SlideShare a Scribd company logo
1 of 17
Quality/Welding inspection during Offshore
Pipeline and Platform Installation
By Rahman Suwandhi
Personal Data
Name: Rahman Suwandhi
Graduated: Technical of Metallurgy 1997
Residence: Batam
Office: EMAS AMC Pte Ltd – Singapore
Position: Quality/Welding Engineer
Main Business: offshore EPCI oil & gas
company
Contact No: +62 8127041931/+65 94524360
Email: r.suwandhi@emas.com or
suwandhi.rahman@gmail.com
Basic Requirements
Qualification and
certification required to
support on the job scope
of work are:
• Welding i.e. CSWIP 3.1,
CWI-AWS
• NDT Level II i.e. ASNT,
PCN
• Painting/Coating i.e.
BGAS, NACE
Production flow chart
Material Receiving
Cutting & Fit up
weld Joint
Welding process
Visual & NDT
inspection
Painting/Coating
Inspection
Welding inspector role:
To ensure quality of material and
welding meet to the requirement
NDT inspector:
To check weld joint using different
methods i.e. RT, UT, MT/PT complied
to the acceptance criteria
Painting/Coating Inspector:
To control & monitor of quality coating
meet to the requirement
Quality Documents:
- ITP (Inspection Testing Plan)
- PQP (Project Quality Plan)
- TQ (Technical Query)
- NCR (Non Conformance Record)
- Procedures: Welding, NDT, Painting, PWHT,
Hydrotest
- Qualified personnel: QC Inspector, Welder, NDT,
Painting Inspector
- Certificates & Reports: material cert, equipments
& tools cert, material & welding traceability record,
NDT report, painting report, PWHT & Hydrotest
report
- MDR (Manufacturing Data Record)
Code/Standard/Specification
Must understand on the following:
• Variety of code i.e. material, general
requirements, testing procedure
• Product application: structure, pressure vessel,
pipeline, piping process, storage tank etc.
• International published i.e. AS, ASTM, API, AWS,
ASME, BS, DIN, EN, EEMUA, ISO, JIS, KS, SNI
• Client’s Specification: Total, Shell, Chevron, Exxon,
ENI
• Third party/class requirements i.e. ABS, LR, GL,
BV, BKI, DNV
Material Inspection
To check the following:
• Surface condition check i.e. mill scale, material
damage, rusty, coating protection
• Dimension check i.e. length, width, thickness,
diameter
• Purchase/Delivery Order, hard stamp
• Material certificates check
Mill Certificates
Welding Procedure & welder qualification test
PWPS
Prepare test coupon &
Record parameters
NDT
DT
WPS
Result
Acc
Reject
PQR
Propose Welder
Prepare test coupon
NDT
DT
Result
Welder Certificate
Acc
Reject
Welding Inspection
To check the following:
• Before welding: approved
procedures in place,
material, consumables &
equipments/tools certificate
available, joint prep &
preheat within tolerance
• During welding: control
parameters i.e. HI, interpass
temp, PWHT
• After welding: visual check
Welding Inspection
Variables to be control & monitor during
production weld:
• Material group i.e. specification, thickness,
diameter
• Joint design, edge preparation
• Welding position & progression
• Welding parameters: voltage, current, travel
speed, Heat Input
• Preheat & interpass temperature
• Post weld heat treatment
WPS (Welding Procedure Specification)
Visual Inspection
To check the following:
• Weld bead, toe blend,
weld consistency, arc
strike, spatter, grinding
mark, mechanical
damage, surface colour,
misalignment, angular
distortion, longitudinal
distortion
• Refer to the acceptance
criteria as per
code/standard i.e. AWS
D1.1, API 1104, ASME IX,
DNV OS F101 etc.
NDT Inspection
• NDT methods: RT, UT,
MT/PT
• Basic testing
• Procedure
Qualification Test
• Approval NDT
procedure
• Acceptance criteria
Painting/Coating Inspection
• Type: Paints, HSS,
3LPP, Concrete
• Procedure
qualification test
• Painting inspection
i.e. DFT, pull test,
salt test
• Acceptance criteria
Qaulity/Welding Inspection during offshore
pipeline & platform installation
Any question?

More Related Content

What's hot

Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Varun Patel
 
16 wis5 consumable
16 wis5 consumable16 wis5 consumable
16 wis5 consumable
Tori Tom
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
Imran Jamil
 
WPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdfWPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdf
mounirbonnois
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
ram111eg
 

What's hot (20)

Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Twi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questionsTwi cswip welding inspection notes and questions
Twi cswip welding inspection notes and questions
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
 
WPS & WPQ
WPS & WPQWPS & WPQ
WPS & WPQ
 
Welder qualification
Welder qualificationWelder qualification
Welder qualification
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1
 
Methods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 TanksMethods of examination of joints(RT) - API 650 Tanks
Methods of examination of joints(RT) - API 650 Tanks
 
16 wis5 consumable
16 wis5 consumable16 wis5 consumable
16 wis5 consumable
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
 
Latest cswip 3.1 book
Latest cswip 3.1 bookLatest cswip 3.1 book
Latest cswip 3.1 book
 
Piping welding notes for beginners
Piping welding notes for beginnersPiping welding notes for beginners
Piping welding notes for beginners
 
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IXA QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
Structural Steel Welding Inspection
Structural Steel Welding InspectionStructural Steel Welding Inspection
Structural Steel Welding Inspection
 
WPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdfWPS -PQR - Welder Qualifications .pdf
WPS -PQR - Welder Qualifications .pdf
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
Welding Inspection
Welding InspectionWelding Inspection
Welding Inspection
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 

Viewers also liked

WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)
Abrianto Akuan
 
Welders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webWelders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_web
miguelbravo
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswip
guest831c1e
 
Interview questions and answers for welding inspector
Interview questions and answers for welding inspectorInterview questions and answers for welding inspector
Interview questions and answers for welding inspector
tonyron13
 

Viewers also liked (18)

WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)WPS-PQR (welding-pengelasan)
WPS-PQR (welding-pengelasan)
 
Guide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wpsGuide to understanding welding procedure specification (wps
Guide to understanding welding procedure specification (wps
 
Welding book
Welding bookWelding book
Welding book
 
Welders qualification
Welders qualificationWelders qualification
Welders qualification
 
Asme wps-demo
Asme wps-demoAsme wps-demo
Asme wps-demo
 
Asme sec ix
Asme sec ixAsme sec ix
Asme sec ix
 
Welders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_webWelders visual inspection_handbook-2013_web
Welders visual inspection_handbook-2013_web
 
Welding Defects
Welding DefectsWelding Defects
Welding Defects
 
Question bank
Question bankQuestion bank
Question bank
 
Welder training
Welder trainingWelder training
Welder training
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswip
 
GTAW & GMAW Welder Qualification - ASME Section IX
GTAW & GMAW Welder Qualification - ASME Section IXGTAW & GMAW Welder Qualification - ASME Section IX
GTAW & GMAW Welder Qualification - ASME Section IX
 
Interview questions and answers for welding inspector
Interview questions and answers for welding inspectorInterview questions and answers for welding inspector
Interview questions and answers for welding inspector
 
Welding defects
Welding defectsWelding defects
Welding defects
 
Duplex welding guidelines
Duplex welding guidelinesDuplex welding guidelines
Duplex welding guidelines
 
Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014
 
Asme section ii c new
Asme section ii c newAsme section ii c new
Asme section ii c new
 
Quality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipelineQuality Control & Quality Assurance of MS pipeline
Quality Control & Quality Assurance of MS pipeline
 

Similar to Offshore qc welding inspection versi 1 (20)

Ananda_Mariyan_DsouzaCV
Ananda_Mariyan_DsouzaCVAnanda_Mariyan_DsouzaCV
Ananda_Mariyan_DsouzaCV
 
Nivin Joseph- resume
Nivin Joseph- resumeNivin Joseph- resume
Nivin Joseph- resume
 
Resume Khurshid
Resume KhurshidResume Khurshid
Resume Khurshid
 
Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1Muhammed Riswan-QC rev1
Muhammed Riswan-QC rev1
 
ANANDHARAJAN CV
ANANDHARAJAN CVANANDHARAJAN CV
ANANDHARAJAN CV
 
Nookaraju - CV
Nookaraju - CVNookaraju - CV
Nookaraju - CV
 
QA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrenceQA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrence
 
Curriculum VITA 2 COMPLETE PIPING
Curriculum VITA 2 COMPLETE PIPINGCurriculum VITA 2 COMPLETE PIPING
Curriculum VITA 2 COMPLETE PIPING
 
Makbul Cv
Makbul CvMakbul Cv
Makbul Cv
 
BALAJI RESUME. UPDATED
BALAJI RESUME. UPDATEDBALAJI RESUME. UPDATED
BALAJI RESUME. UPDATED
 
VENKAT
VENKATVENKAT
VENKAT
 
ANAND CV
ANAND CVANAND CV
ANAND CV
 
Rajeshwaran - Resume
Rajeshwaran - ResumeRajeshwaran - Resume
Rajeshwaran - Resume
 
RESUME__ASATH_MATHANI_-1-2 (1)
RESUME__ASATH_MATHANI_-1-2 (1)RESUME__ASATH_MATHANI_-1-2 (1)
RESUME__ASATH_MATHANI_-1-2 (1)
 
QA QC Inspector.doc 1
QA QC Inspector.doc 1QA QC Inspector.doc 1
QA QC Inspector.doc 1
 
CV-QC Engg Mech- piping & welding
CV-QC Engg Mech- piping & weldingCV-QC Engg Mech- piping & welding
CV-QC Engg Mech- piping & welding
 
Vijay konathala Resume
Vijay konathala ResumeVijay konathala Resume
Vijay konathala Resume
 
ars resume
ars resumears resume
ars resume
 
Resume_Chintan_Gohil_
Resume_Chintan_Gohil_Resume_Chintan_Gohil_
Resume_Chintan_Gohil_
 
Praneshkumar QC Supervisor
Praneshkumar QC SupervisorPraneshkumar QC Supervisor
Praneshkumar QC Supervisor
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 

Recently uploaded (20)

PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
Ghuma $ Russian Call Girls Ahmedabad ₹7.5k Pick Up & Drop With Cash Payment 8...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Computer Graphics Introduction To Curves
Computer Graphics Introduction To CurvesComputer Graphics Introduction To Curves
Computer Graphics Introduction To Curves
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 

Offshore qc welding inspection versi 1

  • 1. Quality/Welding inspection during Offshore Pipeline and Platform Installation By Rahman Suwandhi
  • 2. Personal Data Name: Rahman Suwandhi Graduated: Technical of Metallurgy 1997 Residence: Batam Office: EMAS AMC Pte Ltd – Singapore Position: Quality/Welding Engineer Main Business: offshore EPCI oil & gas company Contact No: +62 8127041931/+65 94524360 Email: r.suwandhi@emas.com or suwandhi.rahman@gmail.com
  • 3. Basic Requirements Qualification and certification required to support on the job scope of work are: • Welding i.e. CSWIP 3.1, CWI-AWS • NDT Level II i.e. ASNT, PCN • Painting/Coating i.e. BGAS, NACE
  • 4. Production flow chart Material Receiving Cutting & Fit up weld Joint Welding process Visual & NDT inspection Painting/Coating Inspection
  • 5. Welding inspector role: To ensure quality of material and welding meet to the requirement NDT inspector: To check weld joint using different methods i.e. RT, UT, MT/PT complied to the acceptance criteria Painting/Coating Inspector: To control & monitor of quality coating meet to the requirement
  • 6. Quality Documents: - ITP (Inspection Testing Plan) - PQP (Project Quality Plan) - TQ (Technical Query) - NCR (Non Conformance Record) - Procedures: Welding, NDT, Painting, PWHT, Hydrotest - Qualified personnel: QC Inspector, Welder, NDT, Painting Inspector - Certificates & Reports: material cert, equipments & tools cert, material & welding traceability record, NDT report, painting report, PWHT & Hydrotest report - MDR (Manufacturing Data Record)
  • 7. Code/Standard/Specification Must understand on the following: • Variety of code i.e. material, general requirements, testing procedure • Product application: structure, pressure vessel, pipeline, piping process, storage tank etc. • International published i.e. AS, ASTM, API, AWS, ASME, BS, DIN, EN, EEMUA, ISO, JIS, KS, SNI • Client’s Specification: Total, Shell, Chevron, Exxon, ENI • Third party/class requirements i.e. ABS, LR, GL, BV, BKI, DNV
  • 8. Material Inspection To check the following: • Surface condition check i.e. mill scale, material damage, rusty, coating protection • Dimension check i.e. length, width, thickness, diameter • Purchase/Delivery Order, hard stamp • Material certificates check
  • 10. Welding Procedure & welder qualification test PWPS Prepare test coupon & Record parameters NDT DT WPS Result Acc Reject PQR Propose Welder Prepare test coupon NDT DT Result Welder Certificate Acc Reject
  • 11. Welding Inspection To check the following: • Before welding: approved procedures in place, material, consumables & equipments/tools certificate available, joint prep & preheat within tolerance • During welding: control parameters i.e. HI, interpass temp, PWHT • After welding: visual check
  • 12. Welding Inspection Variables to be control & monitor during production weld: • Material group i.e. specification, thickness, diameter • Joint design, edge preparation • Welding position & progression • Welding parameters: voltage, current, travel speed, Heat Input • Preheat & interpass temperature • Post weld heat treatment
  • 13. WPS (Welding Procedure Specification)
  • 14. Visual Inspection To check the following: • Weld bead, toe blend, weld consistency, arc strike, spatter, grinding mark, mechanical damage, surface colour, misalignment, angular distortion, longitudinal distortion • Refer to the acceptance criteria as per code/standard i.e. AWS D1.1, API 1104, ASME IX, DNV OS F101 etc.
  • 15. NDT Inspection • NDT methods: RT, UT, MT/PT • Basic testing • Procedure Qualification Test • Approval NDT procedure • Acceptance criteria
  • 16. Painting/Coating Inspection • Type: Paints, HSS, 3LPP, Concrete • Procedure qualification test • Painting inspection i.e. DFT, pull test, salt test • Acceptance criteria
  • 17. Qaulity/Welding Inspection during offshore pipeline & platform installation Any question?