by spraying water to
avoid the loss of water from concrete
The chutes are used for placing
concrete in deep trenches.
2. Columns and deep beams
While placing of concrete in columns
or deep beams it is not suggested to allow
the free fall of concrete more than a meter
unless the mix is designed to be dropped
• The free fall of concrete results in
segregation.
• Then we use the tremie pipe to dropped
cement concrete to the cover blocks and
we also use the sloping board.
TREMIE PIPE
Tremie
pipes
COMPACTION
Compaction is the process of removing
entrapped air bubbles from the fresh concrete
and improving the packing of aggregates to form
dense concrete.
If air bubbles present in structure or placed
concrete Then honey combing or blow holes
are caused in concrete.
This effects the strength of concrete
The approximate air content in fresh concrete
is 25% which is reduced to 2-5% by
compaction.
HAND COMPACTION
It is a type of compaction
done by manually.
There are three types in this
compaction process
1.Roding
2.Ramming
3.Tamping
1. Rodding
A single steel rod is used for pocking
the fresh Concrete.
2. Ramming
A flat metal piece attached to a
hammer is used to hit on the surface of
concrete.
Compaction process of this type is done in
floor construction
3.Tamping
In thin cross sectional surface tamping
is done tamping in the surface of the concrete
with a wooden bar is used.
INTERNAL VIBRATOR
Vibration takes place inside the concrete mix.
Needle vibrator
Poker vibrators essentially consist of
vibrating needle which is inserted into the fresh
concrete
A loosely kept mass attached with the cable inside
the needle hits on the inner surface of the hallow
needle on rotation driven by a motor the hitting
action generates vibration in the needle.
The compaction of concrete takes place due to the
vibration of the needle.
NEEDLE VIBRATOR
EXTERNAL VIBRATOR
Vibration takes place on the surface of the
concrete.
Form vibrator
This is used for vibrating thin section of concrete
members.
Table vibrator
Vibrating tables are used for the compaction of
concrete in the production of precast members.
FORM VIBRATOR
TABLE VIBRATOR
Platform vibrator
• It is used in smaller thickness structures
construction like slabs.
•The compaction of concrete is done by applying
vibration at the surface the platform vibrator
consists of metal platform attached with vibrating
motors.
Screed vibrator
Screed is also used for the compaction of
concrete up to a depth of 100mm the screed
consists of a long beam attached to a frame and
vibrating motor.
PLATFORM VIBRATOR
SCREED VIBRATOR
CONCLUSION
• Placing and compaction of concrete is
interdependent activities and are carried out
simultaneously
• The compacted concrete is dense, strong and
durable.

Placing and compaction of cement concrete

  • 1.
    Seminar On PLACING ANDCOMPACTION OF CONCERTE By, Chiranthan y Department of Civil Engineering MAHARAJA INSTITUTE OF TECHNOLOGY THANDAVAPURA
  • 2.
    PLACING It is aprocess of depositing a fresh concrete on its final position. • Before placing concrete form work must be checked for its rigidity and cleanliness . • Concrete should not be dropped from height as it causes segregation or piled up in heaps . • The wheel barrow or vibrating needle should not be allowed to run over the placed concrete.
  • 3.
    The cautious tobe taken for placing . • The concrete broadly categorized according to type of work
  • 4.
    1. Foundation bed Toconstruct a foundation we have to excavate earth trenches. After excavation of trenches we check the bed of the earth trench The bed of the trench should be free from roots, organic matters and loose earth Trenche is wetted by spraying water to avoid the loss of water from concrete The chutes are used for placing concrete in deep trenches.
  • 5.
    2. Columns anddeep beams While placing of concrete in columns or deep beams it is not suggested to allow the free fall of concrete more than a meter unless the mix is designed to be dropped • The free fall of concrete results in segregation. • Then we use the tremie pipe to dropped cement concrete to the cover blocks and we also use the sloping board.
  • 6.
  • 7.
  • 8.
    COMPACTION Compaction is theprocess of removing entrapped air bubbles from the fresh concrete and improving the packing of aggregates to form dense concrete. If air bubbles present in structure or placed concrete Then honey combing or blow holes are caused in concrete. This effects the strength of concrete The approximate air content in fresh concrete is 25% which is reduced to 2-5% by compaction.
  • 10.
    HAND COMPACTION It isa type of compaction done by manually. There are three types in this compaction process 1.Roding 2.Ramming 3.Tamping
  • 11.
    1. Rodding A singlesteel rod is used for pocking the fresh Concrete. 2. Ramming A flat metal piece attached to a hammer is used to hit on the surface of concrete. Compaction process of this type is done in floor construction 3.Tamping In thin cross sectional surface tamping is done tamping in the surface of the concrete with a wooden bar is used.
  • 12.
    INTERNAL VIBRATOR Vibration takesplace inside the concrete mix. Needle vibrator Poker vibrators essentially consist of vibrating needle which is inserted into the fresh concrete A loosely kept mass attached with the cable inside the needle hits on the inner surface of the hallow needle on rotation driven by a motor the hitting action generates vibration in the needle. The compaction of concrete takes place due to the vibration of the needle.
  • 13.
  • 14.
    EXTERNAL VIBRATOR Vibration takesplace on the surface of the concrete. Form vibrator This is used for vibrating thin section of concrete members. Table vibrator Vibrating tables are used for the compaction of concrete in the production of precast members.
  • 15.
  • 16.
  • 17.
    Platform vibrator • Itis used in smaller thickness structures construction like slabs. •The compaction of concrete is done by applying vibration at the surface the platform vibrator consists of metal platform attached with vibrating motors. Screed vibrator Screed is also used for the compaction of concrete up to a depth of 100mm the screed consists of a long beam attached to a frame and vibrating motor.
  • 18.
  • 19.
  • 20.
    CONCLUSION • Placing andcompaction of concrete is interdependent activities and are carried out simultaneously • The compacted concrete is dense, strong and durable.