Generalized Guidelines for
Structural Steel Welding
Inspection
As per AWS D1.1
Structural Welding Code: Steel
Standard Terms
 CJP: Complete Joint Penetration
 PJP: Partial Joint Penetration
CJP
PJP
Fillet Weld
Scope
 General Requirements
 Design of Welded Connections
 Prequalification
 Qualification
 Fabrication
 Inspection
 Stud Welding
 Strengthening and Repair of Existing
Structure
Limitation of Code
 The code is not intended to be used for the
following:
 (1) Steels with a minimum specified yield
strength greater than 100 ksi (690 MPa)
 (2) Steels less than 1/8 in. (3 mm) thick.
 (3) Pressure vessels or pressure piping
 (4) Base metals other than carbon or low-alloy
steels. AWS D1.6, Structural Welding Code —
Stainless Steel, should be used for welding
stainless steel structures. Whenever contract
documents specify AWS Dl.l for welding
stainless steel, the requirements of AWS D1.6
Design of Welded
Connections
 Part A: Common Requirements for Design of
Welded Connections (Nontubular and Tubular
Members)
 Part B: Specific Requirements for Design of
Nontubular Connections (Statically or Cyclically
Loaded)
 Part C: Specific Requirements for Design of
Nontubular Connections (Cyclically Loaded
 Part D: Specific Requirements for Desing of
Tubular Connections (Statically or Cyclically
Weld Joint Configuration
Weld Joint Configuration: Fillet
Weld
Weld Joint Configuration: Fillet
Weld
Built Up Members
3.0 Prequalification of WPS
 As per article 3 prequalification of WPS is exempt from
WPS qualification if following conditions are met
3.2 Welding Process: SMAW, SAW, GMAW (except
GMAW-S) and FCAW which conform to all of the
provisions of this section shall deemed as
prequalified.
3.3 Base Metal & Filler Metal
Shall conform this table
3.4. Procedure approved by Engineer
3.5. Minimum Preheat & Inter-pass Temperature
Requirement- Shall be as per Table 3.2 of page 68 (AWS
D1.1: 2008 Code)
3.6. Limitation of WPS variables
“All prequalified WPSs to be used shall be prepared by the
manufacturer, fabricator or contractor as written
prequalified WPSs, and shall be available to those
authorized to use or examine them. The welding parameter
listed below shall be specified on the written WPSs .
Change in these parameter , beyond those specified on the
written WPS shall be considered essential changes and
shall require a new or revised prequalified written WPS
i. Amperage (Wire Feed Speed)
ii. Voltage
iii. Travel Speed
iv. Shielding Gas Flow Rate
Prequalification of WPS
 3.9 Minimum Fillet
Weld Requirement- Shall
Conform following
table
Prequalification of WPS
Common Requirements for Parallel Electrode and Multiple
Electrode SAW
4.0 Qualification: WPS
 Welding Qualification (WPS) is not
necessary unless any of the
requirement of prequalification
(section 3) does not met.
5.0 Fabrication
6.0 Inspection
6.11: NDT
GENERAL
COMMENTS
For CJP Groove weld
and Non Tubular
Statically loaded
section,
other than Visual
Inspection no additional
NDT is required form
the code requirement
unless additional NDT
method like DPT/ MPI
specified by the owner
user. Contactor shall
perform such test as
per 6.6.5 para.
6.9 Inspection: Visual Inspection
Table 6.1: Visual Inspection Acceptance Criteria
6.1 Inspection: Visual Inspection Acceptance
Criteria
NDT Requirements

Structural Steel Welding Inspection

  • 1.
    Generalized Guidelines for StructuralSteel Welding Inspection As per AWS D1.1 Structural Welding Code: Steel
  • 2.
    Standard Terms  CJP:Complete Joint Penetration  PJP: Partial Joint Penetration CJP PJP Fillet Weld
  • 3.
    Scope  General Requirements Design of Welded Connections  Prequalification  Qualification  Fabrication  Inspection  Stud Welding  Strengthening and Repair of Existing Structure
  • 4.
    Limitation of Code The code is not intended to be used for the following:  (1) Steels with a minimum specified yield strength greater than 100 ksi (690 MPa)  (2) Steels less than 1/8 in. (3 mm) thick.  (3) Pressure vessels or pressure piping  (4) Base metals other than carbon or low-alloy steels. AWS D1.6, Structural Welding Code — Stainless Steel, should be used for welding stainless steel structures. Whenever contract documents specify AWS Dl.l for welding stainless steel, the requirements of AWS D1.6
  • 5.
    Design of Welded Connections Part A: Common Requirements for Design of Welded Connections (Nontubular and Tubular Members)  Part B: Specific Requirements for Design of Nontubular Connections (Statically or Cyclically Loaded)  Part C: Specific Requirements for Design of Nontubular Connections (Cyclically Loaded  Part D: Specific Requirements for Desing of Tubular Connections (Statically or Cyclically
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
    3.0 Prequalification ofWPS  As per article 3 prequalification of WPS is exempt from WPS qualification if following conditions are met 3.2 Welding Process: SMAW, SAW, GMAW (except GMAW-S) and FCAW which conform to all of the provisions of this section shall deemed as prequalified. 3.3 Base Metal & Filler Metal Shall conform this table
  • 11.
    3.4. Procedure approvedby Engineer 3.5. Minimum Preheat & Inter-pass Temperature Requirement- Shall be as per Table 3.2 of page 68 (AWS D1.1: 2008 Code) 3.6. Limitation of WPS variables “All prequalified WPSs to be used shall be prepared by the manufacturer, fabricator or contractor as written prequalified WPSs, and shall be available to those authorized to use or examine them. The welding parameter listed below shall be specified on the written WPSs . Change in these parameter , beyond those specified on the written WPS shall be considered essential changes and shall require a new or revised prequalified written WPS i. Amperage (Wire Feed Speed) ii. Voltage iii. Travel Speed iv. Shielding Gas Flow Rate Prequalification of WPS
  • 12.
     3.9 MinimumFillet Weld Requirement- Shall Conform following table Prequalification of WPS Common Requirements for Parallel Electrode and Multiple Electrode SAW
  • 13.
    4.0 Qualification: WPS Welding Qualification (WPS) is not necessary unless any of the requirement of prequalification (section 3) does not met.
  • 14.
  • 15.
  • 16.
    6.11: NDT GENERAL COMMENTS For CJPGroove weld and Non Tubular Statically loaded section, other than Visual Inspection no additional NDT is required form the code requirement unless additional NDT method like DPT/ MPI specified by the owner user. Contactor shall perform such test as per 6.6.5 para.
  • 17.
    6.9 Inspection: VisualInspection Table 6.1: Visual Inspection Acceptance Criteria
  • 18.
    6.1 Inspection: VisualInspection Acceptance Criteria
  • 19.