The document provides updates on construction progress at the Leaside and Laird stations for the Crosstown LRT project. For Leaside Station, piling work and wet utilities work are underway on the north side and will continue over the next 3-4 months, with periodic changes to the construction setup. Traffic signals at two intersections will be brought to Council for approval and installation. For Laird Station, 24-hour mining operations are permitted and noise reduction plans will be implemented to minimize impacts, with monitoring and adjustments as needed. Mining work for the main and secondary entrances is underway and expected to continue into late 2019. Progress photos of both station sites are also included.