SlideShare a Scribd company logo
1 of 29
Download to read offline
1
Crosstown Update
Allen Road and Eglinton Avenue
June 19, 2013
Welcome
2
What is the Crosstown?
 The Eglinton Crosstown is a 19 kilometre light rail transit
(LRT) line that will run along Eglinton Avenue through the
heart of Toronto, with an underground central section
 The line will connect Mount Dennis in the west to Kennedy
Road in the east
 The new service will be up to 60% faster than bus service
today
3
Project Schedule
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Sheppard
Finch
Eglinton
Scarborough
RT
SRT / Sheppard
Maintenance
Facility
Note: Timeline reflects initiation of major construction activities
RFQ Issued
RFP Issued
Financial Close
Timeline
2021
4
5
Eglinton Crosstown LRT
 Project
 $4.9 B (2010$), funded by the Province of Ontario
 19 kilometres east-west LRT from Kennedy to
Jane/Black Creek, including 10 kilometres of tunnel
 Connections to Yonge-University-Spadina Subway,
Scarborough RT and GO Stouffville
 Up to 26 stations
6
Tunnelling Update
 The tunnel contract was awarded September 11, 2012
 The winning consortium is comprised of Kenny
Construction Co., Kenaidan Contracting Ltd., Obayashi
Canada Ltd. and Technicore Underground Inc.
 Assembly of the first Tunnel Boring Machine (TBM) at the
West Launch pit at Eglinton and Black Creek is complete
and tunnelling is underway
 A twin machine is being assembled
7
Assembly of Tunnel Boring Machines
8
Assembly and Launch Tunnel Boring Machine
9
Sequence of Tunnel Drive
10
Tunnel Drive Works 2013-Current Status
 The majority of the works in 2013 will take place between
Black Creek Drive and the vicinity of Allen Road
 Crews are starting the construction of headwalls at future
station sites along Eglinton Avenue West
 Work zones are set up at Keele and Caledonia
11
Tunnel Drive Works 2013-Current Status
12
Tunnel Drive Works 2013
 Headwalls: Temporary support walls for future excavation
of the LRT stations
 Made of concrete and installed to the depth of the future
track level
 Two methods of installation used: Secant Pile Walls, Jet
Grout
 Machinery including drill rigs, grout tanks, diggers and other
equipment
 Tunnelling from Black Creek to Caledonia expected by end
of year
13
Tunnel Drive Works 2013
Secant pile wall: formed by
intersecting concrete piles
Jet grout wall: uses engineered
grout to form wall in situ
14
TBM Extraction- Vicinity of Allen Road and
Eglinton
 Extraction Shaft: a deep excavation located just west of
Allen Road where the first two tunnel boring machines will
be removed from the ground
 Utility relocation will occur before excavation begins
 Concrete temporary support walls will form the foundation
of the shaft
 Work will start on the north side of Eglinton Avenue. Traffic
will be shifted according to phases of the work
15
Excavation Shaft West of Allen Road
16
 Launch shaft: deep excavation just east of Allen Road
 Two more tunnel boring machines will be assembled and
launched for the second phase of tunnelling to Yonge
Street
 The site will be active for the delivery of tunnel liners and
the hauling of spoils northbound on Allen Road for 12
months
 Sound barrier will be erected on north side of east
commuter parking lot
 Existing subway service will remain operational
TBM Launch Shaft-Vicinity of Allen Road and
Eglinton
17
TBM Launch-Vicinity of Allen Road and
Eglinton
18
Timeline
 At future station locations underground structures
(emergency exits, cross passages) utility relocation and
headwall installation is expected to last approximately six
months on average
 The deep excavations at Allen Road that provide egress and
access points for TBMs are expected to take up to 24
months to construct
 Tunnelling activities for the second phase of tunnelling to
Yonge are expected to take 12 months
 Following the completion of tunnelling works, the site will be
turned over to the Metrolinx station contractor
19
Utility Relocations
 Construction of the headwalls and shafts requires that
some utilities be moved safely out of the way
 Depending on site conditions: gas, hydro, water mains,
sewers, lighting and telephone and cable lines may be
relocated to allow for construction
 In the vicinity of the launch and extraction shafts Metrolinx
is co-ordinating with Bell, Enbridge, Toronto Water and
Toronto Hydro, Cogeco regarding required relocations
 In most cases utility relocations will be undertaken by
Metrolinx contractor
 Enbridge will coordinate works with Metrolinx
20
Approach to Traffic Management
 Maintain a minimum of one lane eastbound and westbound
on Eglinton in construction work zones
 Buses and general traffic will share this lane
 Additional lanes will be provided if space allows
 Metrolinx will work with City of Toronto Transportation, local
elected officials and neighbours to monitor local traffic
 Signal timing may be modified and turning restrictions may
be added or relaxed
21
Traffic Lane Reductions
22
Anticipated Side Street Closures
In order to safely move utilities out of the way and to install
underground structures, some local streets off of Eglinton
Avenue will be closed during construction phases:
 Strathearn Rd
 Flanders Rd
 Winnett Ave
 Everden Rd
 Atlas Ave
 Park Hill Rd
 Old Park Rd
23
Allen Road Access
 Metrolinx is no longer pursuing the full year-long closure of
Allen Road for an extended period
 Temporary, short-term closures to on and off ramps will be
required during different phases of construction
 We will provide as much notice as possible in advance of
those closures
 Advance warning signs will be placed in the vicinity of the
corridor including electronic changeable message signs
and static signs
24
Transit Services during Tunnel Construction
 Pedestrian and bus access to Eglinton West Station will
remain open
 Both eastbound and westbound TTC stops in the affected
area may be shifted and relocated for the safety of transit
riders. Watch for TTC posted signs indicating the adjusted
stop locations
25
Parking
 Currently, 3 hour paid parking is available on Eglinton
Avenue during off-peak hours
 In order to provide space for construction work, street
parking on Eglinton in the work zone will not be permitted
 In order to off-set street parking losses for users of the
shops and services along Eglinton, Metrolinx is proposing
that one-hour parking on some local roads be extended to
3 hours while construction is impacting parking availability
 The provision of additional all-day parking is not within the
scope of Crosstown works
26
Proposed Parking Alternatives
 The following streets have been proposed to allow 3 hour
parking while construction is impacting on-street parking
availability:
 Glenarden Road: Between Eglinton Avenue & Old Forest
Hill Road WEST SIDE ONLY
 Westover Hill Road: Between Eglinton Avenue &
Dewbourne Avenue EAST SIDE ONLY
 Wembley Road: Between west end point & Hilltop Road
SOUTH SIDE ONLY
27
Pedestrians
 In the construction zone for temporary sidewalks or existing
sidewalks the goal is to maintain 1.5 metre sidewalk widths
wherever possible
 Access to properties from sidewalks should be maintained
 Some sections of sidewalk may be closed and crossings will
be available at traffic signals
 Please take care when travelling near construction. Watch
for additional signage directing pedestrians
28
Pedestrian Detours
29 29
Please get in touch with us
 Franca Di Giovanni
 Nicole Di Carlo
 Mark Iogna
 Denise Jayawardene
 Grace Lau
E-mail:
crosstown@metrolinx.com
Online: www.thecrosstown.ca
Tel: 416-782-8118
Community Office
1848 Eglinton Avenue West
Monday, Wednesday, Friday:
9:00 a.m. – 5:00 p.m.
Tuesday & Thursday: by
appointment
Crosstown Community Relations Team

More Related Content

What's hot

Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Crosstown TO
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Crosstown TO
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
 
Western works final
Western works final Western works final
Western works final Crosstown TO
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020 Crosstown TO
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Crosstown TO
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Crosstown TO
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Crosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meetingCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Crosstown TO
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Crosstown TO
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCrosstown TO
 

What's hot (20)

Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Western works final
Western works final Western works final
Western works final
 
West works open house deck March 12 2020
West works open house deck   March 12 2020 West works open house deck   March 12 2020
West works open house deck March 12 2020
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
 
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022Leaside-Laird CLC Meeting - Presentation - January 10, 2022
Leaside-Laird CLC Meeting - Presentation - January 10, 2022
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 

Viewers also liked

Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open houseCrosstown TO
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house Crosstown TO
 
Caledonia station open house
Caledonia station open houseCaledonia station open house
Caledonia station open houseCrosstown TO
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house Crosstown TO
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house Crosstown TO
 
Chaplin station open house
Chaplin station open houseChaplin station open house
Chaplin station open houseCrosstown TO
 
Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house Crosstown TO
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck finalCrosstown TO
 
Science centre station open house
Science centre station open houseScience centre station open house
Science centre station open houseCrosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 
Imagine Eglinton Drawing Contest
Imagine Eglinton Drawing ContestImagine Eglinton Drawing Contest
Imagine Eglinton Drawing ContestCrosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open houseCrosstown TO
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open HouseCrosstown TO
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open HouseCrosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 

Viewers also liked (18)

Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Caledonia station open house
Caledonia station open houseCaledonia station open house
Caledonia station open house
 
Forest hill station open house
Forest hill station open house Forest hill station open house
Forest hill station open house
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house
 
Chaplin station open house
Chaplin station open houseChaplin station open house
Chaplin station open house
 
Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house  Fairbank and Oakwood stations open house
Fairbank and Oakwood stations open house
 
Chaplin slide deck final
Chaplin slide deck finalChaplin slide deck final
Chaplin slide deck final
 
Science centre station open house
Science centre station open houseScience centre station open house
Science centre station open house
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Imagine Eglinton Drawing Contest
Imagine Eglinton Drawing ContestImagine Eglinton Drawing Contest
Imagine Eglinton Drawing Contest
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open house
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015Former Kodak Lands Update - November 19, 2015
Former Kodak Lands Update - November 19, 2015
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open House
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 

Similar to Eglinton Crosstown Update

Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationCrosstown TO
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Crosstown TO
 
Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014Crosstown TO
 
Chaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall ConstructionChaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall ConstructionCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018Crosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesCrosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor WideCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Crosstown TO
 
Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27loyalj
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Crosstown TO
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseCrosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 

Similar to Eglinton Crosstown Update (20)

Eglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House PresentationEglinton Crosstown Leaside Open House Presentation
Eglinton Crosstown Leaside Open House Presentation
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014Chaplin Grout Plant and Headwall Construction Spring 2014
Chaplin Grout Plant and Headwall Construction Spring 2014
 
Chaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall ConstructionChaplin Grout Plant and Headwall Construction
Chaplin Grout Plant and Headwall Construction
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5Mount Pleasant Junior School Meeting May 5
Mount Pleasant Junior School Meeting May 5
 
Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27Dufferin second-public-notice-june-27
Dufferin second-public-notice-june-27
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Eglinton Park
Eglinton ParkEglinton Park
Eglinton Park
 
Station Design Update Meeting: East Open House
Station Design Update Meeting: East Open HouseStation Design Update Meeting: East Open House
Station Design Update Meeting: East Open House
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...Amil baba
 
PODSCAPE - Brochure 2023_ prefab homes in Bangalore India
PODSCAPE - Brochure 2023_ prefab homes in Bangalore IndiaPODSCAPE - Brochure 2023_ prefab homes in Bangalore India
PODSCAPE - Brochure 2023_ prefab homes in Bangalore IndiaYathish29
 
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130Suhani Kapoor
 
Cheap Rate Call girls Kalkaji 9205541914 shot 1500 night
Cheap Rate Call girls Kalkaji 9205541914 shot 1500 nightCheap Rate Call girls Kalkaji 9205541914 shot 1500 night
Cheap Rate Call girls Kalkaji 9205541914 shot 1500 nightDelhi Call girls
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130Suhani Kapoor
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpmainac1
 
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Yantram Animation Studio Corporation
 
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...Call Girls in Nagpur High Profile
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonDelhi Call girls
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceanilsa9823
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CANestorGamez6
 
MASONRY -Building Technology and Construction
MASONRY -Building Technology and ConstructionMASONRY -Building Technology and Construction
MASONRY -Building Technology and Constructionmbermudez3
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfParomita Roy
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵anilsa9823
 
Cheap Rate Call girls Malviya Nagar 9205541914 shot 1500 night
Cheap Rate Call girls Malviya Nagar 9205541914 shot 1500 nightCheap Rate Call girls Malviya Nagar 9205541914 shot 1500 night
Cheap Rate Call girls Malviya Nagar 9205541914 shot 1500 nightDelhi Call girls
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdfSwaraliBorhade
 
A level Digipak development Presentation
A level Digipak development PresentationA level Digipak development Presentation
A level Digipak development Presentationamedia6
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryWilliamVickery6
 

Recently uploaded (20)

NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
NO1 Trending kala jadu Love Marriage Black Magic Punjab Powerful Black Magic ...
 
PODSCAPE - Brochure 2023_ prefab homes in Bangalore India
PODSCAPE - Brochure 2023_ prefab homes in Bangalore IndiaPODSCAPE - Brochure 2023_ prefab homes in Bangalore India
PODSCAPE - Brochure 2023_ prefab homes in Bangalore India
 
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
VIP Call Girls Service Bhagyanagar Hyderabad Call +91-8250192130
 
Cheap Rate Call girls Kalkaji 9205541914 shot 1500 night
Cheap Rate Call girls Kalkaji 9205541914 shot 1500 nightCheap Rate Call girls Kalkaji 9205541914 shot 1500 night
Cheap Rate Call girls Kalkaji 9205541914 shot 1500 night
 
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
VIP Call Girls Service Kukatpally Hyderabad Call +91-8250192130
 
Kindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUpKindergarten Assessment Questions Via LessonUp
Kindergarten Assessment Questions Via LessonUp
 
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
Captivating Charm: Exploring Marseille's Hillside Villas with Our 3D Architec...
 
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
 
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk GurgaonCheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
Cheap Rate ➥8448380779 ▻Call Girls In Iffco Chowk Gurgaon
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
 
MASONRY -Building Technology and Construction
MASONRY -Building Technology and ConstructionMASONRY -Building Technology and Construction
MASONRY -Building Technology and Construction
 
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdfChapter 19_DDA_TOD Policy_First Draft 2012.pdf
Chapter 19_DDA_TOD Policy_First Draft 2012.pdf
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service  🧵
CALL ON ➥8923113531 🔝Call Girls Kalyanpur Lucknow best Female service 🧵
 
Cheap Rate Call girls Malviya Nagar 9205541914 shot 1500 night
Cheap Rate Call girls Malviya Nagar 9205541914 shot 1500 nightCheap Rate Call girls Malviya Nagar 9205541914 shot 1500 night
Cheap Rate Call girls Malviya Nagar 9205541914 shot 1500 night
 
3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf3D Printing And Designing Final Report.pdf
3D Printing And Designing Final Report.pdf
 
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
escort service sasti (*~Call Girls in Prasad Nagar Metro❤️9953056974
 
A level Digipak development Presentation
A level Digipak development PresentationA level Digipak development Presentation
A level Digipak development Presentation
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William Vickery
 

Eglinton Crosstown Update

  • 1. 1 Crosstown Update Allen Road and Eglinton Avenue June 19, 2013 Welcome
  • 2. 2 What is the Crosstown?  The Eglinton Crosstown is a 19 kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section  The line will connect Mount Dennis in the west to Kennedy Road in the east  The new service will be up to 60% faster than bus service today
  • 3. 3 Project Schedule 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Sheppard Finch Eglinton Scarborough RT SRT / Sheppard Maintenance Facility Note: Timeline reflects initiation of major construction activities RFQ Issued RFP Issued Financial Close Timeline 2021
  • 4. 4
  • 5. 5 Eglinton Crosstown LRT  Project  $4.9 B (2010$), funded by the Province of Ontario  19 kilometres east-west LRT from Kennedy to Jane/Black Creek, including 10 kilometres of tunnel  Connections to Yonge-University-Spadina Subway, Scarborough RT and GO Stouffville  Up to 26 stations
  • 6. 6 Tunnelling Update  The tunnel contract was awarded September 11, 2012  The winning consortium is comprised of Kenny Construction Co., Kenaidan Contracting Ltd., Obayashi Canada Ltd. and Technicore Underground Inc.  Assembly of the first Tunnel Boring Machine (TBM) at the West Launch pit at Eglinton and Black Creek is complete and tunnelling is underway  A twin machine is being assembled
  • 7. 7 Assembly of Tunnel Boring Machines
  • 8. 8 Assembly and Launch Tunnel Boring Machine
  • 10. 10 Tunnel Drive Works 2013-Current Status  The majority of the works in 2013 will take place between Black Creek Drive and the vicinity of Allen Road  Crews are starting the construction of headwalls at future station sites along Eglinton Avenue West  Work zones are set up at Keele and Caledonia
  • 11. 11 Tunnel Drive Works 2013-Current Status
  • 12. 12 Tunnel Drive Works 2013  Headwalls: Temporary support walls for future excavation of the LRT stations  Made of concrete and installed to the depth of the future track level  Two methods of installation used: Secant Pile Walls, Jet Grout  Machinery including drill rigs, grout tanks, diggers and other equipment  Tunnelling from Black Creek to Caledonia expected by end of year
  • 13. 13 Tunnel Drive Works 2013 Secant pile wall: formed by intersecting concrete piles Jet grout wall: uses engineered grout to form wall in situ
  • 14. 14 TBM Extraction- Vicinity of Allen Road and Eglinton  Extraction Shaft: a deep excavation located just west of Allen Road where the first two tunnel boring machines will be removed from the ground  Utility relocation will occur before excavation begins  Concrete temporary support walls will form the foundation of the shaft  Work will start on the north side of Eglinton Avenue. Traffic will be shifted according to phases of the work
  • 15. 15 Excavation Shaft West of Allen Road
  • 16. 16  Launch shaft: deep excavation just east of Allen Road  Two more tunnel boring machines will be assembled and launched for the second phase of tunnelling to Yonge Street  The site will be active for the delivery of tunnel liners and the hauling of spoils northbound on Allen Road for 12 months  Sound barrier will be erected on north side of east commuter parking lot  Existing subway service will remain operational TBM Launch Shaft-Vicinity of Allen Road and Eglinton
  • 17. 17 TBM Launch-Vicinity of Allen Road and Eglinton
  • 18. 18 Timeline  At future station locations underground structures (emergency exits, cross passages) utility relocation and headwall installation is expected to last approximately six months on average  The deep excavations at Allen Road that provide egress and access points for TBMs are expected to take up to 24 months to construct  Tunnelling activities for the second phase of tunnelling to Yonge are expected to take 12 months  Following the completion of tunnelling works, the site will be turned over to the Metrolinx station contractor
  • 19. 19 Utility Relocations  Construction of the headwalls and shafts requires that some utilities be moved safely out of the way  Depending on site conditions: gas, hydro, water mains, sewers, lighting and telephone and cable lines may be relocated to allow for construction  In the vicinity of the launch and extraction shafts Metrolinx is co-ordinating with Bell, Enbridge, Toronto Water and Toronto Hydro, Cogeco regarding required relocations  In most cases utility relocations will be undertaken by Metrolinx contractor  Enbridge will coordinate works with Metrolinx
  • 20. 20 Approach to Traffic Management  Maintain a minimum of one lane eastbound and westbound on Eglinton in construction work zones  Buses and general traffic will share this lane  Additional lanes will be provided if space allows  Metrolinx will work with City of Toronto Transportation, local elected officials and neighbours to monitor local traffic  Signal timing may be modified and turning restrictions may be added or relaxed
  • 22. 22 Anticipated Side Street Closures In order to safely move utilities out of the way and to install underground structures, some local streets off of Eglinton Avenue will be closed during construction phases:  Strathearn Rd  Flanders Rd  Winnett Ave  Everden Rd  Atlas Ave  Park Hill Rd  Old Park Rd
  • 23. 23 Allen Road Access  Metrolinx is no longer pursuing the full year-long closure of Allen Road for an extended period  Temporary, short-term closures to on and off ramps will be required during different phases of construction  We will provide as much notice as possible in advance of those closures  Advance warning signs will be placed in the vicinity of the corridor including electronic changeable message signs and static signs
  • 24. 24 Transit Services during Tunnel Construction  Pedestrian and bus access to Eglinton West Station will remain open  Both eastbound and westbound TTC stops in the affected area may be shifted and relocated for the safety of transit riders. Watch for TTC posted signs indicating the adjusted stop locations
  • 25. 25 Parking  Currently, 3 hour paid parking is available on Eglinton Avenue during off-peak hours  In order to provide space for construction work, street parking on Eglinton in the work zone will not be permitted  In order to off-set street parking losses for users of the shops and services along Eglinton, Metrolinx is proposing that one-hour parking on some local roads be extended to 3 hours while construction is impacting parking availability  The provision of additional all-day parking is not within the scope of Crosstown works
  • 26. 26 Proposed Parking Alternatives  The following streets have been proposed to allow 3 hour parking while construction is impacting on-street parking availability:  Glenarden Road: Between Eglinton Avenue & Old Forest Hill Road WEST SIDE ONLY  Westover Hill Road: Between Eglinton Avenue & Dewbourne Avenue EAST SIDE ONLY  Wembley Road: Between west end point & Hilltop Road SOUTH SIDE ONLY
  • 27. 27 Pedestrians  In the construction zone for temporary sidewalks or existing sidewalks the goal is to maintain 1.5 metre sidewalk widths wherever possible  Access to properties from sidewalks should be maintained  Some sections of sidewalk may be closed and crossings will be available at traffic signals  Please take care when travelling near construction. Watch for additional signage directing pedestrians
  • 29. 29 29 Please get in touch with us  Franca Di Giovanni  Nicole Di Carlo  Mark Iogna  Denise Jayawardene  Grace Lau E-mail: crosstown@metrolinx.com Online: www.thecrosstown.ca Tel: 416-782-8118 Community Office 1848 Eglinton Avenue West Monday, Wednesday, Friday: 9:00 a.m. – 5:00 p.m. Tuesday & Thursday: by appointment Crosstown Community Relations Team