SlideShare a Scribd company logo
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 0
Grades, Part One
Module Ten – 22106-12
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 1 Objectives
When you have completed this module, you will be able to do the
following:
1. Explain the terms used in grade work.
2. Identify types of stakes and explain markings on grade stakes and
benchmark (BM) stakes.
3. Identify equipment used by the operator to check stakes.
4. Explain different types of slopes and slope ratio.
5. Check horizontal and vertical distance of cut and fill slope stakes.
6. Check finish subgrade on a cross slope.
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 2 Performance Tasks
Under the supervision of your instructor, you should be able to do the
following:
1. Identify types of stakes and markings on stakes.
2. Check horizontal and vertical distances of cut and fill slope
stakes.
3. Check finish subgrade on a cross slope.
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 3 Figure 1 – Grades
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 4 Figure 2 – Example of erosion
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 5 Figure 3 – Roadway profile sheet
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 6 Figure 4 – Silt fencing
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 7 Figure 5 – Side and front view of silt fencing
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 8 Figure 6 – Parts of a roadway
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 9 Figure 7 – Excavation of a roadway
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 10 Figure 8 – Foundation plan
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 11 Figure 9 – Excavation of a monolithic slab
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 12 Figure 10 – Typical use of batter boards
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 13 Figure 11 – Calculating a grade
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 14 Table 1 – General Stake Markings
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 15 Figure 12 – Grade stake
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 16 Table 2 – American Public Works Association
(APWA) Underground Color Codes
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 17 Figure 13 – Permanent benchmark
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 18 Figure 14 – Temporary benchmarks and guard stakes
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 19 Figure 15 – Stakes for rough grading
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 20 Figure 16 – Center line stake
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 21 Figure 17 – Plus station
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 22 Figure 18 – Edge of pavement stakes
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 23 Figure 19 – Slope stakes
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 24 Figure 20 – Offset stake
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 25 Figure 21 – Cut and fill (slope) stakes
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 26 Figure 22 – Cross-section of a fill
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 27 Figure 23 – Checking the fill grade
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 28 Figure 24 – Cross-section of a cut
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 29 Figure 25 – Ditch excavation
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 30 Figure 26 – Grader with GPS equipment
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 31 Figure 27 – Basic measuring equipment
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 32 Figure 28 – An automatic level
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 33 Figure 29 – Leveling rods
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 34 Figure 30 – Measuring horizontal distances
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 35 Figure 31 – Measuring horizontal distance across a slope
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 36 Figure 32 – Automatic level tripod
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 37 Figure 33 – Reading a leveling rod
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 38 Figure 34 – Using a leveling rod
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 39 Figure 35 – Using a leveling rod to calculate elevations
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 40 Figure 36 – Laser transmitter and receiver rod
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 41 Figure 37 – One-person operation
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 42 Figure 38 – Rotating beam laser instrument
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 43 Figure 39 – Rotating lasers sweep multiple sensors
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 44 Figure 40 – GPS surveying receiver
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 45 Figure 41 – Graphics of construction plan on GPS surveying equipment
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 46 Figure 42 – Pocket leveling rod
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 47 Figure 43 – Measuring a cut
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 48 Figure 44 – Checking the grade across a roadway
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 49 Figure 45 – Checking the grade with an automatic level
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 50
Supplemental Art
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 51 Course Map
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grades, Part One
Module 22106-12
National Center
for Construction
Education and
Research
Slide 52

More Related Content

Similar to Module Ten - Grades - Part One - NCCER Substation Slides

Module Two - Managing Electrical Hazards - NCCER Substation Slides
Module Two - Managing Electrical Hazards - NCCER Substation SlidesModule Two - Managing Electrical Hazards - NCCER Substation Slides
Module Two - Managing Electrical Hazards - NCCER Substation Slides
Shariq Ayjaz
 
Module Five - Cable Tray - NCCER Substation Slides
Module Five -  Cable Tray - NCCER Substation SlidesModule Five -  Cable Tray - NCCER Substation Slides
Module Five - Cable Tray - NCCER Substation Slides
Shariq Ayjaz
 
Module Four - Conductors and Cable - NCCER Substation Slides
Module Four - Conductors and Cable - NCCER Substation SlidesModule Four - Conductors and Cable - NCCER Substation Slides
Module Four - Conductors and Cable - NCCER Substation Slides
Shariq Ayjaz
 
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Shariq Ayjaz
 
BASIC SAFETY 101-09(1) (1).pptx
BASIC SAFETY 101-09(1) (1).pptxBASIC SAFETY 101-09(1) (1).pptx
BASIC SAFETY 101-09(1) (1).pptx
Fredel De Vera
 
Diploma transcript
Diploma  transcriptDiploma  transcript
Diploma transcript
Dipen Kantariya
 
Battery swapping project
Battery swapping projectBattery swapping project
Battery swapping project
Nagamohan Burugupalli
 
Automatic Phase Changer
Automatic Phase ChangerAutomatic Phase Changer
Automatic Phase Changer
Bhanu Bhawesh
 
Start (ceb) new
Start (ceb) newStart (ceb) new
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKINGDESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
Chukka Nikhil Chakravarthy
 
PROJECT FINAL REPORT
PROJECT FINAL REPORTPROJECT FINAL REPORT
PROJECT FINAL REPORT
LAVA KUMAR ADDEPALLI
 
Parametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programParametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based program
eSAT Journals
 
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptxBATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
23mu08
 
Cert II in Electrotechnology-expert panel report.
Cert II in Electrotechnology-expert panel report.Cert II in Electrotechnology-expert panel report.
Cert II in Electrotechnology-expert panel report.
Allan McLean
 
Solar poweredleadacidbatterycharger
Solar poweredleadacidbatterychargerSolar poweredleadacidbatterycharger
Solar poweredleadacidbatterycharger
ashok 44
 
IRJET- Structural Engineering Aspects of Metro Rail Projects
IRJET- Structural Engineering Aspects of Metro Rail ProjectsIRJET- Structural Engineering Aspects of Metro Rail Projects
IRJET- Structural Engineering Aspects of Metro Rail Projects
IRJET Journal
 
Industrial training report
Industrial training report Industrial training report
Industrial training report
Deshan Arachchige
 
IRJET- Design and Implementation of Solar Charge Controller
IRJET- Design and Implementation of Solar Charge ControllerIRJET- Design and Implementation of Solar Charge Controller
IRJET- Design and Implementation of Solar Charge Controller
IRJET Journal
 
BUCK converter fed by PV array
BUCK converter fed by PV arrayBUCK converter fed by PV array
BUCK converter fed by PV array
Monika Rout
 
B.E. EEE (2021 reg.pdf syallabus anna university
B.E. EEE (2021 reg.pdf syallabus anna universityB.E. EEE (2021 reg.pdf syallabus anna university
B.E. EEE (2021 reg.pdf syallabus anna university
mageshprabhu
 

Similar to Module Ten - Grades - Part One - NCCER Substation Slides (20)

Module Two - Managing Electrical Hazards - NCCER Substation Slides
Module Two - Managing Electrical Hazards - NCCER Substation SlidesModule Two - Managing Electrical Hazards - NCCER Substation Slides
Module Two - Managing Electrical Hazards - NCCER Substation Slides
 
Module Five - Cable Tray - NCCER Substation Slides
Module Five -  Cable Tray - NCCER Substation SlidesModule Five -  Cable Tray - NCCER Substation Slides
Module Five - Cable Tray - NCCER Substation Slides
 
Module Four - Conductors and Cable - NCCER Substation Slides
Module Four - Conductors and Cable - NCCER Substation SlidesModule Four - Conductors and Cable - NCCER Substation Slides
Module Four - Conductors and Cable - NCCER Substation Slides
 
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
Module Three - Alternating Current and Three-Phase Systems - NCCER Substation...
 
BASIC SAFETY 101-09(1) (1).pptx
BASIC SAFETY 101-09(1) (1).pptxBASIC SAFETY 101-09(1) (1).pptx
BASIC SAFETY 101-09(1) (1).pptx
 
Diploma transcript
Diploma  transcriptDiploma  transcript
Diploma transcript
 
Battery swapping project
Battery swapping projectBattery swapping project
Battery swapping project
 
Automatic Phase Changer
Automatic Phase ChangerAutomatic Phase Changer
Automatic Phase Changer
 
Start (ceb) new
Start (ceb) newStart (ceb) new
Start (ceb) new
 
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKINGDESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
DESIGN AND DEVELOPMENT OF SOLAR CHARGE CONTROLLER WITH SUN TRACKING
 
PROJECT FINAL REPORT
PROJECT FINAL REPORTPROJECT FINAL REPORT
PROJECT FINAL REPORT
 
Parametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based programParametric investigation of cable stayed bridge using macro based program
Parametric investigation of cable stayed bridge using macro based program
 
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptxBATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
BATCH 8 - PROJECT PHASE II - SECOND REVIEW.pptx
 
Cert II in Electrotechnology-expert panel report.
Cert II in Electrotechnology-expert panel report.Cert II in Electrotechnology-expert panel report.
Cert II in Electrotechnology-expert panel report.
 
Solar poweredleadacidbatterycharger
Solar poweredleadacidbatterychargerSolar poweredleadacidbatterycharger
Solar poweredleadacidbatterycharger
 
IRJET- Structural Engineering Aspects of Metro Rail Projects
IRJET- Structural Engineering Aspects of Metro Rail ProjectsIRJET- Structural Engineering Aspects of Metro Rail Projects
IRJET- Structural Engineering Aspects of Metro Rail Projects
 
Industrial training report
Industrial training report Industrial training report
Industrial training report
 
IRJET- Design and Implementation of Solar Charge Controller
IRJET- Design and Implementation of Solar Charge ControllerIRJET- Design and Implementation of Solar Charge Controller
IRJET- Design and Implementation of Solar Charge Controller
 
BUCK converter fed by PV array
BUCK converter fed by PV arrayBUCK converter fed by PV array
BUCK converter fed by PV array
 
B.E. EEE (2021 reg.pdf syallabus anna university
B.E. EEE (2021 reg.pdf syallabus anna universityB.E. EEE (2021 reg.pdf syallabus anna university
B.E. EEE (2021 reg.pdf syallabus anna university
 

Recently uploaded

LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
MiscAnnoy1
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
ydzowc
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
Prakhyath Rai
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 

Recently uploaded (20)

LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
Introduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptxIntroduction to AI Safety (public presentation).pptx
Introduction to AI Safety (public presentation).pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
原版制作(Humboldt毕业证书)柏林大学毕业证学位证一模一样
 
Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...Software Engineering and Project Management - Introduction, Modeling Concepts...
Software Engineering and Project Management - Introduction, Modeling Concepts...
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 

Module Ten - Grades - Part One - NCCER Substation Slides

  • 1. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 0 Grades, Part One Module Ten – 22106-12
  • 2. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 1 Objectives When you have completed this module, you will be able to do the following: 1. Explain the terms used in grade work. 2. Identify types of stakes and explain markings on grade stakes and benchmark (BM) stakes. 3. Identify equipment used by the operator to check stakes. 4. Explain different types of slopes and slope ratio. 5. Check horizontal and vertical distance of cut and fill slope stakes. 6. Check finish subgrade on a cross slope.
  • 3. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 2 Performance Tasks Under the supervision of your instructor, you should be able to do the following: 1. Identify types of stakes and markings on stakes. 2. Check horizontal and vertical distances of cut and fill slope stakes. 3. Check finish subgrade on a cross slope.
  • 4. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 3 Figure 1 – Grades
  • 5. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 4 Figure 2 – Example of erosion
  • 6. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 5 Figure 3 – Roadway profile sheet
  • 7. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 6 Figure 4 – Silt fencing
  • 8. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 7 Figure 5 – Side and front view of silt fencing
  • 9. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 8 Figure 6 – Parts of a roadway
  • 10. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 9 Figure 7 – Excavation of a roadway
  • 11. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 10 Figure 8 – Foundation plan
  • 12. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 11 Figure 9 – Excavation of a monolithic slab
  • 13. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 12 Figure 10 – Typical use of batter boards
  • 14. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 13 Figure 11 – Calculating a grade
  • 15. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 14 Table 1 – General Stake Markings
  • 16. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 15 Figure 12 – Grade stake
  • 17. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 16 Table 2 – American Public Works Association (APWA) Underground Color Codes
  • 18. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 17 Figure 13 – Permanent benchmark
  • 19. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 18 Figure 14 – Temporary benchmarks and guard stakes
  • 20. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 19 Figure 15 – Stakes for rough grading
  • 21. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 20 Figure 16 – Center line stake
  • 22. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 21 Figure 17 – Plus station
  • 23. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 22 Figure 18 – Edge of pavement stakes
  • 24. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 23 Figure 19 – Slope stakes
  • 25. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 24 Figure 20 – Offset stake
  • 26. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 25 Figure 21 – Cut and fill (slope) stakes
  • 27. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 26 Figure 22 – Cross-section of a fill
  • 28. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 27 Figure 23 – Checking the fill grade
  • 29. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 28 Figure 24 – Cross-section of a cut
  • 30. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 29 Figure 25 – Ditch excavation
  • 31. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 30 Figure 26 – Grader with GPS equipment
  • 32. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 31 Figure 27 – Basic measuring equipment
  • 33. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 32 Figure 28 – An automatic level
  • 34. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 33 Figure 29 – Leveling rods
  • 35. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 34 Figure 30 – Measuring horizontal distances
  • 36. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 35 Figure 31 – Measuring horizontal distance across a slope
  • 37. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 36 Figure 32 – Automatic level tripod
  • 38. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 37 Figure 33 – Reading a leveling rod
  • 39. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 38 Figure 34 – Using a leveling rod
  • 40. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 39 Figure 35 – Using a leveling rod to calculate elevations
  • 41. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 40 Figure 36 – Laser transmitter and receiver rod
  • 42. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 41 Figure 37 – One-person operation
  • 43. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 42 Figure 38 – Rotating beam laser instrument
  • 44. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 43 Figure 39 – Rotating lasers sweep multiple sensors
  • 45. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 44 Figure 40 – GPS surveying receiver
  • 46. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 45 Figure 41 – Graphics of construction plan on GPS surveying equipment
  • 47. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 46 Figure 42 – Pocket leveling rod
  • 48. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 47 Figure 43 – Measuring a cut
  • 49. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 48 Figure 44 – Checking the grade across a roadway
  • 50. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 49 Figure 45 – Checking the grade with an automatic level
  • 51. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 50 Supplemental Art
  • 52. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 51 Course Map
  • 53. Copyright © by NCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grades, Part One Module 22106-12 National Center for Construction Education and Research Slide 52