1. Resource leveling involves analyzing resource usage and adjusting non-critical activities to reduce overallocation of resources. 2. The document describes calculating an Improvement Factor (IF) for non-critical activities to determine which activities can be moved to reduce resource usage. 3. The example applies the IF calculation to various activities in a project network to level resources, moving Activity G first to reduce the resource usage in period 5 from 9 to 5.