Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Cable Tray
Module Five – 26207-11
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 1
Upon completion of this module, you will be able to do the following:
1. Describe the components that make up a cable tray assembly.
2. Explain the methods used to hang and secure cable tray.
3. Describe how cable enters and exits cable tray.
4. Select the proper cable tray fitting for the situation.
5. Explain the National Electrical Code® (NEC®) requirements for cable tray
installations.
6. Select the required fittings to ensure equipment grounding continuity in
cable.
7. Interpret electrical working drawings showing cable tray fittings.
8. Size cable tray for the number and type of conductors contained in the
system.
Objectives
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 2
Under supervision of the instructor, you should be able to:
1. Generate a list of materials for a cable tray layout. List all the
components required, including the fasteners required to complete
the system.
2. Join two straight, ladder-type cable tray sections together.
Performance Tasks
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 3 Figure 1 – Typical cable tray system
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 4 Figure 2 – Cross section of cable tray comparing
usable dimensions to overall dimensions
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 5 Figure 3 – Cables rest on the bottom of the tray and are
held in place by the longitudinal side rails
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 6 Figure 4 – Two applications of cable tray channel
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 7 Figure 5 – Cables packed closely together can impair efficiency
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 8 Figure 6 – Each tray support should be capable of safely supporting
1.25 times the weight of the entire tray and cable assembly span
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 9 Figure 7 – Bending of loaded tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 10 Figure 8 – Load of cable creates bending moments along the span
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 11 Figure 10 – Several ways in which cables may exit from a cable tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 12 Figure 11 – A dropout plate provides a curved surface
for the cable to follow as it leaves the tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 13 Figure 13 – Fabricating a cable tray offset with swivel plates
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 14 Figure 14 – Expansion joint and splice plates
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 15 Figure 16 – Alternate ways to hang cable tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 16 Figure 17 – Center rail cable tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 17 Figure 18 – NEC® regulations governing the use of cable tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 18 Figure 19 – NEC® regulations governing cable tray construction and installation
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 19 Figure 20 – NEC® regulations governing cable tray grounding
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 20 Figure 21 – Sample floor plan of a cable tray system
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 21
Supplemental Art
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 22 Course Map
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 23 Figure 9 – Cable pulley used to facilitate a cable pull in a tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 24 Figure 12 – Typical application of supports in a vertical run
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 25 Figure 15 – Channel support
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 26 Appendix
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 27 Cable Tray Installations
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 28 Special-Application Cable Management Systems
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 29 Ladder Tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 30 Basket Tray (1 of 3)
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 31 Basket Tray (2 of 3)
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 32 Basket Tray (3 of 3)
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 33 Center Hung Tray
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 34 Cable Tray in Raised-Floor Systems
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 35 Low-Voltage Cable (1 of 2)
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 36 Low –Voltage Cable (2 of 2)
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 37 What’s Wrong With This Picture?
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Cable Tray
Module 26207-11
National Center
for Construction
Education and
Research
Slide 38

More Related Content

Similar to Module Five - Cable Tray - NCCER Substation Slides

Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...
Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...
Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...
Shariq Ayjaz
 
Module Eleven - Concrete Work - NCCER Substation Slides
Module Eleven - Concrete Work - NCCER Substation SlidesModule Eleven - Concrete Work - NCCER Substation Slides
Module Eleven - Concrete Work - NCCER Substation Slides
Shariq Ayjaz
 
Module Thirteen - Intermediate Rigging - NCCER Substation Slides
Module Thirteen - Intermediate Rigging - NCCER Substation SlidesModule Thirteen - Intermediate Rigging - NCCER Substation Slides
Module Thirteen - Intermediate Rigging - NCCER Substation Slides
Shariq Ayjaz
 
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Shariq Ayjaz
 
BUCK converter fed by PV array
BUCK converter fed by PV arrayBUCK converter fed by PV array
BUCK converter fed by PV array
Monika Rout
 
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
ARAVIND U
 
ClientCurrents_2010_vol5
ClientCurrents_2010_vol5ClientCurrents_2010_vol5
ClientCurrents_2010_vol5
Kevin Trippe
 
Start (ceb) new
Start (ceb) newStart (ceb) new
Impact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on GridImpact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on Grid
vivatechijri
 
when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...
theijes
 
design a roof top based solar power station
design a roof top based solar power stationdesign a roof top based solar power station
design a roof top based solar power station
Sumit Sharma
 
CW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
CW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKCW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
CW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
veereshtadasad07
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)
Sindhuja Balaji
 
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptxBATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
23mu08
 
Building Services: Project 1
Building Services: Project 1Building Services: Project 1
Building Services: Project 1
Bahirah Rahman
 
CSTEP BORRERO R poster
CSTEP BORRERO R posterCSTEP BORRERO R poster
CSTEP BORRERO R poster
Raul Martinez Jr.
 
F0366041045
F0366041045F0366041045
F0366041045
theijes
 
Sustainable Energy for All – A multidisciplinary educational approach.
Sustainable Energy for All – A multidisciplinary educational approach.Sustainable Energy for All – A multidisciplinary educational approach.
Sustainable Energy for All – A multidisciplinary educational approach.
lenses
 
SMART LOAD SHEDDING
SMART LOAD SHEDDINGSMART LOAD SHEDDING
SMART LOAD SHEDDING
Hariram R
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
Sanjay Kumar Sharma
 

Similar to Module Five - Cable Tray - NCCER Substation Slides (20)

Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...
Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...
Module Twelve - Mechanical Construction Methods and Materials - NCCER Substat...
 
Module Eleven - Concrete Work - NCCER Substation Slides
Module Eleven - Concrete Work - NCCER Substation SlidesModule Eleven - Concrete Work - NCCER Substation Slides
Module Eleven - Concrete Work - NCCER Substation Slides
 
Module Thirteen - Intermediate Rigging - NCCER Substation Slides
Module Thirteen - Intermediate Rigging - NCCER Substation SlidesModule Thirteen - Intermediate Rigging - NCCER Substation Slides
Module Thirteen - Intermediate Rigging - NCCER Substation Slides
 
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
 
BUCK converter fed by PV array
BUCK converter fed by PV arrayBUCK converter fed by PV array
BUCK converter fed by PV array
 
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
RES & EC Unit 3 PPT - Solar Photovoltaic System and Design & Ocean Energy, Ti...
 
ClientCurrents_2010_vol5
ClientCurrents_2010_vol5ClientCurrents_2010_vol5
ClientCurrents_2010_vol5
 
Start (ceb) new
Start (ceb) newStart (ceb) new
Start (ceb) new
 
Impact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on GridImpact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on Grid
 
when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...when a coil is rotated or turned under a magnetic field, there occurs a force...
when a coil is rotated or turned under a magnetic field, there occurs a force...
 
design a roof top based solar power station
design a roof top based solar power stationdesign a roof top based solar power station
design a roof top based solar power station
 
CW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
CW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKCW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
CW presentation.pptxKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
 
INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)INTERNSHIP REPORT (FINAL)
INTERNSHIP REPORT (FINAL)
 
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptxBATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
 
Building Services: Project 1
Building Services: Project 1Building Services: Project 1
Building Services: Project 1
 
CSTEP BORRERO R poster
CSTEP BORRERO R posterCSTEP BORRERO R poster
CSTEP BORRERO R poster
 
F0366041045
F0366041045F0366041045
F0366041045
 
Sustainable Energy for All – A multidisciplinary educational approach.
Sustainable Energy for All – A multidisciplinary educational approach.Sustainable Energy for All – A multidisciplinary educational approach.
Sustainable Energy for All – A multidisciplinary educational approach.
 
SMART LOAD SHEDDING
SMART LOAD SHEDDINGSMART LOAD SHEDDING
SMART LOAD SHEDDING
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
 

Recently uploaded

一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Transcat
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
Shiny Christobel
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
ijseajournal
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
MadhavJungKarki
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
OKORIE1
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
ElakkiaU
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
AnasAhmadNoor
 
Unit -II Spectroscopy - EC I B.Tech.pdf
Unit -II Spectroscopy - EC  I B.Tech.pdfUnit -II Spectroscopy - EC  I B.Tech.pdf
Unit -II Spectroscopy - EC I B.Tech.pdf
TeluguBadi
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
b0754201
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
aryanpankaj78
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
Paris Salesforce Developer Group
 

Recently uploaded (20)

一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
Tools & Techniques for Commissioning and Maintaining PV Systems W-Animations ...
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
 
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
1FIDIC-CONSTRUCTION-CONTRACT-2ND-ED-2017-RED-BOOK.pdf
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
DESIGN AND MANUFACTURE OF CEILING BOARD USING SAWDUST AND WASTE CARTON MATERI...
 
An Introduction to the Compiler Designss
An Introduction to the Compiler DesignssAn Introduction to the Compiler Designss
An Introduction to the Compiler Designss
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
 
Unit -II Spectroscopy - EC I B.Tech.pdf
Unit -II Spectroscopy - EC  I B.Tech.pdfUnit -II Spectroscopy - EC  I B.Tech.pdf
Unit -II Spectroscopy - EC I B.Tech.pdf
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptxSENTIMENT ANALYSIS ON PPT AND Project template_.pptx
SENTIMENT ANALYSIS ON PPT AND Project template_.pptx
 
Digital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptxDigital Twins Computer Networking Paper Presentation.pptx
Digital Twins Computer Networking Paper Presentation.pptx
 
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
AI + Data Community Tour - Build the Next Generation of Apps with the Einstei...
 

Module Five - Cable Tray - NCCER Substation Slides

  • 1. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Cable Tray Module Five – 26207-11
  • 2. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 1 Upon completion of this module, you will be able to do the following: 1. Describe the components that make up a cable tray assembly. 2. Explain the methods used to hang and secure cable tray. 3. Describe how cable enters and exits cable tray. 4. Select the proper cable tray fitting for the situation. 5. Explain the National Electrical Code® (NEC®) requirements for cable tray installations. 6. Select the required fittings to ensure equipment grounding continuity in cable. 7. Interpret electrical working drawings showing cable tray fittings. 8. Size cable tray for the number and type of conductors contained in the system. Objectives
  • 3. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 2 Under supervision of the instructor, you should be able to: 1. Generate a list of materials for a cable tray layout. List all the components required, including the fasteners required to complete the system. 2. Join two straight, ladder-type cable tray sections together. Performance Tasks
  • 4. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 3 Figure 1 – Typical cable tray system
  • 5. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 4 Figure 2 – Cross section of cable tray comparing usable dimensions to overall dimensions
  • 6. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 5 Figure 3 – Cables rest on the bottom of the tray and are held in place by the longitudinal side rails
  • 7. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 6 Figure 4 – Two applications of cable tray channel
  • 8. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 7 Figure 5 – Cables packed closely together can impair efficiency
  • 9. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 8 Figure 6 – Each tray support should be capable of safely supporting 1.25 times the weight of the entire tray and cable assembly span
  • 10. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 9 Figure 7 – Bending of loaded tray
  • 11. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 10 Figure 8 – Load of cable creates bending moments along the span
  • 12. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 11 Figure 10 – Several ways in which cables may exit from a cable tray
  • 13. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 12 Figure 11 – A dropout plate provides a curved surface for the cable to follow as it leaves the tray
  • 14. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 13 Figure 13 – Fabricating a cable tray offset with swivel plates
  • 15. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 14 Figure 14 – Expansion joint and splice plates
  • 16. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 15 Figure 16 – Alternate ways to hang cable tray
  • 17. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 16 Figure 17 – Center rail cable tray
  • 18. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 17 Figure 18 – NEC® regulations governing the use of cable tray
  • 19. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 18 Figure 19 – NEC® regulations governing cable tray construction and installation
  • 20. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 19 Figure 20 – NEC® regulations governing cable tray grounding
  • 21. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 20 Figure 21 – Sample floor plan of a cable tray system
  • 22. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 21 Supplemental Art
  • 23. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 22 Course Map
  • 24. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 23 Figure 9 – Cable pulley used to facilitate a cable pull in a tray
  • 25. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 24 Figure 12 – Typical application of supports in a vertical run
  • 26. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 25 Figure 15 – Channel support
  • 27. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 26 Appendix
  • 28. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 27 Cable Tray Installations
  • 29. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 28 Special-Application Cable Management Systems
  • 30. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 29 Ladder Tray
  • 31. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 30 Basket Tray (1 of 3)
  • 32. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 31 Basket Tray (2 of 3)
  • 33. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 32 Basket Tray (3 of 3)
  • 34. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 33 Center Hung Tray
  • 35. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 34 Cable Tray in Raised-Floor Systems
  • 36. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 35 Low-Voltage Cable (1 of 2)
  • 37. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 36 Low –Voltage Cable (2 of 2)
  • 38. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 37 What’s Wrong With This Picture?
  • 39. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Cable Tray Module 26207-11 National Center for Construction Education and Research Slide 38