Leiden Institute of Advanced Computer Science




            MS Project – High Level Introduction



            Prof. Dr. Thomas Bäck




                                                   1
Leiden Institute of Advanced Computer Science




A Project Screen (General information, tasks)




        Two tasks




                                                     2
Leiden Institute of Advanced Computer Science




Entering information for a task


                                                      General

                                                      Predecessor

                                                      Ressources

                                                      Special

                                                      Notes
                                                                    3
Leiden Institute of Advanced Computer Science




Checking and supervising progress




        Percentages




                                                     4
Leiden Institute of Advanced Computer Science




Calendar View




                                                     5
Leiden Institute of Advanced Computer Science




Activity Network View




                                                     6
Leiden Institute of Advanced Computer Science




Ressource Utilization View




Meier works
on designing
Module A




                                                       7
Leiden Institute of Advanced Computer Science




An Assignment to Play with MS Project
   !  Assignment 3
   !  Work on it in the computer room
   !  Just play with the software




                                                     8

SDPM - Lecture 4a - MS Project – High Level Introduction

  • 1.
    Leiden Institute ofAdvanced Computer Science MS Project – High Level Introduction Prof. Dr. Thomas Bäck 1
  • 2.
    Leiden Institute ofAdvanced Computer Science A Project Screen (General information, tasks) Two tasks 2
  • 3.
    Leiden Institute ofAdvanced Computer Science Entering information for a task General Predecessor Ressources Special Notes 3
  • 4.
    Leiden Institute ofAdvanced Computer Science Checking and supervising progress Percentages 4
  • 5.
    Leiden Institute ofAdvanced Computer Science Calendar View 5
  • 6.
    Leiden Institute ofAdvanced Computer Science Activity Network View 6
  • 7.
    Leiden Institute ofAdvanced Computer Science Ressource Utilization View Meier works on designing Module A 7
  • 8.
    Leiden Institute ofAdvanced Computer Science An Assignment to Play with MS Project !  Assignment 3 !  Work on it in the computer room !  Just play with the software 8