1. Draw the line of balance chart for the 65 unit construction project with activities R, W, X, Y, Z. 2. At the 46th week, activities R, Y and X have finished. Activity W will finish at the 49th unit. Activity Z is not yet finished. 3. If activity Z finishes at the 60th week in 39 units, recalculate the rate of Z. The new rate of 6.5 units/week is less than the old rate of 4 units/week, so the recommendation would be to expedite activity Z.