1. .
.
START
DATA MATERIAL:
DIMENSION & WEIGHT
REFERENCE:
RIGGING BOOK + EQUIPMENT MANUAL +
RIGGING STANDARD
TYPE OF
LIFTING
MONO CRANE TAILING SYSTEM SPECIAL EQUPMENT
RIGGING STUDY &
LIFTING STUDY
RISK
ANALYSIS
COST
ANALYSIS
RISK
SAFE
AGREE
OVER
LIFTING PLAN
ACTION
CONTROL
REPORT
FINISH
START
DATA OF LOAD:
DIMENSION &
WEIGHT
REFERENCE:
RIGGING BOOK + EQUIPMENT MANUAL +
RIGGING STANDARD + WELDING PROCEDURE
ANALYSIS
STRESS ANALYSIS FRAME ANALYSIS GROUND BEARING
RIGGING STUDY &
LIFTING STUDY BY
GANTRY
RISK
ANALYSIS
COST
ANALYSIS
RISK
SAFE
AGREE
OVER
LIFTING PLAN &
STANDAR
OPERATIONAL
PROCEDURE
ACTION
CONTROL
REPORT
FINISH
SITE CONDITION:
SURFACE &
FOUNDATION
ROW MATERIAL
AND DELIVERY
DRAFT OF GANTRY
CUTTING PLAN MAN POWER PLAN
PURCHASING ORDER
& DELIVERY ORDER
MECHANICAL WORKS
CIVIL WORKS
ELECTRICAL WORKS
QUALITY
CONTROL
POOR
GOOD
.