Leiden Institute of Advanced Computer Science                           Dates

Feb. 1               14:45 – 17:30           Introduction, Project Description
Feb. 2               13:45 – 16:30           STEP WISE Approach to Project Planning
Feb. 9               13:45 – 16:30           Selecting an Appropriate Software Dev.
                                             Approach
Feb. 15              14:45 – 17:30           Activity Planning and Resource Allocation
Feb. 16              13:45 – 16:30           Software Effort Estimation
Feb. 22              14:45 – 17:30           Risk management, project escalation
Feb. 23              13:45 – 16:30           Project monitoring and control
Mar. 1               14:45 – 17:00           Exam
Mar. 2               13:45 – 16:30           Software Quality Assurance
Mar. 8               14:45 – 17:30           Managing People; Contract Management
Mar. 9               13:45 – 16:30           Various
Mar. 15              14:45 – 17:30           Trade Fair


                                                                                      3
Leiden Institute of Advanced Computer Science




ICT Project Management „runaways“ …

  !   Standish „Chaos“ Report
    !    1994:
          •  16% successful
          •  31% cancelled
          •  53% challenged
    !    2000:
          •  34% successful
          •  15% cancelled
          •  51% challenged



                                                      4
Leiden Institute of Advanced Computer Science




Project Management and Success
   !   Technical Issues
       !    Hardware / software / telecommunications systems don‘t work
       !    Frequent failure / errors in operation

   !   Economic Issues
       !    Time or budget overrun
       !    Low / no ROI („productivity paradox“)

   !   Organizational (implementation) Issues
       !    Resulting system fails to achieve desired benefit
       !    Users reject system




                                                                5
Leiden Institute of Advanced Computer Science




Course Content
   !   What is project management ?
        
   !   Student project: Save Energy
        
   !   Planning and revising projects
        
   !   Project lifecycles
        
   !   Estimating effort: size and productivity models
        
   !   Risk management and project escalation
        
   !   Controlling projects, including earned value analysis
        
   !   Managing project and process quality
        
   !   Managing people and organizing teams: motivation and
        
       capability
   !   Contract management



                                                           6
Leiden Institute of Advanced Computer Science



Course Structure
   !   10 interactive lectures:
       !    45 min teaching – 15 min break
       !    45 min teaching – 15 min break
       !    In-class assignments (20 – 40 min) + student presentations
       !    Case studies

   !   Written exam (closed book, Mar. 1)
   !   Hands-on development project
       !    Save Energy application ideas
       !    Project plans, reports
       !    Final trade fair (Mar 15, 14:45 – 17:30)




                                                           7
Leiden Institute of Advanced Computer Science




Grade Composition

   !   15% project proposal (‚bid‘)                        [group]
   !   25% detailed project plan                           [group]
   !   5% Deutsche Bank case                               [group]
   !   5% reflection paper on group project
           [individual]      management issues
   !   5% in-class participation                           [individual]
   !   25% written exam                                    [individual]
   !   20% trade-fair – project presentation               [group]




                                                       8
Leiden Institute of Advanced Computer Science




Required Literature
   !   Bob Hughes, Mike Cotterell: Software
       Project Management, 3e or 4e, McGraw-
       Hill ISBN 007709834
   !   Blackboard: readings and assignments




                                                     9
Leiden Institute of Advanced Computer Science




What is a Project ?                               1.  Temporary
                                                  2.  Unique Products, Services, or Results
                                                  3.  Progressive Elaboration
    !   A definition
       !    „A specific design or plan“

    !   Key elements
       !    Non-routine
       !    Specific objectives
       !    Planned
       !    Predetermined time span
       !    Constrained resources
       !    Work carried out for a third party
       !    Work involves several specializations or phases
       !    Size and complexity



                                                                      10
Leiden Institute of Advanced Computer Science




Typical Project Cost and Staffing




                                                      11
Leiden Institute of Advanced Computer Science




Stakeholder‘s Influence over Time

       Influence of stakeholders




        Cost of changes
                                                     Time



                                                            12
Leiden Institute of Advanced Computer Science




ICT Project Management
  !   Part art, part science
  !   Activities have duration, required resources
      and sequence (path)
  !   Critical path: Link of activities where delay
      causes delay in entire project !




                                                     13
Leiden Institute of Advanced Computer Science




ICT Project Management: Two Exercises
   !   Design a project plan for
        !    Organizing a party next weekend

  Small birthday party …                              Vienna opera ball




                                                       14
Leiden Institute of Advanced Computer Science




Software Engineering is more Difficult !
   !   Due to …
       !    Complexity
       !    Conformity (with human requirements)
       !    Changeability
       !    Invisibility


                               It therefore needs specialized management
                               techniques to deal with it !



                                                          15
Leiden Institute of Advanced Computer Science




Common Activities
                                    Is it worth
                                      doing?        How do we do
   Feasibility Study                                    it ?


                                      Planning                     Do it !


                                                    Execute Project



   !   Feasibility study – decide if project is worth
       doing
   !   Plan how you are going to do it, then do it.
                                                          16
Leiden Institute of Advanced Computer Science



Execute Project (Hughes-Cotterrell Stages)
 Requirements
  Gathering

         Specification


                             Design


                                                Code


                                                       Testing


                                                                      Implement
                                                                 17
Leiden Institute of Advanced Computer Science



Execute Project
    !   Functional Requirements
       !    What the system is to do
       !    Systems analysis aims to provide these
    !   Quality Requirements
       !    Other attributes of the system, e.g., response time,
            usability, reliability
    !   Resource / time Requirements
       !    Cost
       !    Time
    !   Trade-offs between the different factors
                                                            18
Leiden Institute of Advanced Computer Science




Managerial Issues
    !   Management may involve:
       !    Planning                 - deciding what is to be done
       !    Organizing               - making arrangements
       !    Staffing                 - selecting the right people
       !    Directing                - giving instructions
       !    Monitoring               - checking on progress
       !    Controlling              - taking action to remedy hold-ups
       !    Innovating               - coming up with new solutions
       !    Representing             - liaising with users

                                                                     19
Leiden Institute of Advanced Computer Science




Managerial Issues
    !   Internal stakeholders may be:
       !    In the project team
       !    Outside the team but in the organization
    !   External stakeholders may be:
       !    Customers or users affected by the system
       !    Contractors
    !   There will be different types of users with
        different interests
    !   Need for good communication !

                                                        20
Leiden Institute of Advanced Computer Science




Objectives
    !   Different stakeholders will have different
        objectives
       !    Need for agreed objectives
    !   Need for an identifyable project authority
       !    To set, monitor and modify objectives
       !    Can contain user, development and management
            representatives
    !   Objectives
       !    Can be informally expressed as: „In order for the
            project to be a success, the project must …“
                                                           21
Leiden Institute of Advanced Computer Science




Objectives (cont‘d)
    !   Objectives must be:
        !    Concrete
        !    Have measure of success
    !   Objectives can be:
        !    Broken down into sub-objectives or goals
        !    Can be informally expressed as „in order to
             achieve A, we must achieve B, C, D, etc.“
        !    Identifying sub-objectives involves considering the
             „how“ as well as the „what“


                                                            22
Leiden Institute of Advanced Computer Science




Problems - I
    !   Project Manager‘s point of view:
       !    Poor estimates and plans
       !    Lack of quality standards and measures
       !    Lack of guidance about making organizational
            decisions
       !    Lack of techniques to make progress visible
       !    Poor role definition – who does what ?
       !    Incorrect success criteria



                                                           23
Leiden Institute of Advanced Computer Science




Problems - II
    !   Staff‘s point of view:
         !   Inadequate specification of work
         !   Management ignorance of IT
         !   Lack of knowledge and application area
         !   Lack of standards
         !   Lack of up-to-date documentation
         !   Preceding activities not completed on time
         !   Lack of communication between users and technicians
         !   Lack of communication leading to duplication of work
         !   Lack of commitment (especially when tied to one person)
         !   Narrow scope of technical expertise
         !   Changing statutory requirements
         !   Changing software environment
         !   Deadline pressure
         !   Lack of quality control
         !   Remote management
         !   Lack of training
         !   ...
                                                                       24
Leiden Institute of Advanced Computer Science




Examples
   !   German toll collect system (2 years late, 2 billion €).
   !   US IRS was to abandon tax system modernization
       programme after having spend $4 billion.
   !   State of CA spent $1 billion on non-functional welfare
       database system.
   !   500 million € UK air traffic control system 2 years
       behind schedule.
   ! …
   !   All government ? Many industry examples as well.



                                                          25
Leiden Institute of Advanced Computer Science



Other Aspects I
    !   Setting Objectives
       !    Project authority
       !    Project board
       !    Sub-objectives and goals
       !    Measures of effectiveness
             •  Predictive measures (while constructing the system)
             •  Performance measures (operational system)
    !   Stakeholders
       !    Internal to project team
       !    External, but within same organization
       !    External to project team and organization
                                                                      26
Leiden Institute of Advanced Computer Science



Other Aspects II
    !   Business Case
       !    Justification for project
       !    E.g., cost-benefit analysis
    !   Requirement Specification
       !    Functional: Systems Analysis and Design
       !    Quality: Response time, reliability, …
       !    Resources: Time and cost




                                                      27
Leiden Institute of Advanced Computer Science



Feasibility Study: Contents
    !   Introduction: What this document is
    !   Description of current situation
    !   Problem description
        !    Boundaries
        !    Scope
    !   Proposed development
        !    Business and financial aspects
        !    Technical aspects
        !    Organizational aspects
    !   Estimated costs
        !    Development costs
        !    Operational costs
    !   Envisaged benefits
    !   Recommendation
                                                      28
Leiden Institute of Advanced Computer Science


Project Plan: Contents
!       Introduction
!       Background, incl. Reference to the business case.
!       Project objectives
!       Constraints
!       Project products (deliverable and intermediate)
!       Methods
!       Activities to be carried out
!       Resources to be used
!       Risks
!       Management, including
        !    Organizational responsibilities
        !    Quality management
        !    Configuration management
!   Success factors
                                                             29
Leiden Institute of Advanced Computer Science



Project Plan: Structure
    !   Introduction
    !   Management Summary
    !   Goals and objectives
              !    Business goals
              !    Benefits
              !    Objectives
    !       Scope, Key deliverables, Prioritization
    !       Organization, responsibilities, resources
    !       Risks, Risk Containment
    !       Other Issues


                                                            30
Leiden Institute of Advanced Computer Science



The System‘s Development Life Cycle
                                                     6a. Final assembly
                               5. Test                  and delivery
              4. Implemen-
                  tation

                                         7. Correct,
                                          Maintain
       3. System
        Design                                                                 Functional
                                                                                Release



          2. Systems                                      6b. Final assembly
           Analysis                                          and delivery
                              1. Pre-study
                                                             Correction
                                                              Release

                                                                                        31
Leiden Institute of Advanced Computer Science



Project Management and Success
   !   Traditionally: trace production of „milestone“ documents (functional
       specs = 14%, logical design = 30%, …)
   !   But: cost will migrate out of any activity that is measured more
       carefully than its neighboring activities
   !   Escalating committment to failure


                                                                                         % Completion


                                                                  120
                                          Percentage Completion   100

     Law of diminishing                                            80
                                                                   60                                           % Completion

          returns                                                  40
                                                                   20
                                                                    0
                                                                        1   2   3   4    5     6   7    8   9
                                                                                        Time




                                                                                                   32
Leiden Institute of Advanced Computer Science


  Law of diminishing (marginal) returns
            !   When one of the factors of production is held fixed in supply,
                successive additions of the other factors will lead to an increase in
                returns up to a point.
            !   Beyond this point, returns will diminish.
            !   Example: Agricultural production (seed amount – growth
                production, no. of workers – total labor and harvesting done).

                                                                               Diminishing returns
                                                                         140
No. Of    Total physical   Marginal physical   Average Physical
workers   product (TPP)     product (MPP)       Product (APP)            120
  1            10                 10                 10                  100                                               Total physical product
                                                                          80                                               (TPP)
  2            30                 20                 15
                                                                                                                           Marginal physical
                                                                  Tons

  3            90                 60                 30                   60
                                                                                                                           product (MPP)
                                                                          40
  4            120                30                 30                                                                    Average Physical
                                                                          20                                               Product (APP)
  5            130                10                 26
                                                                           0
  6            120               -10                 20
                                                                         -20 0   1   2      3     4       5        6   7

                                                                                         No. of Workers




                                                                                                              33
Leiden Institute of Advanced Computer Science




Prioritizing and Managing Expectations
                                                            Processing in
    Development                                                                 Customer
                       Screening        Prioritization      Development
    Request Entry                                                               Feedback
                                                         (product planning)

                                       Selection of
                                       most relevant
                    Reduction of:      needs
                    •  unclear
                    •  doubles
      100 dev.      •  curr. release
     requests       •  next release        - 60%
     logged in      •  out of scope                                      X selected as planning input
    the system
                                                                         Y denied

                        - 30%                                            Z input for next year planning
                                         archived         Transfer to
                                                          next year‘s
                                                             cycle


                                                                         34
Leiden Institute of Advanced Computer Science




            Your Project: Save Energy



            Demonstrator of innovative application that
            stimulates to save energy
Leiden Institute of Advanced Computer Science




Save Energy

  !   EU project on user behaviour transformation
      by empowerment of the users with ICT

                                                      5 Pilots:
                                                      -Lisbon
                                                      -Leiden
                                                      -Manchester
                                                      -Helsinki
                                                      -Lulea
Leiden Institute of Advanced Computer Science



                     Leiden Employee Behaviour

                !    Electricity, switching on/off:
                      !    PC, monitor
                      !    Lighting
                      !    Miscellaneous equipment


                !    Heating:
                      !    Setpoint for room temperature
                      !    Turn heater on/off
                      !    Close/open windows
Leiden Institute of Advanced Computer Science




Leiden Pilot
Leiden Institute of Advanced Computer Science




Current Initiatives in Leiden Pilot
   !   Weekly Energy Emails


                                            •  Real time energy displays
Leiden Institute of Advanced Computer Science




Assignment

  !   Develop a demonstrator that runs on a pc,
      smart phone or presentation screen that
      displays the current energy consumption of
      individuals and stimulates users to save
      energy.

  !   Present in trade-fair setting
Leiden Institute of Advanced Computer Science




Remarks:

  !   Keep in mind the audience (Municipality
      employees)

  !   Real data is available (SOAP webservice)
    SOAP, originally defined as Simple Object Access Protocol, is a protocol specification for
    exchanging structured information in the implementation of web services in computer
    networks.




  !   Think of what motivates to save energy!
Leiden Institute of Advanced Computer Science




Save Energy Project
    !   Meet as Team
       !    Actually, you will have many meetings …
       !    Teamwork is of critical importance
    !   Project proposal (bid) due by
       !    February 18, midnight

         February 18, midnight         Assignment 1:
                                       Project proposal ( bid )
         February 25, midnight         Assignment 2:
                                       Project Plan including functional specification
         March 1, midnight             Assignment 3:
                                       Deutsche Bank case, 5 ppt slides
         March 1 (14:45 – 17:00)       Exam
         March 15 (14:45 – 17:30)      Trade fair
         March 16, midnight            Assignment 4:
                                       Personal reflection paper on project management




                                                                                         42

SDPM - Lecture 1 - Introduction

  • 1.
    Leiden Institute ofAdvanced Computer Science Introduction System‘s Development and Project Management Prof. Dr. Thomas Bäck 1
  • 2.
    Leiden Institute ofAdvanced Computer Science Introduction !   System‘s Development and Project Management !   Prof. dr. Thomas Bäck, Natural Computing !   Room 169, Tel. 7108, baeck@ liacs.nl !   Also – Company Experience 2
  • 3.
    Leiden Institute ofAdvanced Computer Science Dates Feb. 1 14:45 – 17:30 Introduction, Project Description Feb. 2 13:45 – 16:30 STEP WISE Approach to Project Planning Feb. 9 13:45 – 16:30 Selecting an Appropriate Software Dev. Approach Feb. 15 14:45 – 17:30 Activity Planning and Resource Allocation Feb. 16 13:45 – 16:30 Software Effort Estimation Feb. 22 14:45 – 17:30 Risk management, project escalation Feb. 23 13:45 – 16:30 Project monitoring and control Mar. 1 14:45 – 17:00 Exam Mar. 2 13:45 – 16:30 Software Quality Assurance Mar. 8 14:45 – 17:30 Managing People; Contract Management Mar. 9 13:45 – 16:30 Various Mar. 15 14:45 – 17:30 Trade Fair 3
  • 4.
    Leiden Institute ofAdvanced Computer Science ICT Project Management „runaways“ … !   Standish „Chaos“ Report !  1994: •  16% successful •  31% cancelled •  53% challenged !  2000: •  34% successful •  15% cancelled •  51% challenged 4
  • 5.
    Leiden Institute ofAdvanced Computer Science Project Management and Success !   Technical Issues !  Hardware / software / telecommunications systems don‘t work !  Frequent failure / errors in operation !   Economic Issues !  Time or budget overrun !  Low / no ROI („productivity paradox“) !   Organizational (implementation) Issues !  Resulting system fails to achieve desired benefit !  Users reject system 5
  • 6.
    Leiden Institute ofAdvanced Computer Science Course Content ! What is project management ?   ! Student project: Save Energy   ! Planning and revising projects   ! Project lifecycles   ! Estimating effort: size and productivity models   ! Risk management and project escalation   ! Controlling projects, including earned value analysis   ! Managing project and process quality   ! Managing people and organizing teams: motivation and   capability !   Contract management 6
  • 7.
    Leiden Institute ofAdvanced Computer Science Course Structure !   10 interactive lectures: !  45 min teaching – 15 min break !  45 min teaching – 15 min break !  In-class assignments (20 – 40 min) + student presentations !  Case studies !   Written exam (closed book, Mar. 1) !   Hands-on development project !  Save Energy application ideas !  Project plans, reports !  Final trade fair (Mar 15, 14:45 – 17:30) 7
  • 8.
    Leiden Institute ofAdvanced Computer Science Grade Composition !   15% project proposal (‚bid‘) [group] !   25% detailed project plan [group] !   5% Deutsche Bank case [group] !   5% reflection paper on group project [individual] management issues !   5% in-class participation [individual] !   25% written exam [individual] !   20% trade-fair – project presentation [group] 8
  • 9.
    Leiden Institute ofAdvanced Computer Science Required Literature !   Bob Hughes, Mike Cotterell: Software Project Management, 3e or 4e, McGraw- Hill ISBN 007709834 !   Blackboard: readings and assignments 9
  • 10.
    Leiden Institute ofAdvanced Computer Science What is a Project ? 1.  Temporary 2.  Unique Products, Services, or Results 3.  Progressive Elaboration !   A definition !  „A specific design or plan“ !   Key elements !  Non-routine !  Specific objectives !  Planned !  Predetermined time span !  Constrained resources !  Work carried out for a third party !  Work involves several specializations or phases !  Size and complexity 10
  • 11.
    Leiden Institute ofAdvanced Computer Science Typical Project Cost and Staffing 11
  • 12.
    Leiden Institute ofAdvanced Computer Science Stakeholder‘s Influence over Time Influence of stakeholders Cost of changes Time 12
  • 13.
    Leiden Institute ofAdvanced Computer Science ICT Project Management !   Part art, part science !   Activities have duration, required resources and sequence (path) !   Critical path: Link of activities where delay causes delay in entire project ! 13
  • 14.
    Leiden Institute ofAdvanced Computer Science ICT Project Management: Two Exercises !   Design a project plan for !  Organizing a party next weekend Small birthday party … Vienna opera ball 14
  • 15.
    Leiden Institute ofAdvanced Computer Science Software Engineering is more Difficult ! !   Due to … !  Complexity !  Conformity (with human requirements) !  Changeability !  Invisibility It therefore needs specialized management techniques to deal with it ! 15
  • 16.
    Leiden Institute ofAdvanced Computer Science Common Activities Is it worth doing? How do we do Feasibility Study it ? Planning Do it ! Execute Project !   Feasibility study – decide if project is worth doing !   Plan how you are going to do it, then do it. 16
  • 17.
    Leiden Institute ofAdvanced Computer Science Execute Project (Hughes-Cotterrell Stages) Requirements Gathering Specification Design Code Testing Implement 17
  • 18.
    Leiden Institute ofAdvanced Computer Science Execute Project !   Functional Requirements !  What the system is to do !  Systems analysis aims to provide these !   Quality Requirements !  Other attributes of the system, e.g., response time, usability, reliability !   Resource / time Requirements !  Cost !  Time !   Trade-offs between the different factors 18
  • 19.
    Leiden Institute ofAdvanced Computer Science Managerial Issues !   Management may involve: !  Planning - deciding what is to be done !  Organizing - making arrangements !  Staffing - selecting the right people !  Directing - giving instructions !  Monitoring - checking on progress !  Controlling - taking action to remedy hold-ups !  Innovating - coming up with new solutions !  Representing - liaising with users 19
  • 20.
    Leiden Institute ofAdvanced Computer Science Managerial Issues !   Internal stakeholders may be: !  In the project team !  Outside the team but in the organization !   External stakeholders may be: !  Customers or users affected by the system !  Contractors !   There will be different types of users with different interests !   Need for good communication ! 20
  • 21.
    Leiden Institute ofAdvanced Computer Science Objectives !   Different stakeholders will have different objectives !  Need for agreed objectives !   Need for an identifyable project authority !  To set, monitor and modify objectives !  Can contain user, development and management representatives !   Objectives !  Can be informally expressed as: „In order for the project to be a success, the project must …“ 21
  • 22.
    Leiden Institute ofAdvanced Computer Science Objectives (cont‘d) !   Objectives must be: !  Concrete !  Have measure of success !   Objectives can be: !  Broken down into sub-objectives or goals !  Can be informally expressed as „in order to achieve A, we must achieve B, C, D, etc.“ !  Identifying sub-objectives involves considering the „how“ as well as the „what“ 22
  • 23.
    Leiden Institute ofAdvanced Computer Science Problems - I !   Project Manager‘s point of view: !  Poor estimates and plans !  Lack of quality standards and measures !  Lack of guidance about making organizational decisions !  Lack of techniques to make progress visible !  Poor role definition – who does what ? !  Incorrect success criteria 23
  • 24.
    Leiden Institute ofAdvanced Computer Science Problems - II !   Staff‘s point of view: !   Inadequate specification of work !   Management ignorance of IT !   Lack of knowledge and application area !   Lack of standards !   Lack of up-to-date documentation !   Preceding activities not completed on time !   Lack of communication between users and technicians !   Lack of communication leading to duplication of work !   Lack of commitment (especially when tied to one person) !   Narrow scope of technical expertise !   Changing statutory requirements !   Changing software environment !   Deadline pressure !   Lack of quality control !   Remote management !   Lack of training !   ... 24
  • 25.
    Leiden Institute ofAdvanced Computer Science Examples !   German toll collect system (2 years late, 2 billion €). !   US IRS was to abandon tax system modernization programme after having spend $4 billion. !   State of CA spent $1 billion on non-functional welfare database system. !   500 million € UK air traffic control system 2 years behind schedule. ! … !   All government ? Many industry examples as well. 25
  • 26.
    Leiden Institute ofAdvanced Computer Science Other Aspects I !   Setting Objectives !  Project authority !  Project board !  Sub-objectives and goals !  Measures of effectiveness •  Predictive measures (while constructing the system) •  Performance measures (operational system) !   Stakeholders !  Internal to project team !  External, but within same organization !  External to project team and organization 26
  • 27.
    Leiden Institute ofAdvanced Computer Science Other Aspects II !   Business Case !  Justification for project !  E.g., cost-benefit analysis !   Requirement Specification !  Functional: Systems Analysis and Design !  Quality: Response time, reliability, … !  Resources: Time and cost 27
  • 28.
    Leiden Institute ofAdvanced Computer Science Feasibility Study: Contents !   Introduction: What this document is !   Description of current situation !   Problem description !  Boundaries !  Scope !   Proposed development !  Business and financial aspects !  Technical aspects !  Organizational aspects !   Estimated costs !  Development costs !  Operational costs !   Envisaged benefits !   Recommendation 28
  • 29.
    Leiden Institute ofAdvanced Computer Science Project Plan: Contents !   Introduction !   Background, incl. Reference to the business case. !   Project objectives !   Constraints !   Project products (deliverable and intermediate) !   Methods !   Activities to be carried out !   Resources to be used !   Risks !   Management, including !  Organizational responsibilities !  Quality management !  Configuration management !   Success factors 29
  • 30.
    Leiden Institute ofAdvanced Computer Science Project Plan: Structure !   Introduction !   Management Summary !   Goals and objectives !  Business goals !  Benefits !  Objectives !   Scope, Key deliverables, Prioritization !   Organization, responsibilities, resources !   Risks, Risk Containment !   Other Issues 30
  • 31.
    Leiden Institute ofAdvanced Computer Science The System‘s Development Life Cycle 6a. Final assembly 5. Test and delivery 4. Implemen- tation 7. Correct, Maintain 3. System Design Functional Release 2. Systems 6b. Final assembly Analysis and delivery 1. Pre-study Correction Release 31
  • 32.
    Leiden Institute ofAdvanced Computer Science Project Management and Success !   Traditionally: trace production of „milestone“ documents (functional specs = 14%, logical design = 30%, …) !   But: cost will migrate out of any activity that is measured more carefully than its neighboring activities !   Escalating committment to failure % Completion 120 Percentage Completion 100 Law of diminishing 80 60 % Completion returns 40 20 0 1 2 3 4 5 6 7 8 9 Time 32
  • 33.
    Leiden Institute ofAdvanced Computer Science Law of diminishing (marginal) returns !   When one of the factors of production is held fixed in supply, successive additions of the other factors will lead to an increase in returns up to a point. !   Beyond this point, returns will diminish. !   Example: Agricultural production (seed amount – growth production, no. of workers – total labor and harvesting done). Diminishing returns 140 No. Of Total physical Marginal physical Average Physical workers product (TPP) product (MPP) Product (APP) 120 1 10 10 10 100 Total physical product 80 (TPP) 2 30 20 15 Marginal physical Tons 3 90 60 30 60 product (MPP) 40 4 120 30 30 Average Physical 20 Product (APP) 5 130 10 26 0 6 120 -10 20 -20 0 1 2 3 4 5 6 7 No. of Workers 33
  • 34.
    Leiden Institute ofAdvanced Computer Science Prioritizing and Managing Expectations Processing in Development Customer Screening Prioritization Development Request Entry Feedback (product planning) Selection of most relevant Reduction of: needs •  unclear •  doubles 100 dev. •  curr. release requests •  next release - 60% logged in •  out of scope X selected as planning input the system Y denied - 30% Z input for next year planning archived Transfer to next year‘s cycle 34
  • 35.
    Leiden Institute ofAdvanced Computer Science Your Project: Save Energy Demonstrator of innovative application that stimulates to save energy
  • 36.
    Leiden Institute ofAdvanced Computer Science Save Energy !   EU project on user behaviour transformation by empowerment of the users with ICT 5 Pilots: -Lisbon -Leiden -Manchester -Helsinki -Lulea
  • 37.
    Leiden Institute ofAdvanced Computer Science Leiden Employee Behaviour !  Electricity, switching on/off: !  PC, monitor !  Lighting !  Miscellaneous equipment !  Heating: ! Setpoint for room temperature !  Turn heater on/off !  Close/open windows
  • 38.
    Leiden Institute ofAdvanced Computer Science Leiden Pilot
  • 39.
    Leiden Institute ofAdvanced Computer Science Current Initiatives in Leiden Pilot !   Weekly Energy Emails •  Real time energy displays
  • 40.
    Leiden Institute ofAdvanced Computer Science Assignment !   Develop a demonstrator that runs on a pc, smart phone or presentation screen that displays the current energy consumption of individuals and stimulates users to save energy. !   Present in trade-fair setting
  • 41.
    Leiden Institute ofAdvanced Computer Science Remarks: !   Keep in mind the audience (Municipality employees) !   Real data is available (SOAP webservice) SOAP, originally defined as Simple Object Access Protocol, is a protocol specification for exchanging structured information in the implementation of web services in computer networks. !   Think of what motivates to save energy!
  • 42.
    Leiden Institute ofAdvanced Computer Science Save Energy Project !   Meet as Team !  Actually, you will have many meetings … !  Teamwork is of critical importance !   Project proposal (bid) due by !  February 18, midnight February 18, midnight Assignment 1: Project proposal ( bid ) February 25, midnight Assignment 2: Project Plan including functional specification March 1, midnight Assignment 3: Deutsche Bank case, 5 ppt slides March 1 (14:45 – 17:00) Exam March 15 (14:45 – 17:30) Trade fair March 16, midnight Assignment 4: Personal reflection paper on project management 42