Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 0
National Center
for Construction
Education and
Research
Grounding Systems
Module Nine – 82203-12
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 1
National Center
for Construction
Education and
Research
Objectives
Upon completion of this module, you will be able to do the following:
1. Explain the purpose of a ground grid system.
2. Describe the methods and materials for installing an underground
grid.
3. Explain the safety precautions used and the PPE required when
repairing and/or expanding an existing ground grid.
4. Describe how connections are made in a ground grid system using
exothermic welded, compression, and mechanical connectors.
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 2
National Center
for Construction
Education and
Research
Performance Tasks
Under the supervision of the instructor, you should be able to do the
following:
1. Make connections in a ground grid system using exothermic
welded, compression, and mechanical connectors.
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 3
National Center
for Construction
Education and
Research
Figure 1 — Substation
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 4
National Center
for Construction
Education and
Research
Figure 2 — Electrostatic induction
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 5
National Center
for Construction
Education and
Research
Figure 3 — Electromagnetic induction
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 6
National Center
for Construction
Education and
Research
Figure 4 — Energized soil around an energized grounded object
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 7
National Center
for Construction
Education and
Research
Figure 5 — Step potential hazard
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 8
National Center
for Construction
Education and
Research
Figure 6 — Touch potential hazard
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 9
National Center
for Construction
Education and
Research
Figure 7 — Connections to a grounded grid
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 10
National Center
for Construction
Education and
Research
Figure 8 — Substation grounding plan
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 11
National Center
for Construction
Education and
Research
Figure 9 — Wenner four-point method
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 12
National Center
for Construction
Education and
Research
Figure 10 — Electrolytic electrode
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 13
National Center
for Construction
Education and
Research
Figure 11 — Ground grid layout
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 14
National Center
for Construction
Education and
Research
Table 1 — Ground Grid Conductor Sizes
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 15
National Center
for Construction
Education and
Research
Figure 12 — Fence ground grid dimensions
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 16
National Center
for Construction
Education and
Research
Figure 13 — Ground grid connections
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 17
National Center
for Construction
Education and
Research
Table 2 — Connection Method Advantages and Disadvantages
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 18
National Center
for Construction
Education and
Research
Figure 14 — Mechanical connector
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 19
National Center
for Construction
Education and
Research
Figure 15 — Cable-to-cable mechanical connectors
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 20
National Center
for Construction
Education and
Research
Figure 16 — Mechanical ground connection assembly
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 21
National Center
for Construction
Education and
Research
Figure 17 — Compression connector
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 22
National Center
for Construction
Education and
Research
Figure 18 — Types of compression connectors
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 23
National Center
for Construction
Education and
Research
Figure 19 — Die number stamped in connector body
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 24
National Center
for Construction
Education and
Research
Figure 20 — Crimping tool
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 25
National Center
for Construction
Education and
Research
Figure 21 — Exothermic weld mold
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 26
National Center
for Construction
Education and
Research
Figure 22 — Exothermic electronic igniter
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 27
National Center
for Construction
Education and
Research
Figure 23 — Completed exothermic weld
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 28
National Center
for Construction
Education and
Research
Figure 24 — Cable-to-cable mold configurations
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 29
National Center
for Construction
Education and
Research
Figure 25 — Exothermic welding steps
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 30
National Center
for Construction
Education and
Research
Figure 26 — Ground rod placement
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 31
National Center
for Construction
Education and
Research
Figure 27 — Ground rod installation
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 32
National Center
for Construction
Education and
Research
Figure 28 — Equipotential zone below switch handle
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 33
National Center
for Construction
Education and
Research
Figure 29 — Fall-of-potential test setup
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 34
National Center
for Construction
Education and
Research
Figure 30 — Ground grid test report form
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 35
National Center
for Construction
Education and
Research
Figure 31 — Temporary ground mat
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 36
National Center
for Construction
Education and
Research
Supplemental Art
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 37
National Center
for Construction
Education and
Research
Course Map
Copyright © by NCCER,
Published by Pearson Education, Inc.
Power Line Worker Level Two: Substation – Grounding Systems
Module 82203-12
Slide 38
National Center
for Construction
Education and
Research

Module Nine - Grounding Systems - NCCER Substation Slides

  • 1.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 0 National Center for Construction Education and Research Grounding Systems Module Nine – 82203-12
  • 2.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 1 National Center for Construction Education and Research Objectives Upon completion of this module, you will be able to do the following: 1. Explain the purpose of a ground grid system. 2. Describe the methods and materials for installing an underground grid. 3. Explain the safety precautions used and the PPE required when repairing and/or expanding an existing ground grid. 4. Describe how connections are made in a ground grid system using exothermic welded, compression, and mechanical connectors.
  • 3.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 2 National Center for Construction Education and Research Performance Tasks Under the supervision of the instructor, you should be able to do the following: 1. Make connections in a ground grid system using exothermic welded, compression, and mechanical connectors.
  • 4.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 3 National Center for Construction Education and Research Figure 1 — Substation
  • 5.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 4 National Center for Construction Education and Research Figure 2 — Electrostatic induction
  • 6.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 5 National Center for Construction Education and Research Figure 3 — Electromagnetic induction
  • 7.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 6 National Center for Construction Education and Research Figure 4 — Energized soil around an energized grounded object
  • 8.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 7 National Center for Construction Education and Research Figure 5 — Step potential hazard
  • 9.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 8 National Center for Construction Education and Research Figure 6 — Touch potential hazard
  • 10.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 9 National Center for Construction Education and Research Figure 7 — Connections to a grounded grid
  • 11.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 10 National Center for Construction Education and Research Figure 8 — Substation grounding plan
  • 12.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 11 National Center for Construction Education and Research Figure 9 — Wenner four-point method
  • 13.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 12 National Center for Construction Education and Research Figure 10 — Electrolytic electrode
  • 14.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 13 National Center for Construction Education and Research Figure 11 — Ground grid layout
  • 15.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 14 National Center for Construction Education and Research Table 1 — Ground Grid Conductor Sizes
  • 16.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 15 National Center for Construction Education and Research Figure 12 — Fence ground grid dimensions
  • 17.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 16 National Center for Construction Education and Research Figure 13 — Ground grid connections
  • 18.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 17 National Center for Construction Education and Research Table 2 — Connection Method Advantages and Disadvantages
  • 19.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 18 National Center for Construction Education and Research Figure 14 — Mechanical connector
  • 20.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 19 National Center for Construction Education and Research Figure 15 — Cable-to-cable mechanical connectors
  • 21.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 20 National Center for Construction Education and Research Figure 16 — Mechanical ground connection assembly
  • 22.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 21 National Center for Construction Education and Research Figure 17 — Compression connector
  • 23.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 22 National Center for Construction Education and Research Figure 18 — Types of compression connectors
  • 24.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 23 National Center for Construction Education and Research Figure 19 — Die number stamped in connector body
  • 25.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 24 National Center for Construction Education and Research Figure 20 — Crimping tool
  • 26.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 25 National Center for Construction Education and Research Figure 21 — Exothermic weld mold
  • 27.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 26 National Center for Construction Education and Research Figure 22 — Exothermic electronic igniter
  • 28.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 27 National Center for Construction Education and Research Figure 23 — Completed exothermic weld
  • 29.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 28 National Center for Construction Education and Research Figure 24 — Cable-to-cable mold configurations
  • 30.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 29 National Center for Construction Education and Research Figure 25 — Exothermic welding steps
  • 31.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 30 National Center for Construction Education and Research Figure 26 — Ground rod placement
  • 32.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 31 National Center for Construction Education and Research Figure 27 — Ground rod installation
  • 33.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 32 National Center for Construction Education and Research Figure 28 — Equipotential zone below switch handle
  • 34.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 33 National Center for Construction Education and Research Figure 29 — Fall-of-potential test setup
  • 35.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 34 National Center for Construction Education and Research Figure 30 — Ground grid test report form
  • 36.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 35 National Center for Construction Education and Research Figure 31 — Temporary ground mat
  • 37.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 36 National Center for Construction Education and Research Supplemental Art
  • 38.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 37 National Center for Construction Education and Research Course Map
  • 39.
    Copyright © byNCCER, Published by Pearson Education, Inc. Power Line Worker Level Two: Substation – Grounding Systems Module 82203-12 Slide 38 National Center for Construction Education and Research