Project Management National Conference 2011                                  PMI India




  Your project is in Red, Now What?
  Tools and Techniques for “Green”
  pastures




      Mandar P. Kulkarni PMP, MBA
      Senior Business Analyst – Oracle Financials




2|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                                             PMI India




                                                                                                              Contents



  1   Abstract .............................................................................................................................4
  2   Objectives...........................................................................................................................4
  3   Keywords...........................................................................................................................4
  4   Case Studies.......................................................................................................................8
  5   Summary..........................................................................................................................15
  6   Author’s Profile................................................................................................................15
  7   References:.......................................................................................................................16




3|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India




                 1     Abstract

                 Best-in-class Organizations now have a Project Management Office (PMOi)
                 staffed with project managers who have years of experience in managing
                 projects of varying complexity and detail. Many of these managers also have
                 PMP certification to provide a structured, formal methodology essential to
                 managing projects. Despite superb planning and stakeholder involvement at
                 every stage, and a great team that collaborates effectively, projects do get into
                 the red and have to be brought back into green zone (on-target and on-budget
                 maintaining the triple constraint), otherwise failure is imminent.       Project
                 managers use time-tested tools and techniques as presented in the PMBOK
                 guide and the collective experience of the team to pull through and provide
                 results. This paper discusses two test cases of implementing Oracle ERP and
                 the experiences to battle the odds and come out with flying colors.


                 2     Objectives

                 This presentation will help the audience get familiar with the tools and techniques
                 that are readily available and can be employed quickly to bring the project back
                 on-track and make a successful implementation. These techniques include, but
                 are not limited to, enhanced communication, a closer look at the triple
                 constraints, breaking the project into manageable phases implemented over
                 time, and risk re-analyzing and remediation. This presentation will discuss them
                 in detail and provide two case studies and analyze ‘lessons learned’ at the end of
                 our presentation.


                 3     Keywords

                 Risk Identification and Mitigation, Early Warning Signs


                 Project Management – opportunity to add value (revised and updated)


                 A project is goal oriented (something that can be tangibly achieved as described
                 in the project charter); is temporary in nature and has a distinct time-bound start
                 and end activities. No two projects are the same i.e. each project is unique.
                 Typical large-scale, high visibility, high impact projects are implemented with
                 empowered cross-functional project teams, stakeholder involvement at every
                 stage, and use of project organization structure.


                 Signs of Aging…

4|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                 There are always signs when your project inches towards trouble; sometimes
                 these early warning signs (EWS) are interpreted differently or in the worst-case
                 scenario, the signs are ignored. In any event, these early signs can be identified
                 by the following:


                  (a) Communication – communication is the key as explained in the PMBOK
                        knowledge areas. This activity spans all knowledge areas and process
                        groups explained earlier. Also, the communication channelsii grow
                        exponentially adding to the woes of the Project manager.


                  (b)   Technology – Technology is the driver of the modern corporate engine.
                        Technology encompasses IT (Information Technology) and all the
                        components that make up technology, including but not limited to,
                        software, hardware, architecture, database, network, business process
                        reengineering and the ubiquitous internet. Sometimes, the wrong IT
                        strategy makes the project get into trouble and the triple constraints have
                        to be re-evaluated or changed to make the project feasible again.


                  (c)   Poor risk response strategies – as explained earlier in the presentation,
                        many projects go through the process to identify, analyze and mitigate
                        risks as part of the project management process. But it has been
                        suggested that projects who do not manage their risk response planning
                        properly always end up not managing their triple constraints causing
                        projects to slip.


                  (d)   Disparate Teams – A team that comprises different members of the
                        corporate departments with their unique agendas and animosity amongst
                        the peers definitely can affect the outcome of the project from the strategic
                        vision as encompassed in the project Charter.


                  (e)   Project Scope – incorrect or poorly defined scope is the primary reason
                        why projects go downhill. It is not enough that stakeholders have a good
                        project charter and scope-as-we-know-it-today mentality of the
                        stakeholders. Also, scope creep due to influential stakeholders also adds
                        to the woes of the project managers.


                  (f)   Business and Project Management alignment – many times, the strategic
                        vision as envisioned by the stakeholders and senior management at the
                        strategic level gets distorted when it comes to the tactical and operational
                        level in the organization.




5|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                        PMI India



                 According to Leon Kappelman et al in the paper “Early Warning Signs of IT
                 Project Failures: The Dominant Dozen”iii discuss the “People-related” and
                 “Process-related” early-warning signs. The above six causes can be divided in to
                 the two categories as follows:


                            Cause or Sign of aging                EWS Category

                                 Communication                        Process

                                   Technology                         Process

                          Poor Risk response strategies         People and Process

                                Disparate Teams                        People

                                  Project Scope                        People
                              Business and Project
                                                                People and Process
                             Management Alignment


                             Table 1: Causes of Project Failure and EWS Category


                 As shown in Table 1 above, the causes of failure are both people and process
                 related even though people related EWS take precedence over process EWS
                 due to the critical thinking ability that stakeholders and project manager
                 collectively have to ‘act’ on the EWS and steering the project in the correct
                 direction Also, according to Kappelman et al. the number one EWS is Lack of top
                 management support (people related) and Weak project manager at number 3
                 (also people-related) with lack of success criteria at number 2 (process related).
                 So what can the project manager do about these issues?


                 Tools of the Trade…


                 How to identify the early warning signs and how to use them effectively to
                 monitor your project status and if project is slipping, bring it back from the red
                 into the green zone? There are several tools and techniques available to the
                 project managers to monitor the health of the project. Let us discuss them briefly
                 and the case studies below will provide additional information on how the project
                 team utilized the tools and techniques to bring the project back on track.


                  a)   Communication – As explained earlier, communication is the key area that
                       spans all activities of the project. What can Project Manager do to provide
                       consistent communication across all stakeholders? Communication can be
                       an effective conflict management tool wherein the team members resolve
                       their differences effectively using agreed upon communication strategy.
                       Groupthink should be avoided and project manager must ensure that the
                       effective communication is being reached to the right audience. Rules have

6|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                              PMI India



                       to be place for running effective meetings (no checking emails or taking
                       phone calls, arriving on-time and only discussing the topic defined in the
                       meeting agenda are some examples). Methods of distributing project
                       information should also be part of the communication plan and strictly
                       followed. Lastly, developing better communication skills should be
                       encouraged and developed and leadership should lead by example with
                       planning and support and encouragement to the project team.


                  b)   Technology – The knowledge and tools required to manage technology
                       projects are diverse, vary by industry and business requirements making it a
                       complex set of processes. The Project managers and the stakeholders
                       must ensure the use of right technology on the Project. One example is use
                       off-the-shelf software or to develop custom solution to meet the business
                       needs? The answer will require detail analysis with pro and con of each
                       option and recommended approach. The challenge of ensuring the
                       technology works in both these scenarios will determine the outcome of the
                       project. Case study II discusses this issue in detail.


                  c)   Poor risk response strategies – This is also very important as far as the
                       project outcome is concerned. What is an acceptable risk for a project is
                       determined on how the project is structured and what the success criteria is
                       according to project scope document. The project manager should
                       encourage identification of all potential risks associated with the project and
                       work with the team to develop a risk register and quickly communicate the
                       risks that pose a problem with the help of the early warning signs. Case
                       study I discuss some of the steps the project manager took to avert disaster
                       and bring project back on track.


                  d)   Disparate Teams – It is not uncommon to have teams located across
                       multiple geographies and even on different continents. What is required is a
                       clear communication strategy and team meetings to keep everyone abreast
                       of current status and issues if any. A smart project manager will be able to
                       identify groupthink and associated issues quickly and remedy the situation.
                       Case study I discuss one such scenario and how the team overcame the
                       problem successfully.


                  e)   Project Scope – It is very difficult to identify the four walls of project day one.
                       But the stakeholders must make a conscious decision of writing the problem
                       statement and the desired outcome in great detail which will become the
                       scope of the project. In case study II, the Oracle ERP project required
                       interface with the legacy Logistics software. A decision was made to
                       purchase new logistics software which added considerable scope creep to
                       the project. The interface to and from Oracle became a big technology
                       challenge not only in design but also revised functionality. The logistics
                       software was a critical piece of day-to-day operation of the company and as
7|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                            PMI India



                       such became absolute requirement. How the project team overcame the
                       problem is discussed in detail in the case study.


                  f)   Business and Project Management alignment – The alignment of the
                       business stakeholders and the project team is required for the project to be
                       successful. Take the example of case study II. When it became apparent to
                       the project manager the legacy logistics software was outdated and need to
                       be replaced, the stakeholders were not sure why the Oracle ERP software
                       will not work with the existing legacy system. The alignment had to be
                       reiterated and reestablished and the stakeholders were taken into
                       confidence before moving ahead with the project.


                 4       Case Studies

                 Once it is identified that the project is in red, it is very important to use the tools
                 and techniques mentioned above in addition to identifying the people and
                 process categories for the early warning signs. These should be used effectively
                 to understand the current state of the project and devise an action plan to
                 mitigate and resolve the risks to bring the project back on track.


                 Case Study 1: Project is 25% complete and the project manager realize the big-
                 bang approach of implementing several countries in one go is not working as
                 identified by the EWS


                 Introduction: The Oracle Self-service iSupplier and iProcurement ERP project is
                 to be implemented in several South American Countries in a tight time-frame of
                 nine months. The implementation was cookie-cutter approach based on North
                 America model and the project was kicked off with much fanfare. After about two
                 months into the project, the project team realized that the project plan was
                 slipping and in the third month, the project became red with serious risk of delays
                 from the original plan…


                 Early warning signs that helped the project team identify the project is going
                 south were as follows:


                       1. Communication gap – most of English speaking team were unable to
                          communicate and solicit information from the South American business
                          leads causing confusion and mistrust.


                       2. Disparate teams – the business users were spread across geographies
                          with the Project implementation team located here in the US and the
                          development team located in India. The coordination and managing the
                          teams in different time zones was becoming difficult.

8|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                         PMI India



                     3. Scope change – the cookie-cutter approach was deemed to be not a
                        good fit for the countries as legal and operational difficulties forced the
                        project team to rethink the current approach and provide a tailor-made
                        solution adding several months of design and development efforts.


                 The project team overcame the EWS to bring the project back on-track by
                 implementing the following changes:


                         a. To facilitate effective communication, the team identified a simple
                         way to breakdown the status reporting and assigned two translators to
                         help translate the English version in to the regional (Spanish and
                         Portuguese) languages so that our stakeholders were able to understand
                         very clearly what the project statuses is at all times. The team also
                         created a dedicated sharepoint project website to track all work
                         breakdown structures (WBS) and associated documentation of the
                         project online. The enhanced communication also helped us improve
                         cooperation amongst the stakeholders and the project manager and the
                         extended team.


                         b. To help the stakeholders understand the severity of changing scope,
                         the project manager put together a numerical score for each task and
                         map it back to the project plan and provided a color-coded display of the
                         scope change on the project (see Table 3 below). The numerical score
                         assigned to each task was based on its importance as per the Work
                         breakdown structure and if the task was on critical path. Adding new
                         tasks (because of scope creep) brought the statistical scoring off-
                         balance. The project team was able to identify easily what the %
                         complete status for each week should be (original plan) and what it is
                         (with the scope creep). The steering committee was able to justify
                         acceptance or rejection of the new scope so as not to jeopardize the
                         entire project deliverable.


                         c. Finally, the Business and Project Management alignment was
                         achieved by working with the Business to help drive the importance of
                         the project by clearly demonstrating that the project is part of the global
                         corporate strategy and also helps the regional geographies manage and
                         track spend and enhance the strategic sourcing initiatives.


                 Conclusion: The Results were clear for everyone to see. With correctly tracking
                 the project as per the risk response planning strategy, the stakeholders were
                 able to identify and isolate the issues early on and prevent further escalation and
                 possible failure. By evaluating the risk response strategies, the project manager
                 was able to bring the project back on track in the green zone and deliver it



9|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                                        PMI India



                 successfully with only a delay of eight weeks and the stakeholders were very
                 happy with the implementation team and the project.




                   Project:               IMPLEMENTATION OFP ROCUREMENT ANDS UPPLIER
                                                           I               I
                   Budget Status:         GREEN
                   Schedule Status:       GREEN
                   Risk Assessment:       Low

                   Report Period:         Week Ending June 18, 20
                                                                XX
                   Author:                Mandar P. Kulkarni
                   Project Phase:         Operations Analysis


                                                  Project Status Summary

                     20%
                                                                                15%
                     15%
                                        9%
                     10%
                                                             6%
                      5%

                      0%
                                      Calendar              Budget            Activities




                                         Table 2 Project Status Report


               Task                                                  Rating      14-Jun    21-Jun
               Project Charter                                       5           4         4
               Project Work plan                                     5           3         3
               Business Prototype CRP                                10          3         3
               Integration Testing                                   10
               Test Case Scenarios - Standard
               Operating Procedure                                   5                     2
               Test Case Scenarios - Exceptional
               Conditions                                            5
               Data Gathering and Cleansing -
               Suppliers                                             8
               Data Gathering and Cleansing - Item
               Categories                                            8
               Acceptance Criteria - Identification                  4
               User Acceptance Testing                               8
               Production Loading                                    9
               Contingency Plans                                     4
               Readiness Audits - Definition                         4
               Readiness Audits - Audit                              4
               Cutover Decision                                      10
               Production Support - Approach
               Definition                                            5
               Production Support - Execution                        5
               Statistical Ranking:                                  109         10    12
               Percentage Complete:                                              9.17% 11.01%


10|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                  PMI India



                               Table 3: Project Scorecard




11|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                        PMI India




                 Case Study 2: The project is 70% through the calendar (time) and we realize that
                 the technology challenges are more severe than previously anticipated and we
                 are nowhere near the development target!


                 Introduction: The project is to upgrade Oracle ERP from current version of 11i to
                 Release 12 using Oracle recommended technology for the upgrade. This is very
                 big implementation project spread over eighteen months with a team size of over
                 one hundred with everyone working diligently on the project plan well in to the
                 design and development phase of the project. After about a year on the project,
                 the PM realizes that the risk planning is showing considerable decay and that the
                 project is getting in to the red zone. The project has several issues as listed
                 below:


                         1. Technology – We were in new uncharted Technology territory with
                         the Oracle ERP upgrade with new terms like Oracle Framework
                         development and service-oriented architecture and Oracle Data
                         Integrator tool for Load-extract and translate data for conversions.


                         2. Scope Change – With better understanding of the project and its
                         impact, we realized that the current scope will not provide any real
                         benefits if we do not implement different areas that were previously were
                         considered out-of-scope and also some third-party software integration
                         that seemed necessary by our stakeholders


                         3. Disparate Teams – At one point of time, the project size was well
                         over one hundred developers, consultants, business analysts and
                         stakeholders working in India, and different time-zones in America and
                         lastly,


                         4. Poor risk response strategies to some of the new technology related
                         risks. We identified that the risks were minimal during the initial phases
                         but realized that the learning curve to master the new technologies were
                         longer than anticipated


                         5. Business and Project alignment – the Business was not sure why the
                         existing legacy Logistics software cannot function with the Oracle
                         software. The recommendation of third-party off-the-shelf software
                         integration with oracle was going to add several months of efforts.




12|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                          PMI India



                 After a thorough evaluation of risk response strategies, the project manager
                 identified several remedial techniques to bring the project back on track and into
                 green again.


                         a. Technology issues identified were mostly that they were new to the
                         development staff. Oracle training was provided to several team
                         members including extended development team and consultants with
                         plenty of practice sessions to help them master the topic and helped gain
                         valuable confidence too.


                         b. Communication – The disparate team working in different time zones
                         was not working as an efficient well-oiled machine. The team realized
                         that a war-room concept, where team members work in one big room on
                         a time-zone comfortable to all will work better for this particular project.
                         The communication became more intelligent, and delays in responding
                         with each other also was reduced enabling the team to performing their
                         best in these given difficult circumstances. Also, daily sub-team meeting
                         notes were circulated to the project manager who in turn provided daily
                         status reports to the stakeholders.


                         c. Risk response strategies were enforced including identifying
                         unassigned work performed by team members without explicit
                         authorization by their respective module leader or project managers.
                         Schedule Performance Index (SPI), a measure of schedule efficiency is
                         ratio of earned value (EV) to planned value (PV). The project team
                         started tracking SPI for each sub-team for individual tasks that were
                         lower than 0.6, (considered a critical limit) as well as tracking each team
                         where the overall level was less than 0.8 (refer Table 4: SPI for tracking
                         purposes). This weekly monitoring of SPI helped the project manager
                         tremendously in anticipating the risks and proactively monitoring and
                         mitigating with concrete steps in place to work on the risks as they arose.
                         More than half the teams were below the .8 SPI thresholds, but within 3
                         weeks, all of them were above the .8 threshold and had shown
                         improvement. For the first time, the project manager could ‘see’ the
                         issues as they became visible in real-time and resolve them quickly with
                         strict control on the deliverables.




13|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                    PMI India




                            Table 4: SPI for Project Tracking


                        d. Project Scope – Because the project scope changed due to so many
                        moving parts in the project, the project team decided to manage the
                        projects by breaking down into sub-projects using WBS ((Procure to
                        Pay, Record to Report etc.) into one combined ‘Rollup’ WBS as shown in
                        Table 4 above. This helped the team focus on the newly added scope
                        for the Logistics software interface (DEX) in addition to the existing
                        Oracle ERP module specific tracks.




                           Table 5: Improved Status Reporting

14|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                        PMI India



                 Conclusion: Case study II provided details of a typical large-scale implementation
                 wherein the scope and technology affect the outcome considerably. The case
                 discussed in detail how the early warning signs were missed and once the
                 project went in to red, how the project manager used innovative approach to
                 bring the project back on track. The use of SPI and breaking down the projects in
                 manageable chunks using WBS was also very useful in keeping tight control
                 over the entire operation. Finally, the improved status reporting as shown in
                 Table 5 above was really useful in determining what the planned work was and
                 what unplanned work had to be done (either technology challenges or scope
                 creep) and what effect it had to the critical path. The combination of unique
                 status reporting, managing the scope effectively and effective use of technology
                 enabled the project team to complete the project successfully.


                 5     Summary

                 In summary, we have discussed the Early Warning Signs EWS of why projects
                 slip from their intended target with Communication and Technology being the top
                 two with people related EWS taking precedence over process related EWS. We
                 also discussed in detail two case-studies and how we were able to bring the
                 projects back on track with simple and easy-to-use methodologies. A quick demo
                 of Microsoft Project display SPI was also shown to enable project managers to
                 incorporate the SPI in their status reporting. Finally, EWS can be just an
                 indicator, but the project managers and the stakeholders should work
                 collaboratively to achieve the desired success as simply reporting EWS but not
                 ‘acting’ will most definitely put the project in jeopardy.


                 6     Author’s Profile




                 Mandar P. Kulkarni is Senior Oracle IT Business Analyst with
                 experience implementing Oracle ERP since 1999 and has lived in
                 the USA since 2000. Mandar has MBA (MIS) from Loyola College in

15|P a g e
 Application of Select Tools of Psychology for Effective Project Management
Project Management National Conference 2011                                  PMI India



                 Maryland, USA and also is certified PMP professional. Mandar has
                 experience   with    Oracle     implementation,    upgrade    and
                 enhancements. In the last three years, Mandar has started leading
                 projects combining the project management knowledge and the
                 Oracle ERP expertise. This is Mandar’s first professional paper at
                 PMI conference and he is looking to gain valuable experience and
                 feedback from this conference. Mandar can be reached at
                 MPKULKARNI@loyola.edu

                 Conference Paper: Your Project is in Red, now what? Tools and
                 techniques for green pastures…

                 PMI India Nationa l Conference – Bangalore, India 8-10 September
                 2011


                 7     References:




16|P a g e
 Application of Select Tools of Psychology for Effective Project Management
i
      A.      Project management Office PMO is an organizational unit to centralize and
      coordinate the management of projects under its domain. A PMO oversees
      management of projects or programs or both. The PMO focuses on coordinated
      planning, prioritization and execution of the projects and subprojects that are tied to
      parent organization (or client’s) overall business objective – PMBOK Guide
ii
      B.     Communication channels as defined by the formula N*(N-1)/2 where N =
      number of team members in the communication channel.
iii
      C.     Early Warning Signs of IT Project Failures: The Dominant Dozen”, by Leon
      Kappelman, Robert McKeeman and Lixuan Zhang, Information Systems
      Management Fall 2006 www.ism-journal.com

MCP1

  • 2.
    Project Management NationalConference 2011 PMI India Your project is in Red, Now What? Tools and Techniques for “Green” pastures Mandar P. Kulkarni PMP, MBA Senior Business Analyst – Oracle Financials 2|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 3.
    Project Management NationalConference 2011 PMI India Contents 1 Abstract .............................................................................................................................4 2 Objectives...........................................................................................................................4 3 Keywords...........................................................................................................................4 4 Case Studies.......................................................................................................................8 5 Summary..........................................................................................................................15 6 Author’s Profile................................................................................................................15 7 References:.......................................................................................................................16 3|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 4.
    Project Management NationalConference 2011 PMI India 1 Abstract Best-in-class Organizations now have a Project Management Office (PMOi) staffed with project managers who have years of experience in managing projects of varying complexity and detail. Many of these managers also have PMP certification to provide a structured, formal methodology essential to managing projects. Despite superb planning and stakeholder involvement at every stage, and a great team that collaborates effectively, projects do get into the red and have to be brought back into green zone (on-target and on-budget maintaining the triple constraint), otherwise failure is imminent. Project managers use time-tested tools and techniques as presented in the PMBOK guide and the collective experience of the team to pull through and provide results. This paper discusses two test cases of implementing Oracle ERP and the experiences to battle the odds and come out with flying colors. 2 Objectives This presentation will help the audience get familiar with the tools and techniques that are readily available and can be employed quickly to bring the project back on-track and make a successful implementation. These techniques include, but are not limited to, enhanced communication, a closer look at the triple constraints, breaking the project into manageable phases implemented over time, and risk re-analyzing and remediation. This presentation will discuss them in detail and provide two case studies and analyze ‘lessons learned’ at the end of our presentation. 3 Keywords Risk Identification and Mitigation, Early Warning Signs Project Management – opportunity to add value (revised and updated) A project is goal oriented (something that can be tangibly achieved as described in the project charter); is temporary in nature and has a distinct time-bound start and end activities. No two projects are the same i.e. each project is unique. Typical large-scale, high visibility, high impact projects are implemented with empowered cross-functional project teams, stakeholder involvement at every stage, and use of project organization structure. Signs of Aging… 4|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 5.
    Project Management NationalConference 2011 PMI India There are always signs when your project inches towards trouble; sometimes these early warning signs (EWS) are interpreted differently or in the worst-case scenario, the signs are ignored. In any event, these early signs can be identified by the following: (a) Communication – communication is the key as explained in the PMBOK knowledge areas. This activity spans all knowledge areas and process groups explained earlier. Also, the communication channelsii grow exponentially adding to the woes of the Project manager. (b) Technology – Technology is the driver of the modern corporate engine. Technology encompasses IT (Information Technology) and all the components that make up technology, including but not limited to, software, hardware, architecture, database, network, business process reengineering and the ubiquitous internet. Sometimes, the wrong IT strategy makes the project get into trouble and the triple constraints have to be re-evaluated or changed to make the project feasible again. (c) Poor risk response strategies – as explained earlier in the presentation, many projects go through the process to identify, analyze and mitigate risks as part of the project management process. But it has been suggested that projects who do not manage their risk response planning properly always end up not managing their triple constraints causing projects to slip. (d) Disparate Teams – A team that comprises different members of the corporate departments with their unique agendas and animosity amongst the peers definitely can affect the outcome of the project from the strategic vision as encompassed in the project Charter. (e) Project Scope – incorrect or poorly defined scope is the primary reason why projects go downhill. It is not enough that stakeholders have a good project charter and scope-as-we-know-it-today mentality of the stakeholders. Also, scope creep due to influential stakeholders also adds to the woes of the project managers. (f) Business and Project Management alignment – many times, the strategic vision as envisioned by the stakeholders and senior management at the strategic level gets distorted when it comes to the tactical and operational level in the organization. 5|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 6.
    Project Management NationalConference 2011 PMI India According to Leon Kappelman et al in the paper “Early Warning Signs of IT Project Failures: The Dominant Dozen”iii discuss the “People-related” and “Process-related” early-warning signs. The above six causes can be divided in to the two categories as follows: Cause or Sign of aging EWS Category Communication Process Technology Process Poor Risk response strategies People and Process Disparate Teams People Project Scope People Business and Project People and Process Management Alignment Table 1: Causes of Project Failure and EWS Category As shown in Table 1 above, the causes of failure are both people and process related even though people related EWS take precedence over process EWS due to the critical thinking ability that stakeholders and project manager collectively have to ‘act’ on the EWS and steering the project in the correct direction Also, according to Kappelman et al. the number one EWS is Lack of top management support (people related) and Weak project manager at number 3 (also people-related) with lack of success criteria at number 2 (process related). So what can the project manager do about these issues? Tools of the Trade… How to identify the early warning signs and how to use them effectively to monitor your project status and if project is slipping, bring it back from the red into the green zone? There are several tools and techniques available to the project managers to monitor the health of the project. Let us discuss them briefly and the case studies below will provide additional information on how the project team utilized the tools and techniques to bring the project back on track. a) Communication – As explained earlier, communication is the key area that spans all activities of the project. What can Project Manager do to provide consistent communication across all stakeholders? Communication can be an effective conflict management tool wherein the team members resolve their differences effectively using agreed upon communication strategy. Groupthink should be avoided and project manager must ensure that the effective communication is being reached to the right audience. Rules have 6|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 7.
    Project Management NationalConference 2011 PMI India to be place for running effective meetings (no checking emails or taking phone calls, arriving on-time and only discussing the topic defined in the meeting agenda are some examples). Methods of distributing project information should also be part of the communication plan and strictly followed. Lastly, developing better communication skills should be encouraged and developed and leadership should lead by example with planning and support and encouragement to the project team. b) Technology – The knowledge and tools required to manage technology projects are diverse, vary by industry and business requirements making it a complex set of processes. The Project managers and the stakeholders must ensure the use of right technology on the Project. One example is use off-the-shelf software or to develop custom solution to meet the business needs? The answer will require detail analysis with pro and con of each option and recommended approach. The challenge of ensuring the technology works in both these scenarios will determine the outcome of the project. Case study II discusses this issue in detail. c) Poor risk response strategies – This is also very important as far as the project outcome is concerned. What is an acceptable risk for a project is determined on how the project is structured and what the success criteria is according to project scope document. The project manager should encourage identification of all potential risks associated with the project and work with the team to develop a risk register and quickly communicate the risks that pose a problem with the help of the early warning signs. Case study I discuss some of the steps the project manager took to avert disaster and bring project back on track. d) Disparate Teams – It is not uncommon to have teams located across multiple geographies and even on different continents. What is required is a clear communication strategy and team meetings to keep everyone abreast of current status and issues if any. A smart project manager will be able to identify groupthink and associated issues quickly and remedy the situation. Case study I discuss one such scenario and how the team overcame the problem successfully. e) Project Scope – It is very difficult to identify the four walls of project day one. But the stakeholders must make a conscious decision of writing the problem statement and the desired outcome in great detail which will become the scope of the project. In case study II, the Oracle ERP project required interface with the legacy Logistics software. A decision was made to purchase new logistics software which added considerable scope creep to the project. The interface to and from Oracle became a big technology challenge not only in design but also revised functionality. The logistics software was a critical piece of day-to-day operation of the company and as 7|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 8.
    Project Management NationalConference 2011 PMI India such became absolute requirement. How the project team overcame the problem is discussed in detail in the case study. f) Business and Project Management alignment – The alignment of the business stakeholders and the project team is required for the project to be successful. Take the example of case study II. When it became apparent to the project manager the legacy logistics software was outdated and need to be replaced, the stakeholders were not sure why the Oracle ERP software will not work with the existing legacy system. The alignment had to be reiterated and reestablished and the stakeholders were taken into confidence before moving ahead with the project. 4 Case Studies Once it is identified that the project is in red, it is very important to use the tools and techniques mentioned above in addition to identifying the people and process categories for the early warning signs. These should be used effectively to understand the current state of the project and devise an action plan to mitigate and resolve the risks to bring the project back on track. Case Study 1: Project is 25% complete and the project manager realize the big- bang approach of implementing several countries in one go is not working as identified by the EWS Introduction: The Oracle Self-service iSupplier and iProcurement ERP project is to be implemented in several South American Countries in a tight time-frame of nine months. The implementation was cookie-cutter approach based on North America model and the project was kicked off with much fanfare. After about two months into the project, the project team realized that the project plan was slipping and in the third month, the project became red with serious risk of delays from the original plan… Early warning signs that helped the project team identify the project is going south were as follows: 1. Communication gap – most of English speaking team were unable to communicate and solicit information from the South American business leads causing confusion and mistrust. 2. Disparate teams – the business users were spread across geographies with the Project implementation team located here in the US and the development team located in India. The coordination and managing the teams in different time zones was becoming difficult. 8|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 9.
    Project Management NationalConference 2011 PMI India 3. Scope change – the cookie-cutter approach was deemed to be not a good fit for the countries as legal and operational difficulties forced the project team to rethink the current approach and provide a tailor-made solution adding several months of design and development efforts. The project team overcame the EWS to bring the project back on-track by implementing the following changes: a. To facilitate effective communication, the team identified a simple way to breakdown the status reporting and assigned two translators to help translate the English version in to the regional (Spanish and Portuguese) languages so that our stakeholders were able to understand very clearly what the project statuses is at all times. The team also created a dedicated sharepoint project website to track all work breakdown structures (WBS) and associated documentation of the project online. The enhanced communication also helped us improve cooperation amongst the stakeholders and the project manager and the extended team. b. To help the stakeholders understand the severity of changing scope, the project manager put together a numerical score for each task and map it back to the project plan and provided a color-coded display of the scope change on the project (see Table 3 below). The numerical score assigned to each task was based on its importance as per the Work breakdown structure and if the task was on critical path. Adding new tasks (because of scope creep) brought the statistical scoring off- balance. The project team was able to identify easily what the % complete status for each week should be (original plan) and what it is (with the scope creep). The steering committee was able to justify acceptance or rejection of the new scope so as not to jeopardize the entire project deliverable. c. Finally, the Business and Project Management alignment was achieved by working with the Business to help drive the importance of the project by clearly demonstrating that the project is part of the global corporate strategy and also helps the regional geographies manage and track spend and enhance the strategic sourcing initiatives. Conclusion: The Results were clear for everyone to see. With correctly tracking the project as per the risk response planning strategy, the stakeholders were able to identify and isolate the issues early on and prevent further escalation and possible failure. By evaluating the risk response strategies, the project manager was able to bring the project back on track in the green zone and deliver it 9|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 10.
    Project Management NationalConference 2011 PMI India successfully with only a delay of eight weeks and the stakeholders were very happy with the implementation team and the project. Project: IMPLEMENTATION OFP ROCUREMENT ANDS UPPLIER I I Budget Status: GREEN Schedule Status: GREEN Risk Assessment: Low Report Period: Week Ending June 18, 20 XX Author: Mandar P. Kulkarni Project Phase: Operations Analysis Project Status Summary 20% 15% 15% 9% 10% 6% 5% 0% Calendar Budget Activities Table 2 Project Status Report Task Rating 14-Jun 21-Jun Project Charter 5 4 4 Project Work plan 5 3 3 Business Prototype CRP 10 3 3 Integration Testing 10 Test Case Scenarios - Standard Operating Procedure 5 2 Test Case Scenarios - Exceptional Conditions 5 Data Gathering and Cleansing - Suppliers 8 Data Gathering and Cleansing - Item Categories 8 Acceptance Criteria - Identification 4 User Acceptance Testing 8 Production Loading 9 Contingency Plans 4 Readiness Audits - Definition 4 Readiness Audits - Audit 4 Cutover Decision 10 Production Support - Approach Definition 5 Production Support - Execution 5 Statistical Ranking: 109 10 12 Percentage Complete: 9.17% 11.01% 10|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 11.
    Project Management NationalConference 2011 PMI India Table 3: Project Scorecard 11|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 12.
    Project Management NationalConference 2011 PMI India Case Study 2: The project is 70% through the calendar (time) and we realize that the technology challenges are more severe than previously anticipated and we are nowhere near the development target! Introduction: The project is to upgrade Oracle ERP from current version of 11i to Release 12 using Oracle recommended technology for the upgrade. This is very big implementation project spread over eighteen months with a team size of over one hundred with everyone working diligently on the project plan well in to the design and development phase of the project. After about a year on the project, the PM realizes that the risk planning is showing considerable decay and that the project is getting in to the red zone. The project has several issues as listed below: 1. Technology – We were in new uncharted Technology territory with the Oracle ERP upgrade with new terms like Oracle Framework development and service-oriented architecture and Oracle Data Integrator tool for Load-extract and translate data for conversions. 2. Scope Change – With better understanding of the project and its impact, we realized that the current scope will not provide any real benefits if we do not implement different areas that were previously were considered out-of-scope and also some third-party software integration that seemed necessary by our stakeholders 3. Disparate Teams – At one point of time, the project size was well over one hundred developers, consultants, business analysts and stakeholders working in India, and different time-zones in America and lastly, 4. Poor risk response strategies to some of the new technology related risks. We identified that the risks were minimal during the initial phases but realized that the learning curve to master the new technologies were longer than anticipated 5. Business and Project alignment – the Business was not sure why the existing legacy Logistics software cannot function with the Oracle software. The recommendation of third-party off-the-shelf software integration with oracle was going to add several months of efforts. 12|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 13.
    Project Management NationalConference 2011 PMI India After a thorough evaluation of risk response strategies, the project manager identified several remedial techniques to bring the project back on track and into green again. a. Technology issues identified were mostly that they were new to the development staff. Oracle training was provided to several team members including extended development team and consultants with plenty of practice sessions to help them master the topic and helped gain valuable confidence too. b. Communication – The disparate team working in different time zones was not working as an efficient well-oiled machine. The team realized that a war-room concept, where team members work in one big room on a time-zone comfortable to all will work better for this particular project. The communication became more intelligent, and delays in responding with each other also was reduced enabling the team to performing their best in these given difficult circumstances. Also, daily sub-team meeting notes were circulated to the project manager who in turn provided daily status reports to the stakeholders. c. Risk response strategies were enforced including identifying unassigned work performed by team members without explicit authorization by their respective module leader or project managers. Schedule Performance Index (SPI), a measure of schedule efficiency is ratio of earned value (EV) to planned value (PV). The project team started tracking SPI for each sub-team for individual tasks that were lower than 0.6, (considered a critical limit) as well as tracking each team where the overall level was less than 0.8 (refer Table 4: SPI for tracking purposes). This weekly monitoring of SPI helped the project manager tremendously in anticipating the risks and proactively monitoring and mitigating with concrete steps in place to work on the risks as they arose. More than half the teams were below the .8 SPI thresholds, but within 3 weeks, all of them were above the .8 threshold and had shown improvement. For the first time, the project manager could ‘see’ the issues as they became visible in real-time and resolve them quickly with strict control on the deliverables. 13|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 14.
    Project Management NationalConference 2011 PMI India Table 4: SPI for Project Tracking d. Project Scope – Because the project scope changed due to so many moving parts in the project, the project team decided to manage the projects by breaking down into sub-projects using WBS ((Procure to Pay, Record to Report etc.) into one combined ‘Rollup’ WBS as shown in Table 4 above. This helped the team focus on the newly added scope for the Logistics software interface (DEX) in addition to the existing Oracle ERP module specific tracks. Table 5: Improved Status Reporting 14|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 15.
    Project Management NationalConference 2011 PMI India Conclusion: Case study II provided details of a typical large-scale implementation wherein the scope and technology affect the outcome considerably. The case discussed in detail how the early warning signs were missed and once the project went in to red, how the project manager used innovative approach to bring the project back on track. The use of SPI and breaking down the projects in manageable chunks using WBS was also very useful in keeping tight control over the entire operation. Finally, the improved status reporting as shown in Table 5 above was really useful in determining what the planned work was and what unplanned work had to be done (either technology challenges or scope creep) and what effect it had to the critical path. The combination of unique status reporting, managing the scope effectively and effective use of technology enabled the project team to complete the project successfully. 5 Summary In summary, we have discussed the Early Warning Signs EWS of why projects slip from their intended target with Communication and Technology being the top two with people related EWS taking precedence over process related EWS. We also discussed in detail two case-studies and how we were able to bring the projects back on track with simple and easy-to-use methodologies. A quick demo of Microsoft Project display SPI was also shown to enable project managers to incorporate the SPI in their status reporting. Finally, EWS can be just an indicator, but the project managers and the stakeholders should work collaboratively to achieve the desired success as simply reporting EWS but not ‘acting’ will most definitely put the project in jeopardy. 6 Author’s Profile Mandar P. Kulkarni is Senior Oracle IT Business Analyst with experience implementing Oracle ERP since 1999 and has lived in the USA since 2000. Mandar has MBA (MIS) from Loyola College in 15|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 16.
    Project Management NationalConference 2011 PMI India Maryland, USA and also is certified PMP professional. Mandar has experience with Oracle implementation, upgrade and enhancements. In the last three years, Mandar has started leading projects combining the project management knowledge and the Oracle ERP expertise. This is Mandar’s first professional paper at PMI conference and he is looking to gain valuable experience and feedback from this conference. Mandar can be reached at MPKULKARNI@loyola.edu Conference Paper: Your Project is in Red, now what? Tools and techniques for green pastures… PMI India Nationa l Conference – Bangalore, India 8-10 September 2011 7 References: 16|P a g e Application of Select Tools of Psychology for Effective Project Management
  • 17.
    i A. Project management Office PMO is an organizational unit to centralize and coordinate the management of projects under its domain. A PMO oversees management of projects or programs or both. The PMO focuses on coordinated planning, prioritization and execution of the projects and subprojects that are tied to parent organization (or client’s) overall business objective – PMBOK Guide ii B. Communication channels as defined by the formula N*(N-1)/2 where N = number of team members in the communication channel. iii C. Early Warning Signs of IT Project Failures: The Dominant Dozen”, by Leon Kappelman, Robert McKeeman and Lixuan Zhang, Information Systems Management Fall 2006 www.ism-journal.com