SlideShare a Scribd company logo
1 of 27
Badge#
The load for this task is GATE VALVE
Net weight of the load 3 TON X2200LBS = 6600LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 6600LBS ÷ 0.75 = 8800 LBS
Hitch capacity: 12550LBS X 0.75 = 9412LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
5/8" &
12550LBS
2 20FT 1
7/8"
13000LBS
2 2
2 2
LIFT PLAN (Task)
SAFETY EQUIPMENT
Hi vis VEST
SAFETY CONES
SIGN BOARD
RIGGING EQUIPMENT
WIRE ROPE SLING
SHACKLE
TAG LINE
Badge#
The load for this task is CONCREAT BLOCK
Net weight of the load 2 TON X2200LBS = 4400LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG BRIDLE HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400 LBS DIRECT FROM LOAD CHART
Hitch capacity: 4950 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950LBS
2 10FT 1
5/8"
6500LBS
2 2
2
2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINES
SIGN BOARD
Badge#
The load for this task is PIPE BENDLE
Net weight of the load 1.5 TON X2200LBS = 3300LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: DOUBLE WRAP TWO LEG CHOKER HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 3300LBS ÷ 0.75 = 4400 LBS
Hitch capacity: 4950LBS X 0.75 = 3712LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950LBS
2 15FT 1
5/8"
6500LBS
2 2
2 2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE SIGN BOARD
Badge#
The load for this task is BIG MOTOR
Net weight of the load 4 TON X2200LBS = 8800LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: FOUR LEG BRIDLE HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 8800 LBS DIRECT FROM LOAD CHART
Hitch capacity: 12550 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
5/8" &
12550LBS
4 15FT 1
7/8"
13000LBS
4 2
2
2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINES
SIGN BOARD
Badge#
The load for this task is VALVE DUMPER
Net weight of the load 2 TON X 2200 LBS =4400LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER WITH BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
1 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
3
2TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is FIVE ELBOW SPOOL
Net weight of the load 2.5 TON X 2200 LBS =5500LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
2 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
3
3TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
monitor
Badge#
The load for this task is HEAT EXCHANGER
Net weight of the load 2 TON X2200LBS = 4400LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS
Hitch capacity: 8000 LBS X 0.75 = 6000 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
2 15FT 1
3/4"
9500LBS
2 2
2 2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE SIGN BOARD
Badge#
The load for this task is HEAT EXCHANGER
Net weight of the load 2 TON X2200LBS = 4400LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: DOUBLE BASKET HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400LBS ÷ 2 = 2200 LBS
Hitch capacity: 4950 LBS X 2 = 9900 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950 LBS
2 25FT 1
2 2
2
TAG LINE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
SIGN BOARD
Badge#
The load for this task is SPOOL WITH MOTOR
Net weight of the load 2.5 TON X 2200 LBS =5500LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
2 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
3
3TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is EXCHANGER SPOOL
Net weight of the load 3 TON X 2200 LBS =6600LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER AND BALANCING CHIAN HOIST HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 6600LBS ÷ 0.75 = 8800 LBS
Hitch capacity: 12550 LBS X 0.75 = 9412 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
5/8" &
12550LBS
2 15FT 1
5/8" &
12550LBS
1 6FT 2
5/8" &
12550LBS
1 4FT 2
7/8" &
13000LBS
3
3TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is SPOOL
Net weight of the load 2.5 TON X 2200 LBS =5500LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
2 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
3
3TON 1
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is SPOOL
Net weight of the load 2 TON X 2200 LBS =4400LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER WITH BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
1 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
2
2TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is BIG MOTOR
Net weight of the load 3 TON X2200LBS = 6600LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: FOUR LEG BRIDLE HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 6600 LBS DIRECT FROM LOAD CHART
Hitch capacity: 8000 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000 LBS
4 15FT 1
3/4" &
9500 LBS
4 2
2 2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE SIGN BOARD
Badge#
The load for this task is SPOOL BENT
Net weight of the load 2112 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER WITH CHIAN HOIST HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 2112 LBS ÷ 0.75 = 2816 LBS
Hitch capacity: 4950 LBS X 0.75 = 3712LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950 LBS
1 15FT 1
3/8" &
4950 LBS
1 6FT 2
3/8" &
4950 LBS
1 4FT 2
5/8" &
6500 LBS
2
2TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is BENT ELBOW SPOOL
Net weight of the load 2.5 TON X 2200 LBS =5500LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
2 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
3
3TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is SMALL MOTOR
Net weight of the load 1.5 TON X2200LBS = 3300LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG BRIDLE HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 3300 LBS DIRECT FROM LOAD CHART
Hitch capacity: 4950 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950LBS
2 10FT 1
5/8"
6500LBS
2 2
2 2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE SIGN BOARD
Badge#
The load for this task is PUMP BLOCK
Net weight of the load 3 TON X 2200 LBS = 6600LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: DOUBLE BASKET HITCH AND BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 6600 LBS ÷ 2 = 3300 LBS
Hitch capacity: 4950 LBS X 2 = 9900 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950 LBS
2 25FT 1
3/8" &
4950 LBS
1 6FT 2
3/8" &
4950 LBS
1 6FT 2
3TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
WIRE ROPE SLING SIGN BOARD
CHAIN HOIST
TAG LINE
Badge#
The load for this task is MOTOR
Net weight of the load 2500KG X 2.2 = 5500 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOCKER WITH CHIAN HOIST HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 5500 LBS ÷ 0.75 = 7333 LBS
Hitch capacity: 8000 LBS X 0.75 = 6000 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000 LBS
1 15FT 1
1/2" &
8000 LBS
1 6FT 2
1/2" &
8000 LBS
1 4FT 2
5/8" &
6500 LBS
2 2
2TON 1
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
WIRE ROPE SLING TAG LINES
SHACKLE SIGN BOARD
CHAIN HOIST
Badge#
The load for this task is AC UNIT
Net weight of the load 6000 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: BOUBLE BASKET HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 6000 LBS ÷ 2 = 3000 LBS
Hitch capacity: 4950 LBS X 2 = 9900 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950LBS
2 30FT 1
8 2
2 2
SHAFNER SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE SIGN BOARD
Badge#
The load for this task is C SPOOL
Net weight of the load 2000KG X 2.2 = 4400 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS
Hitch capacity: 8000LBS X 0.75 = 6000LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
1/2" &
8000LBS
2 15FT 1
1/2" &
8000LBS
1 6FT 2
1/2" &
8000LBS
1 4FT 2
3/4" &
9500LBS
3
2 TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is PUMP COVER
Net weight of the load 2 TON X 2200 LBS = 4400 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: TWO LEG BRIDLE WITH BALANCING CHIAN HOIST HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 4400 LBS DIRECT FROM LOAD CAHRT
Hitch capacity: 4950 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950LBS
1 15FT 1
3/8" &
4950LBS
1 6FT 2
3/8" &
4950LBS
1 4FT 2
1-1/2" &
3400LBS
2 2
2 TON 1
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
WIRE ROPE SLING TAG LINES
SHACKLE SIGN BOARD
CHAIN HOIST
Badge#
The load for this task is PUMP SHAFT
Net weight of the load 3000 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: DOUBLE BASKET HITCH WITH CHIAN HOIST HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 3000 LBS ÷ 2 = 1500 LBS
Hitch capacity: 4950 LBS X 2 = 9900 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
2" &
5550 LBS
1 20FT 1
2" &
5550 LBS
2 6FT 2
2TON 1 2
2
WEB SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WEB SLING Hi vis VEST
CHAIN HOIST SIGN BOARD
TAG LINE
Badge#
The load for this task is PUMP SHAFT
Net weight of the load 3000 LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: DOUBLE BASKET HITCH WITH CHIAN HOIST HITCH
Approximate sling angle:______ 60°
Hitch formula if applicable: 3000 LBS ÷ 2 = 1500 LBS
Hitch capacity: 4950 LBS X 2 = 9900 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
2" &
5550 LBS
2 2MTR 1
3/8" &
4950 LBS
1 10FT 2
3/8" &
4950 LBS
1 6FT 2
5/8" &
6500 LBS
2
3TON 1
2
WIRE ROPE SLING SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WEB SLING Hi vis VEST
TAG LINE
WIRE ROPE SLING SIGN BOARD
SHACKLE
CHAIN HOIST
Badge#
The load for this task is ELECTRICAL MOTOR
Net weight of the load 1.5 TON X2200LBS = 3300LBS
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected: SAFE
Crane serial number xxxx Saudi Aramco sticker number____ xxxx
If unsafe, action to be taken:___ N/A
Hitch arrangement to be taken: SINGLE VERTICAL HITCH
Approximate sling angle:______ 90°
Hitch formula if applicable: 3300 LBS DIRECT FROM LOAD CHART
Hitch capacity: 4950 LBS
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
3/8" &
4950 LBS
1 10FT 1
1/2"
4000 LBS
1 2
2 2
SHACKLE SAFETY CONES
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
WIRE ROPE SLING Hi vis VEST
TAG LINE SIGN BOARD
Badge#
The load for this task is
Net weight of the load
The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor.
Complete the following:
Site inspected:
Crane serial number Saudi Aramco sticker number
If unsafe, action to be taken:
Hitch arrangement to be taken:
Approximate sling angle:
Hitch formula if applicable:
Hitch capacity:
Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor
SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED
LIFT PLAN (Task)
RIGGING EQUIPMENT SAFETY EQUIPMENT
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Rajput

More Related Content

Similar to Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Rajput

Lifting & procedure
Lifting & procedureLifting & procedure
Lifting & procedurePavan Noel
 
Class note for btech students lce 463 pavement structure-soil interaction
Class note for btech students lce 463 pavement structure-soil interactionClass note for btech students lce 463 pavement structure-soil interaction
Class note for btech students lce 463 pavement structure-soil interactionabhay mishra
 
Aircraft design lab report converted
Aircraft design lab report convertedAircraft design lab report converted
Aircraft design lab report convertedPramod Yadav
 
Code of safe_practice
Code of safe_practiceCode of safe_practice
Code of safe_practiceRabah HELAL
 
FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480PRIYANSHU KUMAR
 
AST- CV Crane Work Safe.ppt
AST- CV Crane Work Safe.pptAST- CV Crane Work Safe.ppt
AST- CV Crane Work Safe.pptkhoirilanwar17
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdfdinesh622857
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptxAizazFarhat3
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10vtsiri
 
Sop 6.6 kv switchboard edited
Sop 6.6 kv switchboard editedSop 6.6 kv switchboard edited
Sop 6.6 kv switchboard editedprabagaran16
 
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined PilecapPile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined Pilecapazhar ahmad
 
Determining equipment design parameters for overhead conveyors
Determining equipment design parameters for overhead conveyorsDetermining equipment design parameters for overhead conveyors
Determining equipment design parameters for overhead conveyorsphysics101
 
Boom lift training
Boom lift trainingBoom lift training
Boom lift trainingsheila bert
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha classBill Brown
 
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdfFLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdfssuser1edd921
 

Similar to Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Rajput (20)

Lifting & procedure
Lifting & procedureLifting & procedure
Lifting & procedure
 
Class note for btech students lce 463 pavement structure-soil interaction
Class note for btech students lce 463 pavement structure-soil interactionClass note for btech students lce 463 pavement structure-soil interaction
Class note for btech students lce 463 pavement structure-soil interaction
 
Aircraft design lab report converted
Aircraft design lab report convertedAircraft design lab report converted
Aircraft design lab report converted
 
Code of safe_practice
Code of safe_practiceCode of safe_practice
Code of safe_practice
 
FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480FWD report by priyanshu kumar ,960868480
FWD report by priyanshu kumar ,960868480
 
2017 CRW: Below the Hook Lifting – Slings and Hardware
2017 CRW: Below the Hook Lifting – Slings and Hardware2017 CRW: Below the Hook Lifting – Slings and Hardware
2017 CRW: Below the Hook Lifting – Slings and Hardware
 
AST- CV Crane Work Safe.ppt
AST- CV Crane Work Safe.pptAST- CV Crane Work Safe.ppt
AST- CV Crane Work Safe.ppt
 
Campion_Crane-Safety.pdf
Campion_Crane-Safety.pdfCampion_Crane-Safety.pdf
Campion_Crane-Safety.pdf
 
Pile load test
Pile load testPile load test
Pile load test
 
Quality Control Operator Training &.pptx
Quality Control Operator Training &.pptxQuality Control Operator Training &.pptx
Quality Control Operator Training &.pptx
 
Steam drum lifting
Steam drum liftingSteam drum lifting
Steam drum lifting
 
Const cranes 9 3 10
Const cranes 9 3 10Const cranes 9 3 10
Const cranes 9 3 10
 
Sop 6.6 kv switchboard edited
Sop 6.6 kv switchboard editedSop 6.6 kv switchboard edited
Sop 6.6 kv switchboard edited
 
Testtadano60ton
Testtadano60tonTesttadano60ton
Testtadano60ton
 
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined PilecapPile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
 
Determining equipment design parameters for overhead conveyors
Determining equipment design parameters for overhead conveyorsDetermining equipment design parameters for overhead conveyors
Determining equipment design parameters for overhead conveyors
 
Boom lift training
Boom lift trainingBoom lift training
Boom lift training
 
1910.179 osha class
1910.179 osha class1910.179 osha class
1910.179 osha class
 
Lifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptxLifting & Rigging Safety.pptx
Lifting & Rigging Safety.pptx
 
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdfFLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
FLIGHT INSPECTION of CNS FACILITIES [Compatibility Mode].pdf
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputGaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputGaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputGaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputGaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputGaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputGaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputGaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputGaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputGaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputGaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputGaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputGaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
Forklift Safety | Gaurav Singh Rajput
Forklift Safety | Gaurav Singh RajputForklift Safety | Gaurav Singh Rajput
Forklift Safety | Gaurav Singh RajputGaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 
Forklift Safety | Gaurav Singh Rajput
Forklift Safety | Gaurav Singh RajputForklift Safety | Gaurav Singh Rajput
Forklift Safety | Gaurav Singh Rajput
 

Recently uploaded

scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptxrouholahahmadi9876
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfsumitt6_25730773
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 

Recently uploaded (20)

scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 

Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Rajput

  • 1. Badge# The load for this task is GATE VALVE Net weight of the load 3 TON X2200LBS = 6600LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 6600LBS ÷ 0.75 = 8800 LBS Hitch capacity: 12550LBS X 0.75 = 9412LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 5/8" & 12550LBS 2 20FT 1 7/8" 13000LBS 2 2 2 2 LIFT PLAN (Task) SAFETY EQUIPMENT Hi vis VEST SAFETY CONES SIGN BOARD RIGGING EQUIPMENT WIRE ROPE SLING SHACKLE TAG LINE
  • 2. Badge# The load for this task is CONCREAT BLOCK Net weight of the load 2 TON X2200LBS = 4400LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG BRIDLE HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 4400 LBS DIRECT FROM LOAD CHART Hitch capacity: 4950 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950LBS 2 10FT 1 5/8" 6500LBS 2 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINES SIGN BOARD
  • 3. Badge# The load for this task is PIPE BENDLE Net weight of the load 1.5 TON X2200LBS = 3300LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: DOUBLE WRAP TWO LEG CHOKER HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 3300LBS ÷ 0.75 = 4400 LBS Hitch capacity: 4950LBS X 0.75 = 3712LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950LBS 2 15FT 1 5/8" 6500LBS 2 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE SIGN BOARD
  • 4. Badge# The load for this task is BIG MOTOR Net weight of the load 4 TON X2200LBS = 8800LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: FOUR LEG BRIDLE HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 8800 LBS DIRECT FROM LOAD CHART Hitch capacity: 12550 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 5/8" & 12550LBS 4 15FT 1 7/8" 13000LBS 4 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINES SIGN BOARD
  • 5. Badge# The load for this task is VALVE DUMPER Net weight of the load 2 TON X 2200 LBS =4400LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER WITH BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 1 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 3 2TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 6. Badge# The load for this task is FIVE ELBOW SPOOL Net weight of the load 2.5 TON X 2200 LBS =5500LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 2 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 3 3TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 8. Badge# The load for this task is HEAT EXCHANGER Net weight of the load 2 TON X2200LBS = 4400LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS Hitch capacity: 8000 LBS X 0.75 = 6000 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 2 15FT 1 3/4" 9500LBS 2 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE SIGN BOARD
  • 9. Badge# The load for this task is HEAT EXCHANGER Net weight of the load 2 TON X2200LBS = 4400LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: DOUBLE BASKET HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 4400LBS ÷ 2 = 2200 LBS Hitch capacity: 4950 LBS X 2 = 9900 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950 LBS 2 25FT 1 2 2 2 TAG LINE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST SIGN BOARD
  • 10. Badge# The load for this task is SPOOL WITH MOTOR Net weight of the load 2.5 TON X 2200 LBS =5500LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 2 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 3 3TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 11. Badge# The load for this task is EXCHANGER SPOOL Net weight of the load 3 TON X 2200 LBS =6600LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER AND BALANCING CHIAN HOIST HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 6600LBS ÷ 0.75 = 8800 LBS Hitch capacity: 12550 LBS X 0.75 = 9412 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 5/8" & 12550LBS 2 15FT 1 5/8" & 12550LBS 1 6FT 2 5/8" & 12550LBS 1 4FT 2 7/8" & 13000LBS 3 3TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 12. Badge# The load for this task is SPOOL Net weight of the load 2.5 TON X 2200 LBS =5500LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 2 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 3 3TON 1 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 13. Badge# The load for this task is SPOOL Net weight of the load 2 TON X 2200 LBS =4400LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER WITH BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 1 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 2 2TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 14. Badge# The load for this task is BIG MOTOR Net weight of the load 3 TON X2200LBS = 6600LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: FOUR LEG BRIDLE HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 6600 LBS DIRECT FROM LOAD CHART Hitch capacity: 8000 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000 LBS 4 15FT 1 3/4" & 9500 LBS 4 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE SIGN BOARD
  • 15. Badge# The load for this task is SPOOL BENT Net weight of the load 2112 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER WITH CHIAN HOIST HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 2112 LBS ÷ 0.75 = 2816 LBS Hitch capacity: 4950 LBS X 0.75 = 3712LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950 LBS 1 15FT 1 3/8" & 4950 LBS 1 6FT 2 3/8" & 4950 LBS 1 4FT 2 5/8" & 6500 LBS 2 2TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 16. Badge# The load for this task is BENT ELBOW SPOOL Net weight of the load 2.5 TON X 2200 LBS =5500LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 5500LBS ÷ 0.75 = 7333 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 2 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 3 3TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 17. Badge# The load for this task is SMALL MOTOR Net weight of the load 1.5 TON X2200LBS = 3300LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG BRIDLE HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 3300 LBS DIRECT FROM LOAD CHART Hitch capacity: 4950 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950LBS 2 10FT 1 5/8" 6500LBS 2 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE SIGN BOARD
  • 18. Badge# The load for this task is PUMP BLOCK Net weight of the load 3 TON X 2200 LBS = 6600LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: DOUBLE BASKET HITCH AND BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 6600 LBS ÷ 2 = 3300 LBS Hitch capacity: 4950 LBS X 2 = 9900 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950 LBS 2 25FT 1 3/8" & 4950 LBS 1 6FT 2 3/8" & 4950 LBS 1 6FT 2 3TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST WIRE ROPE SLING SIGN BOARD CHAIN HOIST TAG LINE
  • 19. Badge# The load for this task is MOTOR Net weight of the load 2500KG X 2.2 = 5500 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOCKER WITH CHIAN HOIST HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 5500 LBS ÷ 0.75 = 7333 LBS Hitch capacity: 8000 LBS X 0.75 = 6000 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000 LBS 1 15FT 1 1/2" & 8000 LBS 1 6FT 2 1/2" & 8000 LBS 1 4FT 2 5/8" & 6500 LBS 2 2 2TON 1 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST WIRE ROPE SLING TAG LINES SHACKLE SIGN BOARD CHAIN HOIST
  • 20. Badge# The load for this task is AC UNIT Net weight of the load 6000 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: BOUBLE BASKET HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 6000 LBS ÷ 2 = 3000 LBS Hitch capacity: 4950 LBS X 2 = 9900 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950LBS 2 30FT 1 8 2 2 2 SHAFNER SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE SIGN BOARD
  • 21. Badge# The load for this task is C SPOOL Net weight of the load 2000KG X 2.2 = 4400 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG CHOKER HITCH AND BALANCING CHIAN HOIST Approximate sling angle:______ 60° Hitch formula if applicable: 4400LBS ÷ 0.75 = 5866 LBS Hitch capacity: 8000LBS X 0.75 = 6000LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 1/2" & 8000LBS 2 15FT 1 1/2" & 8000LBS 1 6FT 2 1/2" & 8000LBS 1 4FT 2 3/4" & 9500LBS 3 2 TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 22. Badge# The load for this task is PUMP COVER Net weight of the load 2 TON X 2200 LBS = 4400 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: TWO LEG BRIDLE WITH BALANCING CHIAN HOIST HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 4400 LBS DIRECT FROM LOAD CAHRT Hitch capacity: 4950 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950LBS 1 15FT 1 3/8" & 4950LBS 1 6FT 2 3/8" & 4950LBS 1 4FT 2 1-1/2" & 3400LBS 2 2 2 TON 1 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST WIRE ROPE SLING TAG LINES SHACKLE SIGN BOARD CHAIN HOIST
  • 23. Badge# The load for this task is PUMP SHAFT Net weight of the load 3000 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: DOUBLE BASKET HITCH WITH CHIAN HOIST HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 3000 LBS ÷ 2 = 1500 LBS Hitch capacity: 4950 LBS X 2 = 9900 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 2" & 5550 LBS 1 20FT 1 2" & 5550 LBS 2 6FT 2 2TON 1 2 2 WEB SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WEB SLING Hi vis VEST CHAIN HOIST SIGN BOARD TAG LINE
  • 24. Badge# The load for this task is PUMP SHAFT Net weight of the load 3000 LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: DOUBLE BASKET HITCH WITH CHIAN HOIST HITCH Approximate sling angle:______ 60° Hitch formula if applicable: 3000 LBS ÷ 2 = 1500 LBS Hitch capacity: 4950 LBS X 2 = 9900 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 2" & 5550 LBS 2 2MTR 1 3/8" & 4950 LBS 1 10FT 2 3/8" & 4950 LBS 1 6FT 2 5/8" & 6500 LBS 2 3TON 1 2 WIRE ROPE SLING SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WEB SLING Hi vis VEST TAG LINE WIRE ROPE SLING SIGN BOARD SHACKLE CHAIN HOIST
  • 25. Badge# The load for this task is ELECTRICAL MOTOR Net weight of the load 1.5 TON X2200LBS = 3300LBS The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: SAFE Crane serial number xxxx Saudi Aramco sticker number____ xxxx If unsafe, action to be taken:___ N/A Hitch arrangement to be taken: SINGLE VERTICAL HITCH Approximate sling angle:______ 90° Hitch formula if applicable: 3300 LBS DIRECT FROM LOAD CHART Hitch capacity: 4950 LBS Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED 3/8" & 4950 LBS 1 10FT 1 1/2" 4000 LBS 1 2 2 2 SHACKLE SAFETY CONES LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT WIRE ROPE SLING Hi vis VEST TAG LINE SIGN BOARD
  • 26. Badge# The load for this task is Net weight of the load The load must be lifted in a balanced condition and placed at the loaction identified by the test monitor. Complete the following: Site inspected: Crane serial number Saudi Aramco sticker number If unsafe, action to be taken: Hitch arrangement to be taken: Approximate sling angle: Hitch formula if applicable: Hitch capacity: Use the table to list the equipment needed to lift and move the load to the location identified by the test monitor SIZE & CAPACITY QTY LEN INSPECTED QTY INSPECTED LIFT PLAN (Task) RIGGING EQUIPMENT SAFETY EQUIPMENT