SlideShare a Scribd company logo
Resource
Resource in construction
Manpower (labor), equipment, material, subcontractor(sc)
Resource Leveling
1) Draw A.O.N Network
0
A
2
2 2
B
2
4 4
C
3
7 7
D
2
9 9
E
1
10
0
G
2
2
0
F
1
1
4
I
2
6
4
H
1
5
st
Activity Resource  day
A 3
B 2
C 4
D 3
E 2
F 2
G 4
H 3
I 4
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day 9 7 2 2 11 8 4 3 3 2
2) Draw Bar chart with resource distribution
F.F
F.F
F.F
F.F
3) Appling the Improvement Factor to non critical activity
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
A : Activity Name
N : NO of free float days consumed
R : No of resources days used by the activity
𝑹 𝒗 : sum number of resource in days that will be vacated when activity move
𝑹 𝒐 : sum number of resource in days that will be occupied when activity move
𝑵 𝒓 : smaller
The No. of free float consumed
Duration of the activity
Activity I
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (I,1)= 4 ×(𝟏𝟏 − 𝟒 − 𝟒 × (𝟏)) = 12
IF (I,2)= 4 ×(𝟏𝟗 − 𝟕 − 𝟒 × (𝟐)) = 𝟏𝟔
IF (I,3)= 4 ×(19−𝟔 − 𝟒 × (𝟐)) = 𝟐𝟎
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
9 7 2 2 11 8 4 3 3 2
Take the largest value of IF
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
9 7 2 2 7 4 4 7 7 2
Activity H
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (H,1)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 0
IF (H,2)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 𝟎
Take the largest value of IF
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
9 7 2 2 4 4 7 7 7 2
Activity G
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (G,1)= 4 ×(9−𝟐 − 𝟒 × (𝟏)) = 12
IF (G,2)= 4 ×(1𝟔 − 𝟒 − 𝟒 × (𝟐)) = 𝟏𝟔
Activity F
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (F,1)= 2 ×(9−𝟕 − 𝟐 × (𝟏)) = 0
IF (F,2)= 2 ×(9−𝟐 − 𝟐 × (𝟏)) = 𝟎
IF (F,3)= 2 ×(9−𝟐 − 𝟐 × (𝟏)) = 𝟏𝟎
So we decide to move G first
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
5 3 6 6 4 4 7 7 7 2
Activity F
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (F,1)= 2 ×(5−𝟑 − 𝟐 × (𝟏)) = 0
IF (F,2)= 2 ×(5−𝟔 − 𝟐 × (𝟏)) = −𝟔
IF (F,3)= 2 ×(5−𝟔 − 𝟐 × (𝟏)) = −𝟔
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
3 5 6 6 4 4 7 7 7 2
Activity G
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (G,1)= 4 ×(6−𝟓 − 𝟒 × (𝟏)) = -12
IF (G,2)= 4 ×(1𝟐 − 𝟖 − 𝟒 × (𝟐)) = −𝟏𝟔
Activity F
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (F,1)= 2 ×(5−𝟑 − 𝟐 × (𝟏)) = 0
4) Back Float Calculations:
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
5 3 6 6 4 4 7 7 7 2
Activity I
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (I,1)= 4 ×(𝟕 − 𝟕 − 𝟒 × (𝟏)) = -16
IF (I,2)= 4 ×(𝟏𝟒 − 𝟏𝟏 − 𝟒 × (𝟐)) = −𝟐𝟎
IF (I,3)= 4 ×(1𝟒 − 𝟖 − 𝟒 × (𝟐)) = −𝟖
Activity H
IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓))
IF (H,1)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 0
IF (H,2)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 𝟎
Final Bar chart :
Act. 1 2 3 4 5 6 7 8 9 10
A 3 3
B 2 2
C 4 4 4
D 3 3
E 2
F 2
G 4 4
H 3
I 4 4
Resource 
day
5 3 6 6 7 4 4 7 7 2

More Related Content

What's hot

Presentation2
Presentation2Presentation2
Presentation2
chian2208
 
Presentation2
Presentation2Presentation2
Presentation2
chian2208
 
Effects of outliers on productivity analyses based on Farm Accountancy Data N...
Effects of outliers on productivity analyses based on Farm Accountancy Data N...Effects of outliers on productivity analyses based on Farm Accountancy Data N...
Effects of outliers on productivity analyses based on Farm Accountancy Data N...
Mathias Kloss
 
Implementation of k-means clustering algorithm in C
Implementation of k-means clustering algorithm in CImplementation of k-means clustering algorithm in C
Implementation of k-means clustering algorithm in C
Kasun Ranga Wijeweera
 
More Multiplication Properties Exponents
More Multiplication Properties ExponentsMore Multiplication Properties Exponents
More Multiplication Properties Exponents
Bitsy Griffin
 
Post_Number Systems_8
Post_Number Systems_8Post_Number Systems_8
Post_Number Systems_8
Marc King
 

What's hot (19)

Presentation2
Presentation2Presentation2
Presentation2
 
Presentation2
Presentation2Presentation2
Presentation2
 
Illustrator_Sample
Illustrator_SampleIllustrator_Sample
Illustrator_Sample
 
Effects of outliers on productivity analyses based on Farm Accountancy Data N...
Effects of outliers on productivity analyses based on Farm Accountancy Data N...Effects of outliers on productivity analyses based on Farm Accountancy Data N...
Effects of outliers on productivity analyses based on Farm Accountancy Data N...
 
Deriving the inverse of a function1
Deriving the inverse of a function1Deriving the inverse of a function1
Deriving the inverse of a function1
 
Heaps & Adaptable priority Queues
Heaps & Adaptable priority QueuesHeaps & Adaptable priority Queues
Heaps & Adaptable priority Queues
 
RedisGraph Internals: Roi Lipman
RedisGraph Internals: Roi LipmanRedisGraph Internals: Roi Lipman
RedisGraph Internals: Roi Lipman
 
Advanced python concepts
Advanced python conceptsAdvanced python concepts
Advanced python concepts
 
Implementation of k-means clustering algorithm in C
Implementation of k-means clustering algorithm in CImplementation of k-means clustering algorithm in C
Implementation of k-means clustering algorithm in C
 
Bubble in link list
Bubble in link listBubble in link list
Bubble in link list
 
Cobb Douglas production function
Cobb Douglas production functionCobb Douglas production function
Cobb Douglas production function
 
Trinity Kings World Leadership: Gave warnings sent out Family Franchising Sys...
Trinity Kings World Leadership: Gave warnings sent out Family Franchising Sys...Trinity Kings World Leadership: Gave warnings sent out Family Franchising Sys...
Trinity Kings World Leadership: Gave warnings sent out Family Franchising Sys...
 
Control system lab nyquist plot
Control system lab nyquist plotControl system lab nyquist plot
Control system lab nyquist plot
 
More Multiplication Properties Exponents
More Multiplication Properties ExponentsMore Multiplication Properties Exponents
More Multiplication Properties Exponents
 
Agile earned value exercise
Agile earned value exerciseAgile earned value exercise
Agile earned value exercise
 
5.9 notes
5.9 notes5.9 notes
5.9 notes
 
2021 preTEST4A Vector Calculus
2021 preTEST4A Vector Calculus2021 preTEST4A Vector Calculus
2021 preTEST4A Vector Calculus
 
Post_Number Systems_8
Post_Number Systems_8Post_Number Systems_8
Post_Number Systems_8
 
Aa4
Aa4Aa4
Aa4
 

Similar to Resource management

Fungsi eksponen-dan-logaritma
Fungsi eksponen-dan-logaritmaFungsi eksponen-dan-logaritma
Fungsi eksponen-dan-logaritma
Arya Ananda
 

Similar to Resource management (20)

Informed search
Informed search Informed search
Informed search
 
1 ESO - Unit 04 - Exercises 1.4.4. - Powers and Square Roots.
1 ESO - Unit 04 - Exercises 1.4.4. - Powers and Square Roots.1 ESO - Unit 04 - Exercises 1.4.4. - Powers and Square Roots.
1 ESO - Unit 04 - Exercises 1.4.4. - Powers and Square Roots.
 
Rational function activities
Rational function activitiesRational function activities
Rational function activities
 
1. functions
1. functions1. functions
1. functions
 
AnsChap1.pdf
AnsChap1.pdfAnsChap1.pdf
AnsChap1.pdf
 
Modul 1 functions
Modul 1 functionsModul 1 functions
Modul 1 functions
 
SAT based planning for multiagent systems
SAT based planning for multiagent systemsSAT based planning for multiagent systems
SAT based planning for multiagent systems
 
Gen 170212161209 (1)
Gen 170212161209 (1)Gen 170212161209 (1)
Gen 170212161209 (1)
 
introduction to functions grade 11(General Math)
introduction to functions grade 11(General Math)introduction to functions grade 11(General Math)
introduction to functions grade 11(General Math)
 
Gen. math g11 introduction to functions
Gen. math g11  introduction to functionsGen. math g11  introduction to functions
Gen. math g11 introduction to functions
 
Operation on functions
Operation on functionsOperation on functions
Operation on functions
 
FUNCTION EX 1 PROBLEMS WITH SOLUTION UPTO JEE LEVEL
FUNCTION EX 1 PROBLEMS WITH SOLUTION UPTO JEE LEVELFUNCTION EX 1 PROBLEMS WITH SOLUTION UPTO JEE LEVEL
FUNCTION EX 1 PROBLEMS WITH SOLUTION UPTO JEE LEVEL
 
relations-function
relations-functionrelations-function
relations-function
 
Fungsi eksponen-dan-logaritma
Fungsi eksponen-dan-logaritmaFungsi eksponen-dan-logaritma
Fungsi eksponen-dan-logaritma
 
Ans Hw Lesson 8
Ans Hw Lesson 8Ans Hw Lesson 8
Ans Hw Lesson 8
 
Relations and Functions
Relations and FunctionsRelations and Functions
Relations and Functions
 
Probability QA 4
Probability QA 4Probability QA 4
Probability QA 4
 
AA Section 8-1
AA Section 8-1AA Section 8-1
AA Section 8-1
 
Key pat1 1-53
Key pat1 1-53Key pat1 1-53
Key pat1 1-53
 
Algebra 2 Section 5-2
Algebra 2 Section 5-2Algebra 2 Section 5-2
Algebra 2 Section 5-2
 

More from Ahmed Gamal

More from Ahmed Gamal (20)

Graduation book - BFRP
Graduation book - BFRPGraduation book - BFRP
Graduation book - BFRP
 
hti traininig 2018
hti traininig 2018hti traininig 2018
hti traininig 2018
 
Pert2 management
Pert2 managementPert2 management
Pert2 management
 
Pert management
Pert management Pert management
Pert management
 
Lob management
Lob managementLob management
Lob management
 
Lec 2 construction management
Lec 2 construction managementLec 2 construction management
Lec 2 construction management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Crash management
Crash managementCrash management
Crash management
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 
Cash flow
Cash flowCash flow
Cash flow
 
1- construction management
1-  construction management1-  construction management
1- construction management
 
تدريب 2 التجمع الخامس و نادي مدينتي
تدريب 2 التجمع الخامس و نادي مدينتيتدريب 2 التجمع الخامس و نادي مدينتي
تدريب 2 التجمع الخامس و نادي مدينتي
 
01 introduction and layout of steel (1)
01 introduction and layout of steel (1)01 introduction and layout of steel (1)
01 introduction and layout of steel (1)
 
الامن الصناعي
الامن الصناعيالامن الصناعي
الامن الصناعي
 
programming fortran 77 Slide02
programming fortran 77 Slide02programming fortran 77 Slide02
programming fortran 77 Slide02
 
programming fortran 77 Slide01
programming fortran 77 Slide01programming fortran 77 Slide01
programming fortran 77 Slide01
 
7 fatigue
7  fatigue7  fatigue
7 fatigue
 
5 hardness
5  hardness5  hardness
5 hardness
 
4 static shear
4  static shear4  static shear
4 static shear
 
3 bending test
3  bending test3  bending test
3 bending test
 

Recently uploaded

Recently uploaded (7)

Founder-Game Director Workshop (Session 1)
Founder-Game Director  Workshop (Session 1)Founder-Game Director  Workshop (Session 1)
Founder-Game Director Workshop (Session 1)
 
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docxModern Database Management 12th Global Edition by Hoffer solution manual.docx
Modern Database Management 12th Global Edition by Hoffer solution manual.docx
 
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
Oprah Winfrey: A Leader in Media, Philanthropy, and Empowerment | CIO Women M...
 
Create the recognition your teams deserve.pptx
Create the recognition your teams deserve.pptxCreate the recognition your teams deserve.pptx
Create the recognition your teams deserve.pptx
 
TCS AI for Business Study – Key Findings
TCS AI for Business Study – Key FindingsTCS AI for Business Study – Key Findings
TCS AI for Business Study – Key Findings
 
Project Management Professional (PMP)® from PMI
Project Management Professional (PMP)® from PMIProject Management Professional (PMP)® from PMI
Project Management Professional (PMP)® from PMI
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 

Resource management

  • 2. Resource in construction Manpower (labor), equipment, material, subcontractor(sc) Resource Leveling
  • 3. 1) Draw A.O.N Network 0 A 2 2 2 B 2 4 4 C 3 7 7 D 2 9 9 E 1 10 0 G 2 2 0 F 1 1 4 I 2 6 4 H 1 5 st Activity Resource day A 3 B 2 C 4 D 3 E 2 F 2 G 4 H 3 I 4
  • 4. Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 9 7 2 2 11 8 4 3 3 2 2) Draw Bar chart with resource distribution F.F F.F F.F F.F
  • 5. 3) Appling the Improvement Factor to non critical activity IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) A : Activity Name N : NO of free float days consumed R : No of resources days used by the activity 𝑹 𝒗 : sum number of resource in days that will be vacated when activity move 𝑹 𝒐 : sum number of resource in days that will be occupied when activity move 𝑵 𝒓 : smaller The No. of free float consumed Duration of the activity
  • 6. Activity I IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (I,1)= 4 ×(𝟏𝟏 − 𝟒 − 𝟒 × (𝟏)) = 12 IF (I,2)= 4 ×(𝟏𝟗 − 𝟕 − 𝟒 × (𝟐)) = 𝟏𝟔 IF (I,3)= 4 ×(19−𝟔 − 𝟒 × (𝟐)) = 𝟐𝟎 Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 9 7 2 2 11 8 4 3 3 2 Take the largest value of IF
  • 7. Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 9 7 2 2 7 4 4 7 7 2 Activity H IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (H,1)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 0 IF (H,2)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 𝟎 Take the largest value of IF
  • 8. Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 9 7 2 2 4 4 7 7 7 2 Activity G IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (G,1)= 4 ×(9−𝟐 − 𝟒 × (𝟏)) = 12 IF (G,2)= 4 ×(1𝟔 − 𝟒 − 𝟒 × (𝟐)) = 𝟏𝟔 Activity F IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (F,1)= 2 ×(9−𝟕 − 𝟐 × (𝟏)) = 0 IF (F,2)= 2 ×(9−𝟐 − 𝟐 × (𝟏)) = 𝟎 IF (F,3)= 2 ×(9−𝟐 − 𝟐 × (𝟏)) = 𝟏𝟎 So we decide to move G first
  • 9. Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 5 3 6 6 4 4 7 7 7 2 Activity F IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (F,1)= 2 ×(5−𝟑 − 𝟐 × (𝟏)) = 0 IF (F,2)= 2 ×(5−𝟔 − 𝟐 × (𝟏)) = −𝟔 IF (F,3)= 2 ×(5−𝟔 − 𝟐 × (𝟏)) = −𝟔
  • 10. Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 3 5 6 6 4 4 7 7 7 2 Activity G IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (G,1)= 4 ×(6−𝟓 − 𝟒 × (𝟏)) = -12 IF (G,2)= 4 ×(1𝟐 − 𝟖 − 𝟒 × (𝟐)) = −𝟏𝟔 Activity F IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (F,1)= 2 ×(5−𝟑 − 𝟐 × (𝟏)) = 0 4) Back Float Calculations:
  • 11. Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 5 3 6 6 4 4 7 7 7 2 Activity I IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (I,1)= 4 ×(𝟕 − 𝟕 − 𝟒 × (𝟏)) = -16 IF (I,2)= 4 ×(𝟏𝟒 − 𝟏𝟏 − 𝟒 × (𝟐)) = −𝟐𝟎 IF (I,3)= 4 ×(1𝟒 − 𝟖 − 𝟒 × (𝟐)) = −𝟖 Activity H IF (A,N)= R ×(𝑹 𝒗 − 𝑹 𝑶 − 𝑹 × (𝑵 𝒓)) IF (H,1)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 0 IF (H,2)= 3 ×(7−𝟒 − 𝟑 × (𝟏)) = 𝟎
  • 12. Final Bar chart : Act. 1 2 3 4 5 6 7 8 9 10 A 3 3 B 2 2 C 4 4 4 D 3 3 E 2 F 2 G 4 4 H 3 I 4 4 Resource day 5 3 6 6 7 4 4 7 7 2