This document provides a summary of experience and qualifications for Khalid Ali Saad Eldin. It details over 26 years of experience in rotating equipment, projects, and inspection of static equipment. It also lists his education in mechanical engineering and various certifications in piping inspection, pressure vessel inspection, storage tank inspection, and welding inspection. Currently he works as a Poly Olefin Inspection Engineer at Qatar Petrochemical Company, where he manages inspection activities and ensures equipment integrity. Previously he worked as a Vibration Engineer and acted as Head of Engineering Department at Gulf Of Suez Petroleum Co.
Career Objective
Intend to build a career with a leading organization with committed & dedicated people in a challenging and creative environment. Seeking a promising position that offers both a challenge and a good opportunity for growth and to upgrade skills to serve the company better.
A post graduate of petroleum Engineer (from PME) with 10 years of experience in project engineering and project management from conception to commissioning of multi-discipline EPC contracts related to chemical, refinery, oil & gas and LNG sectors including Egypt, Qatar, Abu Dhabi and Oman.
Working in Arabian Industries (AI) LLC for nearly 6 years in feasibility, detailed engineering, EPC, EMC and IMC Projects for PDO (Petroleum Development Oman) and ORPIC.
I’m a petroleum Engineer with an Excellent experience In Oil & Gas Projects and industries such as exploration ,drilling ,work over , Oil & Gas well drilling & ALS Production services and Projects in oil & Gas Energy field section ,My experience in the Drilling , Well control & wellhead equipment Inspection ,Refurbishment , Maintenance , Testing , Recertification and Installation As per API(6A , 6D , 16A , 16D, 16C & 7K ) Specification. Oil & Gas artificial lift production technology and solution. Maintenance, Installation and Overhaul of well head and well control tools and equipment; furthermore, many projects for new rigs (on shore) and offshore rig (ST-Bahari1- Jack up), Prove leadership skills involving managing, developing and motivating teams to achieve their objectives. Reliable, trustworthy and meticulous, gained a good understanding of what is required of Oil & Gas engineering.
• Fourteen (14) years solid experience in different facets of Power Plant industry.
• Strong understanding with different EPC philosophies in power generations and transmissions.
• Well-exposed and experienced in the installation and operation of the following;
• GE Frame 7FA Gas Turbine-Generator Units
• GE Frame 9E Gas Turbine-Generator Units
• Ansaldo Energia Gas Turbine-Generator Units
• Rotating Equipment Maintenance & Operation
Career Objective
Intend to build a career with a leading organization with committed & dedicated people in a challenging and creative environment. Seeking a promising position that offers both a challenge and a good opportunity for growth and to upgrade skills to serve the company better.
A post graduate of petroleum Engineer (from PME) with 10 years of experience in project engineering and project management from conception to commissioning of multi-discipline EPC contracts related to chemical, refinery, oil & gas and LNG sectors including Egypt, Qatar, Abu Dhabi and Oman.
Working in Arabian Industries (AI) LLC for nearly 6 years in feasibility, detailed engineering, EPC, EMC and IMC Projects for PDO (Petroleum Development Oman) and ORPIC.
I’m a petroleum Engineer with an Excellent experience In Oil & Gas Projects and industries such as exploration ,drilling ,work over , Oil & Gas well drilling & ALS Production services and Projects in oil & Gas Energy field section ,My experience in the Drilling , Well control & wellhead equipment Inspection ,Refurbishment , Maintenance , Testing , Recertification and Installation As per API(6A , 6D , 16A , 16D, 16C & 7K ) Specification. Oil & Gas artificial lift production technology and solution. Maintenance, Installation and Overhaul of well head and well control tools and equipment; furthermore, many projects for new rigs (on shore) and offshore rig (ST-Bahari1- Jack up), Prove leadership skills involving managing, developing and motivating teams to achieve their objectives. Reliable, trustworthy and meticulous, gained a good understanding of what is required of Oil & Gas engineering.
• Fourteen (14) years solid experience in different facets of Power Plant industry.
• Strong understanding with different EPC philosophies in power generations and transmissions.
• Well-exposed and experienced in the installation and operation of the following;
• GE Frame 7FA Gas Turbine-Generator Units
• GE Frame 9E Gas Turbine-Generator Units
• Ansaldo Energia Gas Turbine-Generator Units
• Rotating Equipment Maintenance & Operation
• Fourteen (14) years solid experience in different facets of Power Plant industry.
• Strong understanding with different EPC philosophies in power generations and transmissions.
• Well-exposed and experienced in the installation and operation of the following;
• GE Frame 7FA Gas Turbine-Generator Units
• GE Frame 9E Gas Turbine-Generator Units
• Ansaldo Energia Gas Turbine-Generator Units
• Rotating Equipment Maintenance & Operation
1. KHALID ALI SAAD ELDIN
PO Box 50284
Mesaieed, Qatar
Phone: 974 44684813 Mobile: 974 55297170
E-mails: Saadkhaled61@hotmail.com Or: saadkhaled1961@gmail.com
Summary of experience
26 years’ experience in rotating, projects and inspection of static equipment
This experience is classified as follows::
1987 till 1994 – Vibration Engineer / acting as Head of Engineering Department
1994 till present Olefin Inspection Senior Specialist
Personal Information
Date Of Birth: 18 August 1961 Nationality: Egyptian
Marital Status: Married with 4 children
Permanent Address:
Ain Khalid – Doha - Qatar
Phone: 0974 44684813
: 0974 55297170
Profession:
An inspection Engineering Position that requires Strong Background in Inspection of
Static equipment and plant integrity
Education:
B. Sc. in Mechanical Engineering, Faculty of Engineering, Cairo University
Graduated in May 1984 (Grade: Good).
Qualifications:
• Certified Piping Inspector API 570 (P CERT. NO. 39821)
• Certified pressure vessel inspector API 510 (certification no. 23806)
• Certified above ground storage tank inspector API 653 (certification no.
30214)
• Certified API 580 Risk Based Inspection Professional ( CR. NO. 50544 )
• Certified Senior welding Inspector CSWIP 3.2 ( CSWIP CERT.NO. 15380 )
• Attend API 579 ( Fitness of services ) + PCC 2 course
Selected Courses:
A- Vibration Analysis:
* Measurement Of Machinery Vibration (Cairo-Egypt ,Jan 1989)
* Vibration Analysis (Cairo-Egypt ,Jan 1989)
* Introduction to dynamic Balancing (Cairo-Egypt ,Jan 1989)
* Balancing Techniques (Cairo-Egypt, Jan 1989)
* Measurements of vibration in Mech. (Cairo-Egypt, Feb 1988)
& Elect. Machinery
* Measurements and vibration analysis (Cairo- Egypt, June 1987)
* Failure Analysis (Cairo-Egypt , Oct. 1988)
B- Gas Turbine Courses:
* Control System Logic for Solar Saturn (Caterpillar-USA, October1992)
Gas Turbine Generator Sets
* Operation & Routine Maint. I for Solar (Caterpillar-USA, October 1992)
Saturn Gas Turbine Generator Sets
* Operation & Routine Maint.II for Solar (Caterpillar-USA, October 1992)
Saturn Gas Turbine Generator Sets
* Gas Turbine Maintenance (GE-Cairo-Egypt, September 1987)
2. * SPEEDTRONICS Mark II Controls (GE-Cairo-Egypt, September 1987)
C- Inspection, Welding & Testing:
* Ultrasonic Testing level-I (Saudi Arabia, June 1996)
* Welding process, inspection and QC (AUC - Egypt, October 1993)
* Visual Inspection of Welds (Qatar, December 1997)
* Welding inspector (CSWIP) (Qatar, March 1999)
(Certified welding inspector)
* API 510 Pressure vessel inspector (Saudi Arabia, May 2002)
* PSM (Process Safety Management ) ( Qapco - May, 2013)
Work Experience:
Poly Olefin Inspection Engineer
1994 - to present Qatar Petrochemical Company (QAPCO)
Inspection Section
Job Description:
1- Manages and coordinates all Inspection activities in Poly Olefin plant within
the inspection section and with the other departments.
2- Inform and advise the general condition of the plant equipment, which are
within Inspections domain of competence. Anticipates remaining service life
and or repairs to QAPCO equipment and recommends technical solutions.
3- Prepare the inspection planning / duration of the static equipment and piping in
Qapco plants according to French Regulation and API Standards.
4- Review and analyses all inspection reports submitted by inspectors and senior
inspectors and prepare comments and inspection recommendations
depending on nature of inspection findings.
5- Participate with Maint. And Production in the investigation and solving of
problems encountered in the plant and technically advice to solve it to increase
plant mechanical integrity.
6- Schedule all periodic shutdowns and recommend shutdowns when necessary
schedule, and supervise necessary inspection work advising Maint. Dept. of
detail technical requirements.
7- Prepare technical specifications and requirements for external inspection work
services required by QAPCO and participate in the review and evaluation of
bids for inspection work according to specifications.
8- Attend meetings and participate solving technical problems in cooperation with
Maint. And production.
9- Using updated inspection techniques to carry out inspection activities in Poly
Olefin Plant.
10- Review all inspection technical issues with Engineering section for all the new
projects
11- Review WPS / PQR and welder qualification procedures, witness these tests,
interprets radiographic examination results, accept/reject results according to
standards/company requirements and sign acceptance certificates.
12- Preparing technical inspection reports to support the plant integrity by using
2
3. remaining life calculation and fitness for service by using API 510/ 570/ 653
and API 579.
13- By using DNVGL software ( Galiom ) , prepare all static equipment data for
using Risk based inspection which will change inspection strategy from time
base, condition base to be Risk Based inspection.
14- Enforce strict compliance to industry codes and standards related to integrity
inspection performed by AIMD. Review major inspection findings and provide
engineering support to enhance overall AIMD Quality and reputation. Ensure
that inspection reports are issued with desired quality and comprehension and
to expected accuracy.
15- Implement cost saving activities as per section‘s cost saving plan and
managing the sectional operation cost with due diligent.
16- Ensure assigned all engineering tasks and related activities meet corporate
safety and environmental policy and standards in order to minimize risk of
industrial injuries and un-wanted incidents.
17- Lead and advice operation on full life cycle asset integrity engineering of all
static equipment in Poly Olefin Plant.
18- Implement / support asset integrity condition management strategies and
programs for loss containment purpose including corrosion management.
19- Troubleshoot static equipment recurrent problems and participating in root
case analysis ( RCA)
Acting as Department Head of the Engineering department
1987 - 1994 Gulf Of Suez Petroleum Co. (GUPCO)
Engineering Department
Job Description:
Vibration Engineer for all types of machines of GUPCO Gas Plant at Ras
Shukair, Egypt. The Gas Plant contains turbines, gas compressors, generators,
Turbo-expanders , pumps, Electrical motors, gas oil coolers, gas and diesel
generators and air coolers. The job duties are as follows:
1- Prepare vibration survey schedule for all rotating equipment in the Gas
Plant and its Satellite Stations.
2- Determine the vibration monitoring points for every machine.
2- Diagnose all vibration problems.
3- Prepare abnormal vibration reports for all vibration problems.
4- Use updated vibration instruments in collecting data and diagnoses vibration
problems.
5- Use different vibration instruments for surveying such as : IRD, B&K, Bently
Nevada and Scientific Atlanta such as the following:
• IRD MACHANALYSIS 890&880
• B&K TAPE RECORDER 7100
• Scientific Atlanta Analyzer
• TK8 & TK3
3
4. 6- Execute field balancing.
Project Engineer: Execution of different projects in the Gas Plant such as:
• The installation of new Desalination Unit as per the following steps
1. Prepare estimate cost for the project.
2. Prepare quotation for the new units.
3. Receive the offers and compare between them to choose the best
offer.
4. Order the chosen offer after management approval.
5. Review vendor drawings & send comments to finalize the drawing to
be issued for fabrication.
6. Prepare piping isometric for the new unit with the existing piping
system.
7. Prepare the material list required for the project.
8. check the availability of material in the warehouse and order the
material which is not available from local market or abroad.
9. prepare time schedule for the project.
10. Supervise the different stages of the project.
• The study of the efficiency for the fire fighting system of the Gas Plant:
1. Check the amount of firewater and see if it is enough in case of fire.
2. If needed recommendations for additional pumps are recommended.
Fiberglass piping is recommended since seawater is used.
3. Prepare isometric drawings for the project and estimated cost.
4. Receive support from ENPPI for the proposed project.
5. Same steps are followed afterwards as mentioned in the previous
project.
Computer Skills
Well versed with several computer packages:
Windows 7
Office 2000
Lotus 123
MS Project
ADRE for windows (Vibration Monitor Program)
WinCairs-CCM(Corrosion condition monitoring)
References
Mr. Mohd Al Ajji Eng. Services MGR, QAPCO
Phone No. (0974) 44777807
Mr. Yousuf Abdulla M.A.Rebeeh Group Manager Operation. QAPCO
Phone No. (0974) 44777277
4