SlideShare a Scribd company logo
Welding Consumables for
Duplex & Superduplex Alloys
WELDING GUIDELINES FOR
DUPLEX & SUPERDUPLEX
STAINLESS STEELS
Metrode Products Limited
Hanworth Lane, Chertsey,
Surrey, KT16 9LL, UK
Tel: +44 (0)1932 566 721
Fax: +44 (0)1932 569 449
Email: info@metrode.com
http//www.metrode.com
© Metrode Products Ltd
Duplex & superduplex ferritic-austenitic stainless steels
Welding guidelines
CONTENTS
Page
1 Introduction 1
2 Joint preparation 1
3 Preheat 2
4 Interpass temperature 2
5 Heat input 2
6 Welding processes 3
7 Root welding 3
8 2nd “cold” pass 4
9 Filling runs 4
10 Thin wall tube 7
11 Post weld heat treatment 7
12 Dissimilar welding 7
Appendix 1 Welding Procedure Specifications
Appendix 2 Data sheets
See Data Sheets: -
B-60, B-61, B-62, B-63
in Data Sheets folder
© Metrode Products Ltd Page 1 of 7 Issue 1 February 2005
Duplex & superduplex ferritic-austenitic stainless steels
Welding guidelines
1 Introduction
There is a range of stainless steel alloys with a duplex, ferritic-austenitic, microstructure and this
leaflet provides guidance on welding these alloys. Standard duplex is 22%Cr (eg. UNS S31803 and
S32205) and superduplex is 25%Cr with a pitting resistance equivalent number (PREN) 40 (eg.
UNS S32760, S32750 and S32550). These guidelines are based on joints being left in the as-
welded condition. Metrode have a full range of consumables, and data sheets for all products are
included at the end.
2 Joint preparation
The joint preparations will be similar to those used for standard stainless steel fabrication but for
single sided joints it is important to have an open root gap to ensure the addition of adequate filler.
The joint preparation will vary depending on material thickness, see examples below.
Wall
Thickness
mm
Included
angle, 
Included
angle, 
Root gap, g
mm
Root face, f
mm
2 – 3 70 – 90 - 2 – 3 0.5 – 1.5
g

f
> 4 65-75 - 2 – 4 0.5 – 1.5
gf


> 20 70 – 80 15 – 20 2 – 4 0.5 – 1.5

gf
R
> 20 15 – 30
Radius, R
mm
4 – 6
2 – 4 0.5 – 1.5
© Metrode Products Ltd Page 2 of 7 Issue 1 February 2005
Tacking
Tacking is important to ensure the root gap does
not close. Bullet tacks or bridging tacks are
normally used and must be removed as each
segment is completed. All tacks should be
deposited following an approved weld
procedure. There must be sufficient tacks
evenly spaced round the joint to keep a
consistent root gap.
3 Preheat
Preheat is not necessary for most duplex and superduplex stainless steel joints unless the material
is below ~5°C or wet, in which case the material should be preheated (~75-100°C) to prevent
condensation. Heating must be uniform avoiding the creation of localised hot spots.
Some thick section joints to be welded with sub-arc may benefit from a low preheat of ~75-125°C.
On large, thick section joints, which have a significant heat sink the first submerged arc runs can be
prone to pin-hole porosity; a low preheat can help prevent this.
4 Interpass temperature
The interpass temperature for both duplex and superduplex should be controlled to ensure the best
results. For superduplex 150°C is the maximum but for 22%Cr duplex 250°C would probably be
acceptable although most codes do not differentiate between duplex and superduplex so 150°C
maximum should be used for all grades.
Forced air cooling
To improve productivity by reducing the time required to cool below the interpass temperature it is
possible, on some joints, to use forced air cooling. The main application that has taken advantage
of forced air cooling has been rotated submerged arc joints; because in situations where welding is
carried out continuously there is a risk of excessive heat build-up, this can be minimised by forced
cooling. Dried compressed air can be passed through the centre of the pipe once the gas purge has
been removed.
5 Heat input
Heat input needs to be kept within specified limits to ensure optimum properties. Heat inputs in the
range 0.5-2.5kJ/mm for duplex and 0.5-2.0kJ/mm for superduplex should be acceptable, but most
codes restrict the maximum to 1.75 or 2.0kJ.mm for duplex and 1.5 or 1.75kJ/mm for the
superduplex grades.
A maximum heat input is imposed to prevent overheating of the HAZ and previously deposited weld
metal. High heat inputs also produce slower cooling rates which, particularly in superduplex,
increase the risk of intermetallic formation. Very low heat inputs should also be avoided because
this will increase the number of runs required to fill a joint. If more runs are deposited the weld
metal is reheated more times and this again increases the risk of intermetallic formation. A
reasonable working range for the filling runs is about 1.0-1.75kJ/mm, depending on grade of
material and thickness.
© Metrode Products Ltd Page 3 of 7 Issue 1 February 2005
6 Welding processes
The joint can be considered in two parts – the root and the fill. The welding process and
consumable selection should reflect this. The root requires a controllable welding process and filler
capable of delivering the necessary corrosion resistance. The welding process for the filling runs
can be selected to provide maximum productivity, and the consumable selected to deliver the
required mechanical properties (strength and toughness). The range of suitable welding processes
are summarised on the following page:
7 Root welding
Filler wire must always be added, root runs should not be made autogenously. Because of the
control it allows root runs are nearly always deposited using the TIG process. The root run is
critical in order to achieve good corrosion resistance so care should be taken to ensure the root is
deposited correctly. The aim should be to add as much filler as practical within the heat input
restrictions that are imposed. As a guideline the root run thickness should be ~2mm on thin wall
tube (3-4mm) rising to 3 or 4mm as pipe thickness increases.
To ensure good corrosion properties (and good G48A performance) on 22%Cr duplex a superduplex
filler wire is often used for the root run; this approach is recommended for G48A tests at +25°C.
To optimise root corrosion performance in superduplex base material the superduplex filler can be
used in conjunction with argon 1.5-2.5% nitrogen shielding gas; this approach is recommended if
G48A testing is required at +40°C.
© Metrode Products Ltd Page 4 of 7 Issue 1 February 2005
Purging
A gas purge must be used for root runs deposited using the TIG process and will normally be
maintained for the first three layers or approximately 10mm of deposit. Commercially pure argon is
generally used as the purge gas. Purge flow rates are determined by the pipe size but it is
important that following the removal of tacks, grinding etc that the purge is allowed to stabilise
again before welding. The efficiency of the purge should be monitored with an oxygen monitor to
ensure the oxygen content is maintained below 0.5% oxygen.
8 2nd “cold” pass
The second pass is almost as important as the root run when it comes to ensuring good corrosion
performance. The second pass should aim to be about 75% the heat input of the root run to
prevent overheating of the root. The second pass should be a single run; the layer should not be
split to two runs until at least the third layer.
9 Filling runs
TIG (GTAW)
For small diameter tubes and pipes TIG is often used for filling the joint but the TIG process can
also be used for filling thicker wall pipes. The TIG process has the advantage of producing high
quality weld metal and there is no slag to be removed. The productivity of the TIG process can be
improved by using 3.2mm diameter wire.
Metrode has both a duplex (ER329N) and superduplex (Zeron 100X) wire. Commercial purity argon
(99.995%) should be used as the shielding gas or possibly argon-helium mixtures if preferred;
gases containing hydrogen should not be used. As mentioned earlier, for root runs in superduplex
corrosion performance can be improved by using an argon shielding gas containing 1.5-2.5%
nitrogen.
MMA (SMAW)
The MMA process is widely used because of its adaptability and simple equipment requirements.
For positional pipe welding and for applications that have impact requirements Metrode have three
basic coated electrodes: 2205XKS (duplex), 2507XKS and Zeron 100XKS (for superduplex). For
applications where operability and ease of use are the most important factors then there are also
two rutile coated electrodes: Ultramet 2205 (duplex) and Ultramet 2507 (superduplex).
© Metrode Products Ltd Page 5 of 7 Issue 1 February 2005
MIG (GMAW)
The MIG process has not been very widely used for duplex and superduplex. If the MIG process is
to be used it must be in conjunction with a pulsed current power source. The shielding gas that has
proved most successful is argon-35% helium-2% CO2 (there are a number of different proprietary
gases on the market with compositions similar to this).
The spooled wire is also often used for mechanised or automatic TIG welding, and in these
situations pure argon shielding gas is used.
FCAW
The flux cored arc welding process can provide productivity advantages over the TIG or MMA
processes when material is over ~15mm thick and ~200mm diameter. The process can be used
down to ~10mm wall thickness if the diameter is larger and ~150mm diameter if the wall thickness
is great enough. There are both downhand and positional wires available: Supercore 2205
(downhand) and Supercore 2205P (positional) are the 22%Cr duplex wires; Supercore 2507
(downhand) and Supercore Z100XP and Supercore 2507P (positional) are the superduplex wires.
The wires are designed to be used with argon-20% CO2 shielding gas (M21 or M24 in BS EN 439),
and although there are many proprietary gases that would be suitable the argon content should not
exceed 80%. The downhand wires (Supercore 2205 and Supercore 2507) can also be used with
100% CO2 (C1 in BS EN 439). The gas flow rate required is 20-25 l/min. The wire stickout, or
electrode extension, should be 15-20mm; for fixed pipe welding (ASME 5G/6G) it may be necessary
to reduce the electrode extension to 12-15mm. The parameter box for the flux cored wires is
shown below.
15.0
20.0
25.0
30.0
35.0
40.0
90 110 130 150 170 190 210 230 250 270 290 310 330
Tolerance Box
Optimum operating
conditions
© Metrode Products Ltd Page 6 of 7 Issue 1 February 2005
SAW
The submerged arc process provides the highest potential productivity using either 1.6mm or
2.4mm diameter wire. The process is only suitable for welding in the flat position so the component
to be welded must be capable of being positioned in the flat or of being rotated. Before starting the
submerged arc welding ~10mm of deposit needs to be built-up with another process (normally TIG
or MMA) to prevent burn through, or overheating of the root run. Metrode have both duplex
(ER329N) and superduplex (Zeron 100X) filler wires.
The process requires a separate flux and Metrode have two suitable fluxes: SSB and LA491. The
wire stickout is maintained at ~20mm and the flux pile at ~25mm. Handling of the flux is also
important, see next page. Typical welding parameters are:
1.6mm 275A 28V 300mm/min
2.4mm 350A 30V 350mm/min
These parameters are only a guideline and may need to be adjusted for specific applications.
When submerged arc welding on a rotated pipe the torch should be positioned just before the top
of the joint and be angled towards the centre, see below.
New Flux
Store in a Heated
Hopper at >100C
50 – 150kg
At end of shift all
Flux to be returned
to Heated Hopper
A
Sub-Arc Machine
Flux Hopper
~10kg
B
Sieving
Welding
A or B
Vacuum
Recycling Unit
Unused Flux
© Metrode Products Ltd Page 7 of 7 Issue 1 February 2005
10 Thin wall tube
When welding thin wall tube it is even more critical to use a carefully controlled weld procedure
because the tube can easily be overheated. The maximum interpass temperature should be
reduced to 100°C. Even on small diameter tube the weld should be split into segments/quarters to
prevent excessive heat build-up.
11 Post weld heat treatment
Most duplex and superduplex fabrication work in wrought material is left in the as-welded condition
but major repairs to castings are generally specified in the solution annealed condition. Experience
indicates good properties can be achieved with a heat treatment of 1120°C/3-6 hours followed by a
water quench. Heat treatment, other than solution annealing, should not be carried out because
duplex and superduplex alloys are prone to intermetallic formation.
12 Dissimilar welding
Each dissimilar combination has to be assessed on its own merit but some general
recommendations can be made for a number of commonly encountered combinations.
Superduplex 22%Cr duplex Nickel alloys
Austenitic
stainless
steel
Mild and low
alloy steel
Superduplex
Zeron 100
2507
22%Cr duplex (1)
Nickel alloy (eg. C22) 309Mo (2)
309L/309Mo (2)
22%Cr duplex 22%Cr duplex (1)
22%Cr duplex Nickel alloy (eg. C22) 309Mo (3)
309L/309Mo (3)
(1) If it simplifies consumable selection and weld procedures superduplex consumables could be used.
(2) If there are only a limited number of dissimilar joints the superduplex consumables could be used to
simplify the weld procedures and consumable control.
(3) If there are only a limited number of dissimilar joints the duplex consumables could be used to simplify the
weld procedures and consumable control.
n:techliteraturetechnical profilesduplexwps superduplex.doc
Welding Procedure Specification (WPS)
Welding Procedure No: Superduplex TIG/GTAW
Consumables Base Material
Welding process (root): TIG / GTAW Parent Material: Superduplex.
- Consumable: Zeron 100X (UNS S32750 & S32760).
- Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) =
Welding process (fill): TIG / GTAW 10H group 1.
- Consumable: Zeron 100X Thickness: 18.26mm (Schedule 160)
- Specification: BS EN 12072: W 25 9 4 N L Outside Diameter: 6 inch NB
Joint Details Joint Position
Joint Type: Single side butt Welding Position: ASME 6G
Manual/Mechanised: Manual
Joint Sketch Welding Sequences
18.26mm
65°±5°
0.5-1.5mm
2-4mm
6” NB
Schedule 160
Split layers (2 beads per layer) from runs 4/5 onwards.
.
Welding Details
Run Process Consumable
Diameter
mm
Current
A
Voltage
V
Travel
speed
mm/min
Type of current
/ Polarity
Heat
Input
kJ/mm
1
2
Fill
TIG
TIG
TIG
Zeron 100X
Zeron 100X
Zeron 100X
2.4
2.4
3.2
80-100
90-130
200-225
~12
~12
~12
~50
~125
100-175
DC-
DC-
DC-
~1.2
~0.8
~1.5
Electrode Baking or Drying: NA Notes:
Gas – root (TIG) shielding:
backing:
Ar + 2% N2
Ar
1. Tack joint securely to prevent root closure using four
Gas - fill/cap (TIG) – Shielding:
Purge:
Ar
Ar
bridging tacks.
Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Weld pipe in four 90° segments to prevent excessive
Details of Back Gouging/Backing: NA overheating.
Preheat Temperature: 20°C 3. Purge to maintain 0.5% oxygen max.
Interpass Temperature: 150°C max 4. Ar + 2%N2 shielding gas is recommended for the root run
Post-Weld Heat Treatment and/or Ageing: None to ensure G48A properties.
Temperature: 5. Purging 20-30l/min (reduced to ~10l/min for tie-in).
Time: Maintain purge for first two runs.
6. Shielding gas flow rate 8-12l/min.
n:techliteraturetechnical profilesduplexwps superduplex.doc
Welding Procedure Specification (WPS)
Welding Procedure No: Superduplex MMA/SMAW
Consumables Base Material
Welding process (root): TIG / GTAW Parent Material: Superduplex.
- Consumable: Zeron 100X (UNS S32750 & S32760).
- Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) =
Welding process (fill): MMA / SMAW 10H group 1.
- Consumable: Zeron 100XKS / 2507XKS Thickness: 18.26mm (Schedule 160)
- Specification: BS EN 1600: E 25 9 4 N L B 4 2 Outside Diameter: 6 inch NB
Joint Details Joint Position
Joint Type: Single side butt Welding Position: ASME 6G
Manual/Mechanised: Manual
Joint Sketch Welding Sequences
18.26mm
70°±5°
0.5-1.5mm
2-4mm
6” NB
Schedule 160
.
Welding Details
Run Process Consumable
Diameter
mm
Current
A
Voltage
V
Travel
speed
mm/min
Type of
current /
Polarity
Heat
Input
kJ/mm
1
2
Fill
TIG
TIG
MMA
Zeron 100X
Zeron 100X
Zeron 100XKS / 2507XKS
2.4
2.4
3.2
80-100
90-130
75-95
~12
~12
~25
~50
~125
75-125
DC-
DC-
DC+
~1.2
~0.8
~1.2
Electrode Baking or Drying: 200°C/2 hours Notes:
Gas – root (TIG) shielding:
backing:
Ar + 2% N2
Ar
1. Tack joint securely to prevent root closure using four
Gas - fill/cap: Not applicable bridging tacks.
Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Weld pipe in four 90° segments to prevent excessive
Details of Back Gouging/Backing: NA overheating.
Preheat Temperature: 20°C 3. Purge to maintain 0.5% oxygen max.
Interpass Temperature: 150°C max 4. Ar + 2%N2 shielding gas is recommended for the root run
Post-Weld Heat Treatment and/or Ageing: None to ensure G48A properties.
Temperature: 5. Purging 20-30l/min (reduced to ~10l/min for tie-in).
Time: Maintain purge for first two runs.
6. Shielding gas flow rate 8-12l/min.
n:techliteraturetechnical profilesduplexwps superduplex.doc
Welding Procedure Specification (WPS)
Welding Procedure No: Superduplex FCAW
Consumables Base Material
Welding process (root): TIG / GTAW Parent Material: Superduplex.
- Consumable: Zeron 100X (UNS S32750 & S32760).
- Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) =
Welding process (fill): FCAW 10H group 1.
- Consumable: Supercore Z100XP / 2507P Thickness: 23mm (Schedule 160)
- Specification: -- Outside Diameter: 8 inch NB
Joint Details Joint Position
Joint Type: Single side butt Welding Position: ASME 6G
Manual/Mechanised: Manual
Joint Sketch Welding Sequences
23mm
70°±5°
0.5-1.5mm
2-4mm
8” NB
Schedule 160
.
Welding Details
Run Process Consumable
Diameter
mm
Current
A
Voltage
V
Travel
speed
mm/min
Type of
current /
Polarity
Heat
Input
kJ/mm
1
2
3-4
Fill
TIG
TIG
TIG
FCAW
Zeron 100X
Zeron 100X
Zeron 100X
Supercore Z100XP/2507P
2.4
2.4
2.4
1.2
80-100
90-130
140-160
140-180
~12
~12
~12
~26
~50
~125
~75
100-175
DC-
DC-
DC-
DC+
~1.2
~0.8
~1.5
~1.5
Electrode Baking or Drying: NA Notes:
Gas – root (TIG) shielding:
backing:
Ar + 2% N2
Ar
1. Tack joint securely to prevent root closure using four
Gas - fill/cap (FCAW) – Shielding: Ar-20% CO2 bridging tacks.
Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Weld pipe in four 90° segments to prevent excessive
Details of Back Gouging/Backing: NA overheating.
Preheat Temperature: 20°C 3. Purge to maintain 0.5% oxygen max.
Interpass Temperature: 150°C max 4. Ar + 2%N2 shielding gas is recommended for the root run
Post-Weld Heat Treatment and/or Ageing: None to ensure G48A properties.
Temperature: 5. Purging 20-30l/min (reduced to ~10l/min for tie-in).
Time: 6. Shielding gas flow rate: TIG = 8-12l/min, FCAW = 20-25
l/min.
n:techliteraturetechnical profilesduplexwps superduplex.doc
Welding Procedure Specification (WPS)
Welding Procedure No: Superduplex SAW
Consumables Base Material
Welding process (root): TIG / GTAW Parent Material: Superduplex.
- Consumable: Zeron 100X (UNS S32750 & S32760).
- Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) =
Welding process (fill): SAW 10H group 1.
- Consumable: Zeron 100X Thickness: ~25mm
- Specification: BS EN 12072: W 25 9 4 N L Outside Diameter: Not applicable
Joint Details Joint Position
Joint Type: Single side butt Welding Position: ASME 1G
Manual/Mechanised: Mechanised
Joint Sketch Welding Sequences
25mm
65°±5°
0.5-1.5mm
2-4mm
Split layers (2 beads per layer) from runs 4/5 onwards.
.
Welding Details
Run Process Consumable
Diameter
mm
Current
A
Voltage
V
Travel
speed
mm/min
Type of current
/ Polarity
Heat
Input
kJ/mm
1
2
3-4
Fill
TIG
TIG
TIG
SAW
Zeron 100X
Zeron 100X
Zeron 100X
Zeron 100X
2.4
2.4
2.4
2.4
80-100
90-130
140-160
300-400
~12
~12
~12
~30
~50
~125
~75
300-500
DC-
DC-
DC-
DC+
~1.2
~0.8
~1.5
~1.5
Electrode Baking or Drying: NA Notes:
Gas – root (TIG) shielding:
backing:
Ar + 2% N2
Ar
1. Tack joint securely to prevent root closure using four
Flux - fill/cap (SAW) – LA491 bridging tacks.
Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Purge to maintain 0.5% oxygen max.
Details of Back Gouging/Backing: NA 3. Ar + 2%N2 shielding gas is recommended for the root run
Preheat Temperature: 20°C to ensure G48A properties.
Interpass Temperature: 150°C max 4. Purging 20-30l/min (reduced to ~10l/min for tie-in).
Post-Weld Heat Treatment and/or Ageing: None Maintain purge for first two runs.
Temperature: 5. Shielding gas flow rate 8-12l/min.
Time:

More Related Content

What's hot

Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
Jithu John
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
Karthik Banari
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
Jithu John
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
AshifuddinAli
 
ASTM E 190(bend test)
ASTM E 190(bend test)ASTM E 190(bend test)
ASTM E 190(bend test)
Manthan Chavda
 
Welding defects
Welding defectsWelding defects
Welding defects
Hung Le
 
radiographer-s-weld-interpretation-reference
radiographer-s-weld-interpretation-referenceradiographer-s-weld-interpretation-reference
radiographer-s-weld-interpretation-reference
B V
 
Welding defects
Welding defectsWelding defects
Welding defects
Vlastimir Novakovic
 
Saes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) pipingSaes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) piping
abhi10apr
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswipguest831c1e
 
Electrode selection
Electrode selection  Electrode selection
Electrode selection
Prasanth Kumar
 
WPS & WPQ
WPS & WPQWPS & WPQ
Calif. simple soldador API 1104 ed. 2010
Calif. simple soldador   API 1104 ed. 2010Calif. simple soldador   API 1104 ed. 2010
Calif. simple soldador API 1104 ed. 2010
Manuel Salto Cubillos
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
MOHAMMAD ATIF ALI
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
University of Sarajevo, Manufacturing Technology:
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1
Tiago Pereira
 
pipe welding
pipe weldingpipe welding
pipe welding
Marry Sol Lare
 

What's hot (20)

Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Iso new standards
Iso new standardsIso new standards
Iso new standards
 
Asme sec. ix bkr - 051010
Asme sec. ix   bkr - 051010Asme sec. ix   bkr - 051010
Asme sec. ix bkr - 051010
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Radiographic interpretation
Radiographic interpretation Radiographic interpretation
Radiographic interpretation
 
ASTM E 190(bend test)
ASTM E 190(bend test)ASTM E 190(bend test)
ASTM E 190(bend test)
 
Welding defects
Welding defectsWelding defects
Welding defects
 
radiographer-s-weld-interpretation-reference
radiographer-s-weld-interpretation-referenceradiographer-s-weld-interpretation-reference
radiographer-s-weld-interpretation-reference
 
Welding defects
Welding defectsWelding defects
Welding defects
 
Saes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) pipingSaes w-011-welding on plot ( process ) piping
Saes w-011-welding on plot ( process ) piping
 
Welding Inspection Cswip
Welding Inspection CswipWelding Inspection Cswip
Welding Inspection Cswip
 
Welding handbook.pdf
Welding handbook.pdfWelding handbook.pdf
Welding handbook.pdf
 
Electrode selection
Electrode selection  Electrode selection
Electrode selection
 
WPS & WPQ
WPS & WPQWPS & WPQ
WPS & WPQ
 
Calif. simple soldador API 1104 ed. 2010
Calif. simple soldador   API 1104 ed. 2010Calif. simple soldador   API 1104 ed. 2010
Calif. simple soldador API 1104 ed. 2010
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
 
How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1How to write a Welding Procedure Specification (ISO 15614-1
How to write a Welding Procedure Specification (ISO 15614-1
 
pipe welding
pipe weldingpipe welding
pipe welding
 

Similar to Duplex welding guidelines

Tig
TigTig
Metal Inert Gas (MIG)/ Metal Active Gas (MAG) Welding
Metal Inert Gas (MIG)/ Metal Active Gas (MAG) WeldingMetal Inert Gas (MIG)/ Metal Active Gas (MAG) Welding
Metal Inert Gas (MIG)/ Metal Active Gas (MAG) Welding
faheem maqsood
 
Flux Cored - Arc Welding Wires
Flux Cored - Arc Welding WiresFlux Cored - Arc Welding Wires
Flux Cored - Arc Welding Wires
Andrea Belgrado arcomeccanica srl
 
TIG Welding (Tungsten Inert Gas Welding)
TIG Welding (Tungsten Inert Gas Welding) TIG Welding (Tungsten Inert Gas Welding)
TIG Welding (Tungsten Inert Gas Welding)
Aqeel Ur Rehman
 
Welding iv
Welding   ivWelding   iv
Welding iv
Jithu John
 
K10635
K10635K10635
Application of TIG & MIG Welding in Manufacturing
Application of TIG & MIG Welding in ManufacturingApplication of TIG & MIG Welding in Manufacturing
Application of TIG & MIG Welding in Manufacturing
Md. Shahin Mia, CSSBB (ASQ, USA)
 
Chapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdfChapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdf
HemantchandraPatel
 
Mig welding
Mig weldingMig welding
Mig welding
faheem maqsood
 
Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG)
Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG) Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG)
Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG)
faheem maqsood
 
RAUTOMEAD TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...
RAUTOMEAD  TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...RAUTOMEAD  TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...
RAUTOMEAD TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...
Rautomead Limited
 
Esab world pipelines
Esab world pipelinesEsab world pipelines
Esab world pipelines
Jorg Eichhorn
 
Final MIG,TIG.GTAW PPt.pptx
Final MIG,TIG.GTAW PPt.pptxFinal MIG,TIG.GTAW PPt.pptx
Final MIG,TIG.GTAW PPt.pptx
Barsena
 
Unit-V Joining Process-08 n.pptxjuahhajjjwjj
Unit-V Joining Process-08 n.pptxjuahhajjjwjjUnit-V Joining Process-08 n.pptxjuahhajjjwjj
Unit-V Joining Process-08 n.pptxjuahhajjjwjj
SakshiSalunkhe24
 
Welding 2
Welding  2Welding  2
Welding 2
Jithu John
 
experimental investigation of gas metal arc welding (gmaw) on 2.25
 experimental investigation of gas metal arc welding (gmaw) on 2.25 experimental investigation of gas metal arc welding (gmaw) on 2.25
experimental investigation of gas metal arc welding (gmaw) on 2.25
NEERAJKUMAR1898
 
A review of effect of welding and post weld heat treatment on microstructure ...
A review of effect of welding and post weld heat treatment on microstructure ...A review of effect of welding and post weld heat treatment on microstructure ...
A review of effect of welding and post weld heat treatment on microstructure ...
eSAT Journals
 
Wbut or MAKAUT welding notes
Wbut or MAKAUT welding notesWbut or MAKAUT welding notes
Wbut or MAKAUT welding notes
Priyadarsini K
 

Similar to Duplex welding guidelines (20)

Hot wire tig
Hot wire tigHot wire tig
Hot wire tig
 
Tig
TigTig
Tig
 
Metal Inert Gas (MIG)/ Metal Active Gas (MAG) Welding
Metal Inert Gas (MIG)/ Metal Active Gas (MAG) WeldingMetal Inert Gas (MIG)/ Metal Active Gas (MAG) Welding
Metal Inert Gas (MIG)/ Metal Active Gas (MAG) Welding
 
Flux Cored - Arc Welding Wires
Flux Cored - Arc Welding WiresFlux Cored - Arc Welding Wires
Flux Cored - Arc Welding Wires
 
TIG Welding (Tungsten Inert Gas Welding)
TIG Welding (Tungsten Inert Gas Welding) TIG Welding (Tungsten Inert Gas Welding)
TIG Welding (Tungsten Inert Gas Welding)
 
Welding iv
Welding   ivWelding   iv
Welding iv
 
K10635
K10635K10635
K10635
 
Application of TIG & MIG Welding in Manufacturing
Application of TIG & MIG Welding in ManufacturingApplication of TIG & MIG Welding in Manufacturing
Application of TIG & MIG Welding in Manufacturing
 
Chapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdfChapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdf
 
Mig welding
Mig weldingMig welding
Mig welding
 
Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG)
Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG) Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG)
Gass tungsten Arc Welding (GTAW)/ Tungsten Inert Gas Welding (TIG)
 
RAUTOMEAD TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...
RAUTOMEAD  TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...RAUTOMEAD  TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...
RAUTOMEAD TECHNOLOGY FOR CONTINUOUS CASTING OF OXYGEN-FREE COPPER AND DILUTE...
 
Gas Metal Arc Welding
Gas Metal Arc WeldingGas Metal Arc Welding
Gas Metal Arc Welding
 
Esab world pipelines
Esab world pipelinesEsab world pipelines
Esab world pipelines
 
Final MIG,TIG.GTAW PPt.pptx
Final MIG,TIG.GTAW PPt.pptxFinal MIG,TIG.GTAW PPt.pptx
Final MIG,TIG.GTAW PPt.pptx
 
Unit-V Joining Process-08 n.pptxjuahhajjjwjj
Unit-V Joining Process-08 n.pptxjuahhajjjwjjUnit-V Joining Process-08 n.pptxjuahhajjjwjj
Unit-V Joining Process-08 n.pptxjuahhajjjwjj
 
Welding 2
Welding  2Welding  2
Welding 2
 
experimental investigation of gas metal arc welding (gmaw) on 2.25
 experimental investigation of gas metal arc welding (gmaw) on 2.25 experimental investigation of gas metal arc welding (gmaw) on 2.25
experimental investigation of gas metal arc welding (gmaw) on 2.25
 
A review of effect of welding and post weld heat treatment on microstructure ...
A review of effect of welding and post weld heat treatment on microstructure ...A review of effect of welding and post weld heat treatment on microstructure ...
A review of effect of welding and post weld heat treatment on microstructure ...
 
Wbut or MAKAUT welding notes
Wbut or MAKAUT welding notesWbut or MAKAUT welding notes
Wbut or MAKAUT welding notes
 

Recently uploaded

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 

Duplex welding guidelines

  • 1. Welding Consumables for Duplex & Superduplex Alloys WELDING GUIDELINES FOR DUPLEX & SUPERDUPLEX STAINLESS STEELS Metrode Products Limited Hanworth Lane, Chertsey, Surrey, KT16 9LL, UK Tel: +44 (0)1932 566 721 Fax: +44 (0)1932 569 449 Email: info@metrode.com http//www.metrode.com
  • 2. © Metrode Products Ltd Duplex & superduplex ferritic-austenitic stainless steels Welding guidelines CONTENTS Page 1 Introduction 1 2 Joint preparation 1 3 Preheat 2 4 Interpass temperature 2 5 Heat input 2 6 Welding processes 3 7 Root welding 3 8 2nd “cold” pass 4 9 Filling runs 4 10 Thin wall tube 7 11 Post weld heat treatment 7 12 Dissimilar welding 7 Appendix 1 Welding Procedure Specifications Appendix 2 Data sheets See Data Sheets: - B-60, B-61, B-62, B-63 in Data Sheets folder
  • 3. © Metrode Products Ltd Page 1 of 7 Issue 1 February 2005 Duplex & superduplex ferritic-austenitic stainless steels Welding guidelines 1 Introduction There is a range of stainless steel alloys with a duplex, ferritic-austenitic, microstructure and this leaflet provides guidance on welding these alloys. Standard duplex is 22%Cr (eg. UNS S31803 and S32205) and superduplex is 25%Cr with a pitting resistance equivalent number (PREN) 40 (eg. UNS S32760, S32750 and S32550). These guidelines are based on joints being left in the as- welded condition. Metrode have a full range of consumables, and data sheets for all products are included at the end. 2 Joint preparation The joint preparations will be similar to those used for standard stainless steel fabrication but for single sided joints it is important to have an open root gap to ensure the addition of adequate filler. The joint preparation will vary depending on material thickness, see examples below. Wall Thickness mm Included angle,  Included angle,  Root gap, g mm Root face, f mm 2 – 3 70 – 90 - 2 – 3 0.5 – 1.5 g  f > 4 65-75 - 2 – 4 0.5 – 1.5 gf   > 20 70 – 80 15 – 20 2 – 4 0.5 – 1.5  gf R > 20 15 – 30 Radius, R mm 4 – 6 2 – 4 0.5 – 1.5
  • 4. © Metrode Products Ltd Page 2 of 7 Issue 1 February 2005 Tacking Tacking is important to ensure the root gap does not close. Bullet tacks or bridging tacks are normally used and must be removed as each segment is completed. All tacks should be deposited following an approved weld procedure. There must be sufficient tacks evenly spaced round the joint to keep a consistent root gap. 3 Preheat Preheat is not necessary for most duplex and superduplex stainless steel joints unless the material is below ~5°C or wet, in which case the material should be preheated (~75-100°C) to prevent condensation. Heating must be uniform avoiding the creation of localised hot spots. Some thick section joints to be welded with sub-arc may benefit from a low preheat of ~75-125°C. On large, thick section joints, which have a significant heat sink the first submerged arc runs can be prone to pin-hole porosity; a low preheat can help prevent this. 4 Interpass temperature The interpass temperature for both duplex and superduplex should be controlled to ensure the best results. For superduplex 150°C is the maximum but for 22%Cr duplex 250°C would probably be acceptable although most codes do not differentiate between duplex and superduplex so 150°C maximum should be used for all grades. Forced air cooling To improve productivity by reducing the time required to cool below the interpass temperature it is possible, on some joints, to use forced air cooling. The main application that has taken advantage of forced air cooling has been rotated submerged arc joints; because in situations where welding is carried out continuously there is a risk of excessive heat build-up, this can be minimised by forced cooling. Dried compressed air can be passed through the centre of the pipe once the gas purge has been removed. 5 Heat input Heat input needs to be kept within specified limits to ensure optimum properties. Heat inputs in the range 0.5-2.5kJ/mm for duplex and 0.5-2.0kJ/mm for superduplex should be acceptable, but most codes restrict the maximum to 1.75 or 2.0kJ.mm for duplex and 1.5 or 1.75kJ/mm for the superduplex grades. A maximum heat input is imposed to prevent overheating of the HAZ and previously deposited weld metal. High heat inputs also produce slower cooling rates which, particularly in superduplex, increase the risk of intermetallic formation. Very low heat inputs should also be avoided because this will increase the number of runs required to fill a joint. If more runs are deposited the weld metal is reheated more times and this again increases the risk of intermetallic formation. A reasonable working range for the filling runs is about 1.0-1.75kJ/mm, depending on grade of material and thickness.
  • 5. © Metrode Products Ltd Page 3 of 7 Issue 1 February 2005 6 Welding processes The joint can be considered in two parts – the root and the fill. The welding process and consumable selection should reflect this. The root requires a controllable welding process and filler capable of delivering the necessary corrosion resistance. The welding process for the filling runs can be selected to provide maximum productivity, and the consumable selected to deliver the required mechanical properties (strength and toughness). The range of suitable welding processes are summarised on the following page: 7 Root welding Filler wire must always be added, root runs should not be made autogenously. Because of the control it allows root runs are nearly always deposited using the TIG process. The root run is critical in order to achieve good corrosion resistance so care should be taken to ensure the root is deposited correctly. The aim should be to add as much filler as practical within the heat input restrictions that are imposed. As a guideline the root run thickness should be ~2mm on thin wall tube (3-4mm) rising to 3 or 4mm as pipe thickness increases. To ensure good corrosion properties (and good G48A performance) on 22%Cr duplex a superduplex filler wire is often used for the root run; this approach is recommended for G48A tests at +25°C. To optimise root corrosion performance in superduplex base material the superduplex filler can be used in conjunction with argon 1.5-2.5% nitrogen shielding gas; this approach is recommended if G48A testing is required at +40°C.
  • 6. © Metrode Products Ltd Page 4 of 7 Issue 1 February 2005 Purging A gas purge must be used for root runs deposited using the TIG process and will normally be maintained for the first three layers or approximately 10mm of deposit. Commercially pure argon is generally used as the purge gas. Purge flow rates are determined by the pipe size but it is important that following the removal of tacks, grinding etc that the purge is allowed to stabilise again before welding. The efficiency of the purge should be monitored with an oxygen monitor to ensure the oxygen content is maintained below 0.5% oxygen. 8 2nd “cold” pass The second pass is almost as important as the root run when it comes to ensuring good corrosion performance. The second pass should aim to be about 75% the heat input of the root run to prevent overheating of the root. The second pass should be a single run; the layer should not be split to two runs until at least the third layer. 9 Filling runs TIG (GTAW) For small diameter tubes and pipes TIG is often used for filling the joint but the TIG process can also be used for filling thicker wall pipes. The TIG process has the advantage of producing high quality weld metal and there is no slag to be removed. The productivity of the TIG process can be improved by using 3.2mm diameter wire. Metrode has both a duplex (ER329N) and superduplex (Zeron 100X) wire. Commercial purity argon (99.995%) should be used as the shielding gas or possibly argon-helium mixtures if preferred; gases containing hydrogen should not be used. As mentioned earlier, for root runs in superduplex corrosion performance can be improved by using an argon shielding gas containing 1.5-2.5% nitrogen. MMA (SMAW) The MMA process is widely used because of its adaptability and simple equipment requirements. For positional pipe welding and for applications that have impact requirements Metrode have three basic coated electrodes: 2205XKS (duplex), 2507XKS and Zeron 100XKS (for superduplex). For applications where operability and ease of use are the most important factors then there are also two rutile coated electrodes: Ultramet 2205 (duplex) and Ultramet 2507 (superduplex).
  • 7. © Metrode Products Ltd Page 5 of 7 Issue 1 February 2005 MIG (GMAW) The MIG process has not been very widely used for duplex and superduplex. If the MIG process is to be used it must be in conjunction with a pulsed current power source. The shielding gas that has proved most successful is argon-35% helium-2% CO2 (there are a number of different proprietary gases on the market with compositions similar to this). The spooled wire is also often used for mechanised or automatic TIG welding, and in these situations pure argon shielding gas is used. FCAW The flux cored arc welding process can provide productivity advantages over the TIG or MMA processes when material is over ~15mm thick and ~200mm diameter. The process can be used down to ~10mm wall thickness if the diameter is larger and ~150mm diameter if the wall thickness is great enough. There are both downhand and positional wires available: Supercore 2205 (downhand) and Supercore 2205P (positional) are the 22%Cr duplex wires; Supercore 2507 (downhand) and Supercore Z100XP and Supercore 2507P (positional) are the superduplex wires. The wires are designed to be used with argon-20% CO2 shielding gas (M21 or M24 in BS EN 439), and although there are many proprietary gases that would be suitable the argon content should not exceed 80%. The downhand wires (Supercore 2205 and Supercore 2507) can also be used with 100% CO2 (C1 in BS EN 439). The gas flow rate required is 20-25 l/min. The wire stickout, or electrode extension, should be 15-20mm; for fixed pipe welding (ASME 5G/6G) it may be necessary to reduce the electrode extension to 12-15mm. The parameter box for the flux cored wires is shown below. 15.0 20.0 25.0 30.0 35.0 40.0 90 110 130 150 170 190 210 230 250 270 290 310 330 Tolerance Box Optimum operating conditions
  • 8. © Metrode Products Ltd Page 6 of 7 Issue 1 February 2005 SAW The submerged arc process provides the highest potential productivity using either 1.6mm or 2.4mm diameter wire. The process is only suitable for welding in the flat position so the component to be welded must be capable of being positioned in the flat or of being rotated. Before starting the submerged arc welding ~10mm of deposit needs to be built-up with another process (normally TIG or MMA) to prevent burn through, or overheating of the root run. Metrode have both duplex (ER329N) and superduplex (Zeron 100X) filler wires. The process requires a separate flux and Metrode have two suitable fluxes: SSB and LA491. The wire stickout is maintained at ~20mm and the flux pile at ~25mm. Handling of the flux is also important, see next page. Typical welding parameters are: 1.6mm 275A 28V 300mm/min 2.4mm 350A 30V 350mm/min These parameters are only a guideline and may need to be adjusted for specific applications. When submerged arc welding on a rotated pipe the torch should be positioned just before the top of the joint and be angled towards the centre, see below. New Flux Store in a Heated Hopper at >100C 50 – 150kg At end of shift all Flux to be returned to Heated Hopper A Sub-Arc Machine Flux Hopper ~10kg B Sieving Welding A or B Vacuum Recycling Unit Unused Flux
  • 9. © Metrode Products Ltd Page 7 of 7 Issue 1 February 2005 10 Thin wall tube When welding thin wall tube it is even more critical to use a carefully controlled weld procedure because the tube can easily be overheated. The maximum interpass temperature should be reduced to 100°C. Even on small diameter tube the weld should be split into segments/quarters to prevent excessive heat build-up. 11 Post weld heat treatment Most duplex and superduplex fabrication work in wrought material is left in the as-welded condition but major repairs to castings are generally specified in the solution annealed condition. Experience indicates good properties can be achieved with a heat treatment of 1120°C/3-6 hours followed by a water quench. Heat treatment, other than solution annealing, should not be carried out because duplex and superduplex alloys are prone to intermetallic formation. 12 Dissimilar welding Each dissimilar combination has to be assessed on its own merit but some general recommendations can be made for a number of commonly encountered combinations. Superduplex 22%Cr duplex Nickel alloys Austenitic stainless steel Mild and low alloy steel Superduplex Zeron 100 2507 22%Cr duplex (1) Nickel alloy (eg. C22) 309Mo (2) 309L/309Mo (2) 22%Cr duplex 22%Cr duplex (1) 22%Cr duplex Nickel alloy (eg. C22) 309Mo (3) 309L/309Mo (3) (1) If it simplifies consumable selection and weld procedures superduplex consumables could be used. (2) If there are only a limited number of dissimilar joints the superduplex consumables could be used to simplify the weld procedures and consumable control. (3) If there are only a limited number of dissimilar joints the duplex consumables could be used to simplify the weld procedures and consumable control.
  • 10. n:techliteraturetechnical profilesduplexwps superduplex.doc Welding Procedure Specification (WPS) Welding Procedure No: Superduplex TIG/GTAW Consumables Base Material Welding process (root): TIG / GTAW Parent Material: Superduplex. - Consumable: Zeron 100X (UNS S32750 & S32760). - Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) = Welding process (fill): TIG / GTAW 10H group 1. - Consumable: Zeron 100X Thickness: 18.26mm (Schedule 160) - Specification: BS EN 12072: W 25 9 4 N L Outside Diameter: 6 inch NB Joint Details Joint Position Joint Type: Single side butt Welding Position: ASME 6G Manual/Mechanised: Manual Joint Sketch Welding Sequences 18.26mm 65°±5° 0.5-1.5mm 2-4mm 6” NB Schedule 160 Split layers (2 beads per layer) from runs 4/5 onwards. . Welding Details Run Process Consumable Diameter mm Current A Voltage V Travel speed mm/min Type of current / Polarity Heat Input kJ/mm 1 2 Fill TIG TIG TIG Zeron 100X Zeron 100X Zeron 100X 2.4 2.4 3.2 80-100 90-130 200-225 ~12 ~12 ~12 ~50 ~125 100-175 DC- DC- DC- ~1.2 ~0.8 ~1.5 Electrode Baking or Drying: NA Notes: Gas – root (TIG) shielding: backing: Ar + 2% N2 Ar 1. Tack joint securely to prevent root closure using four Gas - fill/cap (TIG) – Shielding: Purge: Ar Ar bridging tacks. Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Weld pipe in four 90° segments to prevent excessive Details of Back Gouging/Backing: NA overheating. Preheat Temperature: 20°C 3. Purge to maintain 0.5% oxygen max. Interpass Temperature: 150°C max 4. Ar + 2%N2 shielding gas is recommended for the root run Post-Weld Heat Treatment and/or Ageing: None to ensure G48A properties. Temperature: 5. Purging 20-30l/min (reduced to ~10l/min for tie-in). Time: Maintain purge for first two runs. 6. Shielding gas flow rate 8-12l/min.
  • 11. n:techliteraturetechnical profilesduplexwps superduplex.doc Welding Procedure Specification (WPS) Welding Procedure No: Superduplex MMA/SMAW Consumables Base Material Welding process (root): TIG / GTAW Parent Material: Superduplex. - Consumable: Zeron 100X (UNS S32750 & S32760). - Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) = Welding process (fill): MMA / SMAW 10H group 1. - Consumable: Zeron 100XKS / 2507XKS Thickness: 18.26mm (Schedule 160) - Specification: BS EN 1600: E 25 9 4 N L B 4 2 Outside Diameter: 6 inch NB Joint Details Joint Position Joint Type: Single side butt Welding Position: ASME 6G Manual/Mechanised: Manual Joint Sketch Welding Sequences 18.26mm 70°±5° 0.5-1.5mm 2-4mm 6” NB Schedule 160 . Welding Details Run Process Consumable Diameter mm Current A Voltage V Travel speed mm/min Type of current / Polarity Heat Input kJ/mm 1 2 Fill TIG TIG MMA Zeron 100X Zeron 100X Zeron 100XKS / 2507XKS 2.4 2.4 3.2 80-100 90-130 75-95 ~12 ~12 ~25 ~50 ~125 75-125 DC- DC- DC+ ~1.2 ~0.8 ~1.2 Electrode Baking or Drying: 200°C/2 hours Notes: Gas – root (TIG) shielding: backing: Ar + 2% N2 Ar 1. Tack joint securely to prevent root closure using four Gas - fill/cap: Not applicable bridging tacks. Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Weld pipe in four 90° segments to prevent excessive Details of Back Gouging/Backing: NA overheating. Preheat Temperature: 20°C 3. Purge to maintain 0.5% oxygen max. Interpass Temperature: 150°C max 4. Ar + 2%N2 shielding gas is recommended for the root run Post-Weld Heat Treatment and/or Ageing: None to ensure G48A properties. Temperature: 5. Purging 20-30l/min (reduced to ~10l/min for tie-in). Time: Maintain purge for first two runs. 6. Shielding gas flow rate 8-12l/min.
  • 12. n:techliteraturetechnical profilesduplexwps superduplex.doc Welding Procedure Specification (WPS) Welding Procedure No: Superduplex FCAW Consumables Base Material Welding process (root): TIG / GTAW Parent Material: Superduplex. - Consumable: Zeron 100X (UNS S32750 & S32760). - Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) = Welding process (fill): FCAW 10H group 1. - Consumable: Supercore Z100XP / 2507P Thickness: 23mm (Schedule 160) - Specification: -- Outside Diameter: 8 inch NB Joint Details Joint Position Joint Type: Single side butt Welding Position: ASME 6G Manual/Mechanised: Manual Joint Sketch Welding Sequences 23mm 70°±5° 0.5-1.5mm 2-4mm 8” NB Schedule 160 . Welding Details Run Process Consumable Diameter mm Current A Voltage V Travel speed mm/min Type of current / Polarity Heat Input kJ/mm 1 2 3-4 Fill TIG TIG TIG FCAW Zeron 100X Zeron 100X Zeron 100X Supercore Z100XP/2507P 2.4 2.4 2.4 1.2 80-100 90-130 140-160 140-180 ~12 ~12 ~12 ~26 ~50 ~125 ~75 100-175 DC- DC- DC- DC+ ~1.2 ~0.8 ~1.5 ~1.5 Electrode Baking or Drying: NA Notes: Gas – root (TIG) shielding: backing: Ar + 2% N2 Ar 1. Tack joint securely to prevent root closure using four Gas - fill/cap (FCAW) – Shielding: Ar-20% CO2 bridging tacks. Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Weld pipe in four 90° segments to prevent excessive Details of Back Gouging/Backing: NA overheating. Preheat Temperature: 20°C 3. Purge to maintain 0.5% oxygen max. Interpass Temperature: 150°C max 4. Ar + 2%N2 shielding gas is recommended for the root run Post-Weld Heat Treatment and/or Ageing: None to ensure G48A properties. Temperature: 5. Purging 20-30l/min (reduced to ~10l/min for tie-in). Time: 6. Shielding gas flow rate: TIG = 8-12l/min, FCAW = 20-25 l/min.
  • 13. n:techliteraturetechnical profilesduplexwps superduplex.doc Welding Procedure Specification (WPS) Welding Procedure No: Superduplex SAW Consumables Base Material Welding process (root): TIG / GTAW Parent Material: Superduplex. - Consumable: Zeron 100X (UNS S32750 & S32760). - Specification: BS EN 12072: W 25 9 4 N L ASME IX: P or S number (QW422) = Welding process (fill): SAW 10H group 1. - Consumable: Zeron 100X Thickness: ~25mm - Specification: BS EN 12072: W 25 9 4 N L Outside Diameter: Not applicable Joint Details Joint Position Joint Type: Single side butt Welding Position: ASME 1G Manual/Mechanised: Mechanised Joint Sketch Welding Sequences 25mm 65°±5° 0.5-1.5mm 2-4mm Split layers (2 beads per layer) from runs 4/5 onwards. . Welding Details Run Process Consumable Diameter mm Current A Voltage V Travel speed mm/min Type of current / Polarity Heat Input kJ/mm 1 2 3-4 Fill TIG TIG TIG SAW Zeron 100X Zeron 100X Zeron 100X Zeron 100X 2.4 2.4 2.4 2.4 80-100 90-130 140-160 300-400 ~12 ~12 ~12 ~30 ~50 ~125 ~75 300-500 DC- DC- DC- DC+ ~1.2 ~0.8 ~1.5 ~1.5 Electrode Baking or Drying: NA Notes: Gas – root (TIG) shielding: backing: Ar + 2% N2 Ar 1. Tack joint securely to prevent root closure using four Flux - fill/cap (SAW) – LA491 bridging tacks. Tungsten Electrode Type/Size: 2%Th/2.4mm 2. Purge to maintain 0.5% oxygen max. Details of Back Gouging/Backing: NA 3. Ar + 2%N2 shielding gas is recommended for the root run Preheat Temperature: 20°C to ensure G48A properties. Interpass Temperature: 150°C max 4. Purging 20-30l/min (reduced to ~10l/min for tie-in). Post-Weld Heat Treatment and/or Ageing: None Maintain purge for first two runs. Temperature: 5. Shielding gas flow rate 8-12l/min. Time: