SlideShare a Scribd company logo
1 of 60
Planning
Author: Jihad Daniel (Construction Consultant)
Index
1.   Planning
2.   Project Schedule
3.   Types of Schedule
4.   Project Management Planning
5.   Work Breakdown Structure
6.   Cost and Resource Loading
7.   Delay Analysis Procedure
1. Planning
  Planning is an important investment in the success of a
 project. Carrying out the process not only prepares you
 for what lies ahead, ensuring you have adequate resources
 and use them in the most effective way possible, but also
 can warn you that a plan is not worth pursuing. This is
 valuable information, however frustrating it may be!

  Good Planning takes place in a cycle, with evaluation
 following detailed planning. Where evaluation indicates a
 plan should not be followed, you can still return to take a
 different course with minimal loss. After a plan you assess
 the plan, and learn how to improve your planning and
 execution.
1. Planning
 Planning cycle is shown below:
1. Planning
 •Spotting What Needs to be Done
 By spotting new ideas, SWOT Analysis, or responding to
 outside pressure.

 •Identifying the Aim of your Plan
 By asking yourself how you want the future to be. Maybe
 prepare a vision or mission statement.

 •Exploring Options
 Firstly evaluating a number of options by logical
 thinking, Brain Storming or research. Selecting options with
 e.g. Decision Trees.
1. Planning

 •Detailed Planning
 By identifying key activities, prioritizing and target
 setting, and by putting control mechanisms into place. The
 plan will be better if it is structured clearly, if you have won
 support for it, have considered transitional arrangements
 and have though about contingencies.
1. Planning

 •Plan Evaluation
 This allows you to work out the likelihood of your plan
 working before you try to implement it. Techniques such as
 cost/benefit analysis, PMI, Force Field Analysis, Cash Flow
 Forecasting and Risk Analysis can alert you to unsuspected
 considerations. Information learned can be fed back into the
 plan. Plan evaluation should also consider unquantifiable
 points such as ethics, effects on people, and the
 environment. Where a plan is not likely to work, it should
 either be adjusted, other options could be explored, or the
 plan could be scrapped.
1. Planning
 •Implementing Change
 Once you have selected a plan, you will have to implement
 it. To do this you will need to monitor execution of the plan
 so that you can apply corrections if necessary. You may
 have to understand and overcome resistance to change.

 •Closing a Plan
 Here the success or failure of the plan is
 acknowledged, and information is fed back into future
 planning.
2. Project Schedule

 A project schedule is a strategic and an important tool in a
 project manager's portfolio for guiding a project
 successfully to its target completion date. For simple
 projects, a project schedule is basically a timeline or
 calendar which lists tasks and activities with expected start
 and finish dates. For more complex projects, a project
 schedule can be layered with different details to enable
 project managers to direct and manage resources more
 smoothly, communicate more frequently and effectively
 with stakeholders, and identify and monitor dependencies
 and constraints between tasks to avert preventable delays.
2. Project Schedule

 The project schedule can be expressed in several display
 forms depending upon the purpose of the schedule, the
 stage of the development of the project, and the primary
 user of the schedule. The three most common types of
 project schedules are the master project schedule, the
 milestone schedule, and the detailed schedule.
3. Types of Project Schedule

  1. Master Project Schedule

  Developed in the initial phase of project planning, the
  master project schedule is a summary level schedule
  which highlights the principal activities and tasks and
  their estimated duration. This schedule's strength lies in its
  ability to aggregate individual activity schedules and
  display them in one convenient document. The schedule
  can serve as an early communication tool for building buy-
  in for the project with upper level management and
  external stakeholders. The schedule is also useful for
  facilitating team brainstorming during the initial phases of
  the project to work out logistics.
3. Types of Project Schedule

  1. Master Project Schedule
3. Types of Project Schedule

  2. Milestone Schedule

  As an advanced schedule, a milestone schedule is often
  referred to throughout the project’s life cycle. The
  milestone schedule is a summary level schedule that
  allows the project team leader to review and identify all of
  the significant and major project related milestones that
  may surface during the course of a project. A milestone is a
  significant event in the project usually marked by the
  completion of a major deliverable. Because of its visually-
  pleasing format, the milestone schedule is recommended
  for reporting status reports to top level management and
  external stakeholders.
3. Types of Project Schedule
  2. Milestone Schedule
3. Types of Project Schedule

  3. Detailed Schedule

  Detailed schedules are operational schedules intended to
  help front line managers in directing hourly, daily, or
  weekly project work. The detailed schedule is considered
  the execution playbook for the project. Analogous to a
  football playbook that can be broken down into activities
  (passes and runs) or the two sides of the game (offense and
  defence), the detailed project schedule playbook can be
  broken down into chapters to show the detailed schedule
  for each activity or each phase of the project as it unfolds.
3. Types of Project Schedule
  3. Detailed Schedule
4. Project Management Planning
  4.0. Introduction

  Traditional project management often do not attach
  importance to the management of planning, resulting in
  large-scale projects in the comprehensive management of
  organizations often overlap, accusing the division of labor
  is unknown, targeted plan is not strong, the work is not
  specific, information is not open, and other issues delayed
  the progress of the projects . Project management planning
  can be adopted in the project planning documents before
  the start of the form of a very good solution to these
  problems.
  Project Management Planning main content includes the
  following:
4. Project Management Planning

  4.1. Determine the Organizational Structure

  By considering the process of project construction, in
  project implementation are project planning and decision-
  making stage, the early stage of the project, the project
  design stage, tender stage of the project, the project
  construction stage, project acceptance and summary
  evaluation stage. In accordance with the phasing of the
  work should be the creation of specialized units of the
  relevant administrative departments to manage.
4. Project Management Planning

  4.2. Decomposition of Project Management Objectives

  Project decomposition is the core project management
  content. Project management in the development of project
  planning should be the goal of total control, including
  investment, progress, quality, security and other control
  objectives, and then will break down these overall
  objectives, can be broken down into various components
  of the specific implementation, through a variety of
  targeted technical, economic, organizational and
  management measures to ensure the achievement of the
  objectives of the various decomposition and thus achieve
  the overall objective of the project.
4. Project Management Planning

  4.3. Decomposition of Project Contract

  Project management is carried out under market
  conditions in particular the management of trading
  activities, trading activity continued to work the whole
  process of project management, and integrated large-scale
  projects in various types of contracts, the number of
  large, it is necessary to carry out the decomposition of the
  contract, the contract decomposition After the monitoring
  of contract performance, coupled with the implementation
  of the project to deal with changes in the contract.
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.1 : Pre-production Management
  The project to conduct a detailed environmental
  investigation, analysis of its planning; preparation of
  feasibility studies, feasibility studies for analysis and
  planning; the preparation of project reports at the idea of
  building a whole, clearly identified issues and report
  submitted for approval to build the work of program to
  identify matters of the staff reported that the division of
  labor to build.
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.2 :Design Management
  Make sure the entire project's architectural style and
  planning program, the selected program to optimize the
  design; the development of survey and design progress
  control program, specifically designed accused; tracking
  the progress of inspections; involved in the analysis and
  assessment of building use function, size distribution, the
  architectural design standards; to review the design stages
  of the design documents; control design changes, design
  changes to check the reasonableness of the economy.
4. Project Management Planning
  4.4. Decomposition of Project Management Work
  4.4.3: Tender management
  An initial contract for the entire project to determine the
  structure of the contract means the planning project; by
  determining the structure of the contract, the contract
  means the preparation of project tenders the progress of
  planning, a clear duty of the parties concerned: the
  drafting of a need for the main material equipment list;
  commissioned by the tender agent, the different
  professional engineering review of tender documents, the
  tender process in the development of risk management
  strategy; review the price-cap Budget: Organization
  contract negotiations, signing of the contract.
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.4: Construction management
  The progress of the preparation of project
  planning, construction progress to determine the overall
  objectives, clear responsibilities of relevant parties;
  organizational design of low cross-check the
  implementation of preparatory work for construction;
  review of construction organization
  design, personnel, equipment, materials availability; for
  government approval to start the necessary matters; audit
  approach and testing materials, finished products, the
  quality of semi-finished products and equipment; review
  the organizational structure
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.4: Construction management
  supervision, supervision planning; the preparation of the
  construction phase of the annual, quarterly, monthly fund
  use plan and control their implementation; inspection of
  construction the production of safe and civilized unit of
  measure is in line with national and local requirements.

  4.4.5: final acceptance and settlement management
  The main content management are: the completion of the
  preparation of project acceptance and settlement
  planning, the unit works to determine
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.5: final acceptance and settlement management
  acceptance, transfer and settlement of the overall objective,
  clearly related to duties of the parties; the implementation
  of concluding the contract, the completion of the case data;
  organization and structure for major facilities, equipment
  list and the use of maintenance manuals for the use of
  departments, organizations of the project operation,
  maintenance personnel training.
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.6: Control whole process of investment management
  The main management says: The total investment for the
  project break down, analyze the achievement of the overall
  investment objectives of the risk, the preparation of
  investment risk management, control of the preparation of
  a variety of investment statements, clearly related to the
  parties accused; the preparation of the book design to
  control the content of the investment the use of funds and
  the stage plan and control their implementation; control in
  accordance with their
4. Project Management Planning

  4.4. Decomposition of Project Management Work
  4.4.6: Control whole process of investment management
  investment plans designed to limit management; review
  the preliminary design of the project construction plans
  and budget estimates, the use of value engineering
  methods, the potential for mining investment savings; to
  carry out their investment plans and actual values of
  Comparison of dynamic tracking.
4. Project Management Planning

  4.5. Master Control Plan
  In the domestic construction of large and medium-sized
  projects, progress is often the principal contradiction. To
  resolve this contradiction, we must do a good job in
  controlling the progress of the total. The total project plan
  is to control the progress of the project's overall
  planning, is to ensure that the overall objective of the
  project is expected to commence by the programmatic
  document. Total control in the preparation of plans
  recommend the use of network technology for the
  preparation of plans, so that the progress of the possession
  or control of the project critical path, the key work, the
4. Project Management Planning

  4.5. Master Control Plan
  timely detection of deviations and to take measures to
  reform, the implementation of corrective. Precision control
  of the total time scale network planning and is reported
  from the project pre-construction (approved) the work of
  clearing up to the completion of the project so far, in
  accordance with the procedures and the work of building
  the logic of the relationship between the
  preparation, covering the entire process of project
  construction, it achieved very good The overall control
  scheme.
5. Work Breakdown Structure

 A work breakdown structure (WBS) in project
 management and systems engineering, is a tool used to
 define and group a project's discrete work elements (or
 tasks) in a way that helps organize and define the total
 work scope of the project

 A work breakdown structure element may be a
 product, data, a service, or any combination. A WBS also
 provides the necessary framework for detailed cost
 estimating and control along with providing guidance for
 schedule development and control. Additionally the WBS
 is a dynamic tool and can be revised and updated as
 needed by the project manager.
5. Work Breakdown Structure

 The Work Breakdown Structure is a tree structure, which
 shows a subdivision of effort required to achieve an
 objective; for example a program, project, and contract. In
 a project or contract, the WBS is developed by starting
 with the end objective and successively subdividing it into
 manageable components in terms of size, duration, and
 responsibility
 (e.g., systems, subsystems, components, tasks, subtasks, a
 nd work packages) which include all steps necessary to
 achieve the objective. The lowest level of each branch of
 the WBS is
 called the Work Package. Work Packages are decomposed
 into smaller components called activities.
5. Work Breakdown Structure

 The Work Breakdown Structure provides a common
 framework for the natural development of the overall
 planning and control of a contract and is the basis for
 dividing work into definable increments from which the
 statement of work can be developed and
 technical, schedule, cost, and labor hour reporting can be
 established. In planning any project, you follow the same
 simple steps: if an item is too complicated to manage, it
 becomes a list of simpler items. People call this producing a
 work breakdown structure to make it sound more formal and
 impressive. Without following this formal approach you
 are unlikely to remember all the niggling little details; with
 this procedure, the details are simply displayed on the final
 lists.
5. Work Breakdown Structure

 One common fault is to produce too much detail at the
 initial planning stage. You should be stop when you have a
 sufficient description of the activity to provide a clear
 instruction for the person who will actually do the
 work, and to have a reasonable estimate for the total
 time/effort involved. You need the former to allocate (or
 delegate) the task; you need the latter to finish the
 planning.
5. Work Breakdown Structure
5. Work Breakdown Structure
 Example of WBS
5. Work Breakdown Structure
 Example of WBS
6. Cost and Resource Loading

 The major goal of the planning effort is an integrated
 project schedule and budget. Schedule planning results in a
 schedule that describes the sequence of technical work and
 the task interdependencies necessary for a successful
 project outcome. Cost planning begins with the
 development of a cost estimate for all authorized work that
 eventually leads to the establishment of the project budget.
 Proper project planning ensures the amount of work to be
 accomplished, the time allotted to accomplish the project
 activities, and the resources required to complete the work
 scope are evenly balanced.
6. Cost and Resource Loading

 Once the schedule and cost planning are concluded, the
 resultant plans can be merged to form a time-phased
 project budget that is seamlessly integrated with the
 network schedule. This resource loaded schedule and
 initial project budget are validated and approved as the
 Integrated Project Baseline which is endorsed by the project
 team as the Performance Measurement Baseline, a
 foundational element of earned value management.
 Meaningful earned value performance metrics enable
 better management insight and decision making to help
 keep the project on track.
6. Cost and Resource Loading

 The objectives of schedule planning are to generate a
 reasonable schedule of work that leads to project
 completion, and to establish a schedule baseline that, when
 integrated with a cost baseline using resource loading
 techniques, will result in an Integrated Project Baseline for
 the project. The core of the schedule planning process is the
 Schedule Management System and its associated
 scheduling software. This system provides the requisite
 PM tools to plan and sequence project milestones and work
 activities, to assign resources to the activities, to monitor
 progress of activities toward project objectives, to forecast
 future schedule performance, and to provide the basis for
 earned value and performance calculations.
6. Cost and Resource Loading

 A. Cost planning is the other major planning activity
 required to develop an Integrated Project Baseline. The
 purpose of cost planning is to identify the resources needed
 to accomplish the scope of work and estimate the
 associated costs. Cost represents the dollar value required
 to accomplish the technical work scope within schedule
 and programmatic constraints. A preliminary
 cost estimate can be started after an initial WBS is
 developed. Cost estimate integration with the WBS occurs
 when the work scope in each project work and planning
 package has a definitive cost/resource estimate associated
 with it. Once the cost estimate is approved at all
 management levels, it becomes the cost baseline, i.e., the
 project’s budget.
6. Cost and Resource Loading

 B. Elements of the cost estimate include both direct charges
 and indirect charges.
 Direct charges are costs applicable to, and identified
 specifically with, the project work scope. Examples of these
 types of costs include labor, travel, material, subcontractor
 costs, etc. Indirect charges are costs that cannot be
 consistently or economically identified against a project
 and are spread over the total project portfolio.
6. Cost and Resource Loading

   Example of Cost Baseline & Cash Flow
6. Cost and Resource Loading

 With the work activities identified in the Control Account
 Plan, the Planning Manager estimates the resources
 (labor, expenses, and procurements) and the quantity
 (hours, dollars) required to accomplish the work activities.
 Labor resources are estimated according to various cost
 element categories, such as Plant Engineer, Mechanical
 Engineer, and Scientist, etc. Expense
 estimates are prepared for such items as supplies and
 materials, travel, and consulting. Labor and expense
 estimates are assigned to the month/fiscal year during
 which they will be used or expended. Estimates for
 procurements are also made and are assigned to the
 month/fiscal year in which payment is anticipated to
 occur.
6. Cost and Resource Loading

 Nominally, the cost estimates are entered in current year
 direct dollars. Once the resources have been identified and
 their costs estimated, a schedule of the work activities is
 developed with start dates, activity durations, and activity
 predecessors. Data from the Control Account Plan sheet is
 used to develop the initial Detail Schedule within the
 Schedule Management System.
 Once this initial resource-loaded Detail Schedule is created
 using the Control Account Plan sheets, the Detail Schedule
 then becomes the basis for future development of the
 Control Account Plans.
6. Cost and Resource Loading
   Example of Control Account Plan
7. Delay Analysis Procedure

 A- Introduction:

 Time is important to everyone, especially to those in the
 construction industry. Every construction contract
 stipulates either a time of performance or a specific project
 completion date. Yet, with so much attention to
 time, construction projects are frequently subject to delays.
 Sorting out the issues and determining which party is
 responsible often proves difficult and time-consuming.
 Though many techniques are available for determining
 schedule impacts, not all produce valid results.
7. Delay Analysis Procedure

 B- Type of Delay Analysis:

 Delay analysis techniques can be classified into three
 separate categories: the Foresight Method, the Hindsight
 Method, and the Contemporaneous Method. The differences
 between these delay analysis techniques involve the baseline
 schedule used for measuring the delay, the point in time
 when the delay is measured, and the treatment, if any, of
 concurrent delay.
7. Delay Analysis Procedure

 B.1- The Foresight Method:

 Commonly thought of as the simplest and easiest, generally
 employs two approaches: Impacted As-Planned, where only
 the owner-caused delays are identified, and Adjusted As-
 Planned, where only contractor-caused delays are identified.
 In both approaches, the alleged delays are reviewed to
 determine where and how the revisions should be
 incorporated into the as-planned or baseline schedule.
7. Delay Analysis Procedure

 B.1- The Foresight Method:

 The result of these implanted activities is an adjusted project
 completion date, which demonstrates, either directly or
 indirectly, the owner’s impact on the contractor’s planned
 schedule of performance.

 The Foresight Method is not generally favoured by courts
 and boards, because it ignores the as-built history of the
 project; it produces theoretical results; it does not measure
 the effect of delay on actual performance; and it assumes that
 the as-planned schedule does not change.
7. Delay Analysis Procedure
   Example of Impacted As Planned
7. Delay Analysis Procedure

 B.2- The Hindsight Method:

 It centres on an as-built schedule - a schedule depicting the
 dates that events actually occurred. Delaying events are
 normally depicted as distinct activities on the as-built
 schedule, which are invariably tied to the critical path.
 Typically, under this method, there are two approaches: As-
 Built Critical Path, which allocates time by determining the
 responsibility for the delays on the so-called critical path of
 the project, and Collapsed As-Built, which removes delays
 caused by one party to determine when the work would
 have been completed, if not for the delays of the other party.
7. Delay Analysis Procedure

 B.2- The Hindsight Method:

 The Hindsight Method has a number of disadvantages that
 include difficulty determining which work activities or delay
 events controlled the pace of the work; not considering what
 was critical at the time a delay occurred; not considering
 float through various paths at different periods of time; not
 accounting for concurrent delay; and not attempting to
 determine the individual impact of each delay.
7. Delay Analysis Procedure
   Example of Collapsed As Built
7. Delay Analysis Procedure
   Example of As Planned versus As Built
7. Delay Analysis Procedure

 B.3- The Contemporaneous Method:

 It hinges on the principle that in order to determine the
 impact of delaying events, the status of the project must be
 established at the time those events occurred. In essence, the
 schedule needs, first, to be updated at the time of the delay
 and, second, to be updated to incorporate any planning
 changes to coincide with the contractor’s plan for pursuing
 the work. The goal of this method is to develop a freeze-
 frame picture of the project - identifying the delaying
 event, the impact of the delay, and the plan to complete the
 remaining work at the time the delay occurred.
7. Delay Analysis Procedure

 B.3- The Contemporaneous Method:

 Two approaches are commonly used as part of this method:
 Time Impact Analysis, which looks at a particular point in time
 and utilizes a series of chronological time slices to evaluate
 major scheduling variations that occurred during the
 project, and Window Analysis, which examines the critical
 path between two points in time and assesses the delay as it
 occurs. Courts and boards hold that contemporaneous
 schedule updates should be considered in evaluating delay.
7. Delay Analysis Procedure

 B.3- The Contemporaneous Method:

 The Contemporaneous Method is favoured because it
 provides a baseline for measuring delay; the status of the
 project at the time a delay occurs; the impact of delaying
 events on remaining work; and insight into float, changes to
 critical path, and revisions to the plan to complete.
7. Delay Analysis Procedure
   Example of Time Impact Analysis
J.S. Daniel presentation on planning

More Related Content

What's hot

Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviromentjuwes
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt projectSamehTeleb
 
Project controls function
Project controls functionProject controls function
Project controls functionHatem Hegazi
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Ahmed Fouad, MCIArb, PMP, SP, RMP
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?maria_singh
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 

What's hot (20)

Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviroment
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Conveyor belt project
Conveyor belt projectConveyor belt project
Conveyor belt project
 
Project controls function
Project controls functionProject controls function
Project controls function
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Building services planning manual 2007
Building services planning manual 2007Building services planning manual 2007
Building services planning manual 2007
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Construction project management
Construction project managementConstruction project management
Construction project management
 

Viewers also liked

J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel
 
Planning in French Language
Planning in French LanguagePlanning in French Language
Planning in French LanguageJ.S. Daniel
 
J.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resourcesJ.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resourcesJ.S. Daniel
 
Office Construction - Practice project
Office Construction - Practice projectOffice Construction - Practice project
Office Construction - Practice projectMansoor Shoaib
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 

Viewers also liked (19)

J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitratorsJ.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
J.S. Daniel paper on Arbitrated cases in lebanon and decisions of arbitrators
 
Planning in French Language
Planning in French LanguagePlanning in French Language
Planning in French Language
 
الاخطار في الفديك
الاخطار في الفديكالاخطار في الفديك
الاخطار في الفديك
 
Contract Manager Presentation
Contract Manager PresentationContract Manager Presentation
Contract Manager Presentation
 
Material logistic plan
Material logistic planMaterial logistic plan
Material logistic plan
 
Quality plan
Quality planQuality plan
Quality plan
 
Safety manual
Safety manualSafety manual
Safety manual
 
Safety plan
Safety planSafety plan
Safety plan
 
Delay analysis final
Delay analysis finalDelay analysis final
Delay analysis final
 
J.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resourcesJ.S. Daniel paper for roads and bridges construction methods & resources
J.S. Daniel paper for roads and bridges construction methods & resources
 
Construction claims
Construction claimsConstruction claims
Construction claims
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Office Construction - Practice project
Office Construction - Practice projectOffice Construction - Practice project
Office Construction - Practice project
 
Commentary on fidic iv clauses
Commentary on fidic iv clausesCommentary on fidic iv clauses
Commentary on fidic iv clauses
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
Boq sample
Boq sampleBoq sample
Boq sample
 
J.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycleJ.S. Daniel paper for high rise building construction cycle
J.S. Daniel paper for high rise building construction cycle
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
 

Similar to J.S. Daniel presentation on planning

Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 NotesSamarthVarpe
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMdAliMujawar1
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptxayanadamtew
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410Saqib Imran
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021Sprintzeal
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptxAtulBhagwat6
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practicekrunalchem
 
Program or project management process report
Program or project management process report Program or project management process report
Program or project management process report Danes Ganancial
 
Project management
Project managementProject management
Project managementArnab Ghosh
 
What are the five stages of project management
What are the five stages of project managementWhat are the five stages of project management
What are the five stages of project managementAselTemir
 
An introduction to project management
An introduction to project management An introduction to project management
An introduction to project management Siva Teja Boddeti
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planningYasirHamour
 
4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdfeyevisioncare1
 

Similar to J.S. Daniel presentation on planning (20)

Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
 
Project management revised
Project management revisedProject management revised
Project management revised
 
MODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptxMODULE II - M.ARCH.pptx
MODULE II - M.ARCH.pptx
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptx
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021PROJECT SCOPE MANAGEMENT GUIDE 2021
PROJECT SCOPE MANAGEMENT GUIDE 2021
 
SPM Unit 1.pptx
SPM Unit 1.pptxSPM Unit 1.pptx
SPM Unit 1.pptx
 
Unit2 Project phases.pptx
Unit2 Project phases.pptxUnit2 Project phases.pptx
Unit2 Project phases.pptx
 
Project management
Project managementProject management
Project management
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 
Program or project management process report
Program or project management process report Program or project management process report
Program or project management process report
 
Project management
Project managementProject management
Project management
 
What are the five stages of project management
What are the five stages of project managementWhat are the five stages of project management
What are the five stages of project management
 
An introduction to project management
An introduction to project management An introduction to project management
An introduction to project management
 
5 project management project planning
5 project management  project planning5 project management  project planning
5 project management project planning
 
Planning skill.pdf
Planning skill.pdfPlanning skill.pdf
Planning skill.pdf
 
4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf4. Proper planning of a software project unless the project is trivia.pdf
4. Proper planning of a software project unless the project is trivia.pdf
 

J.S. Daniel presentation on planning

  • 1. Planning Author: Jihad Daniel (Construction Consultant)
  • 2. Index 1. Planning 2. Project Schedule 3. Types of Schedule 4. Project Management Planning 5. Work Breakdown Structure 6. Cost and Resource Loading 7. Delay Analysis Procedure
  • 3. 1. Planning Planning is an important investment in the success of a project. Carrying out the process not only prepares you for what lies ahead, ensuring you have adequate resources and use them in the most effective way possible, but also can warn you that a plan is not worth pursuing. This is valuable information, however frustrating it may be! Good Planning takes place in a cycle, with evaluation following detailed planning. Where evaluation indicates a plan should not be followed, you can still return to take a different course with minimal loss. After a plan you assess the plan, and learn how to improve your planning and execution.
  • 4. 1. Planning Planning cycle is shown below:
  • 5. 1. Planning •Spotting What Needs to be Done By spotting new ideas, SWOT Analysis, or responding to outside pressure. •Identifying the Aim of your Plan By asking yourself how you want the future to be. Maybe prepare a vision or mission statement. •Exploring Options Firstly evaluating a number of options by logical thinking, Brain Storming or research. Selecting options with e.g. Decision Trees.
  • 6. 1. Planning •Detailed Planning By identifying key activities, prioritizing and target setting, and by putting control mechanisms into place. The plan will be better if it is structured clearly, if you have won support for it, have considered transitional arrangements and have though about contingencies.
  • 7. 1. Planning •Plan Evaluation This allows you to work out the likelihood of your plan working before you try to implement it. Techniques such as cost/benefit analysis, PMI, Force Field Analysis, Cash Flow Forecasting and Risk Analysis can alert you to unsuspected considerations. Information learned can be fed back into the plan. Plan evaluation should also consider unquantifiable points such as ethics, effects on people, and the environment. Where a plan is not likely to work, it should either be adjusted, other options could be explored, or the plan could be scrapped.
  • 8. 1. Planning •Implementing Change Once you have selected a plan, you will have to implement it. To do this you will need to monitor execution of the plan so that you can apply corrections if necessary. You may have to understand and overcome resistance to change. •Closing a Plan Here the success or failure of the plan is acknowledged, and information is fed back into future planning.
  • 9. 2. Project Schedule A project schedule is a strategic and an important tool in a project manager's portfolio for guiding a project successfully to its target completion date. For simple projects, a project schedule is basically a timeline or calendar which lists tasks and activities with expected start and finish dates. For more complex projects, a project schedule can be layered with different details to enable project managers to direct and manage resources more smoothly, communicate more frequently and effectively with stakeholders, and identify and monitor dependencies and constraints between tasks to avert preventable delays.
  • 10. 2. Project Schedule The project schedule can be expressed in several display forms depending upon the purpose of the schedule, the stage of the development of the project, and the primary user of the schedule. The three most common types of project schedules are the master project schedule, the milestone schedule, and the detailed schedule.
  • 11. 3. Types of Project Schedule 1. Master Project Schedule Developed in the initial phase of project planning, the master project schedule is a summary level schedule which highlights the principal activities and tasks and their estimated duration. This schedule's strength lies in its ability to aggregate individual activity schedules and display them in one convenient document. The schedule can serve as an early communication tool for building buy- in for the project with upper level management and external stakeholders. The schedule is also useful for facilitating team brainstorming during the initial phases of the project to work out logistics.
  • 12. 3. Types of Project Schedule 1. Master Project Schedule
  • 13. 3. Types of Project Schedule 2. Milestone Schedule As an advanced schedule, a milestone schedule is often referred to throughout the project’s life cycle. The milestone schedule is a summary level schedule that allows the project team leader to review and identify all of the significant and major project related milestones that may surface during the course of a project. A milestone is a significant event in the project usually marked by the completion of a major deliverable. Because of its visually- pleasing format, the milestone schedule is recommended for reporting status reports to top level management and external stakeholders.
  • 14. 3. Types of Project Schedule 2. Milestone Schedule
  • 15. 3. Types of Project Schedule 3. Detailed Schedule Detailed schedules are operational schedules intended to help front line managers in directing hourly, daily, or weekly project work. The detailed schedule is considered the execution playbook for the project. Analogous to a football playbook that can be broken down into activities (passes and runs) or the two sides of the game (offense and defence), the detailed project schedule playbook can be broken down into chapters to show the detailed schedule for each activity or each phase of the project as it unfolds.
  • 16. 3. Types of Project Schedule 3. Detailed Schedule
  • 17. 4. Project Management Planning 4.0. Introduction Traditional project management often do not attach importance to the management of planning, resulting in large-scale projects in the comprehensive management of organizations often overlap, accusing the division of labor is unknown, targeted plan is not strong, the work is not specific, information is not open, and other issues delayed the progress of the projects . Project management planning can be adopted in the project planning documents before the start of the form of a very good solution to these problems. Project Management Planning main content includes the following:
  • 18. 4. Project Management Planning 4.1. Determine the Organizational Structure By considering the process of project construction, in project implementation are project planning and decision- making stage, the early stage of the project, the project design stage, tender stage of the project, the project construction stage, project acceptance and summary evaluation stage. In accordance with the phasing of the work should be the creation of specialized units of the relevant administrative departments to manage.
  • 19. 4. Project Management Planning 4.2. Decomposition of Project Management Objectives Project decomposition is the core project management content. Project management in the development of project planning should be the goal of total control, including investment, progress, quality, security and other control objectives, and then will break down these overall objectives, can be broken down into various components of the specific implementation, through a variety of targeted technical, economic, organizational and management measures to ensure the achievement of the objectives of the various decomposition and thus achieve the overall objective of the project.
  • 20. 4. Project Management Planning 4.3. Decomposition of Project Contract Project management is carried out under market conditions in particular the management of trading activities, trading activity continued to work the whole process of project management, and integrated large-scale projects in various types of contracts, the number of large, it is necessary to carry out the decomposition of the contract, the contract decomposition After the monitoring of contract performance, coupled with the implementation of the project to deal with changes in the contract.
  • 21. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.1 : Pre-production Management The project to conduct a detailed environmental investigation, analysis of its planning; preparation of feasibility studies, feasibility studies for analysis and planning; the preparation of project reports at the idea of building a whole, clearly identified issues and report submitted for approval to build the work of program to identify matters of the staff reported that the division of labor to build.
  • 22. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.2 :Design Management Make sure the entire project's architectural style and planning program, the selected program to optimize the design; the development of survey and design progress control program, specifically designed accused; tracking the progress of inspections; involved in the analysis and assessment of building use function, size distribution, the architectural design standards; to review the design stages of the design documents; control design changes, design changes to check the reasonableness of the economy.
  • 23. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.3: Tender management An initial contract for the entire project to determine the structure of the contract means the planning project; by determining the structure of the contract, the contract means the preparation of project tenders the progress of planning, a clear duty of the parties concerned: the drafting of a need for the main material equipment list; commissioned by the tender agent, the different professional engineering review of tender documents, the tender process in the development of risk management strategy; review the price-cap Budget: Organization contract negotiations, signing of the contract.
  • 24. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.4: Construction management The progress of the preparation of project planning, construction progress to determine the overall objectives, clear responsibilities of relevant parties; organizational design of low cross-check the implementation of preparatory work for construction; review of construction organization design, personnel, equipment, materials availability; for government approval to start the necessary matters; audit approach and testing materials, finished products, the quality of semi-finished products and equipment; review the organizational structure
  • 25. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.4: Construction management supervision, supervision planning; the preparation of the construction phase of the annual, quarterly, monthly fund use plan and control their implementation; inspection of construction the production of safe and civilized unit of measure is in line with national and local requirements. 4.4.5: final acceptance and settlement management The main content management are: the completion of the preparation of project acceptance and settlement planning, the unit works to determine
  • 26. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.5: final acceptance and settlement management acceptance, transfer and settlement of the overall objective, clearly related to duties of the parties; the implementation of concluding the contract, the completion of the case data; organization and structure for major facilities, equipment list and the use of maintenance manuals for the use of departments, organizations of the project operation, maintenance personnel training.
  • 27. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.6: Control whole process of investment management The main management says: The total investment for the project break down, analyze the achievement of the overall investment objectives of the risk, the preparation of investment risk management, control of the preparation of a variety of investment statements, clearly related to the parties accused; the preparation of the book design to control the content of the investment the use of funds and the stage plan and control their implementation; control in accordance with their
  • 28. 4. Project Management Planning 4.4. Decomposition of Project Management Work 4.4.6: Control whole process of investment management investment plans designed to limit management; review the preliminary design of the project construction plans and budget estimates, the use of value engineering methods, the potential for mining investment savings; to carry out their investment plans and actual values of Comparison of dynamic tracking.
  • 29. 4. Project Management Planning 4.5. Master Control Plan In the domestic construction of large and medium-sized projects, progress is often the principal contradiction. To resolve this contradiction, we must do a good job in controlling the progress of the total. The total project plan is to control the progress of the project's overall planning, is to ensure that the overall objective of the project is expected to commence by the programmatic document. Total control in the preparation of plans recommend the use of network technology for the preparation of plans, so that the progress of the possession or control of the project critical path, the key work, the
  • 30. 4. Project Management Planning 4.5. Master Control Plan timely detection of deviations and to take measures to reform, the implementation of corrective. Precision control of the total time scale network planning and is reported from the project pre-construction (approved) the work of clearing up to the completion of the project so far, in accordance with the procedures and the work of building the logic of the relationship between the preparation, covering the entire process of project construction, it achieved very good The overall control scheme.
  • 31. 5. Work Breakdown Structure A work breakdown structure (WBS) in project management and systems engineering, is a tool used to define and group a project's discrete work elements (or tasks) in a way that helps organize and define the total work scope of the project A work breakdown structure element may be a product, data, a service, or any combination. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Additionally the WBS is a dynamic tool and can be revised and updated as needed by the project manager.
  • 32. 5. Work Breakdown Structure The Work Breakdown Structure is a tree structure, which shows a subdivision of effort required to achieve an objective; for example a program, project, and contract. In a project or contract, the WBS is developed by starting with the end objective and successively subdividing it into manageable components in terms of size, duration, and responsibility (e.g., systems, subsystems, components, tasks, subtasks, a nd work packages) which include all steps necessary to achieve the objective. The lowest level of each branch of the WBS is called the Work Package. Work Packages are decomposed into smaller components called activities.
  • 33. 5. Work Breakdown Structure The Work Breakdown Structure provides a common framework for the natural development of the overall planning and control of a contract and is the basis for dividing work into definable increments from which the statement of work can be developed and technical, schedule, cost, and labor hour reporting can be established. In planning any project, you follow the same simple steps: if an item is too complicated to manage, it becomes a list of simpler items. People call this producing a work breakdown structure to make it sound more formal and impressive. Without following this formal approach you are unlikely to remember all the niggling little details; with this procedure, the details are simply displayed on the final lists.
  • 34. 5. Work Breakdown Structure One common fault is to produce too much detail at the initial planning stage. You should be stop when you have a sufficient description of the activity to provide a clear instruction for the person who will actually do the work, and to have a reasonable estimate for the total time/effort involved. You need the former to allocate (or delegate) the task; you need the latter to finish the planning.
  • 35. 5. Work Breakdown Structure
  • 36. 5. Work Breakdown Structure Example of WBS
  • 37. 5. Work Breakdown Structure Example of WBS
  • 38. 6. Cost and Resource Loading The major goal of the planning effort is an integrated project schedule and budget. Schedule planning results in a schedule that describes the sequence of technical work and the task interdependencies necessary for a successful project outcome. Cost planning begins with the development of a cost estimate for all authorized work that eventually leads to the establishment of the project budget. Proper project planning ensures the amount of work to be accomplished, the time allotted to accomplish the project activities, and the resources required to complete the work scope are evenly balanced.
  • 39. 6. Cost and Resource Loading Once the schedule and cost planning are concluded, the resultant plans can be merged to form a time-phased project budget that is seamlessly integrated with the network schedule. This resource loaded schedule and initial project budget are validated and approved as the Integrated Project Baseline which is endorsed by the project team as the Performance Measurement Baseline, a foundational element of earned value management. Meaningful earned value performance metrics enable better management insight and decision making to help keep the project on track.
  • 40. 6. Cost and Resource Loading The objectives of schedule planning are to generate a reasonable schedule of work that leads to project completion, and to establish a schedule baseline that, when integrated with a cost baseline using resource loading techniques, will result in an Integrated Project Baseline for the project. The core of the schedule planning process is the Schedule Management System and its associated scheduling software. This system provides the requisite PM tools to plan and sequence project milestones and work activities, to assign resources to the activities, to monitor progress of activities toward project objectives, to forecast future schedule performance, and to provide the basis for earned value and performance calculations.
  • 41. 6. Cost and Resource Loading A. Cost planning is the other major planning activity required to develop an Integrated Project Baseline. The purpose of cost planning is to identify the resources needed to accomplish the scope of work and estimate the associated costs. Cost represents the dollar value required to accomplish the technical work scope within schedule and programmatic constraints. A preliminary cost estimate can be started after an initial WBS is developed. Cost estimate integration with the WBS occurs when the work scope in each project work and planning package has a definitive cost/resource estimate associated with it. Once the cost estimate is approved at all management levels, it becomes the cost baseline, i.e., the project’s budget.
  • 42. 6. Cost and Resource Loading B. Elements of the cost estimate include both direct charges and indirect charges. Direct charges are costs applicable to, and identified specifically with, the project work scope. Examples of these types of costs include labor, travel, material, subcontractor costs, etc. Indirect charges are costs that cannot be consistently or economically identified against a project and are spread over the total project portfolio.
  • 43. 6. Cost and Resource Loading  Example of Cost Baseline & Cash Flow
  • 44. 6. Cost and Resource Loading With the work activities identified in the Control Account Plan, the Planning Manager estimates the resources (labor, expenses, and procurements) and the quantity (hours, dollars) required to accomplish the work activities. Labor resources are estimated according to various cost element categories, such as Plant Engineer, Mechanical Engineer, and Scientist, etc. Expense estimates are prepared for such items as supplies and materials, travel, and consulting. Labor and expense estimates are assigned to the month/fiscal year during which they will be used or expended. Estimates for procurements are also made and are assigned to the month/fiscal year in which payment is anticipated to occur.
  • 45. 6. Cost and Resource Loading Nominally, the cost estimates are entered in current year direct dollars. Once the resources have been identified and their costs estimated, a schedule of the work activities is developed with start dates, activity durations, and activity predecessors. Data from the Control Account Plan sheet is used to develop the initial Detail Schedule within the Schedule Management System. Once this initial resource-loaded Detail Schedule is created using the Control Account Plan sheets, the Detail Schedule then becomes the basis for future development of the Control Account Plans.
  • 46. 6. Cost and Resource Loading  Example of Control Account Plan
  • 47. 7. Delay Analysis Procedure A- Introduction: Time is important to everyone, especially to those in the construction industry. Every construction contract stipulates either a time of performance or a specific project completion date. Yet, with so much attention to time, construction projects are frequently subject to delays. Sorting out the issues and determining which party is responsible often proves difficult and time-consuming. Though many techniques are available for determining schedule impacts, not all produce valid results.
  • 48. 7. Delay Analysis Procedure B- Type of Delay Analysis: Delay analysis techniques can be classified into three separate categories: the Foresight Method, the Hindsight Method, and the Contemporaneous Method. The differences between these delay analysis techniques involve the baseline schedule used for measuring the delay, the point in time when the delay is measured, and the treatment, if any, of concurrent delay.
  • 49. 7. Delay Analysis Procedure B.1- The Foresight Method: Commonly thought of as the simplest and easiest, generally employs two approaches: Impacted As-Planned, where only the owner-caused delays are identified, and Adjusted As- Planned, where only contractor-caused delays are identified. In both approaches, the alleged delays are reviewed to determine where and how the revisions should be incorporated into the as-planned or baseline schedule.
  • 50. 7. Delay Analysis Procedure B.1- The Foresight Method: The result of these implanted activities is an adjusted project completion date, which demonstrates, either directly or indirectly, the owner’s impact on the contractor’s planned schedule of performance. The Foresight Method is not generally favoured by courts and boards, because it ignores the as-built history of the project; it produces theoretical results; it does not measure the effect of delay on actual performance; and it assumes that the as-planned schedule does not change.
  • 51. 7. Delay Analysis Procedure  Example of Impacted As Planned
  • 52. 7. Delay Analysis Procedure B.2- The Hindsight Method: It centres on an as-built schedule - a schedule depicting the dates that events actually occurred. Delaying events are normally depicted as distinct activities on the as-built schedule, which are invariably tied to the critical path. Typically, under this method, there are two approaches: As- Built Critical Path, which allocates time by determining the responsibility for the delays on the so-called critical path of the project, and Collapsed As-Built, which removes delays caused by one party to determine when the work would have been completed, if not for the delays of the other party.
  • 53. 7. Delay Analysis Procedure B.2- The Hindsight Method: The Hindsight Method has a number of disadvantages that include difficulty determining which work activities or delay events controlled the pace of the work; not considering what was critical at the time a delay occurred; not considering float through various paths at different periods of time; not accounting for concurrent delay; and not attempting to determine the individual impact of each delay.
  • 54. 7. Delay Analysis Procedure  Example of Collapsed As Built
  • 55. 7. Delay Analysis Procedure  Example of As Planned versus As Built
  • 56. 7. Delay Analysis Procedure B.3- The Contemporaneous Method: It hinges on the principle that in order to determine the impact of delaying events, the status of the project must be established at the time those events occurred. In essence, the schedule needs, first, to be updated at the time of the delay and, second, to be updated to incorporate any planning changes to coincide with the contractor’s plan for pursuing the work. The goal of this method is to develop a freeze- frame picture of the project - identifying the delaying event, the impact of the delay, and the plan to complete the remaining work at the time the delay occurred.
  • 57. 7. Delay Analysis Procedure B.3- The Contemporaneous Method: Two approaches are commonly used as part of this method: Time Impact Analysis, which looks at a particular point in time and utilizes a series of chronological time slices to evaluate major scheduling variations that occurred during the project, and Window Analysis, which examines the critical path between two points in time and assesses the delay as it occurs. Courts and boards hold that contemporaneous schedule updates should be considered in evaluating delay.
  • 58. 7. Delay Analysis Procedure B.3- The Contemporaneous Method: The Contemporaneous Method is favoured because it provides a baseline for measuring delay; the status of the project at the time a delay occurs; the impact of delaying events on remaining work; and insight into float, changes to critical path, and revisions to the plan to complete.
  • 59. 7. Delay Analysis Procedure  Example of Time Impact Analysis