SlideShare a Scribd company logo
Initial Design Discussion What the Project Engineer Needs to Know
Agenda ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
What the Project Engineer Needs to Know ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
The Load ,[object Object],[object Object],[object Object],[object Object],[object Object],©   Baldor Electric Co. © LDPI, Inc.
Electrical Design Elements ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Electrical Design Elements ,[object Object],[object Object],[object Object]
Electrical Design Development ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
The Power Source  Flywheel UPS © Liebert Engine Generator Set © Cummins Power Generation Pole Mounted Transformers Pad Mounted Transformers
The Power Source  ,[object Object],[object Object],[object Object],[object Object],Flywheel UPS
The Power Source  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Flywheel UPS
The Power Source ,[object Object],[object Object],[object Object],[object Object],http://www.energyandpowermanagement.com/CDA/Articles
Nominal System Voltages Substation  13.2kV; 69kV; 115kV Plant Distribution 4160V; 480V; 208V Control 120V Signal 24V
Working Clearances under 600V NEC ®  2005 Clearances shall be provided & maintained to permit ready and safe operation and maintenance ,[object Object],[object Object],[object Object],[object Object]
Working Clearances under 600V 2005 NEC Article 110.26  Spaces About Electrical Equipment   (C) Entrance to Working Space.  (2) Large Equipment. For equipment rated 1,200A or more, an entrance measuring not less than 24 in. wide and 61/2 ft high, is required at each end of the working space. Where the entrance to the working space has a door, the door must open out and be equipped with panic hardware or other devices that open under simple pressure. This material was extracted from Mike Holt Training Materials copyright 2007 by permission. Visit  www.NECCode.com  or call 1.888.NEC.Code (632-2633) for more information.  NEC ®  2002
Working Clearances under 600V
Working Clearances over 600V NEC ®  2005
Protection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Low Voltage Circuit Breakers © Square D
Protection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Protection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Power Circuit Breakers with  Arc Flash Protection © Square D
Protection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Medium Voltage Circuit Breaker © Eaton Cutler-Hammer
Protection ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Monitor and Control ,[object Object],[object Object],[object Object],[object Object],[object Object]
Monitor and Control ,[object Object],[object Object],[object Object],[object Object]
Monitor and Control ,[object Object],[object Object],[object Object],[object Object]
Summary ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Summary ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Summary ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Discussion Thank You!
Acknowledgements

More Related Content

What's hot

Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
Girish Gupta
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
Himmelstern
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
Siddhartha mudgal
 
Substations
SubstationsSubstations
Substations
itfakash
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
Himmelstern
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizing
Asif Eqbal
 
Substation and It's Equipment
Substation and It's Equipment Substation and It's Equipment
Substation and It's Equipment
Chandan Kumar
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Nadir Baloch
 
Electric power calculations
Electric power calculationsElectric power calculations
Electric power calculations
michaeljmack
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
ZuhairQadri
 
Electrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary InterfacesElectrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary Interfacesbiiswashruta
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Ahmed Saada, (PRMG)
 
Basics of electrical control panel
Basics of electrical control panelBasics of electrical control panel
Basics of electrical control panel
CHACKOCHEN MATHEW
 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
Himmelstern
 
33kv substation
33kv substation33kv substation
33kv substation
Abhishek Dawachya
 
Single line diagram
Single line diagramSingle line diagram
Single line diagram
Md. Rimon Mia
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
Carl Tim Lapinig
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
Jay Ranvir
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
Sheikh Nazmul Islam
 
Solar Power Charge Controller
Solar Power Charge ControllerSolar Power Charge Controller
Solar Power Charge Controller
Edgefxkits & Solutions
 

What's hot (20)

Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Substations
SubstationsSubstations
Substations
 
ETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standardETAP - Short circuit analysis iec standard
ETAP - Short circuit analysis iec standard
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizing
 
Substation and It's Equipment
Substation and It's Equipment Substation and It's Equipment
Substation and It's Equipment
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Electric power calculations
Electric power calculationsElectric power calculations
Electric power calculations
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
 
Electrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary InterfacesElectrical Deliverables - Interdisciplinary Interfaces
Electrical Deliverables - Interdisciplinary Interfaces
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Basics of electrical control panel
Basics of electrical control panelBasics of electrical control panel
Basics of electrical control panel
 
ETAP - Power system modeling
ETAP - Power system modelingETAP - Power system modeling
ETAP - Power system modeling
 
33kv substation
33kv substation33kv substation
33kv substation
 
Single line diagram
Single line diagramSingle line diagram
Single line diagram
 
Electrical maintenance
Electrical maintenanceElectrical maintenance
Electrical maintenance
 
Electrical bus bar and its types
Electrical bus bar and its typesElectrical bus bar and its types
Electrical bus bar and its types
 
Maintenance schedule of Substation.
Maintenance schedule of Substation.Maintenance schedule of Substation.
Maintenance schedule of Substation.
 
Solar Power Charge Controller
Solar Power Charge ControllerSolar Power Charge Controller
Solar Power Charge Controller
 

Viewers also liked

Top 10 electrical design engineer interview questions and answers
Top 10 electrical design engineer interview questions and answersTop 10 electrical design engineer interview questions and answers
Top 10 electrical design engineer interview questions and answersrivherjonh
 
Marketing plan
Marketing planMarketing plan
Marketing plan
Maurice Smith
 
Bt freestyle 2500 User Guide from Telephones Online www.telephonesonline.co.uk
Bt freestyle 2500 User Guide from Telephones Online  www.telephonesonline.co.ukBt freestyle 2500 User Guide from Telephones Online  www.telephonesonline.co.uk
Bt freestyle 2500 User Guide from Telephones Online www.telephonesonline.co.uk
Telephones Online
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a Building
GAURAV. H .TANDON
 
Building Electrical Systems Design
Building Electrical Systems DesignBuilding Electrical Systems Design
Building Electrical Systems Design
Victor Sun
 
0 to 2,500 Customers with No Cold Calls
0 to 2,500 Customers with No Cold Calls0 to 2,500 Customers with No Cold Calls
0 to 2,500 Customers with No Cold CallsHubSpot
 
MasterPlus - Sistema Binário
MasterPlus - Sistema BinárioMasterPlus - Sistema Binário
MasterPlus - Sistema Binário
MasterplusBrasil
 
Strip your charts
Strip your chartsStrip your charts
Strip your chartsuwseidl
 
Apresentacao
ApresentacaoApresentacao
Resultado Final do Concurso de Bom Sucesso
Resultado Final do Concurso de Bom Sucesso Resultado Final do Concurso de Bom Sucesso
Resultado Final do Concurso de Bom Sucesso Joao Rivonaldo Silva
 
Exames médicos valores - União Sindical
Exames médicos   valores - União SindicalExames médicos   valores - União Sindical
Exames médicos valores - União Sindical
sinteimp
 
Acoples rapidos
Acoples rapidosAcoples rapidos
Acoples rapidos
Fernando Cotes
 
2500 years of learning theory: The good, the bad & the ugly - Donald Clark
2500 years of learning theory: The good, the bad & the ugly - Donald Clark2500 years of learning theory: The good, the bad & the ugly - Donald Clark
2500 years of learning theory: The good, the bad & the ugly - Donald Clark
Learning Pool Ltd
 
Labor Market and Salary Survey in Russia
Labor Market and Salary Survey in RussiaLabor Market and Salary Survey in Russia
Labor Market and Salary Survey in RussiaAwara Direct Search
 
Sarah Palin\'s Shopping Spree
Sarah Palin\'s Shopping SpreeSarah Palin\'s Shopping Spree
Sarah Palin\'s Shopping Spree
coolstuff
 
Lineadeltiempodelacomputacion Iiuac
Lineadeltiempodelacomputacion IiuacLineadeltiempodelacomputacion Iiuac
Lineadeltiempodelacomputacion IiuacOscorp
 
Atelier (re)Commencez votre plan média
Atelier (re)Commencez votre plan média Atelier (re)Commencez votre plan média
Atelier (re)Commencez votre plan média
Lucie PELLICIER
 
Clase 4 Plan De Mercado Y Promociones Febrero
Clase 4 Plan De Mercado Y Promociones  FebreroClase 4 Plan De Mercado Y Promociones  Febrero
Clase 4 Plan De Mercado Y Promociones Febrerodeisy torrico
 

Viewers also liked (20)

Top 10 electrical design engineer interview questions and answers
Top 10 electrical design engineer interview questions and answersTop 10 electrical design engineer interview questions and answers
Top 10 electrical design engineer interview questions and answers
 
Marketing plan
Marketing planMarketing plan
Marketing plan
 
Bt freestyle 2500 User Guide from Telephones Online www.telephonesonline.co.uk
Bt freestyle 2500 User Guide from Telephones Online  www.telephonesonline.co.ukBt freestyle 2500 User Guide from Telephones Online  www.telephonesonline.co.uk
Bt freestyle 2500 User Guide from Telephones Online www.telephonesonline.co.uk
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a Building
 
Building Electrical Systems Design
Building Electrical Systems DesignBuilding Electrical Systems Design
Building Electrical Systems Design
 
0 to 2,500 Customers with No Cold Calls
0 to 2,500 Customers with No Cold Calls0 to 2,500 Customers with No Cold Calls
0 to 2,500 Customers with No Cold Calls
 
MasterPlus - Sistema Binário
MasterPlus - Sistema BinárioMasterPlus - Sistema Binário
MasterPlus - Sistema Binário
 
Strip your charts
Strip your chartsStrip your charts
Strip your charts
 
Apresentacao
ApresentacaoApresentacao
Apresentacao
 
Resultado Final do Concurso de Bom Sucesso
Resultado Final do Concurso de Bom Sucesso Resultado Final do Concurso de Bom Sucesso
Resultado Final do Concurso de Bom Sucesso
 
Exames médicos valores - União Sindical
Exames médicos   valores - União SindicalExames médicos   valores - União Sindical
Exames médicos valores - União Sindical
 
Acoples rapidos
Acoples rapidosAcoples rapidos
Acoples rapidos
 
Option Strategies
Option StrategiesOption Strategies
Option Strategies
 
2500 years of learning theory: The good, the bad & the ugly - Donald Clark
2500 years of learning theory: The good, the bad & the ugly - Donald Clark2500 years of learning theory: The good, the bad & the ugly - Donald Clark
2500 years of learning theory: The good, the bad & the ugly - Donald Clark
 
Labor Market and Salary Survey in Russia
Labor Market and Salary Survey in RussiaLabor Market and Salary Survey in Russia
Labor Market and Salary Survey in Russia
 
Sarah Palin\'s Shopping Spree
Sarah Palin\'s Shopping SpreeSarah Palin\'s Shopping Spree
Sarah Palin\'s Shopping Spree
 
Catálogo de delícias
Catálogo de delíciasCatálogo de delícias
Catálogo de delícias
 
Lineadeltiempodelacomputacion Iiuac
Lineadeltiempodelacomputacion IiuacLineadeltiempodelacomputacion Iiuac
Lineadeltiempodelacomputacion Iiuac
 
Atelier (re)Commencez votre plan média
Atelier (re)Commencez votre plan média Atelier (re)Commencez votre plan média
Atelier (re)Commencez votre plan média
 
Clase 4 Plan De Mercado Y Promociones Febrero
Clase 4 Plan De Mercado Y Promociones  FebreroClase 4 Plan De Mercado Y Promociones  Febrero
Clase 4 Plan De Mercado Y Promociones Febrero
 

Similar to Electrical Engineering Basics - What Design Engineers Need to Know

EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
Littelfuse
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor corrector
JoeChueng
 
Littelfuse Solutions: Industrial Motor Drives and Soft Starters
Littelfuse Solutions: Industrial Motor Drives and Soft StartersLittelfuse Solutions: Industrial Motor Drives and Soft Starters
Littelfuse Solutions: Industrial Motor Drives and Soft Starters
Littelfuse
 
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
IRJET Journal
 
Protasis Gp 2011 6
Protasis Gp 2011 6Protasis Gp 2011 6
Protasis Gp 2011 6
Evi Katogoudis
 
1489 series circuit breaker guide
1489 series circuit breaker guide1489 series circuit breaker guide
1489 series circuit breaker guide
Juan Carlos Lara Quiroz
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordination
Himmelstern
 
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
 Ph.D. Defence on "High power medium voltage dc/dc converter technology for D... Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
CatalinGabrielDincan
 
AMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product CatalogAMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product CatalogPaul Chang
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
michaeljmack
 
Littelfuse Fuseology Basics
Littelfuse Fuseology BasicsLittelfuse Fuseology Basics
Littelfuse Fuseology Basics
Littelfuse
 
Littelfuse Wireless Charging Capabilities
Littelfuse Wireless Charging CapabilitiesLittelfuse Wireless Charging Capabilities
Littelfuse Wireless Charging Capabilities
Littelfuse
 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdf
ssusera5c9a31
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
Himmelstern
 
ETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done Right
Himmelstern
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
Archili Kokhtashvili
 
An Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power SystemAn Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power System
vkmalik
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterPaul Plavicheanu
 

Similar to Electrical Engineering Basics - What Design Engineers Need to Know (20)

EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor corrector
 
Littelfuse Solutions: Industrial Motor Drives and Soft Starters
Littelfuse Solutions: Industrial Motor Drives and Soft StartersLittelfuse Solutions: Industrial Motor Drives and Soft Starters
Littelfuse Solutions: Industrial Motor Drives and Soft Starters
 
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
Simulation of DVR by using Ultra Capacitor to Analysis of THD with and withou...
 
Protasis Gp 2011 6
Protasis Gp 2011 6Protasis Gp 2011 6
Protasis Gp 2011 6
 
1489 series circuit breaker guide
1489 series circuit breaker guide1489 series circuit breaker guide
1489 series circuit breaker guide
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordination
 
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
 Ph.D. Defence on "High power medium voltage dc/dc converter technology for D... Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
Ph.D. Defence on "High power medium voltage dc/dc converter technology for D...
 
AMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product CatalogAMSC D-SVC™ Product Catalog
AMSC D-SVC™ Product Catalog
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Littelfuse Fuseology Basics
Littelfuse Fuseology BasicsLittelfuse Fuseology Basics
Littelfuse Fuseology Basics
 
D-SVC Data Sheet R2
D-SVC Data Sheet R2D-SVC Data Sheet R2
D-SVC Data Sheet R2
 
Littelfuse Wireless Charging Capabilities
Littelfuse Wireless Charging CapabilitiesLittelfuse Wireless Charging Capabilities
Littelfuse Wireless Charging Capabilities
 
arc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdfarc-flash-analysis-done-right.pdf
arc-flash-analysis-done-right.pdf
 
ETAP - Arc flash analysis etap
ETAP - Arc flash analysis etapETAP - Arc flash analysis etap
ETAP - Arc flash analysis etap
 
ETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done RightETAP - Arc flash analysis done Right
ETAP - Arc flash analysis done Right
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
 
An Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power SystemAn Overview Of Agbami Fpso Electrical Power System
An Overview Of Agbami Fpso Electrical Power System
 
ANBARASAN R CV
ANBARASAN R CV ANBARASAN R CV
ANBARASAN R CV
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft Starter
 

Electrical Engineering Basics - What Design Engineers Need to Know

  • 1. Initial Design Discussion What the Project Engineer Needs to Know
  • 2.
  • 3.
  • 4.
  • 5.
  • 6.
  • 7.
  • 8. The Power Source Flywheel UPS © Liebert Engine Generator Set © Cummins Power Generation Pole Mounted Transformers Pad Mounted Transformers
  • 9.
  • 10.
  • 11.
  • 12. Nominal System Voltages Substation 13.2kV; 69kV; 115kV Plant Distribution 4160V; 480V; 208V Control 120V Signal 24V
  • 13.
  • 14. Working Clearances under 600V 2005 NEC Article 110.26 Spaces About Electrical Equipment (C) Entrance to Working Space. (2) Large Equipment. For equipment rated 1,200A or more, an entrance measuring not less than 24 in. wide and 61/2 ft high, is required at each end of the working space. Where the entrance to the working space has a door, the door must open out and be equipped with panic hardware or other devices that open under simple pressure. This material was extracted from Mike Holt Training Materials copyright 2007 by permission. Visit www.NECCode.com or call 1.888.NEC.Code (632-2633) for more information. NEC ® 2002
  • 16. Working Clearances over 600V NEC ® 2005
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.

Editor's Notes

  1. Design elements Load types and characteristics [Mike C and 2H] Power sources – utility and private [Mike C and 2H] Discussion on protective devices and safety aspects [HRZ] Devices for monitoring and control and system discussion [Mike P] Pulling it together SLD power connection diagram P&ID control and monitoring diagram
  2. Load: If it needs electricity to operate: rotate, revolve, move, heat or illuminate, it’s a load. Is a switch a load? Motors [process and building] Lights control cabinets contain a system of loads: PLCs, indicating lights, relays Characteristics and ratings: Single phase, three phase, frequency, [unit of power is KW or KVA] Voltage, amperage Enclosure types for different operational and environmental factors: Safety: Protective devices for transient voltages, voltage surges, overcurrent, overvoltage, and ground fault Enclosures for energized parts, raceways, insulators Control: On, off, and somewhere in between [vary voltage or current to control rotation or intensity] Monitor: Power: Always metered by the utility but instrumentation is used for individual monitoring of equipment or systems to determine efficiency Run time: to schedule maintenance Temperature: to determine potential problems
  3. These elements are considered in all designs, though all may not be applicable. Without exception, project engineers need to know about the LOAD, the SOURCE, and the CONTROL, to ensure SAFETY, COMPLIANCE and provide for proper MAINTENANCE The LOAD can be building or 1,000; but each load receives the same thought process and evaluation to follow recommended practices, standards and codes. It’s all about protection of life and property.
  4. These elements are considered in all designs, though all may not be applicable. Without exception, project engineers need to know about the LOAD, the SOURCE, and the CONTROL, to ensure SAFETY, COMPLIANCE and provide for proper MAINTENANCE The LOAD can be building or 1,000; but each load receives the same thought process and evaluation to follow recommended practices, standards and codes. It’s all about protection of life and property.
  5. After all the loads are tabulated [hp converted to kva], the service or the power source size is determined. 2. Source 2.a. What is the source? 2.a.1. Utility transfomer 2.a.2. Distribution transformer 2.a.3. Generator 2.a.4. UPS or battery 2.b. What are the source ratings? 2.b.1. KVA- transformer 2.b.2. Volts (primary & secondary on transformer) 2.b.3. Kw (generator) 2.b.4. Phases 2.c. How is the source protected? 2.c.1. Circuit breaker 2.c.2. Fuse 2.d. Where is source protection located? 2.d.1. Panelboard 2.d.2. Enclosure 2.e. Where is the source located? 2.e.1. Pole 2.e.2. Padmounted 2.e.3. Room (elevation, number)
  6. After all the loads are tabulated [hp converted to kva], the service or the power source size is determined. 2. Source 2.a. What is the source? 2.a.1. Utility transfomer 2.a.2. Distribution transformer 2.a.3. Generator 2.a.4. UPS or battery 2.b. What are the source ratings? 2.b.1. KVA- transformer 2.b.2. Volts (primary & secondary on transformer) 2.b.3. Kw (generator) 2.b.4. Phases 2.c. How is the source protected? 2.c.1. Circuit breaker 2.c.2. Fuse 2.d. Where is source protection located? 2.d.1. Panelboard 2.d.2. Enclosure 2.e. Where is the source located? 2.e.1. Pole 2.e.2. Padmounted 2.e.3. Room (elevation, number)
  7. After all the loads are tabulated [hp converted to kva], the service or the power source size is determined. 2. Source 2.a. What is the source? 2.a.1. Utility transfomer 2.a.2. Distribution transformer 2.a.3. Generator 2.a.4. UPS or battery 2.b. What are the source ratings? 2.b.1. KVA- transformer 2.b.2. Volts (primary & secondary on transformer) 2.b.3. Kw (generator) 2.b.4. Phases 2.c. How is the source protected? 2.c.1. Circuit breaker 2.c.2. Fuse 2.d. Where is source protection located? 2.d.1. Panelboard 2.d.2. Enclosure 2.e. Where is the source located? 2.e.1. Pole 2.e.2. Padmounted 2.e.3. Room (elevation, number)
  8. The newsroom at WBRZ-TV, the ABC television affiliate, in Baton Rouge, LA, is another flywheel application. The news operation is active 24 hours every day of the year. Television and radio stations are required by law to continue broadcasting if power is lost in the power grid.
  9. IEEE Standard for Industrial and Commercial Power Systems Low: 120/240 to 600V – used to supply utilization equipment Medium: 2400 to 69kV – supply distribution transformers or large motors [13.8kV and lower] High: 115 to 230kV – transmission voltage between substations IEEE Power Engineering Society High = above 1000V NEC High = over 600V
  10. Article 110 requires specific clearances around equipment based on voltage levels, and changes have occurred from the 2002 NEC. Ea
  11. Article 110 requires specific clearances around equipment based on voltage levels, and changes have occurred from the 2002 NEC. The requirement that equipment rated 1,200A or more had to be over 6 ft wide before an entrance was required at each end of the working space was removed. The argument for the change was that the size of the arc blast is directly related to the ampere rating of the equipment, and not the physical width of the equipment.
  12. Based on the information provided and discussions that ensue, the early design decisions are made. Article 110 requires specific clearances around equipment based on voltage levels.
  13. Based on the information provided and discussions that ensue, the early design decisions are made. Article 110 requires specific clearances around equipment based on voltage levels.
  14. What are the options to protect the load? 3.a. How is the load protected? 3.a.1. Circuit breaker 3.a.2. Fuse 3.b. Where is protection located? Environment? 3.b.1. Panel 3.b.2. MCC These devices are assembled and connected to conductive metal called bus bars. the energized parts are protected inside panels which will have NEMA enclosure ratings, which Mike Currie will address later.
  15. What are the options to protect the load? 3.a. How is the load protected? 3.a.1. Circuit breaker 3.a.2. Fuse 3.b. Where is protection located? Environment? 3.b.1. Panel 3.b.2. MCC These devices are assembled and connected to conductive metal called bus bars. the energized parts are protected inside panels which will have NEMA enclosure ratings, which Mike Currie will address later.
  16. What are the options to protect the load? 3.a. How is the load protected? 3.a.1. Circuit breaker 3.a.2. Fuse 3.b. Where is protection located? Environment? 3.b.1. Panel 3.b.2. MCC These devices are assembled and connected to conductive metal called bus bars. the energized parts are protected inside panels which will have NEMA enclosure ratings, which Mike Currie will address later.
  17. What are the options to protect the load? 3.a. How is the load protected? 3.a.1. Circuit breaker 3.a.2. Fuse 3.b. Where is protection located? Environment? 3.b.1. Panel 3.b.2. MCC These devices are assembled and connected to conductive metal called bus bars. the energized parts are protected inside panels which will have NEMA enclosure ratings, which Mike Currie will address later.
  18. E-rated fuses: Bolt-In • EBI055 - E-rated medium voltage, current-limiting fuses for transformer and feeder protection. CL-14 • ECL055 - E-rated medium voltage, current-limiting fuses for transformer and feeder protection. • ECL155 - E-rated medium voltage, current-limiting fuses for transformer and feeder protection. for potential & small power transformers • JCD - Indicating and non-indicating E-rated medium voltage, current-limiting fuses for potential & small power transformers. • JCE - Indicating and non-indicating E-rated medium voltage, current-limiting fuses for potential & small power transformers. • JCI - Indicating and non-indicating E-rated medium voltage, current-limiting fuses for potential & small power transformers. • JCQ - Indicating and non-indicating E-rated medium voltage, current-limiting fuses for potential & small power transformers. • JCT - Indicating and non-indicating E-rated medium voltage, current-limiting fuses for potential & small power transformers. • JCW - Indicating and non-indicating E-rated medium voltage, current-limiting fuses for potential & small power transformers. for transformer & feeder protection • JCU - Indoor/enclosure E-rated medium voltage, current-limiting fuses for potential & small power transformers with blown fuse indication. • JCX - Indoor/enclosure E-rated medium voltage, current-limiting fuses for potential & small power transformers with blown fuse indication. • JCY - Indoor/enclosure E-rated medium voltage, current-limiting fuses for potential & small power transformers with blown fuse indication. • JCZ - Indoor/enclosure E-rated medium voltage, current-limiting fuses for potential & small power transformers with blown fuse indication. • JDZ - Indoor/enclosure E-rated medium voltage, current-limiting fuses for potential & small power transformers with blown fuse indication. for transformers and feeders • MV055 - E-rated medium, voltage current-limiting fuses: for transformer and feeder protection. • MV155 - E-rated medium, voltage current-limiting fuses: for transformer and feeder protection. Fast-acting fuses Non-time delay • HVA - Medium voltage, non-time delay, fast-acting fuses. • HVB - Medium voltage, non-time delay, fast-acting fuses. • HVJ - Medium voltage, non-time delay, fast-acting fuses. • HVL - Medium voltage, non-time delay, fast-acting fuses. • HVR - Medium voltage, non-time delay, fast-acting fuses. • HVT - Medium voltage, non-time delay, fast-acting fuses. • HVU - Medium voltage, non-time delay, fast-acting fuses. • HVX - Medium voltage, non-time delay, fast-acting fuses. R-rated fuses for motor circuit protection • JCG - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCH - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCK - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCK-A - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCK-B - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCL-A - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCL-B - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCR-A - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. • JCR-B - Indoor/enclosure R-rated medium voltage, current-limiting fuses for motor circuit protection. Type H & N (High Surge) • EEI-NEMA - Medium voltage fuses: Type H (high surge) Type K (Fast) • EEI-NEMA - EEI-NEMA Type K (fast-acting) Type T (Slow) • EEI-NEMA - EEI-NEMA Type T (slow-acting).
  19. What are the options to control the load? What parameters should be monitored? Individual component devices are useful but only if they work in concert. Field devices must report to a command center where decisions are made and action taken. Someone watches a gauge or gauges and turns a knob or flips a switch based on the information displayed or the decision to open a value, turn on a pump, or raise a temperature is determined a multitude of feedback set points that are processed in nanoseconds. SCADA systems can monitor and control plant and process equipment to save clients time and money Verify system performance for regulatory compliance, energy cost savings, Anticipate schedule maintenance times – reduce unanticipated down times Equipment Temperature switches Ammeters, Voltmeters, KWh meters Phase monitors Under/overvoltage monitors Process Level transmitters/ switches Pressure switches Motorized valves
  20. Individual component devices are useful but only if they work in concert. Field devices must report to a command center where decisions are made and action taken. Someone watches a guage or gauges and turns a knob or flips a switch based on the information displayed or the decision to open a value, turn on a pump, or raise a temperature is determined a multitude of feedback set points that are processed in nanoseconds. SCADA systems can monitor and control plant and process equipment to save clients time and money Verify system performance for regulatory compliance, energy cost savings, Anticipate schedule maintenance times – reduce unanticipated down times Monitoring devices: Equipment Temperature switches Ammeters, Voltmeters, KWh meters Phase monitors Under/overvoltage monitors Process Level transmitters/ switches Pressure switches Motorized valves
  21. All these devices are tied together to form our operational systems. we represent these systems in power diagrams and P&IDs process and instrumentation diagrams, which will be discussed in greater detail later in the presentation.
  22. Early discussion of the design is beneficial To minimize change orders during construction Planning for future growth Safe, long term operation
  23. Load lists provided by the PM are used to develop single line diagrams and P&ID’s